CN114960711A - End reinforcement construction method based on shield tunneling - Google Patents

End reinforcement construction method based on shield tunneling Download PDF

Info

Publication number
CN114960711A
CN114960711A CN202110204234.8A CN202110204234A CN114960711A CN 114960711 A CN114960711 A CN 114960711A CN 202110204234 A CN202110204234 A CN 202110204234A CN 114960711 A CN114960711 A CN 114960711A
Authority
CN
China
Prior art keywords
area
construction method
shield tunneling
slurry
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110204234.8A
Other languages
Chinese (zh)
Inventor
张四俊
惠海鹏
刘克强
郭文学
罗石磊
李费辰
曹冲
姬毅天
穆旋
许卓亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
CCCC Tunnel Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
CCCC Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, CCCC Tunnel Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202110204234.8A priority Critical patent/CN114960711A/en
Publication of CN114960711A publication Critical patent/CN114960711A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Abstract

The invention discloses a shield tunneling-based end reinforcement construction method, which comprises the following steps: and constructing a triaxial mixing pile, and reinforcing soil of the region which is at the peripheral region of the end and is positioned in the advancing direction of the shield tunneling machine by constructing the triaxial mixing pile to form an outer ring waterproof curtain. According to the invention, the outer ring water-stop curtain is additionally arranged, so that the water-stop effect is improved, the water and soil loss at the periphery of a station is prevented, the risks of starting and receiving of the shield are reduced, the uneven settlement and collapse caused by the water and soil loss at the outer side of the reinforcement body to peripheral buildings, structures, pipelines and the like are prevented, and the major safety accidents caused by the uneven settlement and collapse are prevented; if the water level is greatly reduced, the weak part can be found out, and double-liquid slurry is injected through the guide hole to reinforce and stop water.

Description

End reinforcement construction method based on shield tunneling
Technical Field
The invention relates to the technical field of shield construction, in particular to a shield tunneling-based end reinforcement construction method.
Background
When the shield machine enters and exits the hole, the working face is in an open state, and the open state lasts for a long time. If the treatment is improper, underground water, sand gushing, water gushing and the like can enter the working well, and cave entrance collapse can be caused under severe conditions. Therefore, the end reinforcement work is very important in shield construction.
Disclosure of Invention
The invention aims to solve the defects in the prior art, and provides a shield tunneling-based end reinforcement construction method.
In order to achieve the purpose, the invention adopts the following technical scheme:
a shield tunneling-based end reinforcement construction method comprises the following steps:
constructing a triaxial mixing pile, and reinforcing soil mass in a region which is arranged in the advancing direction of the shield tunneling machine and is arranged in the peripheral region of the end head by adopting triaxial mixing pile construction to form an outer ring waterproof curtain, wherein a reinforcing region is formed between the outer ring waterproof curtain and a station;
constructing and reinforcing the reinforcing area by adopting a triaxial mixing pile, and arranging an area A and an area B for the shield tunneling machine to pass through, wherein the area B is arranged close to an outer ring waterproof curtain;
constructing a high-pressure jet grouting pile, namely constructing and arranging the high-pressure jet grouting pile on the soil body in the reinforced area by adopting the high-pressure jet grouting pile to form an end face water-stopping curtain, wherein the end face water-stopping curtain is positioned on one side of the area A, which is far away from the area B;
and (4) dewatering construction, wherein a dewatering well and an observation well are arranged on the edge of the reinforced area, and the dewatering well and the observation well are arranged at intervals.
Preferably, the construction method of the triaxial mixing pile comprises the following steps: measuring and paying off → guide groove construction → positioning and setting → pile machine in place → cement slurry mixing → sinking and lifting of a drill rod of the pile machine → grouting, stirring and lifting → interlocking construction of a stirring pile.
Preferably, in the step of placing the pile machine in place, the verticality of a drill rod of the pile machine is less than 3 per thousand.
Preferably, in the step of mixing cement slurry, common portland cement is adopted, the water cement ratio is 1.5, the mixing amount of cement in empty piles is 9.7%, the mixing amount of cement in solid piles is 27.69% in an area A and 20.7% in an area B, the grouting pressure is about 0.5Mpa, after soil body reinforcement, the unconfined compressive strength of the mixing piles in the area A in the 28-day age is more than or equal to 1.0Mpa, and the unconfined compressive strength of the mixing piles in the area B in the 28-day age is more than or equal to 0.5 Mpa.
Preferably, in the above construction step, when stopping slurry for any reason, the mixer is lifted or sunk to a position 0.5m below the slurry stopping point, and when slurry supply is resumed, slurry spraying and stirring are carried out again.
Preferably, the construction method of the high-pressure jet grouting pile comprises the following steps: hole location → drilling → lower injection pipe → pulping → injection lifting → recharge.
Preferably, in the step of pulping, ordinary portland cement is adopted, the water cement ratio is 0.8-1.0, the cement mixing amount is 300kg/m, the slurry is stirred by a high-speed stirrer, the stirring slurry is required to be continuous and uniform, the stirring time is not less than 30s, and the using time of one-time stirring is also controlled within 4 h.
Preferably, in the step of spraying and lifting, the control parameters are 0.7MPa of air pressure, 3MPa of slurry pressure, 25MPa of water pressure, 10cm/min of lifting speed, 10r/min of rotating speed and 100L/min of slurry flow.
Preferably, the construction process of the dewatering well comprises the following steps: measuring, lofting hole sites, acceptance inspection → a drilling machine is in place → drilling, hole forming → a final hole → a lower well pipe → gravel filling → mud filling and sealing → well washing → well forming ending → pumping by a pump.
Preferably, in step gravel packing, standard graded sand is used, and the gravel packing particle size is 6-12 times the particle size of the aquifer surrounding the filter tube.
Compared with the prior art, the invention has the beneficial effects that:
1. by additionally arranging the outer ring waterproof curtain, the waterproof effect is improved, the water and soil loss at the periphery of a station is prevented, the risks of starting and receiving of a shield are reduced, and the serious safety accidents caused by uneven settlement and collapse of peripheral buildings, structures, pipelines and the like caused by the water and soil loss outside a reinforcement body are prevented;
2. before the shield machine starts and receives, internal precipitation is carried out on the reinforcing body in advance through a precipitation well, so that the starting and receiving safety of the shield machine is improved;
3. the observation well is additionally arranged on the outer side of the reinforced body, the reinforced body is subjected to precipitation before the shield starts and receives, and the water stop effect of the reinforced area can be further verified through the water level variation amplitude of the observation well; if the water level is greatly reduced, the weak part can be found out, and double-liquid slurry is injected through the guide hole to reinforce and stop water.
Drawings
In order to more particularly and intuitively illustrate an embodiment of the present invention or a prior art solution, a brief description of the drawings needed for use in the description of the embodiment or the prior art will be provided below.
FIG. 1 is a schematic structural diagram according to the present invention;
fig. 2 is a schematic cross-sectional view of fig. 1.
In the figure: the waterproof curtain comprises an outer ring waterproof curtain 1, a B area 2, an A area 3, an end face waterproof curtain 4, a dewatering well 5 and an observation well 6.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-2, a shield tunneling-based end reinforcement construction method includes the following steps:
constructing a triaxial mixing pile, reinforcing soil in a region which is arranged in the traveling direction of the shield tunneling machine and is arranged in the peripheral region of the end by adopting the triaxial mixing pile construction to form an outer ring waterproof curtain 1, and forming a reinforcing region between the outer ring waterproof curtain and a station;
constructing and reinforcing the reinforcing area by adopting a triaxial mixing pile, arranging an area A3 and an area B2 for the shield tunneling machine to pass through, wherein the area B is arranged close to the outer ring waterproof curtain 1 by the area B2;
constructing a high-pressure jet grouting pile, namely constructing and arranging the high-pressure jet grouting pile on the soil body of the reinforced area by adopting the high-pressure jet grouting pile to form an end face water-stopping curtain 4, wherein the end face water-stopping curtain 4 is positioned on one side of the area A3, which is far away from the area B2;
precipitation construction, set up precipitation well 5 and observation well 6 at the limit portion of consolidating the district, and precipitation well 5 and 6 intervals of observation well set up.
The construction method of the triaxial mixing pile comprises the following steps: measuring and paying off → guide groove construction → positioning and setting → pile machine in place → cement slurry mixing → sinking and lifting of a drill rod of the pile machine → grouting, stirring and lifting → interlocking construction of a stirring pile.
In the step of taking the pile driver in place, the verticality of a drill rod of the pile driver is less than 3 per thousand, the verticality of the pile frame can be adjusted by a verticality indicator of the pile frame, and a total station of a plumb bob is used for checking. An iron ring with the radius of 5cm is welded on the pile frame, a plumb bob is hung at the height of 10m, and a total station is utilized to straighten the verticality of the drill rod, so that the plumb bob just passes through the center of the iron ring. Before each construction, the drill rod must be properly adjusted to ensure that the plumb bob is positioned in the iron ring, namely the verticality error of the drill rod is controlled within 3 per mill.
In the step of cement slurry mixing, common portland cement is adopted, the water cement ratio is 1.5, the cement mixing amount of an empty pile is 9.7%, the cement mixing amount of a real pile is 27.69% in an area A and 20.7% in an area B, the grouting pressure is about 0.5Mpa, after soil body reinforcement, the unconfined compressive strength of the mixing pile in the area A in the 28-day age is more than or equal to 1.0Mpa, and the unconfined compressive strength of the mixing pile in the area B in the 28-day age is more than or equal to 0.5 Mpa.
In the construction steps, when the slurry is stopped for reasons, the stirring machine is lifted or sunk to a position 0.5m below the slurry stopping point, and the slurry is sprayed and drilled when the slurry supply is resumed.
The construction method of the high-pressure jet grouting pile comprises the following steps: hole location → drilling → lower injection pipe → pulping → injection lifting → recharge.
In the step of pulping, ordinary portland cement is adopted, the water cement ratio is 0.8-1.0, the cement mixing amount is 300kg/m, the slurry is stirred by a high-speed stirrer, the stirring slurry is required to be continuous and uniform, the stirring time is not less than 30s, and the one-time stirring use time is also controlled within 4 h.
In the step of spraying and lifting, the control parameters are that the air pressure is 0.7MPa, the slurry pressure is 3MPa, the water pressure is 25MPa, the lifting speed is 10cm/min, the rotating speed is 10r/min, and the slurry flow is 100L/min.
The construction process of the dewatering well comprises the following steps: measuring, lofting hole sites, checking and accepting → positioning of a drilling machine → drilling, hole forming → final hole → lower well pipe → gravel filling → mud filling and sealing → well washing → well completion → pump discharge and water pumping.
In the step of gravel filling, standard graded sand is adopted, and the grain size of the gravel filling is 6-12 times of the grain size of the aquifer around the filter pipe.
In the scheme, the outer ring waterproof curtain is additionally arranged, so that the waterproof effect is improved, the water and soil loss around a station is prevented, and the risks of starting and receiving of the shield are reduced. The method has the advantages that the major safety accidents caused by uneven settlement and collapse caused by water and soil loss outside the reinforcing body to surrounding buildings, structures, pipelines and the like are prevented, internal precipitation is carried out on the reinforcing body in advance through the precipitation well before the shield machine starts and receives so as to improve the safety of the shield machine in starting and receiving, the observation well is additionally arranged outside the reinforcing body, precipitation is carried out on the reinforcing body before the shield machine starts and receives, and the water stopping effect of the reinforcing area can be further verified through the water level variation amplitude of the observation well; if the water level is greatly reduced, the weak part can be found out, and double grout is injected into the guide hole to reinforce and stop water.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (10)

1. A shield tunneling-based end reinforcement construction method is characterized by comprising the following steps:
constructing a triaxial mixing pile, and reinforcing soil in a region which is arranged in the advancing direction of the shield tunneling machine and is arranged in the peripheral region of the end head by adopting triaxial mixing pile construction to form an outer ring waterproof curtain (1), wherein a reinforcing region is formed between the outer ring waterproof curtain and a station;
constructing and reinforcing the reinforcing area by adopting a triaxial mixing pile, arranging an area A (3) and an area B (2) for the shield tunneling machine to pass through, and arranging the area B close to the outer ring waterproof curtain (1) by the area (2);
constructing high-pressure jet grouting piles, namely constructing the high-pressure jet grouting piles on the soil body of the reinforced area by adopting the high-pressure jet grouting piles to form an end face water-stopping curtain (4), wherein the end face water-stopping curtain (4) is positioned on one side of the area A (3) far away from the area B (2);
precipitation construction, set up precipitation well (5) and observation well (6) at the limit portion of consolidating the district, and precipitation well (5) and observation well (6) interval set up.
2. The shield tunneling-based end reinforcement construction method according to claim 1, wherein the construction method of the triaxial mixing pile comprises the following steps: measuring and paying off → guide groove construction → positioning and setting → pile machine in place → cement slurry mixing → sinking and lifting of a drill rod of the pile machine → grouting, stirring and lifting → interlocking construction of a stirring pile.
3. The shield tunneling-based end reinforcement construction method according to claim 2, wherein in the step of placing the pile machine in place, the verticality of a drill rod of the pile machine is less than 3 per thousand.
4. The shield tunneling-based end reinforcement construction method according to claim 3, wherein in the step of mixing cement slurry, ordinary portland cement is used, the water cement ratio is 1.5, the cement content of empty piles is 9.7%, the cement content of solid piles is 27.69% in the area A and 20.7% in the area B, the grouting pressure is about 0.5Mpa, and after soil reinforcement, the unconfined compressive strength of the mixing piles in the area A in the 28-day age is not less than 1.0Mpa, and the unconfined compressive strength of the mixing piles in the area B in the 28-day age is not less than 0.5 Mpa.
5. The shield tunneling-based end reinforcement construction method according to claim 4, wherein in the construction step, when the slurry is stopped for any reason, the stirrer is lifted or sunk to a position 0.5m below the slurry stop point, and when the slurry supply is resumed, the slurry is sprayed and drilled.
6. The shield tunneling-based end head reinforcing construction method according to claim 5, wherein the high-pressure jet grouting pile construction method comprises the following steps: hole location → drilling → lower injection pipe → pulping → injection lifting → recharge.
7. The shield tunneling-based end reinforcement construction method according to claim 6, characterized in that in the step of slurrying, ordinary portland cement is adopted, the water cement ratio is 0.8-1.0, the cement mixing amount is 300kg/m, the slurry is stirred by a high-speed stirrer, the stirred slurry is required to be continuous and uniform, the stirring time is not less than 30s, and the one-time stirring use time is also controlled within 4 h.
8. The shield tunneling-based end reinforcement construction method according to claim 7, wherein in the step of injection lifting, the control parameters are air pressure of 0.7MPa, slurry pressure of 3MPa, water pressure of 25MPa, lifting speed of 10cm/min, rotation speed of 10r/min and slurry flow rate of 100L/min.
9. The shield tunneling-based end reinforcement construction method according to claim 8, wherein the dewatering well construction process comprises the following steps: measuring, lofting hole sites, acceptance inspection → a drilling machine is in place → drilling, hole forming → a final hole → a lower well pipe → gravel filling → mud filling and sealing → well washing → well forming ending → pumping by a pump.
10. The shield tunneling-based head end reinforcing construction method according to claim 9, wherein standard graded sand is used in the step of gravel packing, and the grain size of the gravel packing is 6-12 times that of the aquifer around the filter pipe.
CN202110204234.8A 2021-02-24 2021-02-24 End reinforcement construction method based on shield tunneling Pending CN114960711A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110204234.8A CN114960711A (en) 2021-02-24 2021-02-24 End reinforcement construction method based on shield tunneling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110204234.8A CN114960711A (en) 2021-02-24 2021-02-24 End reinforcement construction method based on shield tunneling

Publications (1)

Publication Number Publication Date
CN114960711A true CN114960711A (en) 2022-08-30

Family

ID=82974088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110204234.8A Pending CN114960711A (en) 2021-02-24 2021-02-24 End reinforcement construction method based on shield tunneling

Country Status (1)

Country Link
CN (1) CN114960711A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11241593A (en) * 1998-02-25 1999-09-07 Hazama Gumi Ltd Ground collapse preventing method in shield construction
CN106194218A (en) * 2016-08-30 2016-12-07 中铁第四勘察设计院集团有限公司 The shield end soil body reinforcement system in high water head deep and thick sand area
CN106545005A (en) * 2016-12-05 2017-03-29 中交第三航务工程局有限公司 A kind of reinforcing body and reinforcement means of subway tunnel shield termination
CN106812540A (en) * 2017-03-20 2017-06-09 中铁十四局集团有限公司 A kind of shield launching element wall closing water sealing consolidation structure and construction technology
CN106988753A (en) * 2017-05-08 2017-07-28 中建三局基础设施工程有限公司 A kind of U-shaped plain concrete ground-connecting-wall adds steel bushing shield structure and its method of reseptance
CN108625863A (en) * 2018-03-21 2018-10-09 浙江大学城市学院 A kind of weak soil shield receives control and reinforcement means
CN109751056A (en) * 2019-01-31 2019-05-14 中铁工程装备集团有限公司 A kind of water rich strata shield-tunneling construction active well end processing method
CN110344834A (en) * 2019-07-12 2019-10-18 中铁十二局集团有限公司 Nearly section water-rich silty sand layers shield machine receives construction method
JP6632018B1 (en) * 2019-07-26 2020-01-15 株式会社タック Tunnel waterproofing method, tunnel waterproofing system, and waterproofing material
CN111810176A (en) * 2020-08-12 2020-10-23 通州建总集团有限公司 Subway station end reinforcement construction method for water-rich sand layer shield construction

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11241593A (en) * 1998-02-25 1999-09-07 Hazama Gumi Ltd Ground collapse preventing method in shield construction
CN106194218A (en) * 2016-08-30 2016-12-07 中铁第四勘察设计院集团有限公司 The shield end soil body reinforcement system in high water head deep and thick sand area
CN106545005A (en) * 2016-12-05 2017-03-29 中交第三航务工程局有限公司 A kind of reinforcing body and reinforcement means of subway tunnel shield termination
CN106812540A (en) * 2017-03-20 2017-06-09 中铁十四局集团有限公司 A kind of shield launching element wall closing water sealing consolidation structure and construction technology
CN106988753A (en) * 2017-05-08 2017-07-28 中建三局基础设施工程有限公司 A kind of U-shaped plain concrete ground-connecting-wall adds steel bushing shield structure and its method of reseptance
CN108625863A (en) * 2018-03-21 2018-10-09 浙江大学城市学院 A kind of weak soil shield receives control and reinforcement means
CN109751056A (en) * 2019-01-31 2019-05-14 中铁工程装备集团有限公司 A kind of water rich strata shield-tunneling construction active well end processing method
CN110344834A (en) * 2019-07-12 2019-10-18 中铁十二局集团有限公司 Nearly section water-rich silty sand layers shield machine receives construction method
JP6632018B1 (en) * 2019-07-26 2020-01-15 株式会社タック Tunnel waterproofing method, tunnel waterproofing system, and waterproofing material
CN111810176A (en) * 2020-08-12 2020-10-23 通州建总集团有限公司 Subway station end reinforcement construction method for water-rich sand layer shield construction

Similar Documents

Publication Publication Date Title
AU2020103672A4 (en) Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
CN100591866C (en) Drifting sand layer and gravel stratum water-moving double-liquid high pressure slip-casting water-blocking construction method
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN106545005A (en) A kind of reinforcing body and reinforcement means of subway tunnel shield termination
CN107246267A (en) Mine Shaft Lining, constructing device and method in a kind of poor strata
CN111119940B (en) Grouting construction treatment method
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN111411970B (en) Shield starting construction method under geological condition of water-rich sand layer
CN104631480A (en) Method for performing deep foundation pit waterproof curtain construction by adopting high-pressure jet grouting pile machine
CN104674798A (en) Construction method for non-replacement and up-and-down convertible spouting five-shaft cement mixing pile
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN105731978B (en) A kind of grouting serous fluid and grouting method for fine sand layer jacking culvert solidifying of the working face
CN106013078B (en) A kind of construction method of highly permeable stratum consolidation curtain structure
CN107338789A (en) A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake
CN207377562U (en) Mine Shaft Lining and constructing device in a kind of poor strata
CN210509175U (en) Reinforced structure of building is worn to shield closely side
CN110777775A (en) Foundation pit structure and construction method thereof
CN103174135B (en) Repair method of unqualified post-grouting bored concrete pile
CN108894247A (en) A kind of Metro Connection Passage periphery soil body subsidence pressure circle spray reinforcement structure and construction method
CN113027483A (en) Shield tunnel broken zone stratum grouting reinforcement equipment and grouting reinforcement method thereof
CN108755671A (en) A kind of rich water gravel layer three axes agitating pile construction method
CN111962516A (en) Grouting construction process for jet grouting pile for reinforcing underground excavation shaft
CN107227958A (en) Shaft wall structure, constructing device and the method for the high spray curtain pile of shaft collar section
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination