CN114808654A - A kind of fully prefabricated prefabricated bridge and its construction method - Google Patents
A kind of fully prefabricated prefabricated bridge and its construction method Download PDFInfo
- Publication number
- CN114808654A CN114808654A CN202210543767.3A CN202210543767A CN114808654A CN 114808654 A CN114808654 A CN 114808654A CN 202210543767 A CN202210543767 A CN 202210543767A CN 114808654 A CN114808654 A CN 114808654A
- Authority
- CN
- China
- Prior art keywords
- bridge
- pier
- prefabricated
- bent cap
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 54
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 77
- 239000010959 steel Substances 0.000 claims abstract description 77
- 238000000034 method Methods 0.000 claims abstract description 36
- 239000002131 composite material Substances 0.000 claims abstract description 26
- 238000009434 installation Methods 0.000 claims abstract description 21
- 238000003780 insertion Methods 0.000 claims abstract description 9
- 230000037431 insertion Effects 0.000 claims abstract description 9
- 239000004567 concrete Substances 0.000 claims description 36
- 239000002184 metal Substances 0.000 claims description 15
- 229910052751 metal Inorganic materials 0.000 claims description 15
- 239000010410 layer Substances 0.000 claims description 14
- 239000011241 protective layer Substances 0.000 claims description 8
- 238000003466 welding Methods 0.000 claims description 7
- 238000013461 design Methods 0.000 claims description 6
- 238000012423 maintenance Methods 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 6
- 238000004140 cleaning Methods 0.000 claims description 4
- 239000004570 mortar (masonry) Substances 0.000 claims description 4
- 239000004593 Epoxy Substances 0.000 claims description 3
- 239000004746 geotextile Substances 0.000 claims description 3
- 239000011440 grout Substances 0.000 claims description 3
- 239000011178 precast concrete Substances 0.000 claims description 3
- 238000009417 prefabrication Methods 0.000 claims description 3
- 238000003860 storage Methods 0.000 claims description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims 4
- CURLTUGMZLYLDI-UHFFFAOYSA-N Carbon dioxide Chemical compound O=C=O CURLTUGMZLYLDI-UHFFFAOYSA-N 0.000 claims 2
- 229910052742 iron Inorganic materials 0.000 claims 2
- 238000010009 beating Methods 0.000 claims 1
- 230000000903 blocking effect Effects 0.000 claims 1
- 229910002092 carbon dioxide Inorganic materials 0.000 claims 1
- 239000001569 carbon dioxide Substances 0.000 claims 1
- 239000011248 coating agent Substances 0.000 claims 1
- 239000008267 milk Substances 0.000 claims 1
- 210000004080 milk Anatomy 0.000 claims 1
- 235000013336 milk Nutrition 0.000 claims 1
- 239000002002 slurry Substances 0.000 claims 1
- 238000003892 spreading Methods 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 1
- 238000009736 wetting Methods 0.000 claims 1
- 238000004804 winding Methods 0.000 claims 1
- 238000002513 implantation Methods 0.000 abstract description 6
- 230000005540 biological transmission Effects 0.000 abstract description 2
- 238000009415 formwork Methods 0.000 description 12
- 238000011161 development Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 239000007888 film coating Substances 0.000 description 2
- 238000009501 film coating Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012552 review Methods 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D1/00—Bridges in general
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种全预制装配式桥梁及其施工方法,包括管桩、承台、墩柱、盖梁和桥梁上部结构,所述管桩采用打入法或植入法插打进地下,所述承台设置在插打完毕后的管桩上端,每个承台下方设置四根管桩,所述承台上方与墩柱插接,所述盖梁下部与墩柱固定连接,且盖梁的设置方向与桥梁方向垂直,所述盖梁为钢板组合梁墩顶盖梁或轻型T梁墩顶盖梁,所述盖梁上沿桥梁方向设置有桥梁上部结构,所述桥梁上部结构为窄箱组合梁、钢板组合梁或轻型T梁。全预制装配式桥梁,结构简单、传力路径明确、承载能力强,在事先打入的桩柱搭设施工平台,既能实现全预制装配式桥梁各工序全程可移动不落地平行施工,大大提高了施工的效率。
The invention discloses a fully prefabricated and assembled bridge and a construction method thereof, comprising a pipe pile, a cap, a pier column, a cover beam and a bridge superstructure. The pipe pile is driven into the ground by a driving method or an implantation method, The caps are arranged on the upper end of the pipe piles after the insertion and driving, four pipe piles are arranged under each cap, the upper part of the cap is inserted with the pier column, the lower part of the cover beam is fixedly connected with the pier column, and the cover is connected to the pier column. The installation direction of the beam is perpendicular to the direction of the bridge, the cover beam is a steel plate composite beam pier top cover beam or a light T-beam pier top cover beam, the cover beam is provided with a bridge superstructure along the bridge direction, and the bridge superstructure is a narrow box Composite beam, steel plate composite beam or light T beam. The fully prefabricated bridge has simple structure, clear force transmission path and strong bearing capacity. The construction platform is built on the piles driven in advance, which can realize the whole process of the fully prefabricated bridge. construction efficiency.
Description
技术领域technical field
本发明涉及装配式桥梁技术领域,具体为一种全预制装配式桥梁及其施工方法。The invention relates to the technical field of prefabricated bridges, in particular to a fully prefabricated prefabricated bridge and a construction method thereof.
背景技术Background technique
近几年,各类大型、特大型铁路桥梁陆续建设,而其中也不乏一些桥梁应用装配式施工。国内装配式混凝土桥梁的研究和应用晚于国外,随着近些年随着我国经济的发展,建造了大量的桥梁,应用了很多新技术、新工艺,装配式桥梁也出现的越来越多,但还没有全预制装配式桥梁,而全预制装配式桥梁是高速公路建设迈入新台阶的契机,也是未来桥梁的发展方向。In recent years, all kinds of large and extra-large railway bridges have been built one after another, and some of them are built using prefabricated construction. The research and application of prefabricated concrete bridges in China is later than that in foreign countries. With the development of my country's economy in recent years, a large number of bridges have been built, many new technologies and processes have been applied, and more and more prefabricated bridges have appeared. , but there is no fully prefabricated bridge, and the fully prefabricated bridge is an opportunity for highway construction to enter a new level, and it is also the development direction of future bridges.
全预制装配式桥梁的发展带来了很大的便利,大部分桥梁建造工序在工厂内完成,最大限度降低对施工现场环境的影响,装配式安装可以缩短桥梁的建设周期,但中国装配式桥梁发展较晚,某些技术细节上还不成熟,导致施工时周期依然较长,因此,为了解决上述问题,我们设计出了一种全预制装配式桥梁及其施工方法。The development of fully prefabricated prefabricated bridges has brought great convenience. Most of the bridge construction processes are completed in the factory, which minimizes the impact on the construction site environment. Prefabricated installation can shorten the construction period of bridges, but China's prefabricated bridges The development is relatively late, and some technical details are immature, resulting in a long construction period. Therefore, in order to solve the above problems, we have designed a fully prefabricated bridge and its construction method.
发明内容SUMMARY OF THE INVENTION
本发明要解决的技术问题是克服现有的缺陷,提供一种全预制装配式桥梁及其施工方法,将管桩、承台、墩柱、盖梁、桥梁上部结构这些组件提前预制,在现场组装,可以有效解决背景技术中的问题。The technical problem to be solved by the present invention is to overcome the existing defects and provide a fully prefabricated bridge and a construction method thereof. Assembly can effectively solve the problems in the background technology.
为实现上述目的,本发明提供如下技术方案:一种全预制装配式桥梁,包括管桩、承台、墩柱、盖梁和桥梁上部结构,所述管桩采用打入法或植入法插打进地下,所述承台设置在插打完毕后的管桩上端,每个承台下方设置四根管桩,所述承台上方与墩柱插接,所述盖梁下部与墩柱固定连接,且盖梁的设置方向与桥梁方向垂直,所述盖梁为钢板组合梁墩顶盖梁或轻型T梁墩顶盖梁,所述盖梁上沿桥梁方向设置有桥梁上部结构,所述桥梁上部结构为窄箱组合梁、钢板组合梁或轻型T梁,所述桥梁上部结构为窄箱组合梁或轻型T梁时,对应的盖梁为轻型T梁墩顶盖梁,所述桥梁上部结构为钢板组合梁时,对应的盖梁为钢板组合梁墩顶盖梁,所述管桩、承台、墩柱、盖梁和桥梁上部结构都采用全预制结构。In order to achieve the above purpose, the present invention provides the following technical solutions: a fully prefabricated bridge, comprising pipe piles, caps, pier columns, cover beams and bridge superstructure, and the pipe piles are inserted by a driving method or an implantation method. Drive into the ground, the caps are arranged at the upper end of the pipe piles after the insertion and driving, four pipe piles are arranged under each cap, the upper part of the cap is inserted with the pier column, and the lower part of the cover beam is fixed to the pier column connected, and the setting direction of the cover beam is perpendicular to the direction of the bridge, the cover beam is a steel plate composite beam pier top cover beam or a light T-beam pier top cover beam, the cover beam is provided with a bridge superstructure along the bridge direction, and the upper part of the bridge The structure is a narrow box composite beam, a steel plate composite beam or a light T beam, and when the bridge superstructure is a narrow box composite beam or a light T beam, the corresponding cover beam is a light T beam pier top cover beam, and the bridge superstructure is When the steel plate composite beam is used, the corresponding cover beam is the steel plate composite beam pier top cover beam, and the pipe piles, caps, pier columns, cover beams and bridge superstructure are all prefabricated structures.
进一步的,所述墩柱上端预留有长度与盖梁厚度一致的钢筋,盖梁中间也预留有金属波纹管,金属波纹管与植入筋的数量和设置位置适配,且一一对应插接。Further, steel bars with the same length as the thickness of the cover beam are reserved at the upper end of the pier column, and metal corrugated pipes are also reserved in the middle of the cover beam. plugged in.
一种全预制装配式桥梁的施工方法,包括以下步骤:A construction method for a fully prefabricated bridge, comprising the following steps:
S1按照设计规格分别预制管桩、承台、墩柱、盖梁和桥梁上部结构,管桩和墩柱采用离心法预制;S1 Prefabricated pipe piles, caps, pier columns, cover beams and bridge superstructures according to the design specifications, and the pipe piles and pier columns are prefabricated by centrifugal method;
S2管桩施工,管桩采用打入法或植入法施工;S2 pipe pile construction, the pipe pile is constructed by driving method or implantation method;
S3承台施工,承台安装时采用吊车吊装,使承台下方与管桩固定连接;For the construction of the S3 cap, a crane is used to hoist the cap, so that the bottom of the cap is fixedly connected to the pipe pile;
S4墩柱施工,墩柱安装时采用吊车吊装,使墩柱下方与承台固定连接;S4 pier column construction, the pier column is hoisted by a crane, so that the bottom of the pier column is fixedly connected to the bearing platform;
S5盖梁施工,盖梁安装时采用吊车吊装,将盖梁下部与墩柱固定连接;S5 cover beam construction, when the cover beam is installed, the crane is hoisted, and the lower part of the cover beam is fixedly connected to the pier column;
S6桥梁上部结构施工,桥梁上部结构通过吊车安装到盖梁上方,最后浇筑桥梁上部结构间的湿接缝混凝土,桥梁上部结构采用窄箱组合梁、钢板组合梁和轻型T梁三种结构,轻型T梁架设时使用全幅架设工艺;S6 bridge superstructure construction, the bridge superstructure is installed above the cover beam by crane, and finally the wet joint concrete between the bridge superstructure is poured. The bridge superstructure adopts three structures of narrow box composite beam, steel plate composite beam and light T beam. The full-width erection process is used when the T beam is erected;
S7依次重复步骤1)至6)即可不断地向前完成全预制装配式桥梁的施工。S7 repeats steps 1) to 6) in sequence to continuously complete the construction of the fully prefabricated bridge.
进一步的,预制管桩的混凝土等级为C80,钢筋为抗拉强度不小于1420MPa的预应力钢筋,单节管桩长度为7-15m,以1m模数递增。Further, the concrete grade of the prefabricated pipe piles is C80, the steel bars are prestressed steel bars with a tensile strength of not less than 1420MPa, and the length of the single-section pipe piles is 7-15m, in increments of 1m modulus.
进一步的,承台为空心杯状结构,尺寸:3*3*2m。Further, the bearing platform is a hollow cup-shaped structure with a size of 3*3*2m.
进一步的,墩柱的规格:中空圆柱结构,外直径1.2m、内直径0.7m、壁厚0.25m,预制混凝土强度等级为C80。Further, the specifications of the pier column: hollow cylindrical structure, with an outer diameter of 1.2m, an inner diameter of 0.7m, a wall thickness of 0.25m, and a precast concrete strength grade of C80.
进一步的,盖梁为钢板组合梁墩顶盖梁时,尺寸1.8*1.8*1m,采用C40混凝土浇筑;盖梁为轻型T梁墩顶盖梁时,尺寸4.8*1.9*1.4m。Further, when the cover beam is a steel plate composite beam pier top cover beam, the size is 1.8*1.8*1m, and C40 concrete is used for pouring; when the cover beam is a light T beam pier top cover beam, the size is 4.8*1.9*1.4m.
进一步的,预制盖梁的施工方法,包括以下步骤:Further, the construction method of the prefabricated cover beam includes the following steps:
A1骨架安装,绑扎钢筋时,钢筋的交叉点采用扎丝绑扎结实,绑扎采取逐点改变绕丝方向的8字形方式交错扎接,绑扎使用的铁丝要向内弯,不得伸向保护层内;钢筋绑扎搭接长度HPB235钢筋搭接长度不小于25d,HRB钢筋搭接长度不小于35d,HRB400、RRB400钢筋搭接长度不小于45d,钢筋骨架的焊接采用二氧化碳保护焊,焊接接头采用双面焊,垫块布设数量不少于4个/㎡;When installing the A1 skeleton, when tying the steel bars, the intersections of the steel bars should be tied with wire ties. The lap length of HPB235 steel bar shall not be less than 25d, the lap length of HRB steel bar shall not be less than 35d, and the lap length of HRB400 and RRB400 steel bar shall not be less than 45d. The number of pads shall not be less than 4/㎡;
A2模板安装,钢筋骨架利用龙门吊进行安装,安装完成后首先使用波纹管定位钢棒进行波纹管定位,完成后人工使用旋转螺杆进行合模;预制盖梁模板采用定型钢模,模板使用前涂刷涂膜剂,钢筋骨架绑扎完毕、预埋钢筋、预埋钢板和波纹管这些预埋件安装完成后进行模板立设;A2 formwork is installed, and the steel frame is installed by gantry crane. After the installation is completed, the bellows positioning steel rod is used to locate the bellows. After completion, the rotating screw is used to close the mold; the prefabricated cover beam formwork adopts the stereotyped steel form, and the formwork is painted before use. After the film coating agent, the reinforcement frame is bound, the pre-embedded steel bars, the pre-embedded steel plates and the corrugated pipes are installed and the formwork is erected;
A3混凝土浇筑,混凝土的浇筑采用分层连续推移的方式进行,不得随意留置施工缝;浇筑后进行振捣,采用插入式振捣器振捣混凝土,不得随意加密振点或漏振,每点的振捣时间以表面泛浆或不冒大气泡为准,插入式振捣器的振捣采取分层振捣,定点振捣,快插慢拨,插点均匀排列,逐点移动,不得漏振,移动间距不大于振捣器作用半径的1.5倍,振捣上一层时应插入下层5-10cm,以消除两层间的接缝,振捣时间间隔不得大于下层混凝土初凝时间;A3 Concrete pouring, the concrete pouring is carried out in a layered and continuous way, and construction joints shall not be left at will; vibrate after pouring, and use a plug-in vibrator to vibrate the concrete. The vibrating time is subject to the surface flooding or no big bubbles. The vibrating of the plug-in vibrator adopts layered vibrating, fixed-point vibrating, fast insertion and slow dialing, and the insertion points are evenly arranged and moved point by point, without vibration leakage. , the moving distance should not be greater than 1.5 times the action radius of the vibrator. When vibrating the upper layer, it should be inserted into the lower layer 5-10cm to eliminate the joint between the two layers. The vibration time interval should not be greater than the initial setting time of the lower layer of concrete;
A4养护与存放,拆模后,迅速对新暴露混凝土进行后期潮湿养护,采用土工布将暴露面混凝土覆盖或包裹,洒水养护,养护时间不少于7d。A4 Maintenance and storage: After the formwork is removed, the newly exposed concrete should be quickly cured in the later stage, and the exposed surface concrete should be covered or wrapped with geotextile, and the curing time should not be less than 7d.
进一步的,浇筑混凝土前,指定专人仔细检查钢筋保护层垫块的位置、数量及模板、支架、钢筋、预埋件的紧固程度,构件侧面和底面的垫块至少应为4个/m2,绑扎垫块和钢筋的铁丝头不得伸入保护层内。Further, before pouring concrete, designate a special person to carefully check the position and quantity of the steel protective layer pads and the degree of tightening of the formwork, brackets, steel bars and embedded parts. The wire ends of the binding pads and reinforcing bars shall not protrude into the protective layer.
进一步的,盖梁的安装方法,包括以下步骤:Further, the installation method of the cover beam includes the following steps:
B1调平层施工,施工前复核预制墩墩顶高程,墩顶拼接面清理,清理干净后铺设档浆模板并进行调平处理,铺设2cm厚度的C50环氧砂浆调平层,砂浆铺筑前对墩顶进行洒水湿润;B1 leveling layer construction, review the elevation of the prefabricated pier top before construction, clean the splicing surface of the pier top, lay the grout template and level it after cleaning, and lay a 2cm-thick C50 epoxy mortar leveling layer. The top of the pier is sprinkled and moistened;
B2构件运输,预制构件混凝土强度达到设计强度的90%后可进行运输,利用车辆将构件从预制场内运输至工地;B2 component transportation, the prefabricated components can be transported after the concrete strength reaches 90% of the design strength, and the components are transported from the prefabricated site to the construction site by vehicles;
B3构件安装,盖梁拼装时,使用履带吊将盖梁吊装到离墩柱钢筋顶面大于10cm时停止下降,使用人工辅助定位,精确对位后,缓缓放下盖梁,墩柱上端预留钢筋插入盖梁内部的金属波纹管内,插接后,对金属波纹管逐个灌浆。B3 component installation, when the cover beam is assembled, use the crawler crane to hoist the cover beam to the top of the pier column and stop the descent when it is more than 10cm away from the top surface of the steel bar of the pier column. Use manual auxiliary positioning. After accurate alignment, slowly lower the cover beam, and the upper end of the pier column is reserved. The steel bars are inserted into the metal corrugated pipes inside the cover beam, and after being inserted, the metal corrugated pipes are grouted one by one.
进一步的,金属波纹管应与箍筋、锚固钢筋制作成整体模块后置于盖梁钢筋笼内。Further, the metal bellows should be made into an integral module with stirrups and anchoring steel bars and then placed in the cover beam reinforcement cage.
与现有技术相比,本发明的有益效果是:本全预制装配式桥梁及其施工方法,具有以下好处:Compared with the prior art, the beneficial effects of the present invention are: the fully prefabricated prefabricated bridge and its construction method have the following advantages:
1、全预制装配式桥梁,结构简单、传力路径明确、承载能力强,在事先打入的桩柱搭设施工平台,既能实现全预制装配式桥梁各工序全程可移动不落地平行施工,大大提高了施工的效率;此外,在施工作业过程中无需在桥梁周围修建栈桥及便道,从而降低了施工作业对桥梁周围原始环境的破坏。1. The fully prefabricated bridge has a simple structure, clear force transmission path, and strong bearing capacity. The construction platform is built on the piles driven in advance, which can realize the full prefabricated bridge. The efficiency of construction is improved; in addition, during the construction operation, there is no need to build trestle bridges and access roads around the bridge, thereby reducing the damage to the original environment around the bridge.
2、管桩采用打入法、植入法两种,墩柱采用离心法预制、吊车安装;盖梁使用旋转合页式模板预制,免除龙门吊安拆,释放产能。2. The pipe pile adopts the driving method and the implantation method. The pier column is prefabricated by the centrifugal method and installed by crane; the cover beam is prefabricated by the rotating hinge template, which eliminates the installation and dismantling of the gantry crane and releases the production capacity.
附图说明Description of drawings
图1为本发明一种全预制装配式桥梁的前视示意图;1 is a schematic front view of a fully prefabricated bridge of the present invention;
图2为本发明一种全预制装配式桥梁的侧视示意图;Figure 2 is a schematic side view of a fully prefabricated bridge of the present invention;
图3为本发明中管桩结构配筋示意图;Fig. 3 is a schematic diagram of the reinforcement of the pipe pile structure in the present invention;
图4为本发明中承台的结构示意图;Fig. 4 is the structural representation of the platform in the present invention;
图5为本发明中盖梁的结构示意图;Fig. 5 is the structural representation of the cover beam in the present invention;
图6为本发明中盖梁的俯视示意图。6 is a schematic top view of a cover beam in the present invention.
图中:1管桩、2承台、3墩柱、4盖梁、5桥梁上部结构。In the picture: 1 pipe pile, 2 cap, 3 pier column, 4 cover beam, 5 bridge superstructure.
具体实施方式Detailed ways
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明,即所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。通常在此处附图中描述和示出的本发明实施例的组件可以以各种不同的配置来布置和设计。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, but not to limit the present invention, that is, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. The components of the embodiments of the invention generally described and illustrated in the drawings herein may be arranged and designed in a variety of different configurations.
因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明的实施例,本领域技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本发明保护的范围。Thus, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work fall within the protection scope of the present invention.
需要说明的是,术语“第一”和“第二”等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that relational terms such as the terms "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any relationship between these entities or operations. any such actual relationship or sequence exists. Moreover, the terms "comprising", "comprising" or any other variation thereof are intended to encompass a non-exclusive inclusion such that a process, method, article or device comprising a list of elements includes not only those elements, but also includes not explicitly listed or other elements inherent to such a process, method, article or apparatus. Without further limitation, an element qualified by the phrase "comprising a..." does not preclude the presence of additional identical elements in a process, method, article or apparatus that includes the element.
以下结合实施例对本发明的特征和性能作进一步的详细描述。The features and performances of the present invention will be further described in detail below in conjunction with the embodiments.
请参阅图1-6,本发明提供以下技术方案:Please refer to Figures 1-6, the present invention provides the following technical solutions:
如图1-2所示,一种全预制装配式桥梁,包括管桩1、承台2、墩柱3、盖梁4和桥梁上部结构5,管桩1采用打入法或植入法插打进地下,所述承台2设置在插打完毕后的管桩1上端,每个承台1下方设置四根管桩2,所述承台2上方与墩柱3插接,盖梁4下部与墩柱3固定连接,且盖梁4的设置方向与桥梁方向垂直,盖梁4为钢板组合梁墩顶盖梁或轻型T梁墩顶盖梁,所述盖梁4上沿桥梁方向设置有桥梁上部结构5,桥梁上部结构5为窄箱组合梁、钢板组合梁或轻型T梁,桥梁上部结构5为窄箱组合梁或轻型T梁时,对应的盖梁4为轻型T梁墩顶盖梁,桥梁上部结构5为钢板组合梁时,对应的盖梁4为钢板组合梁墩顶盖梁,管桩1、承台2、墩柱3、盖梁4和桥梁上部结构5都采用全预制结构,在本实施例中,桥梁上部结构5为轻型T梁。As shown in Figure 1-2, a fully prefabricated bridge includes pipe piles 1, caps 2,
其中,墩柱3上端预留有长度与盖梁4厚度一致的钢筋,盖梁4中间也预留有金属波纹管,金属波纹管与植入筋的数量和设置位置适配,且一一对应插接。Among them, the upper end of the
一种全预制装配式桥梁的施工方法,其利用了上述施工平台,包括以下步骤:A construction method for a fully prefabricated bridge, which utilizes the above-mentioned construction platform, comprises the following steps:
S1按照设计规格分别预制管桩1、承台2、墩柱3、盖梁4和桥梁上部结构5,管桩1和墩柱3采用离心法预制;S1 are prefabricated pipe piles 1, caps 2,
S2管桩1施工,管桩1采用打入法或植入法施工;S2 pipe pile 1 is constructed, and the pipe pile 1 is constructed by driving method or implantation method;
S3承台2施工,承台2安装时采用吊车吊装,使承台2下方与管桩1固定连接;S3 for the construction of the
S4墩柱3施工,墩柱3安装时采用吊车吊装,使墩柱3下方与承台2固定连接;
S5盖梁4施工,盖梁4安装时采用吊车吊装,将盖梁4下部与墩柱3固定连接;
S6桥梁上部结构5施工,桥梁上部结构5通过吊车安装到盖梁4上方,最后浇筑桥梁上部结构5间的湿接缝混凝土,桥梁上部结构5采用窄箱组合梁、钢板组合梁和轻型T梁三种结构,轻型T梁架设时使用全幅架设工艺;S6 Construction of the
S7依次重复步骤1)至6)即可不断地向前完成全预制装配式桥梁的施工。S7 repeats steps 1) to 6) in sequence to continuously complete the construction of the fully prefabricated bridge.
如图3所示,预制管桩1的混凝土等级为C80,钢筋为抗拉强度不小于1420MPa的预应力钢筋,单节管桩长度为7-15m,以1m模数递增。As shown in Figure 3, the concrete grade of the prefabricated pipe pile 1 is C80, the steel bar is a prestressed steel bar with a tensile strength of not less than 1420MPa, and the length of the single-section pipe pile is 7-15m, and the modulus is incremented by 1m.
如图4所示,承台2为空心杯状结构,尺寸:3*3*2m。As shown in Figure 4, the
其中,墩柱3的规格:中空圆柱结构,外直径1.2m、内直径0.7m、壁厚0.25m,预制混凝土强度等级为C80。Among them, the specifications of pier column 3: hollow cylindrical structure, outer diameter of 1.2m, inner diameter of 0.7m, wall thickness of 0.25m, and precast concrete strength grade of C80.
其中,盖梁4为钢板组合梁墩顶盖梁时,尺寸1.8*1.8*1m,采用C40混凝土浇筑。Among them, when the
另一个实施例,如图5-6所示,盖梁4为轻型T梁墩顶盖梁时,尺寸4.8*1.9*1.4m。In another embodiment, as shown in Figures 5-6, when the
步骤S1中,预制盖梁4的施工方法,包括以下步骤:In step S1, the construction method of the
A1骨架安装,钢筋加工在标准化钢筋加工场完成加工,绑扎钢筋时,钢筋的交叉点采用扎丝绑扎结实,绑扎采取逐点改变绕丝方向的8字形方式交错扎接,绑扎使用的铁丝要向内弯,不得伸向保护层内;钢筋绑扎搭接长度HPB235钢筋搭接长度不小于25d,HRB钢筋搭接长度不小于35d,HRB400、RRB400钢筋搭接长度不小于45d,钢筋骨架的焊接采用二氧化碳保护焊,焊接接头采用双面焊。垫块布设数量不少于4个/㎡;The A1 skeleton is installed, and the steel bars are processed in the standardized steel bar processing plant. When tying the steel bars, the intersections of the steel bars are tied with wire ties. Bend inward and shall not protrude into the protective layer; the lap length of HPB235 rebar shall not be less than 25d, the lap length of HRB rebar shall not be less than 35d, and the lap length of HRB400 and RRB400 shall not be less than 45d. Protection welding, welding joints are double-sided welding. The number of pads shall not be less than 4/㎡;
A2模板安装,钢筋骨架利用龙门吊进行安装,安装完成后首先使用波纹管定位钢棒进行波纹管定位,完成后人工使用旋转螺杆进行合模;预制盖梁模板采用定型钢模,模板使用前涂刷涂膜剂,钢筋骨架绑扎完毕、预埋钢筋、预埋钢板和波纹管这些预埋件安装完成后进行模板立设;盖梁使用合页式加旋转螺杆模板预制,可免除龙门吊安拆,同时加快模板安装定位,减少人工、机械资源消耗;A2 formwork is installed, and the steel frame is installed by gantry crane. After the installation is completed, the bellows positioning steel rod is used to locate the bellows. After completion, the rotating screw is used to close the mold; the prefabricated cover beam formwork adopts the stereotyped steel form, and the formwork is painted before use. After the film coating agent, the binding of the steel skeleton, the embedded steel bars, the embedded steel plates and the corrugated pipes are completed, the formwork shall be erected; Speed up template installation and positioning, reduce labor and mechanical resource consumption;
A3混凝土浇筑,浇筑混凝土前,指定专人仔细检查钢筋保护层垫块的位置、数量及模板、支架、钢筋、预埋件的紧固程度,构件侧面和底面的垫块至少应为4个/m2,绑扎垫块和钢筋的铁丝头不得伸入保护层内,混凝土的浇筑采用分层连续推移的方式进行,不得随意留置施工缝;浇筑后进行振捣,采用插入式振捣器振捣混凝土,不得随意加密振点或漏振,每点的振捣时间以表面泛浆或不冒大气泡为准,插入式振捣器的振捣采取分层振捣,定点振捣,快插慢拨,插点均匀排列,逐点移动,不得漏振,移动间距不大于振捣器作用半径的1.5倍,振捣上一层时应插入下层5-10cm,以消除两层间的接缝,振捣时间间隔不得大于下层混凝土初凝时间;A3 Concrete pouring. Before pouring concrete, designate a special person to carefully check the position and quantity of the steel protective layer pads and the degree of tightening of the formwork, brackets, reinforcing bars and embedded parts. The pads on the side and bottom of the component should be at least 4/m2 , the wire ends of the binding pads and steel bars shall not protrude into the protective layer. The concrete is poured in a layered and continuous way, and construction joints shall not be left at will; vibrate after pouring, and use a plug-in vibrator to vibrate the concrete. Do not randomly add vibration points or leak vibration. The vibration time of each point is subject to the surface slurring or no large bubbles. The vibration of the plug-in vibrator adopts layered vibration, fixed-point vibration, fast insertion and slow dialing. The insertion points are evenly arranged, move point by point without vibration leakage, and the moving distance is not greater than 1.5 times the action radius of the vibrator. The time interval shall not be greater than the initial setting time of the lower concrete;
A4养护与存放,拆模后,迅速对新暴露混凝土进行后期潮湿养护,采用土工布将暴露面混凝土覆盖或包裹,洒水养护,养护时间不少于7d。A4 Maintenance and storage: After the formwork is removed, the newly exposed concrete should be quickly cured in the later stage, and the exposed surface concrete should be covered or wrapped with geotextile, and the curing time should not be less than 7d.
预制后,盖梁4的安装方法,包括以下步骤:After prefabrication, the installation method of the
B1调平层施工,施工前复核预制墩墩顶高程,墩顶拼接面清理,清理干净后铺设档浆模板并进行调平处理,铺设2cm厚度的C50环氧砂浆调平层,砂浆铺筑前对墩顶进行洒水湿润;B1 leveling layer construction, review the elevation of the prefabricated pier top before construction, clean the splicing surface of the pier top, lay the grout template and level it after cleaning, and lay a 2cm-thick C50 epoxy mortar leveling layer. The top of the pier is sprinkled and moistened;
B2构件运输,预制构件混凝土强度达到设计强度的90%后可进行运输,利用车辆将构件从预制场内运输至工地;B2 component transportation, the prefabricated components can be transported after the concrete strength reaches 90% of the design strength, and the components are transported from the prefabricated site to the construction site by vehicles;
B3构件安装,盖梁4拼装时,使用履带吊将盖梁4吊装到离墩柱3钢筋顶面大于10cm时停止下降,使用人工辅助定位,精确对位后,缓缓放下盖梁4,墩柱3上端预留钢筋插入盖梁4内部的金属波纹管内,插接后,对金属波纹管逐个灌浆,灌浆设备宜采用专用灌浆设备,高强无收缩水泥灌浆料在拌浆时应制取试块,对应每个拼接部位应制取不少于3组,分别测试7天和28天龄期抗压强度。B3 component installation, when the
其中,金属波纹管应与箍筋、锚固钢筋制作成整体模块后置于盖梁钢筋笼内,金属波纹管安装定位允许偏差为±2mm,盖梁4钢筋笼吊装吊点处应局部加强,同时应安装盖梁4成品所需的吊点预埋件、现场调节设备用的预埋件、支座预埋件等各类预埋件,盖梁4的模板侧面采用钢模板,钢模板应满足刚度、承载能力、稳定性要求。Among them, the metal bellows should be made into an integral module with stirrups and anchoring steel bars and then placed in the cover beam reinforcement cage. The allowable deviation of the metal bellows installation and positioning is ±2mm, and the hoisting point of the
混凝土浇筑前应再次对金属波纹管定位进行检查,允许偏差均为±2mm;同时应对台座表面标高及水平度进行复测,标高允许偏差为±1mm;水平度允许偏差为±1mm/m;盖梁4的混凝土应一次性浇筑完成,盖梁预制完成后应对盖梁4空间尺寸、金属波纹管定位进行复测,各项允许偏差均为±2mm。Before the concrete is poured, the positioning of the metal bellows should be checked again, and the allowable deviation is ±2mm; at the same time, the surface elevation and levelness of the pedestal should be re-measured, and the allowable deviation of the elevation is ±1mm; the allowable deviation of the levelness is ±1mm/m; The concrete of the
值得注意的是,本实施例中所公开的钢板组合梁墩顶盖梁、轻型T梁墩顶盖梁、窄箱组合梁、钢板组合梁、轻型T梁,都为建筑工程中常用的技术,且组成结构和原理都已公开,可根据实际应用场景自由配置。It is worth noting that the steel plate composite beam pier roof beam, the light T beam pier roof beam, the narrow box composite beam, the steel plate composite beam, and the light T beam disclosed in this embodiment are all commonly used technologies in construction projects. And the composition structure and principle have been disclosed, which can be freely configured according to actual application scenarios.
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, and substitutions can be made in these embodiments without departing from the principle and spirit of the invention and modifications, the scope of the present invention is defined by the appended claims and their equivalents.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210543767.3A CN114808654A (en) | 2022-05-18 | 2022-05-18 | A kind of fully prefabricated prefabricated bridge and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210543767.3A CN114808654A (en) | 2022-05-18 | 2022-05-18 | A kind of fully prefabricated prefabricated bridge and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114808654A true CN114808654A (en) | 2022-07-29 |
Family
ID=82515837
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210543767.3A Pending CN114808654A (en) | 2022-05-18 | 2022-05-18 | A kind of fully prefabricated prefabricated bridge and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114808654A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115262403A (en) * | 2022-08-05 | 2022-11-01 | 中交一公局第五工程有限公司 | Bridge pad stone prefabricating and mounting construction method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110273359A (en) * | 2019-06-05 | 2019-09-24 | 成都建工工业化建筑有限公司 | A kind of prefabricated bent cap and construction method of packaged type bridges |
DE202020103270U1 (en) * | 2019-07-03 | 2020-06-24 | BEIJING-Harbin Railway Passenger Dedicated Line beijing-hebei Co., Ltd. | Prefabricated assembled structure for assembled high speed railway bridges |
CN211200023U (en) * | 2019-10-10 | 2020-08-07 | 中铁建苏州设计研究院有限公司 | Prefabricated bridge construction of full assembled |
CN111648228A (en) * | 2020-05-29 | 2020-09-11 | 中铁北京工程局集团第一工程有限公司 | Assembled pier and construction process thereof |
CN111996906A (en) * | 2020-09-21 | 2020-11-27 | 山东鲁桥建设有限公司 | Efficient construction method of assembled pier |
CN112853914A (en) * | 2021-03-04 | 2021-05-28 | 北京国道通公路设计研究院股份有限公司 | Fully-prefabricated assembled bridge and construction method thereof |
CN214401370U (en) * | 2020-12-29 | 2021-10-15 | 呼和浩特市政工程设计研究院有限公司 | Prefabricated viaduct structure of assembling of municipal administration |
-
2022
- 2022-05-18 CN CN202210543767.3A patent/CN114808654A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110273359A (en) * | 2019-06-05 | 2019-09-24 | 成都建工工业化建筑有限公司 | A kind of prefabricated bent cap and construction method of packaged type bridges |
DE202020103270U1 (en) * | 2019-07-03 | 2020-06-24 | BEIJING-Harbin Railway Passenger Dedicated Line beijing-hebei Co., Ltd. | Prefabricated assembled structure for assembled high speed railway bridges |
CN211200023U (en) * | 2019-10-10 | 2020-08-07 | 中铁建苏州设计研究院有限公司 | Prefabricated bridge construction of full assembled |
CN111648228A (en) * | 2020-05-29 | 2020-09-11 | 中铁北京工程局集团第一工程有限公司 | Assembled pier and construction process thereof |
CN111996906A (en) * | 2020-09-21 | 2020-11-27 | 山东鲁桥建设有限公司 | Efficient construction method of assembled pier |
CN214401370U (en) * | 2020-12-29 | 2021-10-15 | 呼和浩特市政工程设计研究院有限公司 | Prefabricated viaduct structure of assembling of municipal administration |
CN112853914A (en) * | 2021-03-04 | 2021-05-28 | 北京国道通公路设计研究院股份有限公司 | Fully-prefabricated assembled bridge and construction method thereof |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115262403A (en) * | 2022-08-05 | 2022-11-01 | 中交一公局第五工程有限公司 | Bridge pad stone prefabricating and mounting construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112982181B (en) | Construction method for steel-concrete combined section of through-type steel box continuous arch bridge | |
CN114892552B (en) | Box girder type bridge reconstruction construction method | |
CN112627434B (en) | Cross construction method for complex V-shaped stiff columns and irregular ring beams of large stadium | |
CN110952456A (en) | Pile type bridge construction process | |
CN110939052B (en) | A kind of subway cover beam construction method | |
CN110130488A (en) | A new prefabricated building node and its construction form | |
CN107574762A (en) | A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities | |
CN110670770A (en) | Combined structure and construction method of solid shear wall and laminated plate edge member | |
CN112030772A (en) | Rapid construction method of continuous rigid frame bridge | |
CN113638304B (en) | Concrete beam type bridge hidden cover beam structure system and construction method thereof | |
CN114108917A (en) | Height-adjustable assembly type composite floor slab construction method | |
CN113202222A (en) | Construction method for assembled type superposed beam slab | |
CN212103636U (en) | A prefabricated assembled hollow pier based on UHPC joints | |
CN112554077A (en) | Steel pipe concrete assembled truss composite beam construction system and construction method | |
CN114808654A (en) | A kind of fully prefabricated prefabricated bridge and its construction method | |
CN114438896A (en) | Assembling construction method for assembled segmental beam of 100t span-pier gantry crane | |
CN114263275A (en) | High-rise assembled steel structure-core tube same-layer construction method | |
CN107905115A (en) | Through Steel pipe concrete truss combination beamss bridge construction method | |
CN107586068B (en) | Upright column concrete and construction method of concrete upright column | |
CN107514012A (en) | A kind of partial precast assembly steel concrete combination underground pipe gallery for exempting from template | |
CN110439002A (en) | A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab | |
CN216108007U (en) | Concrete beam type bridge and cast-in-situ hidden cover beam thereof | |
CN114108841B (en) | A 3D printed concrete structural column bottom vertical reinforcement anchor component and construction method | |
CN216129955U (en) | Steel-concrete combined section structure of through-type steel box continuous arch bridge | |
CN112942659A (en) | Recycled concrete laminated slab containing prestressed FRP tendon fiber and manufacturing method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |