CN114941266A - Reusable temporary road construction process - Google Patents

Reusable temporary road construction process Download PDF

Info

Publication number
CN114941266A
CN114941266A CN202210420780.XA CN202210420780A CN114941266A CN 114941266 A CN114941266 A CN 114941266A CN 202210420780 A CN202210420780 A CN 202210420780A CN 114941266 A CN114941266 A CN 114941266A
Authority
CN
China
Prior art keywords
prefabricated
road
temporary road
construction
roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202210420780.XA
Other languages
Chinese (zh)
Inventor
王飞龙
周崇旭
安雷刚
任帅
龙飞
辛佳洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNNC Huachen Construction Engineering Co Ltd
Original Assignee
CNNC Huachen Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNNC Huachen Construction Engineering Co Ltd filed Critical CNNC Huachen Construction Engineering Co Ltd
Priority to CN202210420780.XA priority Critical patent/CN114941266A/en
Publication of CN114941266A publication Critical patent/CN114941266A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/08Temporary pavings
    • E01C9/086Temporary pavings made of concrete, wood, bitumen, rubber or synthetic material or a combination thereof
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/06Pavings made of prefabricated single units made of units with cement or like binders
    • E01C5/08Reinforced units with steel frames
    • E01C5/085Reinforced units with steel frames on prefabricated supporting structures or prefabricated foundation elements except coverings made of layers of similar elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a reusable temporary road construction process, which relates to the technical field of road construction and comprises the following steps: step 1: blanking a prefabricated outer frame of the temporary road, and welding the outer frame; step 2: prefabricating and welding a lifting ring; and step 3: binding steel bars, pouring prefabricated temporary roads and maintaining; and 4, step 4: treating a roadbed; and 5: hoisting and installing the prefabricated road; step 6: and (5) hoisting and transferring. The temporary road can be prefabricated in advance, and the construction period can be saved compared with a cast-in-place temporary road; the field is prefabricated and maintained, so that the construction quality of the temporary road can be improved, and the service life is prolonged; the prefabricated road can be quickly transferred, no garbage is generated, and the environment is protected; the prefabricated temporary road can be repeatedly used for many times, and the investment cost of the temporary road is saved.

Description

Reusable temporary road construction process
Technical Field
The invention relates to the technical field of road construction, in particular to a reusable temporary road construction process.
Background
In industry and civil building engineering field, for convenient construction, the interim construction road that generally needs to be built, its main function is for providing the current road for the construction overall process, at present, what domestic interim construction road mostly adopted is disposable concrete pavement, the construction time is longer, the construction operation degree of difficulty is big, after engineering major structure construction and installation are accomplished basically, interim construction road will be demolishd, the broken back of demolising of road can produce more rubbish, the broken clearance time of road is long, and can cause the waste of material.
Disclosure of Invention
Based on the above, the invention aims to provide a construction process for a recyclable temporary road, so as to solve the technical problems of long construction time, high construction operation difficulty, long road crushing and cleaning time, material waste and the like easily caused by the traditional temporary road.
In order to achieve the purpose, the invention provides the following technical scheme: a construction process for a reusable temporary road comprises the following steps:
step 1: blanking a prefabricated outer frame of the temporary road, and welding the outer frame;
prefabricating the temporary road in two frames, prefabricating concrete blocks with specific thickness, firstly, blanking angle steel, using reinforcing steel bars as supports, and welding the angle steel into an iron frame by an upper layer and a lower layer;
step 2: prefabricating and welding a lifting ring;
cutting round steel into a specific length, manufacturing the round steel into embedded hanging rings with two straight ends and a bent middle part on a steel bar bending machine, placing the hanging rings on angle steel at the lower part of a prefabricated frame, welding and connecting two straight sections of the hanging rings with the angle steel, and symmetrically installing another hanging ring at the opposite angle;
and step 3: binding reinforcing steel bars, pouring prefabricated temporary roads and maintaining;
paving a plastic film in a prefabricated site, stably placing an outer frame welded in advance above the plastic film, binding a single-layer net piece above a lower-layer prefabricated frame, installing stirrup steel bars, binding upper steel bars, installing a template with a specific height at the top of a hanging ring, pouring commercial concrete after all work checks are qualified, performing concrete vibration and surface collection work in the process, and performing water spraying maintenance after the concrete is initially set;
and 4, step 4: treating a roadbed;
carrying out roadbed treatment in advance in the concrete pavement prefabricating process, carrying out measurement and paying-off on an original site according to a road layout drawing, leveling the site, compacting the roadbed by a road roller, and using a cutting ring sampling method to make a soil compaction coefficient;
and 5: hoisting and installing the prefabricated road;
after the maintenance age of the prefabricated road is reached, hoisting the prefabricated road into a transport vehicle by using a truck-mounted crane, placing the prefabricated road on the plane in the transport vehicle, separating an upper layer and a lower layer by using a spacer, standing the truck-mounted crane outside a roadbed during field hoisting, arranging a warning band in a hoisting operation range during installation, preparing an installer for correcting the elevation of the roadbed at any time during the installation process, and leveling the elevation of the top of the roadbed;
step 6: hoisting and transferring;
and after the temporary road is used, quickly transferring the temporary road.
The invention further provides that in the step 1, the width of the temporary road in the construction site is 6m, the thickness of the precast concrete block is 3000mm x 200mm, the size of the angle steel is 50mm x 5mm, and the size of the iron frame is 3000mm x 200 mm.
The invention is further set in the step 2, the diameter of the round steel is 16mm, the round steel is cut into a length of 1000mm, the middle of the round steel is bent up by 180mm, the top of the hanging ring is 10mm lower than the top mark of the prefabricated frame, two flat and straight sections of the hanging ring are completely overlapped with the angle steel, and the flat and straight sections of the hanging ring are fully welded with two surfaces of the angle steel.
The invention is further provided that in the step 3, the size of the single-layer net sheet is phi 14@200, the size of the binding upper reinforcing steel bar is phi 14@200, and the size of the installation template is 100mm x 50 mm.
The invention is further configured that, in the step 4, the compaction coefficient is ensured to be not lower than 0.95.
The invention is further set in the step 5, the leveling error of the top elevation of the pavement is controlled within +/-5 mm, and tight abutted seams are ensured.
The invention is further arranged that in the step 6, the step 4 is also adopted to process the roadbed in place when the temporary road part is built, and the hoisting installation is carried out according to the step 5.
In summary, the invention mainly has the following beneficial effects:
1. the temporary road can be prefabricated in advance, and the construction period can be shortened compared with a cast-in-place temporary road.
2. The invention can improve the construction quality of temporary roads and prolong the service life by performing and maintaining on the field.
3. The prefabricated road can be quickly transferred, no garbage is generated, and the environment is protected.
4. The prefabricated temporary road can be repeatedly used for many times, and the temporary road investment cost is saved.
Drawings
FIG. 1 is a diagram of a temporary road pre-fabricated frame according to the present invention;
FIG. 2 is a view of the temporary road pavement of the present invention;
fig. 3 is a flow chart of the operation of the present invention.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. The embodiments described below with reference to the accompanying drawings are illustrative only for the purpose of explaining the present invention, and are not to be construed as limiting the present invention.
The following describes an embodiment of the present invention based on its overall structure.
A construction process for a reusable temporary road comprises the following steps:
step 1: blanking of prefabricated outer frame of temporary road and welding of outer frame
Welding 3000mm, 3000mm and 200mm double-layer prefabricated frames according to design requirements, firstly cutting and blanking finished angle steels of 50mm, 50mm and 5mm, pre-assembling the angle steel prefabricated frames after blanking is finished, ensuring equal side length and equal diagonal lines, emphasizing corner welding quality in the welding process, ensuring full welding of corner lap joints and connecting parts, timely cleaning welding slag off after welding is finished, connecting the two layers of prefabricated frames, and performing four-corner welding connection by using 190mm long steel bars which are cut in advance, ensuring that outer frames of the two layers of prefabricated frames are flush and level, and checking by using a leveling rod in the process;
step 2: prefabricating and welding the hoisting ring
Cutting a finished phi 16 round steel into a straight bar with the length of 1000mm, manufacturing the round steel into embedded lifting rings with two straight ends and 180mm high middle bent (the top of each lifting ring is lower than the top of a prefabricated frame by 10mm), attaching the lifting rings to the lower angle steel of the prefabricated frame, symmetrically arranging the lifting rings at two positions, ensuring that the two straight sections of each lifting ring are completely attached to the angle steel in the lifting ring placement process, then welding and connecting the two straight sections of each lifting ring with the angle steel, ensuring that the two straight sections of each lifting ring and the two sides of the surface of the angle steel are fully welded, symmetrically installing the other lifting ring at opposite angles, and ensuring the firmness and reliability in the lifting ring welding and installation;
and step 3: pouring and maintaining of steel bar binding and prefabricated temporary road
Paving a plastic film on a prefabricated site, stably placing an outer frame welded in advance above the plastic film, binding a single-layer mesh sheet of phi 14@200 above a lower-layer prefabricated frame, installing stirrup steel bars, binding upper phi 14@200 steel bars, installing a template of 100mm in length and 100mm in width and 50mm in height at the top of a lifting ring (preventing the top of the lifting ring from being covered by concrete in the concrete pouring process, facilitating later-stage hoisting), pouring C30 commercial concrete after all work checks and acceptance, performing concrete vibration and surface collection work in the process, and performing water spraying and maintenance after the concrete is initially set;
and 4, step 4: roadbed treatment
The roadbed can be treated in advance in the concrete pavement prefabricating process, the original site is measured and set out according to a road layout drawing, the site is leveled, a road roller compacts the roadbed, a cutting ring sampling method is used for making a soil compaction coefficient, and the compaction coefficient is ensured to be not lower than 0.95;
and 5: hoisting and mounting prefabricated road
After the maintenance age of the prefabricated road is reached, hoisting the prefabricated road into a transport vehicle by using a truck-mounted crane, placing the plane in the transport vehicle, separating an upper layer and a lower layer by using a spacer, standing the truck-mounted crane outside a roadbed during field hoisting, arranging a warning band in a hoisting operation range during installation, preparing installation personnel for correcting the elevation of the roadbed at any time during installation, leveling the elevation of the top of the roadbed, controlling the error within +/-5 mm, and ensuring tight abutted seams;
step 6: hoisting transfer
After the temporary road is used, in order to carry out next process construction as soon as possible, the temporary road needs to be quickly transferred (the traditional temporary road needs to be broken, garbage is transported outside, energy conservation and environmental protection are not facilitated), the temporary road part needs to be built, the roadbed is treated in place in the step 4, and the temporary road part is hoisted and installed according to the step 5.
Although embodiments of this invention have been shown and described, it is to be understood that such embodiments are merely illustrative of and not restrictive on the broad invention, and that any one or more of the described features, structures, materials, or characteristics may be combined in any suitable manner in any one or more embodiments or examples, and that modifications, substitutions, and variations that do not materially contribute to the novel teachings of this invention may be made by those skilled in the art after reading this disclosure without departing from the principles and spirit of this invention, but within the scope of the appended claims.

Claims (7)

1. A construction process for a reusable temporary road is characterized by comprising the following steps: the method comprises the following steps:
step 1: blanking a prefabricated outer frame of the temporary road, and welding the outer frame;
prefabricating the temporary road in two frames, prefabricating concrete blocks with specific thickness, firstly, blanking angle steel, using reinforcing steel bars as supports, and welding the angle steel into an iron frame by an upper layer and a lower layer;
step 2: prefabricating and welding a lifting ring;
cutting round steel into a specific length, manufacturing the round steel into embedded lifting rings with two straight ends and a bent middle part on a steel bar bending machine, placing the lifting rings on angle steel at the lower part of a prefabricated frame, welding and connecting two straight sections of the lifting rings with the angle steel, and symmetrically installing another lifting ring at the opposite angle;
and step 3: binding reinforcing steel bars, pouring prefabricated temporary roads and maintaining;
paving a plastic film in a prefabricated site, stably placing an outer frame welded in advance above the plastic film, binding a single-layer net piece above a lower-layer prefabricated frame, installing stirrup steel bars, binding upper steel bars, installing a template with a specific height at the top of a hanging ring, pouring commercial concrete after all work checks are qualified, performing concrete vibration and surface collection work in the process, and performing water spraying maintenance after the concrete is initially set;
and 4, step 4: treating a roadbed;
carrying out roadbed treatment in advance in the concrete pavement prefabricating process, carrying out measurement and paying-off on an original site according to a road layout drawing, leveling the site, compacting the roadbed by a road roller, and using a cutting ring sampling method to make a soil compaction coefficient;
and 5: hoisting and installing the prefabricated road;
after the maintenance age of the prefabricated road is reached, hoisting the prefabricated road into a transport vehicle by using a truck-mounted crane, placing the prefabricated road on the plane in the transport vehicle, separating an upper layer and a lower layer by using a spacer, standing the truck-mounted crane outside a roadbed during field hoisting, arranging a warning band in a hoisting operation range during installation, preparing an installer for correcting the elevation of the roadbed at any time during the installation process, and leveling the elevation of the top of the roadbed;
step 6: hoisting and transferring;
and after the temporary road is used, quickly transferring the temporary road.
2. A process for the construction of a reusable temporary road according to claim 1, characterized in that: in the step 1, the width of the temporary road in the construction site is 6m, the thickness of the precast concrete block is 3000mm by 200mm, the size of the angle steel is 50mm by 5mm, and the size of the iron frame is 3000mm by 200 mm.
3. A process for the construction of a reusable temporary road according to claim 1, characterized in that: in the step 2, the round steel is 16mm in diameter and cut into 1000mm long, the middle of the round steel is bent up by 180mm, the top of the hanging ring is 10mm lower than the height of the top of the prefabricated frame, two straight sections of the hanging ring are completely overlapped with the angle steel, and the straight sections of the hanging ring are fully welded with two faces of the angle steel face.
4. A process for the construction of a reusable temporary road according to claim 1, characterized in that: in the step 3, the size of the single-layer net sheet is phi 14@200, the size of the upper binding reinforcing steel bar is phi 14@200, and the size of the installation template is 100mm x 50 mm.
5. A process for the construction of a reusable temporary road according to claim 1, characterized in that: and in the step 4, ensuring that the compaction coefficient is not lower than 0.95.
6. A process for the construction of a reusable temporary road according to claim 1, characterized in that: and in the step 5, the leveling error of the top elevation of the pavement is controlled within +/-5 mm, and tight abutted seams are ensured.
7. A process for the construction of a reusable temporary road according to claim 1, characterized in that: and in the step 6, constructing the temporary road part, treating the roadbed in place by adopting the step 4, and hoisting and installing according to the step 5.
CN202210420780.XA 2022-04-20 2022-04-20 Reusable temporary road construction process Withdrawn CN114941266A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210420780.XA CN114941266A (en) 2022-04-20 2022-04-20 Reusable temporary road construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210420780.XA CN114941266A (en) 2022-04-20 2022-04-20 Reusable temporary road construction process

Publications (1)

Publication Number Publication Date
CN114941266A true CN114941266A (en) 2022-08-26

Family

ID=82907838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210420780.XA Withdrawn CN114941266A (en) 2022-04-20 2022-04-20 Reusable temporary road construction process

Country Status (1)

Country Link
CN (1) CN114941266A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116005510A (en) * 2022-12-20 2023-04-25 中交一公局集团有限公司 Construction method of chessboard type mixed pavement of automobile test field

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003313803A (en) * 2002-04-19 2003-11-06 Gisho Lee Prefabricated cement concrete slab for pavement
US20060034652A1 (en) * 2004-08-13 2006-02-16 Sanders Mark E Temporary driveway
CN103590299A (en) * 2013-11-18 2014-02-19 北京中建建筑科学研究院有限公司 Construction method of reusable temporary road plate
CN105563640A (en) * 2015-12-30 2016-05-11 江海燕 Manufacturing process for environment-friendly construction modularization tool type temporary road plate block
CN206359848U (en) * 2016-11-14 2017-07-28 青岛新世纪预制构件有限公司 Detachably reuse prefabricated temporary road
CN210657852U (en) * 2019-09-16 2020-06-02 中冶建工集团有限公司 Prefabricated road deck and temporary road structure
CN210946354U (en) * 2019-10-28 2020-07-07 河北建设集团股份有限公司 Temporary road with in-situ prefabricated reinforced concrete prefabricated slab

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003313803A (en) * 2002-04-19 2003-11-06 Gisho Lee Prefabricated cement concrete slab for pavement
US20060034652A1 (en) * 2004-08-13 2006-02-16 Sanders Mark E Temporary driveway
CN103590299A (en) * 2013-11-18 2014-02-19 北京中建建筑科学研究院有限公司 Construction method of reusable temporary road plate
CN105563640A (en) * 2015-12-30 2016-05-11 江海燕 Manufacturing process for environment-friendly construction modularization tool type temporary road plate block
CN206359848U (en) * 2016-11-14 2017-07-28 青岛新世纪预制构件有限公司 Detachably reuse prefabricated temporary road
CN210657852U (en) * 2019-09-16 2020-06-02 中冶建工集团有限公司 Prefabricated road deck and temporary road structure
CN210946354U (en) * 2019-10-28 2020-07-07 河北建设集团股份有限公司 Temporary road with in-situ prefabricated reinforced concrete prefabricated slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116005510A (en) * 2022-12-20 2023-04-25 中交一公局集团有限公司 Construction method of chessboard type mixed pavement of automobile test field
CN116005510B (en) * 2022-12-20 2024-04-26 中交一公局集团有限公司 Construction method of chessboard type mixed pavement of automobile test field

Similar Documents

Publication Publication Date Title
CN105563640A (en) Manufacturing process for environment-friendly construction modularization tool type temporary road plate block
CN210975404U (en) Composite assembled road surface board
CN108130837A (en) A kind of prefabricated road plate and its construction method
CN103334359B (en) Prefabricated reinforced concrete pavement plate and pavement construction method
CN105603843A (en) Assembled reinforced concrete prefabricated pavement slab and construction method thereof
CN108086353B (en) Hollow wall plate mixed prefabricated assembly type comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof
CN102619152A (en) Split mounting type prefabricated reinforced concrete construction temporary road
CN106835887A (en) Prefabricated board temporary road and its construction method
CN102454239A (en) Precast slab construction member
CN108193712A (en) Factory construction device and method for components of superposed assembly type pipe gallery structure system
CN114941266A (en) Reusable temporary road construction process
CN110700023A (en) Steel spring floating plate integral ballast bed construction method based on rail engineering
CN107965081A (en) Plastic hollow ball overlaps prefabricated board
CN108571173A (en) Manufacturing and mounting method of fully-assembled sunken floor
CN205443834U (en) Novel reinforced concrete prefabricated section
CN212427210U (en) UHPC-RC combination coincide assembled utility tunnel structure
CN204112712U (en) A kind of side root haunch cast-in-place wall model sheetinstallat device
EP4350074A1 (en) Prefabricated track structure for built-in pump house section in rail transportation and construction method
CN106400838B (en) A kind of city integrated Pipe rack of prefabricated assembled concrete and construction method
CN101761287A (en) Reinforced concrete windowsill coping adverse construction method
CN210288480U (en) Inspection well head reinforcing apparatus in town road pipe network engineering
CN103397778A (en) Method for constructing high-rise commercial and residential building structure transfer floor
CN209759116U (en) Filter plate for denitrification filter tank
CN203768754U (en) Double-layer superimposed pavement
CN203373631U (en) Prefabricated reinforced concrete pavement slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20220826

WW01 Invention patent application withdrawn after publication