CN114808757A - Large-span steel concrete arch bridge cantilever construction structure and method under combined system - Google Patents

Large-span steel concrete arch bridge cantilever construction structure and method under combined system Download PDF

Info

Publication number
CN114808757A
CN114808757A CN202210516353.1A CN202210516353A CN114808757A CN 114808757 A CN114808757 A CN 114808757A CN 202210516353 A CN202210516353 A CN 202210516353A CN 114808757 A CN114808757 A CN 114808757A
Authority
CN
China
Prior art keywords
post
arch ring
pouring
segment
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210516353.1A
Other languages
Chinese (zh)
Other versions
CN114808757B (en
Inventor
蔡岳
田仲初
张祖军
戴业
许斌林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN202210516353.1A priority Critical patent/CN114808757B/en
Publication of CN114808757A publication Critical patent/CN114808757A/en
Application granted granted Critical
Publication of CN114808757B publication Critical patent/CN114808757B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Abstract

The invention discloses a large-span steel concrete arch bridge cantilever construction structure and a method under a connecting sleeve and a combined system, wherein the construction structure comprises a cable-stayed buckling and hanging system, an arch ring segment, a suspension system and a post-cast strip; the suspension system is used for hoisting the arch ring segments, the arch ring segments are prefabricated segments in a factory, all the arch ring segments are connected in sequence, and the connecting positions among all the arch ring segments are used for pouring post-cast strips. The method comprises the steps of hoisting prefabricated sections of an arch ring through hoisting cables of a suspension system, moving the prefabricated sections to an appointed position to perform the construction of assembling the current prefabricated sections, assembling the prefabricated sections and pouring a post-pouring belt, and simultaneously carrying part of load of cantilever sections before tensioning buckling cables and anchor cables, so that the influence of additional bending moment and vertical force generated by the cantilever loads on the deflection of a buckling tower, cable force and the stress of the poured sections is reduced; the cable-stayed system ensures that the line shape and the stress of the finished arch ring segment meet the design requirements by applying initial tension to the anchor cable anchored on the foundation and the buckling tower and the buckling cable anchored on the buckling tower and the arch ring segment.

Description

Large-span steel concrete arch bridge cantilever construction structure and method under combined system
Technical Field
The invention relates to a construction structure and a construction method of a large-span steel concrete arch bridge cantilever under a combined system, and belongs to the field of civil engineering bridge construction.
Background
The western mountainous area is dangerous in terrain, many canyons exist, the geological condition is complex, the construction cost of the deck type reinforced concrete arch bridge is low, the maintenance is simple, meanwhile, the reasonable span can span across the canyons without arranging pier seats in the middle, and a plurality of advantages cause the arch bridge to be widely applied. In the construction of arch rings of arch bridges, the construction process of obliquely pulling buckles hanging cantilevers is widely popularized in the construction process of domestic large-span reinforced concrete arch bridges, the construction method mainly takes 'moving hanging baskets, binding reinforcing steel bars and templates, pouring concrete, tensioning buckles and anchor cables' as a segment pouring program, and the construction of the arch rings is continuously and circularly completed according to the construction sequence. In actual construction, before the buckles and the anchor cables at the current casting section position are not tensioned, the self weight of the current section and the load of a temporary structure are borne by a cast arch ring and a cable-stayed buckle hanging system, and the additional vertical load and the additional bending moment need to be added with a part of tensioning force additionally by the cast anchor cables to enable the buckling tower to generate reverse deviation, so that the buckling tower deviation meets the 5cm requirement of the standard requirement when the current section is cast. Meanwhile, in the construction process, improper control of the guy cable can cause one side of the arch ring concrete to be pulled to generate tensile stress, and the tensile stress exceeds the tensile strength of the concrete to cause the concrete to crack. Due to the reasons, the length and the weight of the cast-in-place segment of the arch bridge are limited to a certain extent, more cast-in-place segments need to be divided in the design process, so that the construction period is increased continuously, and the problems are more prominent along with the continuous increase of the span of the arch bridge.
Disclosure of Invention
The invention provides a connecting sleeve, which is used for realizing the connection between reinforcing steel bars and further used for the construction of a large-span reinforced concrete arch bridge; the cantilever construction structure of the large-span reinforced concrete arch bridge under the combined system is provided for constructing a construction structure for constructing the large-span reinforced concrete arch bridge by adopting the prefabricated sections and further matching with a construction method for construction.
The technical scheme of the invention is as follows: a connecting sleeve comprises a sleeve 18 and a sleeve connecting piece 19, wherein two ends of the sleeve connecting piece 19 are respectively connected with one end of one sleeve 18, and the sleeve 18 can rotate around the sleeve connecting piece 19.
The sleeve connecting piece 19 comprises a cylindrical body, and two ends and the middle part of the cylindrical body are respectively provided with a cylindrical rotating body and a cylindrical positioning body which are coaxial; the diameter of the cylindrical rotating body and the diameter of the cylindrical positioning body are both larger than the diameter of the cylindrical body.
According to another aspect of the embodiment of the invention, the invention also provides a large-span reinforced concrete arch bridge cantilever construction structure under the combined system, which comprises a cable-stayed buckling system, an arch ring segment, a suspension system and a post-cast strip 11; the suspension system is used for hoisting arch ring segments, the arch ring segments are prefabricated segments in a factory, all the arch ring segments are connected in sequence, the connecting positions among all the arch ring segments are used for pouring post-cast strips 11, and n-1 post-cast strips 11 are arranged on n arch ring segments.
The suspension system comprises a bearing cable anchoring system 1, a cable tower 2, a bearing cable 3 and a hoisting cable 4; the hoisting cable 4 hung on the bearing cable 3 traveling crown block is used for hoisting the arch ring segment, the bearing cable 3 realizes the steering effect through a saddle at the top of the tower 2, and the two ends of the bearing cable 3 are fixed through a bearing cable anchoring system 1.
The n-1 post-cast belts are composed of s delayed casting post-cast belts and n-1-s current casting post-cast belts.
The connection between the arch ring sections is specifically as follows: the current prefabricated segment 10 and the finished prefabricated segment 9 are temporarily fixed through a connecting screw rod 14, and the current prefabricated segment 10 and a main rib 16 of the finished prefabricated segment 9 are connected through a connecting sleeve 17.
According to another aspect of the embodiments of the present invention, there is also provided a method for constructing a cantilever of a long-span reinforced concrete arch bridge in a combined system, including:
s1, establishing a finite element model in the construction process of the large-span steel concrete arch bridge;
s2, obtaining the delayed pouring post-cast strip position of the arch ring segment and the current pouring post-cast strip position according to the finite element model in the construction process of the large-span steel concrete arch bridge;
s3, hoisting the prefabricated segment through a suspension system, moving to an assembling position, and connecting the prefabricated segment 9 with the current prefabricated segment 10; wherein, the prefabricated sections are sequentially installed from two ends to the middle;
s4, pouring a post-cast strip:
if the connection position of the prefabricated segment 9 and the current prefabricated segment 10 is the position of the current casting post-cast strip, directly installing a template after the prefabricated segment 9 and the current prefabricated segment 10 are connected, and casting the post-cast strip 11 by selecting concrete with the strength not lower than the mark strength of the arch ring concrete; after pouring, installing a prefabricated segment buckle cable 12 and a prefabricated segment anchor cable 13 on the current prefabricated segment 10, tensioning the cable force to a designed value, and loosening a suspension system; then, performing subsequent construction of the prefabricated sections;
if the connection part of the prefabricated segment 9 and the current prefabricated segment 10 is the post-cast strip delayed pouring part, after the prefabricated segment 9 and the current prefabricated segment 10 are connected, installing a prefabricated segment buckle cable 12 and a prefabricated segment anchor cable 13 on the current prefabricated segment 10, tensioning the cable force to a designed value, and loosening a suspension system; and directly carrying out construction of subsequent prefabricated sections, and carrying out post-cast strip casting at the position of the delayed casting post-cast strip according to the casting time in the construction stage of the subsequent prefabricated sections.
The method for obtaining the delayed pouring post-cast strip position of the arch ring segment and the current pouring post-cast strip position according to the finite element model in the construction process of the long-span steel concrete arch bridge comprises the following steps:
acquiring tensile stress values of initial arch ring sections at different construction stages according to a finite element model in the construction process of the large-span reinforced concrete arch bridge; the method comprises the following steps that firstly, all arch ring sections are sequentially connected, connecting positions among all arch ring sections are used for forming post-cast belts, n arch ring sections are provided with n-1 post-cast belts, and the n-1 post-cast belts are composed of s post-cast belts which are cast in a delayed mode and n-1-s post-cast belts which are cast at present; the construction stage comprises: assembling arch ring segments, pouring post-cast strips, and tensioning buckles and anchor cables;
selecting the arch ring position where the tensile stress value exceeds the design allowable value as a post-pouring belt of delayed pouring;
if the arch ring position where the tensile stress value exceeds the design allowable value is on the initial ith arch ring segment, adjusting the connection position of the initial (i-1) th arch ring segment and the ith arch ring segment to the position where the tensile stress value of the initial ith arch ring segment exceeds the design allowable value to serve as a post-cast strip for delayed casting; or adjusting the connecting positions of the initial ith arch ring segment and the (i + 1) th arch ring segment to the position where the tensile stress value of the initial ith arch ring segment exceeds the design allowable value to be used as a position of a delayed casting post-cast strip, and keeping the connecting positions of the rest arch ring segments unchanged to be used as the position of the current casting post-cast strip;
if the arch ring position where the tensile stress value exceeds the design allowable value is located at the connection position of the initial arch ring segment and the segment, the connection position of each arch ring segment is unchanged, the connection position of the initial arch ring segment and the segment where the tensile stress value exceeds the design allowable value is used as a post-pouring delay strip, and the connection positions of the other arch ring segments are used as the post-pouring current strip.
The pouring time is as follows: and in the subsequent construction stage, maintaining the tensile stress value smaller than the design requirement value.
Selecting a critical position of the pouring opportunity as the opportunity for pouring the post-pouring belt at the position of the delayed pouring post-pouring belt; and the critical position of the pouring opportunity is the initial stage of the pouring opportunity.
The invention has the beneficial effects that: the construction of the long-span reinforced concrete arch bridge segment is carried out through a 'suspension-cable-stayed' combined system structure, the arch ring prefabricated segment is lifted through a hoisting cable of a suspension system, the prefabricated segment is moved to a specified position to carry out the current prefabricated segment, the prefabricated segment assembly and the post-cast strip pouring construction, and simultaneously, a part of load of the cantilever segment is borne before tensioning of a buckling cable and an anchor cable, so that the influence of additional bending moment and vertical force generated by the cantilever load on the deflection of a buckling tower, cable force and the stress of the poured segment is reduced; the cable-stayed system ensures that the line shape and the stress of the finished arch ring segment meet the design requirements by applying initial tension to the anchor cable anchored on the foundation and the buckling tower and the buckling cable anchored on the buckling tower and the arch ring segment. Furthermore, through the concrete prefabrication construction process, the arch ring segments can be manufactured in batch in advance, the construction period and the cost are greatly saved compared with the traditional cantilever pouring construction process, and meanwhile, the influence of contraction and creep of traditional cast-in-place concrete on the line shape and the stress can be effectively reduced through the segment prefabrication. And furthermore, post-cast strips are arranged among the prefabricated sections, later-stage concrete pouring is carried out to ensure connection among the sections, the post-cast strips are constructed by concrete with the strength grade not lower than that of the prefabricated sections, the defects of insufficient wet joint strength, poor connection performance and the like of the traditional precast beam sections are overcome by the post-cast strips, meanwhile, the post-cast strips can be arranged at the position where the arch ring is easy to crack, and concrete pouring construction is carried out when the post-cast strips are integrally pressed, so that cracks in the arch ring construction process can be effectively avoided, and the overall safety of the structure is improved.
Drawings
FIG. 1 is a schematic view of a coupling sleeve construction;
FIG. 2 is a cross-sectional view of the connecting sleeve;
FIG. 3 is a schematic view of a cantilever construction structure of a large-span reinforced concrete arch bridge under a combined system;
FIG. 4 is a partial enlarged schematic view of a cantilever construction structure of a large-span reinforced concrete arch bridge under a combination system;
FIG. 5 is a schematic view showing a construction process of a cantilever of a long-span reinforced concrete arch bridge under an assembly system;
FIG. 6 is a schematic view of a cantilever construction process of a large-span reinforced concrete arch bridge under an assembly system;
FIG. 7 is a third schematic view of a cantilever construction process of a large-span reinforced concrete arch bridge under a combined system;
FIG. 8 is a fourth schematic view of the construction process of the cantilever of the large-span reinforced concrete arch bridge under the combined system;
the reference numbers in the figures are: 1-a load bearing cable anchoring system; 2-a cable tower; 3-a load bearing cable; 4-hoisting cable; 5, anchor cable; 6-a buckle cable; 7-rear anchor system; 8-buckling the tower; 9-finished prefabricated segment; 10-current prefabricated segment; 11-post-cast strip; 12-prefabricated segment lanyard 12; 13-prefabricating a segment anchor cable; 14-connecting screw; 15-a connecting plate; 16-main reinforcement; 17-a connecting sleeve; 18-a sleeve; 19-a socket connection.
Detailed Description
The invention will be further described with reference to the following figures and examples, but the scope of the invention is not limited thereto.
Example 1: as shown in fig. 1 to 8, a connecting sleeve 17 comprises a sleeve 18 and a sleeve connecting piece 19, wherein both ends of the sleeve connecting piece 19 are respectively connected with one end of one sleeve 18, and the sleeve 18 can rotate around the sleeve connecting piece 19. The other end of the sleeve 18 is used for connection to the reinforcement.
Further, the sleeve connecting piece 19 may be provided to include a cylindrical body, and the two ends and the middle part of the cylindrical body are respectively provided with a cylindrical rotating body and a cylindrical positioning body which are coaxial; the diameter of the cylindrical rotating body and the diameter of the cylindrical positioning body are both larger than the diameter of the cylindrical body.
The left bottom surface and the right bottom surface of the cylindrical positioning body are respectively attached to the reinforcing steel bars, the sleeves 18 are in clearance fit with the sleeve connecting pieces 19, the sleeves 18 can rotate independently around the sleeve connecting pieces 19, in the construction process, an operator only needs to twist the sleeves 18 to complete the occlusion between the main reinforcing steel bars and the sleeves 18, and the cylindrical positioning body is independent of each other, does not interfere with each other and is high in safety.
According to another aspect of the embodiment of the invention, the invention also provides a large-span reinforced concrete arch bridge cantilever construction structure under the combined system, which comprises a cable-stayed buckling system, an arch ring segment, a suspension system and a post-cast strip 11; the suspension system is used for hoisting arch ring segments, the arch ring segments are prefabricated segments in a factory, all the arch ring segments are connected in sequence, the connecting positions among all the arch ring segments are used for pouring post-cast strips 11, and n-1 post-cast strips 11 are arranged on n arch ring segments.
Further, the suspension system can be arranged to comprise a bearing cable anchoring system 1, a cable tower 2, a bearing cable 3 and a hoisting cable 4; the hoisting cable 4 hung on the travelling crane is used for hoisting the arch ring segment, the travelling crane travels on the bearing cable 3, the bearing cable 3 realizes steering action through a saddle at the top of the tower of the cable tower 2, and two ends of the bearing cable 3 are fixed through the bearing cable anchoring system 1. In practical application, the suspension system structure is not limited to the structure, the bearing cable 3 can be anchored in a mountain body under the condition that the design sag requirement of the bearing cable 3 is met according to the terrain conditions of two banks, the cable tower 2 is omitted, and the construction period and the cost are reduced. The anchoring system is used for fixing the bearing cable and ensuring the integral stability of the suspension system; the cable tower is used for supporting the bearing cable, providing a steering effect for the bearing cable and simultaneously transmitting part of the load of the bearing cable to the foundation; the bearing cable is used for suspending a main bearing structure of the system and transmitting the whole load of the structure to the anchoring system and the cable tower; the hoisting cable is used for hoisting a heavy object and transferring hoisting load to the bearing cable.
Further, the cable-stayed buckling and hanging system can be arranged to comprise an anchor cable 5, a buckling cable 6, a rear anchor system 7 and a buckling tower 8; one end of a buckle cable 6 is anchored in the arch ring segment, the other end of the buckle cable 6 is anchored in a buckle tower 8, one end of an anchor cable 5 is fixed through a rear anchor system 7, and the other end of the anchor cable 5 is anchored in the buckle tower 8. The anchor cable is used for balancing the horizontal acting force of the buckling cable on the buckling tower and controlling the buckling tower to deviate; the buckling rope is used for providing tension force for the arch ring segments and ensuring that the stress and deformation of the segments in the construction process can meet the design requirements; the rear anchor system is used for fixing the anchor cable and transmitting the force of the anchor cable to the ground; and the buckling tower is used for supporting buckling cable and anchor cable structures and transferring the load of the cable structures to a foundation.
Further, the n-1 post-cast belts can be formed by s delayed casting post-cast belts and n-1-s current casting post-cast belts.
Further, the connection between the arch ring segments may be specifically: the current prefabricated segment 10 and the finished prefabricated segment 9 are temporarily fixed through a connecting screw rod 14, and the current prefabricated segment 10 and a main rib 16 of the finished prefabricated segment 9 are connected through a connecting sleeve 17.
According to another aspect of the embodiments of the present invention, there is also provided a method for constructing a cantilever of a long-span reinforced concrete arch bridge in a combined system, including:
s1, establishing a finite element model in the construction process of the large-span reinforced concrete arch bridge by adopting finite element software according to the design specification requirements (the requirement of tensile stress of each arch ring, the requirement of safety coefficient of a cable structure and the requirement of deviation of a buckling tower) of the large-span reinforced concrete arch bridge;
s2, obtaining the delayed pouring post-cast strip position of the arch ring segment and the current pouring post-cast strip position according to the finite element model in the construction process of the large-span steel concrete arch bridge;
s3, hoisting the prefabricated segment through a suspension system, moving to an assembling position, and connecting the prefabricated segment 9 with the current prefabricated segment 10; wherein, the prefabricated sections are sequentially installed from two ends to the middle; the prefabricated section 9 is a prefabricated section which is constructed, and the current prefabricated section 10 is a prefabricated section which is constructed currently; the connection of the finished prefabricated segment 9 and the current prefabricated segment 10 is specifically: the current prefabricated segment 10 and the finished prefabricated segment 9 are temporarily fixed through a connecting screw rod 14, and the current prefabricated segment 10 and a main rib 16 of the finished prefabricated segment 9 are connected through a connecting sleeve 17.
S4, pouring a post-cast strip:
if the connection position of the prefabricated segment 9 and the current prefabricated segment 10 is the position of the current casting post-cast strip, directly installing a template after the prefabricated segment 9 and the current prefabricated segment 10 are connected, and casting the post-cast strip 11 by selecting concrete with the strength not lower than the mark strength of the arch ring concrete; after pouring, installing a prefabricated segment buckle cable 12 and a prefabricated segment anchor cable 13 on the current prefabricated segment 10, tensioning the cable force to a designed value, and loosening a suspension system; then, performing subsequent construction of the prefabricated sections; hoisting and connecting the next prefabricated segment by adopting an S3 mode, then executing S4, and performing subsequent construction according to different conditions; in addition, the casting and tensioning of the post-cast strip are constructed according to the sequence, and the post-cast strip can be tensioned in place in one step, so that secondary tensioning is avoided, and the construction steps are reduced.
If the connection part of the prefabricated segment 9 and the current prefabricated segment 10 is the post-cast strip delayed pouring part, after the prefabricated segment 9 and the current prefabricated segment 10 are connected, installing a prefabricated segment buckle cable 12 and a prefabricated segment anchor cable 13 on the current prefabricated segment 10, tensioning the cable force to a designed value, and loosening a suspension system; and directly carrying out construction of subsequent prefabricated sections, and carrying out post-cast strip casting at the position of the delayed casting post-cast strip according to the casting time in the construction stage of the subsequent prefabricated sections. If the current construction is delayed casting of the post-cast strip, after tensioning the current prefabricated segment, hoisting and connecting the next prefabricated segment in an S3 mode and casting the post-cast strip at the current casting post-cast strip; and in the subsequent construction stage, post-cast strip pouring is carried out at the position of the post-cast strip delayed according to the pouring time. For example, if the post-cast strip is delayed to be poured between the 1 st and 2 nd segments, the post-cast strip is poured at the position of the delayed pouring post-cast strip when the 2 nd segment is tensioned, and then the subsequent construction of the 3 rd,.. multideck and n segments is performed, and in the subsequent construction process of the 3 rd,.. multideck and n segments, the post-cast strip is poured at the position of the delayed pouring post-cast strip when the pouring opportunity is reached.
Specifically, prefabricated sections are manufactured in a factory, hanging hooks for hoisting and connecting plates 15 are embedded in the sections (the hanging hooks and the connecting plates can be detached in the later period, for example, a welding machine is used for cutting), beam sections are poured and maintained according to requirements, and after the strength of section concrete meets the requirements, concrete on the end faces of two ends of the sections is subjected to scabbling treatment, so that the occlusion degree between new concrete and old concrete is improved; hoisting the prefabricated segment by a hoisting cable 4 in the suspension system, moving to an assembling position, installing connecting plates at top and bottom plates by connecting screws 14 after reaching a specified position (temporary fixation between the current prefabricated segment 10 and the finished prefabricated segment 9 can be realized by connecting screws), and connecting the finished prefabricated segment 9 with main ribs 16 of the current prefabricated segment 10 by connecting sleeves 17; if the post-cast strip needs to be poured, binding the residual steel bars at the position of the post-cast strip, installing a template, and pouring the post-cast strip by selecting concrete with the strength not lower than the grade strength of the arch ring concrete; and (4) removing the template after the concrete of the post-cast strip 11 reaches the designed strength (such as 80%).
Wherein the currently prefabricated segment 10 is hoisted by means of hoisting ropes 4 in the suspension system, see fig. 5. Moving to an assembling position, installing connecting screw rods 14 at the top plate and the bottom plate after reaching a designated position, and connecting the prefabricated section 9 and a main rib 16 of the current prefabricated section 10 through a double-sleeve connecting piece 17, as shown in fig. 6; installing a prefabricated section buckling cable 12 and a prefabricated section anchor cable 13, and tensioning the cable force to a designed value, as shown in fig. 7; and (5) loosening the hoisting cable 4 to finish the construction of the arch ring segment at a new stage, as shown in figure 8.
Further, the step of obtaining the delayed pouring post-cast strip position of the arch ring segment and the current pouring post-cast strip position according to the finite element model in the construction process of the large-span steel concrete arch bridge comprises the following steps:
acquiring tensile stress values of initial arch ring sections at different construction stages according to a finite element model in the construction process of the large-span reinforced concrete arch bridge; the method comprises the following steps that firstly, all arch ring sections are sequentially connected, connecting positions among all arch ring sections are used for forming post-cast belts, n arch ring sections are provided with n-1 post-cast belts, and the n-1 post-cast belts are composed of s post-cast belts which are cast in a delayed mode and n-1-s post-cast belts which are cast at present; the construction stage comprises: the method comprises the following steps of arch ring segment assembling, post-cast strip casting, tensioning buckle and anchor cable (when a tensile stress numerical value is obtained, the post-cast strip casting is regarded as a front-back cast strip casting stage, then according to the obtained tensile stress numerical value, whether the position of part of the post-cast strip is readjusted or not is determined according to the following mode, and the post-cast strip is classified according to the delayed casting post-cast strip position and the current casting post-cast strip position);
selecting the arch ring position where the tensile stress value exceeds the design allowable value as the post-cast strip of delayed pouring (for example, the tensile stress value exceeds the design allowable value and can be selected as the maximum tensile stress value);
if the arch ring position where the tensile stress value exceeds the design allowable value is on the initial ith arch ring segment, adjusting the connecting position of the initial (i-1) th arch ring segment and the ith arch ring segment to the position where the tensile stress value of the initial ith arch ring segment exceeds the design allowable value to be used as a post-cast strip of delayed pouring (namely, the length of the (i-1) th arch ring segment is lengthened, the length of the ith arch ring segment is shortened, and the rest is unchanged); or adjusting the connecting position of the initial ith arch ring segment and the (i + 1) th arch ring segment to the position where the tensile stress value of the initial ith arch ring segment exceeds the design allowable value to be used as the position of the delayed pouring post-pouring zone (namely the length of the (i + 1) th arch ring segment is increased, the length of the ith arch ring segment is shortened, and the rest of the lengths are unchanged), and using the connecting positions of the rest of the arch ring segments as the position of the current pouring post-pouring zone; when the position of the arch ring where the tensile stress value exceeds the design allowable value is located on the initial ith arch ring section, two different modes are selected at the position of the delayed pouring post-cast strip, so that different design requirements can be met, and the construction is more convenient.
If the position of the arch ring where the tensile stress value exceeds the design allowable value is located at the connecting position of the initial arch ring section and the sections, the connecting position of each arch ring section is unchanged, the connecting position of the initial arch ring section and the sections where the tensile stress value exceeds the design allowable value is used as a position for delayed casting of the post-cast strip, and the connecting positions of the rest of the arch ring sections are used as positions for the current casting of the post-cast strip.
Further, the pouring time can be set as follows: and in the subsequent construction stage, maintaining the tensile stress value smaller than the design requirement value.
Furthermore, a critical position of the casting time can be set as the time for casting the post-cast strip at the position of the post-cast strip in the delayed casting; and the critical position of the pouring opportunity is the initial stage of the pouring opportunity. For example, according to a finite element model in the construction process of the large-span steel concrete arch bridge, the tensile stress values of the initial arch ring segments at different construction stages are obtained through analysis, if the tensile stress value of the position of the post-pouring delayed strip is kept smaller than the design requirement value all the time in the subsequent 10 th stage to the end stage, the 10 th stage is selected as the critical position of the pouring opportunity (the design requirement value can be selected as the value in the compressed state, for example, the tensile stress value of the position of the post-pouring delayed strip is in the compressed state in the subsequent 10 th stage to the end stage, and the 10 th stage is selected as the critical position of the pouring opportunity). By selecting the critical position of the pouring time as the time for pouring the post-pouring belt at the position of the delayed pouring post-pouring belt, the structural stability of the whole construction can be better.
While the present invention has been described in detail with reference to the embodiments shown in the drawings, the present invention is not limited to the embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art.

Claims (10)

1. A coupling sleeve, characterized by: the sleeve comprises a sleeve (18) and a sleeve connecting piece (19), wherein two ends of the sleeve connecting piece (19) are respectively connected with one end of the sleeve (18), and the sleeve (18) can rotate around the sleeve connecting piece (19).
2. A coupling sleeve according to claim 1, wherein: the sleeve connecting piece (19) comprises a cylindrical body, and two ends and the middle part of the cylindrical body are respectively provided with a cylindrical rotating body and a cylindrical positioning body which are coaxial; the diameter of the cylindrical rotating body and the diameter of the cylindrical positioning body are both larger than the diameter of the cylindrical body.
3. The utility model provides a large-span steel concrete arch bridge cantilever construction structure under assembly system, detains system, arch ring section, its characterized in that including drawing to one side: the device also comprises a suspension system and a post-cast strip (11); the suspension system is used for hoisting the arch ring segments, the arch ring segments are prefabricated segments in a factory, all the arch ring segments are connected in sequence, the connecting positions among all the arch ring segments are used for pouring post-cast belts (11), and n-1 post-cast belts (11) are arranged on the n arch ring segments.
4. The cantilever construction structure of the large-span reinforced concrete arch bridge under the combined system according to claim 3, wherein: the suspension system comprises a bearing cable anchoring system (1), a cable tower (2), a bearing cable (3) and a hoisting cable (4); the hoisting cable (4) hung on the traveling crown block of the bearing cable (3) is used for hoisting the arch ring segment, the bearing cable (3) realizes the steering action through a saddle at the top of the tower of the cable tower (2), and the two ends of the bearing cable (3) are fixed through a bearing cable anchoring system (1).
5. The cantilever construction structure of the large-span reinforced concrete arch bridge under the combined system according to claim 3, wherein: the n-1 post-pouring belts are composed of s post-pouring belts for delayed pouring and n-1-s post-pouring belts for current pouring.
6. The cantilever construction structure of the large-span reinforced concrete arch bridge under the combined system according to claim 3, wherein: the connection between the arch ring sections is specifically as follows: the current prefabricated segment (10) and the finished prefabricated segment (9) are temporarily fixed through a connecting screw rod (14), and the current prefabricated segment (10) and a main rib (16) of the finished prefabricated segment (9) are connected together through a connecting sleeve (17).
7. A construction method of a large-span reinforced concrete arch bridge cantilever under a combined system is characterized by comprising the following steps: the method comprises the following steps:
s1, establishing a finite element model in the construction process of the large-span steel concrete arch bridge;
s2, obtaining the delayed pouring post-cast strip position of the arch ring segment and the current pouring post-cast strip position according to the finite element model in the construction process of the large-span steel concrete arch bridge;
s3, hoisting the prefabricated segment through a suspension system, moving to an assembling position, and connecting the prefabricated segment (9) with the current prefabricated segment (10); wherein, the prefabricated sections are sequentially installed from two ends to the middle;
s4, pouring a post-cast strip:
if the connection position of the prefabricated segment (9) and the current prefabricated segment (10) is the position of the current casting post-cast strip, directly installing a template after the prefabricated segment (9) and the current prefabricated segment (10) are connected, and casting the post-cast strip (11) by selecting concrete with the strength not lower than the mark strength of the arch ring concrete; after pouring, installing a prefabricated section buckling rope (12) and a prefabricated section anchor rope (13) on the current prefabricated section (10), tensioning the rope force to a designed value, and loosening a suspension system; then, performing subsequent construction of the prefabricated sections;
if the connection part of the prefabricated segment (9) and the current prefabricated segment (10) is the post-cast strip delayed pouring part, after the prefabricated segment (9) and the current prefabricated segment (10) are connected, installing a prefabricated segment buckle cable (12) and a prefabricated segment anchor cable (13) on the current prefabricated segment (10), tensioning the cable force to a designed value, and loosening a suspension system; and directly carrying out construction of subsequent prefabricated sections, and carrying out post-cast strip casting at the position of the delayed casting post-cast strip according to the casting time in the construction stage of the subsequent prefabricated sections.
8. The cantilever construction method of the long-span reinforced concrete arch bridge under the combined system according to claim 7, wherein the cantilever construction method comprises the following steps: the method for obtaining the delayed pouring post-cast strip position of the arch ring segment and the current pouring post-cast strip position according to the finite element model in the construction process of the long-span steel concrete arch bridge comprises the following steps:
acquiring tensile stress values of initial arch ring sections at different construction stages according to a finite element model in the construction process of the large-span reinforced concrete arch bridge; the method comprises the following steps that firstly, all arch ring sections are sequentially connected, connecting positions among all arch ring sections are used for forming post-cast belts, n arch ring sections are provided with n-1 post-cast belts, and the n-1 post-cast belts are composed of s post-cast belts which are cast in a delayed mode and n-1-s post-cast belts which are cast at present; the construction stage comprises: assembling arch ring segments, pouring post-cast strips, and tensioning buckles and anchor cables;
selecting the arch ring position where the tensile stress value exceeds the design allowable value as a post-pouring belt of delayed pouring;
if the arch ring position where the tensile stress value exceeds the design allowable value is on the initial ith arch ring segment, adjusting the connection position of the initial (i-1) th arch ring segment and the ith arch ring segment to the position where the tensile stress value of the initial ith arch ring segment exceeds the design allowable value to serve as a post-cast strip for delayed casting; or adjusting the connecting positions of the initial ith arch ring segment and the (i + 1) th arch ring segment to the position where the tensile stress value of the initial ith arch ring segment exceeds the design allowable value to be used as a position of a delayed casting post-cast strip, and keeping the connecting positions of the rest arch ring segments unchanged to be used as the position of the current casting post-cast strip;
if the arch ring position where the tensile stress value exceeds the design allowable value is located at the connection position of the initial arch ring segment and the segment, the connection position of each arch ring segment is unchanged, the connection position of the initial arch ring segment and the segment where the tensile stress value exceeds the design allowable value is used as a post-pouring delay strip, and the connection positions of the other arch ring segments are used as the post-pouring current strip.
9. The cantilever construction method of the long-span reinforced concrete arch bridge under the combined system according to claim 7, wherein the cantilever construction method comprises the following steps: the pouring time is as follows: and in the subsequent construction stage, maintaining the tensile stress value smaller than the design requirement value.
10. The cantilever construction method of the long-span reinforced concrete arch bridge under the combined system according to claim 7, wherein the cantilever construction method comprises the following steps: selecting a critical position of the pouring opportunity as the opportunity for pouring the post-pouring belt at the position of the delayed pouring post-pouring belt; and the critical position of the pouring opportunity is the initial stage of the pouring opportunity.
CN202210516353.1A 2022-05-12 2022-05-12 Construction structure and method for cantilever of large-span steel concrete arch bridge under combined system Active CN114808757B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210516353.1A CN114808757B (en) 2022-05-12 2022-05-12 Construction structure and method for cantilever of large-span steel concrete arch bridge under combined system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210516353.1A CN114808757B (en) 2022-05-12 2022-05-12 Construction structure and method for cantilever of large-span steel concrete arch bridge under combined system

Publications (2)

Publication Number Publication Date
CN114808757A true CN114808757A (en) 2022-07-29
CN114808757B CN114808757B (en) 2023-12-05

Family

ID=82513484

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210516353.1A Active CN114808757B (en) 2022-05-12 2022-05-12 Construction structure and method for cantilever of large-span steel concrete arch bridge under combined system

Country Status (1)

Country Link
CN (1) CN114808757B (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206046A (en) * 2013-04-01 2013-07-17 中冶交通工程技术有限公司 Reinforcing bar connector
CN203174890U (en) * 2013-03-19 2013-09-04 中交一公局海威工程建设有限公司 Pre-stressed tendon single pole multi-thread connector for batch production
CN206512932U (en) * 2017-02-28 2017-09-22 中国建筑第八工程局有限公司 Free-standing reinforced bar sleeve
CN108038326A (en) * 2017-12-22 2018-05-15 广西路桥工程集团有限公司 A kind of arch bridge free cantilever erection construction optimization model and optimized calculation method
CN108625272A (en) * 2018-06-27 2018-10-09 中铁二院工程集团有限责任公司 A kind of large-span concrete Arch Bridge Ribs method for controlling crack and construction
CN110700109A (en) * 2019-10-30 2020-01-17 贵州省公路工程集团有限公司 Construction process of concrete arch ring of steel pipe stiff skeleton of bridge
CN111475883A (en) * 2020-04-16 2020-07-31 重庆交通大学 Arch rib line shape control method for large-span steel pipe concrete arch bridge
CN111608084A (en) * 2020-05-29 2020-09-01 中国铁建大桥工程局集团有限公司 Integral prefabrication and assembly construction method for reinforced concrete arch bridge arch ring segments
CN111749113A (en) * 2020-06-05 2020-10-09 中铁建大桥工程局集团第三工程有限公司 Mortise and tenon connection steel-concrete combined assembly type arch bridge and construction method thereof
CN112796198A (en) * 2021-02-04 2021-05-14 长安大学 Hollow arch bridge system connected by UHPC wet joints and construction method
CN113235458A (en) * 2021-05-24 2021-08-10 长沙理工大学 Arch bridge cantilever construction system and method
CN113605253A (en) * 2021-09-17 2021-11-05 中电建十一局工程有限公司 Cable-stayed buckling and hanging linear control installation construction method for large-span steel tube arch bridge

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203174890U (en) * 2013-03-19 2013-09-04 中交一公局海威工程建设有限公司 Pre-stressed tendon single pole multi-thread connector for batch production
CN103206046A (en) * 2013-04-01 2013-07-17 中冶交通工程技术有限公司 Reinforcing bar connector
CN206512932U (en) * 2017-02-28 2017-09-22 中国建筑第八工程局有限公司 Free-standing reinforced bar sleeve
CN108038326A (en) * 2017-12-22 2018-05-15 广西路桥工程集团有限公司 A kind of arch bridge free cantilever erection construction optimization model and optimized calculation method
CN108625272A (en) * 2018-06-27 2018-10-09 中铁二院工程集团有限责任公司 A kind of large-span concrete Arch Bridge Ribs method for controlling crack and construction
CN110700109A (en) * 2019-10-30 2020-01-17 贵州省公路工程集团有限公司 Construction process of concrete arch ring of steel pipe stiff skeleton of bridge
CN111475883A (en) * 2020-04-16 2020-07-31 重庆交通大学 Arch rib line shape control method for large-span steel pipe concrete arch bridge
CN111608084A (en) * 2020-05-29 2020-09-01 中国铁建大桥工程局集团有限公司 Integral prefabrication and assembly construction method for reinforced concrete arch bridge arch ring segments
CN111749113A (en) * 2020-06-05 2020-10-09 中铁建大桥工程局集团第三工程有限公司 Mortise and tenon connection steel-concrete combined assembly type arch bridge and construction method thereof
CN112796198A (en) * 2021-02-04 2021-05-14 长安大学 Hollow arch bridge system connected by UHPC wet joints and construction method
CN113235458A (en) * 2021-05-24 2021-08-10 长沙理工大学 Arch bridge cantilever construction system and method
CN113605253A (en) * 2021-09-17 2021-11-05 中电建十一局工程有限公司 Cable-stayed buckling and hanging linear control installation construction method for large-span steel tube arch bridge

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
何宝;: "零弯矩法计算新型装配式混凝土拱桥扣索索力的适用性研究", 决策探索(中), no. 09 *
周朋;: "龙场渡槽拱圈施工过程数值模拟", 北方交通, no. 06, pages 17 - 19 *
昌力涛;王良彬;陈红娣;龚潇鉴;李建霖;: "65m跨空腹上承式现浇箱形拱桥的钢筋施工技术", 建筑施工, no. 12 *
林福全;: "特大跨径钢筋混凝土拱桥悬拼施工", 公路交通科技(应用技术版), no. 04 *
蓝文兵;: "主拱圈线形偏位对结构内力的影响分析", 世界桥梁, vol. 1, no. 06, pages 163 *
雷运华;: "宁德天池大桥主拱施工技术", 桥梁建设, no. 03 *

Also Published As

Publication number Publication date
CN114808757B (en) 2023-12-05

Similar Documents

Publication Publication Date Title
KR100969005B1 (en) Constructing method of suspension bridge and temporary cable therefor
CN110409304B (en) Cantilever assembling construction method for segment prefabricated bent cap
KR100536489B1 (en) Manufacturing method for prestressed steel composite girder and prestressed steel composite girder thereby
KR101171039B1 (en) Partially and fully earth-anchored cable-stayed bridge using main span prestressing appratus and construction method for the same
CN110042769B (en) Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge
CN101597960B (en) Large-tonnage jack tension construction technology for non-bonded prestressed silo
CN106120568B (en) The construction method of cross a river Main Bridge bridge pier secondary locking temporary consolidation structure
CN110552296B (en) Cable-stayed bridge dismantling construction method
KR20130036890A (en) Tied arched p.s.c girder for bridge and construction method for bridge by it
CN112267367A (en) Method for converting arch-first beam-later system of self-anchored steel box tied arch bridge
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN111364350A (en) Large cantilever arm quickly-mounted light steel-concrete combined bent cap
CN114808722A (en) Construction method of cable-stayed bridge reinforced concrete main beam
CN113897880B (en) Method for cast-in-situ construction of short-span suspension spliced arch bridge of large-span concrete arch bridge
CN112064519B (en) Long platform guy cable hanging basket and main beam segment construction method
CN210621476U (en) Segment prefabricated bent cap cantilever assembling construction device
KR100256511B1 (en) The manufacturing method of a composition prestress-beam having a joint
CN111519530A (en) Pier head type tunnel anchor and construction method
CN114808757A (en) Large-span steel concrete arch bridge cantilever construction structure and method under combined system
CN110528401A (en) Suspended pouring construction hanging basket system
JP3877995B2 (en) How to build a string string bridge
CN104775365B (en) A kind of construction method of cable-stayed bridge
CN107142830A (en) Steel pipe web prestressing force steel reinforced concrete combines main beam structure and construction method
CN206752288U (en) A kind of interior suspension cable compound section bridge
KR101739658B1 (en) steel box girder bridge of wide slab and all slab concrete section used as compression member and slab assemblied with steel box

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant