CN110344834A - Nearly section water-rich silty sand layers shield machine receives construction method - Google Patents

Nearly section water-rich silty sand layers shield machine receives construction method Download PDF

Info

Publication number
CN110344834A
CN110344834A CN201910630189.5A CN201910630189A CN110344834A CN 110344834 A CN110344834 A CN 110344834A CN 201910630189 A CN201910630189 A CN 201910630189A CN 110344834 A CN110344834 A CN 110344834A
Authority
CN
China
Prior art keywords
shield
construction
stabilization zone
shield machine
last
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910630189.5A
Other languages
Chinese (zh)
Inventor
张德强
曹志勇
李自力
王利军
闫希东
梁素芳
武鑫星
黎鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201910630189.5A priority Critical patent/CN110344834A/en
Publication of CN110344834A publication Critical patent/CN110344834A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • E21D9/0671Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end with means for consolidating the rock in front of the shield by injection of consolidating substances through boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield

Abstract

The present invention provides a kind of nearly section water-rich silty sand layers shield machine reception construction method, this method is tunneled in shield machine to before shield end, shield strengthening construction is carried out by three axes agitating pile and high-pressure rotary jet grouting pile in shield end and carries out dewatering construction in shield end, when the cutterhead of shield machine is tunneled to portal, the construction of first time secondary grouting is carried out in the shield tail of shield machine, in the case where shield machine is tunneled to last ring of tunnel, second of secondary grouting construction is carried out in the shield tail of shield machine, after shield machine is detached from last endless tube piece, the gap between last endless tube piece and portal steel loop is blocked with steel plate, and mortar depositing construction is carried out in gap, shield is completed to receive.The method provided through the invention can effectively ensure that the received safety of shield in the nearly section water-rich silty sand layers of shield, and portal is avoided to abolish surface subsidence caused by rear soil erosion and collapsing, reduce the received construction risk of shield water rich strata.

Description

Nearly section water-rich silty sand layers shield machine receives construction method
Technical field
The present invention relates to Municipal Engineering Construction fields, and in particular, to a kind of nearly section water-rich silty sand layers shield machine reception Construction method.
Background technique
Shield method has the features such as construction speed is fast, mechanization degree is high, security performance is strong, is applied by China tunnel at present Work field is widely applied.With the fast development of urban track traffic, the large quantities of cities in the coastal areas such as China East China, south China are opened Begin to carry out constructing metro tunnel using shield method.
Coastal area geology is commonly sandy silt soil stratum, and ground, underground water are extremely abundant, in shield launching and receive process In easily occur because soil erosion cause surface subsidence even collapse the phenomenon that.In the prior art, three axes agitating pile can be passed through It is reinforced, but consolidation effect is poor, will appear flowing water in portal location of the coring procedure, gushes the problem of sand, can not carry out portal on time It abolishes, or abolishes completion in portal, carry out the received section of jurisdiction rear portion water in the process of shield and gush out portal sealing, cause to seal Failure, the serious end regions ground that even results in deforms, collapses.
Summary of the invention
For when sandy silt soil stratum carries out shield-tunneling construction, being easy to appear soil erosion, seal failure shows in the prior art As, cause consolidation effect poor, shield end ground deformation, collapse the technical issues of, the present invention provides a kind of nearly section rich waters Silty sand ground shield machine receives construction method, using this method it is possible to prevente effectively from portal to abolish ground caused by rear soil erosion heavy Drop and collapsing reduce shield and receive risk, shorten construction period, guarantee construction safety.
To achieve the above object, it includes following that nearly section water-rich silty sand layers shield machine provided by the invention, which receives construction method, Step: in the case where shield machine is apart from the shield end pre-determined distance, according to the size of shield machine in the shield end Determine shield stabilization zone;Shield strengthening construction is carried out by three axes agitating pile and high-pressure rotary jet grouting pile in the shield stabilization zone;? Tunnel two sides set multiple dewatering wells with preset interval;In the case where the shield cutter of the shield machine is tunneled to portal, stop Only shield driving carries out the construction of first time secondary grouting in the shield tail of the shield machine;It constructs in the first time secondary grouting After completion, continue the shield driving;In the case where the shield machine is tunneled to last ring of the tunnel, described in stopping Shield driving carries out second of secondary grouting construction in the shield tail of the shield machine;It has constructed in second of secondary grouting At the shield driving later, is continued, until the shield tail of the shield machine is detached from last endless tube piece and reaches shield reception bracket; Gap between last described endless tube piece and portal steel loop is blocked using steel plate;In last described endless tube piece and the portal steel Mortar depositing construction is carried out in the gap of interannular, to complete shield reception.
Further, described to be applied in the shield stabilization zone by three axes agitating pile and high-pressure rotary jet grouting pile progress shield reinforcing Work, comprising: the shield stabilization zone is in turn divided into the first stabilization zone and the second stabilization zone along tunnel piercing direction;Exist respectively First stabilization zone carries out three axes agitating pile construction, carries out Construction of High Pressure Jet Grouting Pile in second stabilization zone.
Further, described to carry out three axes agitating pile construction in first stabilization zone, comprising: by first stabilization zone First weak stabilization zone is divided by earth's surface to tunnel inverted arch next coming in order and including the last the first stabilization zone in the tunnel;Respectively Three axes agitating pile construction is carried out in the last the first stabilization zone and the first weak stabilization zone, wherein the last the first stabilization zone Cement mixing content is 20%, and the cement mixing content of the first weak stabilization zone is 7%.
Further, two neighboring three axes agitating pile mutually overlaps a hole.
Further, the method also includes: the shield stabilization zone by three axes agitating pile and high-pressure rotary jet grouting pile into After row shield strengthening construction, before the tunnel two sides set multiple dewatering wells with preset interval: vertical in the portal Set multiple coring holes;Detect the compression strength and infiltration coefficient of the Kong Xin in the coring hole;It is greater than in the compression strength In the case that preset strength and infiltration coefficient are less than preset value, successively installed from inside to outside in the coring hole described for observing The detection pipe and valve of portal geological condition.
Further, the shield tail in the shield machine carries out the construction of first time secondary grouting, comprising: in the shield The second ring and third ring of machine shield tail carry out the first time secondary grouting construction;The shield tail in the shield machine carries out Second of secondary grouting construction, comprising: carried out in the second ring and third ring of the shield machine shield tail described secondary for the second time Mortar depositing construction.
Further, the injection slurry of the first time secondary grouting construction and second of secondary grouting construction includes Cement and waterglass.
Further, the method also includes: blocked between last described endless tube piece and portal steel loop using steel plate After gap, in the gap between last described endless tube piece and the portal steel loop before progress mortar depositing construction: in institute It states and opens up gas vent on steel plate;In valve of the gas vent installation for exhaust.
The technical solution provided through the invention, the present invention at least have the following technical effect that
Nearly section water-rich silty sand layers shield machine of the invention receives construction method, shield machine tunnel to shield end it Before, shield strengthening construction is carried out by three axes agitating pile and high-pressure rotary jet grouting pile in shield end and carries out precipitation in shield end Construction carries out the construction of first time secondary grouting in the shield tail of shield machine, in shield machine when the cutterhead of shield machine is tunneled to portal In the case where driving to last ring of tunnel, second of secondary grouting construction is carried out in the shield tail of shield machine, is detached from shield machine After last endless tube piece, the gap between last endless tube piece and portal steel loop is blocked with steel plate, and slip casting is carried out in gap Construction is completed shield and is received.The method provided through the invention can effectively ensure that shield in the nearly section water-rich silty sand layers of shield Received safety effectively avoids portal from abolishing surface subsidence caused by rear soil erosion and collapsing, reduces shield water rich strata Received construction risk, effective guarantee shield machine receive safely.
Other features and advantages of the present invention will the following detailed description will be given in the detailed implementation section.
Detailed description of the invention
Fig. 1 is the flow chart that nearly section water-rich silty sand layers shield machine provided in an embodiment of the present invention receives construction method;
Fig. 2 is secondary for the first time in nearly section water-rich silty sand layers shield machine reception construction method provided in an embodiment of the present invention The schematic diagram of slip casting;
Fig. 3 is secondary for the second time in nearly section water-rich silty sand layers shield machine reception construction method provided in an embodiment of the present invention The schematic diagram of slip casting;
Fig. 4 is that nearly section water-rich silty sand layers shield machine provided in an embodiment of the present invention receives the first weak reinforcing in construction method The schematic diagram in area and the last the first stabilization zone.
Specific embodiment
It is described in detail below in conjunction with specific embodiment of the attached drawing to the embodiment of the present invention.It should be understood that this Locate described specific embodiment and be merely to illustrate and explain the present invention embodiment, is not intended to restrict the invention embodiment.
It should be noted that in the absence of conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
In the present invention, in the absence of explanation to the contrary, the noun of locality used such as " upper and lower, top, bottom " is usually needle For direction shown in the drawings either for it is vertical, on vertical or gravity direction for each component mutual alignment relation Word is described.
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
Fig. 1-Fig. 3 is please referred to, the embodiment of the present invention provides a kind of nearly section water-rich silty sand layers shield machine reception construction method, Method includes the following steps: S101: in the case where shield machine is apart from the shield end pre-determined distance, according to shield machine Size determines shield stabilization zone in the shield end;S102: it is revolved in the shield stabilization zone by three axes agitating pile and high pressure It sprays stake and carries out shield strengthening construction;S103: multiple dewatering wells are set with preset interval in tunnel two sides;S104: in the shield In the case that the shield cutter of machine is tunneled to portal, stop shield driving, is carried out in the shield tail of the shield machine secondary for the first time Mortar depositing construction;S105: after first time secondary grouting construction is completed, continue the shield driving;S106: in the shield In the case that structure machine is tunneled to last ring of the tunnel, stop the shield driving, carries out the in the shield tail of the shield machine Secondary secondary grouting construction;S107: after second of secondary grouting construction is completed, continuing the shield driving, until The shield tail of the shield machine is detached from last endless tube piece and reaches shield reception bracket;S108: using steel plate block it is described last Gap between endless tube piece and portal steel loop;S109: it is carried out in the gap between last described endless tube piece and the portal steel loop Mortar depositing construction, to complete shield reception.
Specifically, in embodiment of the present invention, before shield machine reaches shield end, according to the size of shield machine in shield Structure end determines shield stabilization zone, and shield stabilization zone is greater than the head length of shield in the length of tunneling direction, perpendicular to pick It is greater than the width in tunnel into the length in direction.The a length of 9.6m of the shield body of shield machine in the embodiment of the present invention, therefore shield stabilization zone It is set as 12m in the length of tunneling direction.Pass through three axes agitating pile respectively in shield stabilization zone and high-pressure rotary jet grouting pile carries out shield Strengthening construction improves the soil structures in shield stabilization zone, improves uniformity, leakproofness and the independence of the stabilization zone soil body.It Multiple dewatering wells are set in tunnel two sides afterwards, carry out dewatering construction before shield machine reaches shield end, guaranteed water level is in tunnel 1 meter below road bottom, shield machine could tunnel shield end.
Shield machine is promoted through shield stabilization zone, until shield machine is shut down, in shield tail when cutterhead top to the portal of shield machine First time after-teeming slurry is carried out from the bottom to top, and the underground water outside shield stabilization zone is isolated.First time, secondary grouting was (in the present embodiment Secondary grouting be synchronous grouting after benefit mortar depositing construction) complete after, determine it is anhydrous in shield soil storehouse after, continue shield pick Into, start carry out portal abolish construction.It tunnels to last ring shield tail of tunnel in the shield tail of shield machine also without departing from shield duct piece When, stop shield machine driving, carries out second of after-teeming slurry from the bottom to top in shield tail, block the water at section of jurisdiction rear portion, prevent shield There is soil erosion situation after being detached from section of jurisdiction in machine.After second of secondary grouting construction is completed, continue shield driving, until shield The shield tail of structure machine is detached from last endless tube piece and reaches shield reception bracket.Then between last endless tube piece and portal steel loop between Gap is blocked at gap using plurality of steel plates, the outer diameter of steel plate is equal to steel loop internal diameter, and internal diameter is with can be with section of jurisdiction Welding is advisable, and carries out mortar depositing construction to gap, prevents water and soil from flowing out out of gap.
The method provided through the invention can effectively avoid surface subsidence caused by soil erosion in shield receive process And collapse, guarantee the received safety of shield in the nearly section water-rich silty sand layers of shield, reduces the received construction of shield water rich strata Risk.
Further, described to be applied in the shield stabilization zone by three axes agitating pile and high-pressure rotary jet grouting pile progress shield reinforcing Work, comprising: the shield stabilization zone is in turn divided into the first stabilization zone and the second stabilization zone along tunnel piercing direction;Exist respectively First stabilization zone carries out three axes agitating pile construction, carries out Construction of High Pressure Jet Grouting Pile in second stabilization zone.
Specifically, in embodiment of the present invention, shield stabilization zone edge is in turn divided into first along tunnel piercing direction and is added Gu Qu and the second stabilization zone.First stabilization zone carries out three axis close to portal, in the first stabilization zone close to shield machine, the second stabilization zone Mixing pile construction carries out Construction of High Pressure Jet Grouting Pile in the second stabilization zone.
The method provided through the invention can improve the soil body situation of shield end, prevent outside shield end region The underground water in shield end region is reduced in Groundwater infiltration shield end region, occurs flowing water when preventing shield from receiving, gushes sand and ask Topic guarantees that shield receives safely.
Further, described to carry out three axes agitating pile construction in first stabilization zone, comprising: by first stabilization zone First weak stabilization zone is divided by earth's surface to tunnel inverted arch next coming in order and including the last the first stabilization zone in the tunnel;Respectively Three axes agitating pile construction is carried out in the last the first stabilization zone and the first weak stabilization zone, wherein the last the first stabilization zone Cement mixing content is 20%, and the cement mixing content of the first weak stabilization zone is 7%.
Referring to FIG. 4, specifically, in embodiment of the present invention, the first stabilization zone be divided into from top to bottom first it is weak plus Gu Qu and the last the first stabilization zone region Liang Ge, the first weak stabilization zone include earth's surface to the region of tunnel vault, and cement mixing content is 7%.The last the second stabilization zone includes the region of tunnel vault to tunnel inverted arch or less 3m, cement mixing content 20%.
The method provided through the invention reinforces to divide into first and forces Gu Qu and weak stabilization zone and can guarantee to reinforce The usage amount that cement is reduced while effect, reduces construction cost.
Further, two neighboring three axes agitating pile mutually overlaps a hole.
Specifically, in embodiment of the present invention, three axes agitating pile construction is carried out in such a way that the first stabilization zone is beaten using set, Adjacent two three axes agitating piles mutually overlap a hole, to improve the pile quality of three axes agitating pile.
Further, the method also includes: the shield stabilization zone by three axes agitating pile and high-pressure rotary jet grouting pile into After row shield strengthening construction, before the tunnel two sides set multiple dewatering wells with preset interval: vertical in the portal Set multiple coring holes;Detect the compression strength and infiltration coefficient of the Kong Xin in the coring hole;It is greater than in the compression strength In the case that preset strength and infiltration coefficient are less than preset value, successively installed from inside to outside in the coring hole described for observing The detection pipe and valve of portal geological condition.
Specifically, in embodiment of the present invention, after carrying out strengthening construction to shield end, multiple take is set in portal Core bore, and the compression strength and infiltration coefficient of detection hole core are more than or equal to 0.8mPa in compression strength, and infiltration coefficient is less than or equal to 1*10-7When cm/s, determine that shield strengthening construction complies with standard.Detection pipe and valve are installed in the position in coring hole later, then beaten If dewatering well.Shield machine can open valve before abolishing portal, whether coring hole in there are flowing out, if not having in coring hole if detecting It there are flowing out, then it represents that it is anhydrous in native storehouse, progress portal can be started and abolish construction.
The method provided through the invention can facilitate and detect to shield consolidation effect.
Further, the shield tail in the shield machine carries out the construction of first time secondary grouting, comprising: in the shield The second ring and third ring of machine shield tail carry out the first time secondary grouting construction;The shield tail in the shield machine carries out Second of secondary grouting construction, comprising: carried out in the second ring and third ring of the shield machine shield tail described secondary for the second time Mortar depositing construction.
Further, the injection slurry of the first time secondary grouting construction and second of secondary grouting construction includes Cement and waterglass.
Further, the method also includes: blocked between last described endless tube piece and portal steel loop using steel plate After gap, in the gap between last described endless tube piece and the portal steel loop before progress mortar depositing construction: in institute It states and opens up gas vent on steel plate;In valve of the gas vent installation for exhaust.
Specifically, in embodiment of the present invention, after blocking the gap between last endless tube piece and portal steel loop, in steel Multiple gas vents are opened up on plate, and valve is installed in gas vent, when carrying out mortar depositing construction to gap, Open valve, benefit Be discharged in by the air in gap, facilitate smooth slip casting, and can by gas vent and valve detection, whether slip casting is completed, Having in valve, which can determine in gap when injection slurry outflow, has been filled with full injection slurry.
It is described the prefered embodiments of the present invention in detail above in conjunction with attached drawing, still, the present invention is not limited to above-mentioned realities The detail in mode is applied, within the scope of the technical concept of the present invention, a variety of letters can be carried out to technical solution of the present invention Monotropic type, these simple variants all belong to the scope of protection of the present invention.
It is further to note that specific technical features described in the above specific embodiments, in not lance In the case where shield, can be combined in any appropriate way, in order to avoid unnecessary repetition, the present invention to it is various can No further explanation will be given for the combination of energy.
In addition, various embodiments of the present invention can be combined randomly, as long as it is without prejudice to originally The thought of invention, it should also be regarded as the disclosure of the present invention.

Claims (8)

1. a kind of nearly section water-rich silty sand layers shield machine receives construction method, which is characterized in that the described method includes:
It is true in the shield end according to the size of shield machine in the case where shield machine is apart from the shield end pre-determined distance Determine shield stabilization zone;
Shield strengthening construction is carried out by three axes agitating pile and high-pressure rotary jet grouting pile in the shield stabilization zone;
Multiple dewatering wells are set with preset interval in tunnel two sides;
In the case where the shield cutter of the shield machine is tunneled to portal, stop shield driving, in the shield tail of the shield machine Carry out the construction of first time secondary grouting;
After first time secondary grouting construction is completed, continue the shield driving;
In the case where the shield machine is tunneled to last ring of the tunnel, stop the shield driving, in the shield machine Shield tail carry out second of secondary grouting construction;
After second of secondary grouting construction is completed, continue the shield driving, until the shield tail of the shield machine is de- Shield, which is reached, from last endless tube piece receives bracket;
Gap between last described endless tube piece and portal steel loop is blocked using steel plate;
Mortar depositing construction is carried out in gap between last described endless tube piece and the portal steel loop, to complete shield reception.
2. the method according to claim 1, wherein it is described in the shield stabilization zone by three axes agitating pile and High-pressure rotary jet grouting pile carries out shield strengthening construction, comprising:
The shield stabilization zone is in turn divided into the first stabilization zone and the second stabilization zone along tunnel piercing direction;
Three axes agitating pile construction is carried out in first stabilization zone respectively, high-pressure rotary jet grouting pile is carried out in second stabilization zone and applies Work.
3. according to the method described in claim 2, it is characterized in that, described apply in first stabilization zone progress three axes agitating pile Work, comprising:
First stabilization zone by earth's surface to tunnel inverted arch next coming in order is divided into the first weak stabilization zone and including the tunnel The last the first stabilization zone in road;
Three axes agitating pile construction is carried out in the last the first stabilization zone and the first weak stabilization zone respectively, wherein the last the first The cement mixing content of stabilization zone is 20%, and the cement mixing content of the first weak stabilization zone is 7%.
4. according to the method described in claim 3, it is characterized in that, two neighboring three axes agitating pile mutually overlaps a hole.
5. the method according to claim 1, wherein the method also includes:
After the shield stabilization zone carries out shield strengthening construction by three axes agitating pile and high-pressure rotary jet grouting pile, in the tunnel Two sides are set with preset interval before multiple dewatering wells:
Multiple coring holes are vertically set in the portal;
Detect the compression strength and infiltration coefficient of the Kong Xin in the coring hole;
In the case where the compression strength is greater than preset strength and infiltration coefficient and is less than preset value, the coring hole from it is interior to Detection pipe and valve for observing the portal geological condition is successively installed outside.
6. the method according to claim 1, wherein
The shield tail in the shield machine carries out the construction of first time secondary grouting, comprising:
The first time secondary grouting construction is carried out in the second ring and third ring of the shield machine shield tail;
The shield tail in the shield machine carries out second of secondary grouting construction, comprising:
Second of secondary grouting construction is carried out in the second ring and third ring of the shield machine shield tail.
7. according to the method described in claim 6, it is characterized in that, first time secondary grouting construction and described second The injection slurry of secondary grouting construction includes cement and waterglass.
8. the method according to claim 1, wherein the method also includes:
It is described in last described endless tube after blocking the gap between last described endless tube piece and portal steel loop using steel plate In gap between piece and the portal steel loop before progress mortar depositing construction:
Gas vent is opened up on the steel plate;
In valve of the gas vent installation for exhaust.
CN201910630189.5A 2019-07-12 2019-07-12 Nearly section water-rich silty sand layers shield machine receives construction method Pending CN110344834A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910630189.5A CN110344834A (en) 2019-07-12 2019-07-12 Nearly section water-rich silty sand layers shield machine receives construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910630189.5A CN110344834A (en) 2019-07-12 2019-07-12 Nearly section water-rich silty sand layers shield machine receives construction method

Publications (1)

Publication Number Publication Date
CN110344834A true CN110344834A (en) 2019-10-18

Family

ID=68175198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910630189.5A Pending CN110344834A (en) 2019-07-12 2019-07-12 Nearly section water-rich silty sand layers shield machine receives construction method

Country Status (1)

Country Link
CN (1) CN110344834A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111396067A (en) * 2020-03-30 2020-07-10 中铁十二局集团有限公司 Comprehensive shield steel sleeve receiving construction method in complex environment
CN111411970A (en) * 2020-03-25 2020-07-14 中铁三局集团有限公司 Shield starting construction method under water-rich sand layer geological condition
CN111734420A (en) * 2020-06-16 2020-10-02 中建三局基础设施建设投资有限公司 Water-rich stratum shield underwater receiving method provided with tunnel portal mortar retaining wall
CN112031794A (en) * 2020-09-11 2020-12-04 中铁四局集团第二工程有限公司 Shield receiving construction method for approaching existing subway operation line in water-rich silt stratum
CN114960711A (en) * 2021-02-24 2022-08-30 中交隧道工程局有限公司 End reinforcement construction method based on shield tunneling

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07259078A (en) * 1994-03-22 1995-10-09 Nkk Corp Steel material for shield opening, constructing method for underground continuous wall, and boring method for pit
CN102518441A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Method for constructing karren stratum shield tunnel
CN106285693A (en) * 2016-08-31 2017-01-04 中铁十六局集团北京轨道交通工程建设有限公司 A kind of shield steel bushing airtight reception construction method
CN108798686A (en) * 2018-06-27 2018-11-13 中铁十二局集团有限公司 Tunneling boring water-rich sand layer shield receives construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07259078A (en) * 1994-03-22 1995-10-09 Nkk Corp Steel material for shield opening, constructing method for underground continuous wall, and boring method for pit
CN102518441A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Method for constructing karren stratum shield tunnel
CN106285693A (en) * 2016-08-31 2017-01-04 中铁十六局集团北京轨道交通工程建设有限公司 A kind of shield steel bushing airtight reception construction method
CN108798686A (en) * 2018-06-27 2018-11-13 中铁十二局集团有限公司 Tunneling boring water-rich sand layer shield receives construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孟善宝: "承压水砂层盾构钢套筒接收施工技术", 《价值工程》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111411970A (en) * 2020-03-25 2020-07-14 中铁三局集团有限公司 Shield starting construction method under water-rich sand layer geological condition
CN111411970B (en) * 2020-03-25 2022-05-13 中铁三局集团有限公司 Shield starting construction method under geological condition of water-rich sand layer
CN111396067A (en) * 2020-03-30 2020-07-10 中铁十二局集团有限公司 Comprehensive shield steel sleeve receiving construction method in complex environment
CN111734420A (en) * 2020-06-16 2020-10-02 中建三局基础设施建设投资有限公司 Water-rich stratum shield underwater receiving method provided with tunnel portal mortar retaining wall
CN111734420B (en) * 2020-06-16 2021-11-12 中建三局基础设施建设投资有限公司 Water-rich stratum shield underwater receiving method provided with tunnel portal mortar retaining wall
CN112031794A (en) * 2020-09-11 2020-12-04 中铁四局集团第二工程有限公司 Shield receiving construction method for approaching existing subway operation line in water-rich silt stratum
CN114960711A (en) * 2021-02-24 2022-08-30 中交隧道工程局有限公司 End reinforcement construction method based on shield tunneling

Similar Documents

Publication Publication Date Title
CN110344834A (en) Nearly section water-rich silty sand layers shield machine receives construction method
CN104278993B (en) A kind of bias voltage Skew Tunnel enters the constructional method in hole
CN111119940B (en) Grouting construction treatment method
CN106285693B (en) A kind of closed reception construction method of shield steel bushing
CN109098733B (en) Rapid grouting reinforcement method for large-section tunnel in fracture zone rock stratum
CN103899323B (en) A kind of construction method of shield crossing rail yard
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN105484269B (en) Foundation pit enclosure structure seepage prevention and treatment construction method under blasting condition
CN202117686U (en) Surrounding rock advanced support structure for railway tunnel at deep-buried watery and weak stratums
CN204253056U (en) A kind of shield machine export & import reinforcing structure
CN110130936B (en) Construction method for sudden encountering untreated karst cave or crack in shield tunneling process
CN105525619B (en) A kind of water rich strata bored tunnel occlusion pipe curtain
CN105297741A (en) Prevention method for foundation pit retaining structure hole-punching and water-gushing caused by blast of stratum with soft upper portion and hard lower portion
CN109944600B (en) Shield receiving end reinforcing construction method
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN111593726A (en) Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing
CN211500658U (en) Shallow tunnel supporting construction that nearly connects that buries suitable for sand ground
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN105019913A (en) Base rock uplift region shielding tool-changing in-situ reinforcement method
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN108999218A (en) Antiseepage panel wall construction method is passed through in the construction of shield section
CN203796288U (en) Water seepage prevention structure used for shield entrance door employing SMW piles
CN206529779U (en) A kind of foundation pit enclosure structure of multiple tracks diaphram wall combination stratum consolidation and precipitation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191018

RJ01 Rejection of invention patent application after publication