CN114763732A - Pressure control casing drilling method for underground injection pressure containing stratum - Google Patents
Pressure control casing drilling method for underground injection pressure containing stratum Download PDFInfo
- Publication number
- CN114763732A CN114763732A CN202210022276.4A CN202210022276A CN114763732A CN 114763732 A CN114763732 A CN 114763732A CN 202210022276 A CN202210022276 A CN 202210022276A CN 114763732 A CN114763732 A CN 114763732A
- Authority
- CN
- China
- Prior art keywords
- drilling
- well
- pressure
- casing
- cementing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 91
- 238000000034 method Methods 0.000 title claims abstract description 30
- 238000002347 injection Methods 0.000 title claims abstract description 20
- 239000007924 injection Substances 0.000 title claims abstract description 20
- 230000015572 biosynthetic process Effects 0.000 claims abstract description 19
- 238000012360 testing method Methods 0.000 claims abstract description 16
- 238000006073 displacement reaction Methods 0.000 claims abstract description 5
- 230000007935 neutral effect Effects 0.000 claims abstract 2
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 6
- 239000004568 cement Substances 0.000 claims description 6
- 230000008878 coupling Effects 0.000 claims description 3
- 238000010168 coupling process Methods 0.000 claims description 3
- 238000005859 coupling reaction Methods 0.000 claims description 3
- 229910052742 iron Inorganic materials 0.000 claims description 3
- 238000002955 isolation Methods 0.000 claims description 2
- 239000007788 liquid Substances 0.000 claims 1
- 238000004519 manufacturing process Methods 0.000 abstract description 15
- 230000000694 effects Effects 0.000 abstract description 8
- 238000005065 mining Methods 0.000 abstract description 3
- 238000005755 formation reaction Methods 0.000 description 11
- 239000012530 fluid Substances 0.000 description 5
- 238000007711 solidification Methods 0.000 description 4
- 230000008023 solidification Effects 0.000 description 4
- 238000011084 recovery Methods 0.000 description 3
- 238000007789 sealing Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000009833 condensation Methods 0.000 description 1
- 230000005494 condensation Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 229920000642 polymer Polymers 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B21/00—Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
- E21B21/08—Controlling or monitoring pressure or flow of drilling fluid, e.g. automatic filling of boreholes, automatic control of bottom pressure
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B47/00—Survey of boreholes or wells
- E21B47/06—Measuring temperature or pressure
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/20—Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geophysics (AREA)
- Mechanical Engineering (AREA)
- Earth Drilling (AREA)
Abstract
Description
技术领域technical field
本发明涉及油田领域,具体的说是一种用于井下含有地层注入压力的控制压力套管钻井方法。The invention relates to the field of oil fields, in particular to a pressure-controlled casing drilling method used for downhole containing formation injection pressure.
背景技术Background technique
经过多年油田开发,三采区块的套损问题井数越来越多。根据三采区块产能建设需要,需要钻更新井数越来越多。但是,常规钻更新井存在以下问题:After years of oilfield development, the number of wells with casing damage problems in the third production block is increasing. According to the production capacity construction needs of the third mining block, more and more wells need to be drilled and updated. However, conventional drilling of newer wells has the following problems:
(1)钻关对产量影响大:由于更新井分布零散,常规钻井时需要降压(即所谓“钻关”),对于一些井网密度大的区域,钻一口零散更新井450米的钻关范围平均关注水(入)井40口,影响时间达35天左右,常规钻一口更新井影响油量大,且造成局部井区压力变化大,不利于套管防护。(1) Drilling passes have a great impact on production: due to the scattered distribution of update wells, pressure reduction is required during conventional drilling (the so-called "drilling pass"). On average, there are 40 water (inlet) wells in the scope, and the impact time is about 35 days. Conventional drilling of one renewal well affects the oil volume and causes large pressure changes in the local well area, which is not conducive to casing protection.
(2)更新井钻关影响三次采油开发效果:按照驱油方案要求,为确保三采正注聚区块开发效果,在注入周期内要求连续注入,这使得三次采油区块内的套损井不能得到及时更新,局部井网注采不完善;若更新井为三采井网井,等待一个周期结束后更新,则更新井区的储量在三次采油过程中没有得到有效动用,无法再进行三次采油;若采取钻关降压会造成聚区段塞松懈,将影响三采开发效果和效益。(2) The drilling level of the updated well affects the development effect of tertiary oil recovery: According to the requirements of the oil displacement plan, in order to ensure the development effect of the tertiary production positive polymer injection block, continuous injection is required during the injection period, which makes casing damaged wells in the tertiary oil recovery block. It cannot be updated in time, and the injection and production of the local well pattern is not perfect; if the updated well is a three-production well pattern well, and it is updated after waiting for one cycle, the reserves in the updated well area have not been effectively produced during the tertiary oil recovery process and cannot be carried out three times. Oil production; if the pressure reduction at the drilling pass is adopted, the plug of the accumulation section will be loosened, which will affect the development effect and benefit of the third production.
(3)不钻关对常规钻井条件下钻井安全和固井质量影响大:地层静态压力局部特高压可能还难以确定,且部分区块可能存在浅层气等叠加风险。(3) Not drilling shutoffs will have a great impact on drilling safety and cementing quality under conventional drilling conditions: it may be difficult to determine local ultra-high pressure of formation static pressure, and there may be superimposed risks such as shallow gas in some blocks.
目前,针对上述地质条件,为了确保钻井安全和固井质量,常规钻更新井是在钻关停井条件下完成的,在不钻关停井条件下很难钻成更新井。At present, in view of the above geological conditions, in order to ensure drilling safety and cementing quality, conventional drilling of replacement wells is completed under the conditions of drilling, shutting down and shutting down wells.
发明内容SUMMARY OF THE INVENTION
为了克服现有的三采套损井钻关更新井时影响产量及三采开发效果、不钻关影响钻井安全的不足,本发明提供一种用于井下含有地层注入压力的控制压力套管钻井方法,采用该用于井下含有地层注入压力的控制压力套管钻井方法,可以在不停井条件下钻更新井,既能及时完善套损井组注采关系,又不影响钻井区域的注入,保证正常的区块开发效果。In order to overcome the deficiencies of the existing tertiary production casing damaged wells that affect production and the tertiary production development effect when drilling and shutting down the well, and that the drilling safety is affected by not drilling shut-ins, the present invention provides a pressure-controlled casing drilling for downhole containing formation injection pressure Method, by adopting the pressure-controlled casing drilling method for the injection pressure of underground formations, new wells can be drilled under the condition of non-stop well, which can not only improve the injection-production relationship of casing-damaged well groups in time, but also does not affect the injection in the drilling area. Guarantee the normal block development effect.
本发明的技术方案是:一种用于井下含有地层注入压力的控制压力套管钻井方法,包括以下步骤:一开钻井,一开固井,安装控压钻井设备并试压;二开非油层段钻井,液力加压防斜工具测试,并记录过程中立管压力和泵排量;二开套管钻井段钻井,二开固井;测井。The technical scheme of the present invention is: a control pressure casing drilling method for downhole containing formation injection pressure, comprising the following steps: first drilling, opening cementing, installing managed pressure drilling equipment and testing pressure; second opening non-oil layers Section drilling, hydraulic pressurization anti-deviation tool test, and record riser pressure and pump displacement during the process; second casing drilling section drilling, second opening cementing; logging.
进一步,一开固井后,牙轮钻头钻塞,继续钻进5~10m,然后安装控压钻井设备。Further, after the cementing is started, the roller cone bit drills the plug, continues to drill for 5-10m, and then installs the managed pressure drilling equipment.
进一步,二开套管钻井段钻井时,首先将管柱放到井底,旋转钻进,再循环、接立柱控压钻井,完钻后卸掉部分套管,划眼、通井后,再连接卸掉的套管;Further, when drilling in the second open casing drilling section, first put the pipe string to the bottom of the well, rotate the drilling, recirculate, connect to the column for managed pressure drilling. connect the removed casing;
进一步,二开固井前,先调整套管短节长度,确保接箍在留足口袋后,刚好露出套管头;连接联顶节,上扣扭矩为最低上扣扭矩;连接钻井泵,循环;地层漏失试验。Further, before the second-opening cementing, adjust the length of the casing short section to ensure that the coupling is just exposed to the casing head after the sufficient pocket; connect the top joint, and the make-up torque is the lowest make-up torque; connect the drilling pump and circulate; Formation leakage test.
进一步,二开固井时,连接旋转固井水泥头,打隔离液,注水泥,压胶塞,顶替,套管试压;固井后关闭封井器,环空加回压候凝。Further, during the second opening cementing, connect the rotary cementing cement head, apply spacer fluid, inject cement, press the rubber plug, replace it, and test the casing pressure; after cementing, close the well sealing device, and add back pressure in the annulus to wait for solidification.
进一步,二开固井后,卸掉联顶节,安装环铁。Further, after the second-opening cementing, remove the header joint and install the ring iron.
本发明具有如下有益效果:该用于带压钻井的控制压力套管钻井方法使用特殊套管进行钻进,应用控制压力设备和方法精确控制井眼内环空压力,完钻后直接固井,具有缩短钻井周期、简化钻井工艺、减少喷冒漏钻井事故等优势。利用套管钻井所具有的“钻井就是下套管过程,完钻就可以固井”的特点,减少了常规钻井“完钻后电测及下套管”的过程期间井底压力失去控制的事故发生。The invention has the following beneficial effects: the control pressure casing drilling method for pressure drilling uses a special casing for drilling, the control pressure equipment and method are used to precisely control the annular pressure in the wellbore, and the well is directly cemented after drilling, It has the advantages of shortening the drilling cycle, simplifying the drilling process, and reducing the drilling accidents of blowout and leakage. Using the feature of casing drilling that "drilling is the process of running casing, and cementing can be done after drilling", it reduces the accident of loss of bottom hole pressure during the process of "electrical measurement and casing running after drilling" in conventional drilling. occur.
具体实施方式Detailed ways
下面对本发明作进一步说明:The present invention is further described below:
一种用于井下含有地层注入压力的控制压力套管钻井方法,包括以下步骤:A control pressure casing drilling method for downhole containing formation injection pressure, comprising the following steps:
(一)、一开钻井,一开固井,一开固井后,牙轮钻头钻塞,继续钻进一定进尺,如5~10m,然后安装控压钻井设备,对控压钻井设备进行调试、试压,进行联合调试,试运行正常后方可开始施工。(1) Once drilling, once cementing, after the first cementing, drill the plug with the roller cone bit and continue to drill for a certain footage, such as 5-10m, then install the managed pressure drilling equipment and debug the managed pressure drilling equipment , pressure test, joint debugging, and the construction can be started after the test run is normal.
(二)、二开非油层段钻井,选择液力加压防斜工具,通过顶驱使液力加压防斜工具开启至闭合,进行测试并记录过程中立管压力和泵排量,以此判断工具是否正常,确定工具是否畅通,流体经过工具的压力是否正常。(2) For drilling in the non-oil zone of the second opening, select the hydraulic pressurized anti-slope tool, open and close the hydraulic pressurized anti-slope tool through the top drive, test and record the riser pressure and pump displacement during the process, so as to judge Whether the tool is normal, determine whether the tool is unobstructed, and whether the pressure of the fluid passing through the tool is normal.
(三)、二开套管钻井段钻井,二开固井:(3) Drilling in the second casing drilling section and cementing in the second opening:
a、连接两根套管为一个立柱,在每个立柱上端连接驱动杆保护接头,立柱下端带上公护丝,立放于钻台上;a. Connect two casings into a column, connect the drive rod protection joint at the upper end of each column, and put a male protection wire on the lower end of the column, which is placed on the drill floor;
b、将管柱下放至井底,旋转钻进,再循环,将立柱接在套管上控压钻井,完钻后卸掉部分套管,划眼、通井后,再连接卸掉的这些套管;b. Lower the pipe string to the bottom of the well, rotate the drilling, recirculate, connect the vertical string to the casing for managed pressure drilling, remove part of the casing after drilling, ream the hole and pass the well, and then connect the removed pipes casing;
c、连接固井管柱,调整套管短节长度,确保接箍在留足口袋后,刚好露出套管头;连接联顶节,上扣扭矩为最低上扣扭矩,既保证连接和密封,又便于固井后卸扣;连接钻井泵,循环,地层漏失试验;c. Connect the cementing string, adjust the length of the casing short section, and ensure that the coupling is just exposed to the casing head after the pocket is left; when connecting the top section, the make-up torque is the minimum make-up torque, which not only ensures the connection and sealing, but also It is convenient to shackle after cementing; connect drilling pump, circulation, and formation leakage test;
d、连接旋转固井水泥头,打隔离液,注水泥(可以上提下放固井管柱,也可以旋转固井管柱),如果因为循环泵压高,水泥浆不流经钻头和螺杆钻具,则投球憋压打开旁通阀;压胶塞,顶替(可以上提下放固井管柱,也可以旋转固井管柱,不同时进行),胶塞碰压;套管试压,试压结束后,敞压候凝,敞不住压的井,关井候凝,关井压力比环空平衡压力大1~2MPa;固井后关闭封井器,环空加回压候凝;若止回阀失灵,计算管内外压差,憋压候凝。d. Connect the rotary cementing cement head, apply isolation fluid, and inject cement (the cementing string can be lifted and lowered, or the cementing string can be rotated). If the cement slurry does not flow through the drill bit and the screw drill due to the high pressure of the circulating pump If the tool is installed, then throw the ball and hold the pressure to open the bypass valve; press the rubber plug to replace (the cementing string can be lifted up and down, or the cementing string can be rotated, but not at the same time), the rubber plug touches the pressure; casing pressure test, test After the pressure is finished, open the well pressure and wait for solidification. If the well can not be opened, shut in the well and wait for solidification. The shut-in pressure is 1-2MPa higher than the equilibrium pressure of the annulus. After cementing, close the well sealing device, and add back pressure in the annulus to wait for the solidification. If the check valve fails, calculate the pressure difference between the inside and outside of the pipe, and hold the pressure for condensation.
e、卸掉联顶节,安装环铁;e. Remove the top section and install the ring iron;
f、测井:进行地质参数、工程参数测量。f. Well logging: to measure geological parameters and engineering parameters.
该钻井方法针对零散更新井钻关影响产量的问题,采用井口环空施加回压的方式,提出了零散更新井控压套管钻完井方案,实现完善井网的目的,并减少对产量的影响。在钻进、循环、接单根时,通过调节自动节流管汇对井口施加回压;一趟钻完井,直接固井,实现全过程控制压力,降低起下钻及下套管过程控制风险;同时考虑周边井地质情况明确,采取套后测井;固井顶替、侯凝通过调节自动节流管汇对井口施加环空回压。针对一个井筒内有的层位的地层破裂压力高于地层孔隙压力的问题,为了减少钻井液压漏地层的问题出现,降低钻井液密度,应用控制压力设备和方法精确控制井眼内环空压力,确保不塌漏也不喷冒安全钻井。使用液力加压防斜工具,可以在不使用钻铤的条件下,确保套管不受轴向压缩所产生弯曲,防止井斜,柔性地给钻头施加钻压,同时隔离了钻头破岩对套管所产生的振动损害。Aiming at the problem that the drilling level of the scattered update wells affects the production, this drilling method adopts the method of applying back pressure in the wellhead annulus, and proposes a drilling and completion plan for the control pressure casing of the scattered update wells, so as to achieve the purpose of improving the well pattern and reduce the impact on production. influences. During drilling, circulation, and single connection, back pressure is applied to the wellhead by adjusting the automatic choke manifold; one drilling and completion, direct cementing, realizes the whole process control pressure, reduces the control of the tripping and casing running process At the same time, considering the clear geological conditions of the surrounding wells, logging after casing is adopted; cementing replacement and Hou Ning apply annulus back pressure to the wellhead by adjusting the automatic choke manifold. Aiming at the problem that the formation fracture pressure of some layers in a wellbore is higher than the formation pore pressure, in order to reduce the occurrence of drilling fluid leakage and formation, reduce the drilling fluid density, and use pressure control equipment and methods to accurately control the annular pressure in the wellbore. Make sure that there is no collapse or leakage and safe drilling. The use of hydraulic pressurized anti-deflection tools can ensure that the casing is not bent due to axial compression without the use of drill collars, prevent the well deviation, flexibly apply WOB to the drill bit, and at the same time isolate the rock breaking effect of the drill bit. Vibration damage from casing.
Claims (6)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2021100356622 | 2021-01-12 | ||
CN202110035662.2A CN112780176A (en) | 2021-01-12 | 2021-01-12 | Pressure control casing drilling method for underground injection pressure containing stratum |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114763732A true CN114763732A (en) | 2022-07-19 |
Family
ID=75757064
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110035662.2A Pending CN112780176A (en) | 2021-01-12 | 2021-01-12 | Pressure control casing drilling method for underground injection pressure containing stratum |
CN202210022276.4A Pending CN114763732A (en) | 2021-01-12 | 2022-01-10 | Pressure control casing drilling method for underground injection pressure containing stratum |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110035662.2A Pending CN112780176A (en) | 2021-01-12 | 2021-01-12 | Pressure control casing drilling method for underground injection pressure containing stratum |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN112780176A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114183070A (en) * | 2021-12-07 | 2022-03-15 | 托普威尔石油技术股份公司 | Drilling method without drilling and closing under pressure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040118614A1 (en) * | 2002-12-20 | 2004-06-24 | Galloway Gregory G. | Apparatus and method for drilling with casing |
CN107313744A (en) * | 2017-07-18 | 2017-11-03 | 山西晋城无烟煤矿业集团有限责任公司 | A kind of small guide hole grouting and reinforcing coal bed gas well passes through the construction method in goaf |
CN107476797A (en) * | 2017-08-22 | 2017-12-15 | 陕西省煤田地质集团有限公司 | A kind of construction method of the casing programme of the horizontal docking geothermal well of heat exchange type |
CN111502540A (en) * | 2020-05-20 | 2020-08-07 | 陕西正通煤业有限责任公司 | Large-aperture drilling construction process for penetrating through huge-thickness aquifer |
CN111997544A (en) * | 2020-10-22 | 2020-11-27 | 中国电建集团河南工程有限公司 | Sedimentary potted landscape ultra-deep layer heat storage geothermal well drilling construction method |
-
2021
- 2021-01-12 CN CN202110035662.2A patent/CN112780176A/en active Pending
-
2022
- 2022-01-10 CN CN202210022276.4A patent/CN114763732A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040118614A1 (en) * | 2002-12-20 | 2004-06-24 | Galloway Gregory G. | Apparatus and method for drilling with casing |
CN107313744A (en) * | 2017-07-18 | 2017-11-03 | 山西晋城无烟煤矿业集团有限责任公司 | A kind of small guide hole grouting and reinforcing coal bed gas well passes through the construction method in goaf |
CN107476797A (en) * | 2017-08-22 | 2017-12-15 | 陕西省煤田地质集团有限公司 | A kind of construction method of the casing programme of the horizontal docking geothermal well of heat exchange type |
CN111502540A (en) * | 2020-05-20 | 2020-08-07 | 陕西正通煤业有限责任公司 | Large-aperture drilling construction process for penetrating through huge-thickness aquifer |
CN111997544A (en) * | 2020-10-22 | 2020-11-27 | 中国电建集团河南工程有限公司 | Sedimentary potted landscape ultra-deep layer heat storage geothermal well drilling construction method |
Also Published As
Publication number | Publication date |
---|---|
CN112780176A (en) | 2021-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110118069B (en) | Ultra-deep well drilling pressure control equipment and operation method | |
CN101586462B (en) | Method of suspending, completing and working over a well | |
CN100412312C (en) | Method and device for repairing oil and gas drilling casing | |
CN103244071B (en) | Old well plugging method for underground gas storage | |
CN112012667B (en) | Oil testing and well completion integrated pipe string combined with fine pressure control technology | |
CN111305795A (en) | Method for applying cannula bridge plug lower tube pump | |
CN107489396A (en) | A kind of towed cementing method of small borehole bushing window sidetracking well | |
CN210768666U (en) | Pressure control equipment for drilling of ultra-deep well | |
CN114763732A (en) | Pressure control casing drilling method for underground injection pressure containing stratum | |
CN114396243B (en) | Gas drilling high-pressure gas well completion method | |
CN104963656B (en) | A kind of casing programme and its installation method for natural petroleum gas field | |
CN100412313C (en) | A kind of non-plug cementing cementing method | |
Marca | 13 Remedial Cementing | |
CN112081535A (en) | Ultra-deep high-sulfur-content gas well completion pipe string and construction method thereof | |
CN114183070A (en) | Drilling method without drilling and closing under pressure | |
CN100575659C (en) | An Underbalanced Well Completion Method | |
CN204571946U (en) | A kind of casing programme for natural petroleum gas field | |
CN219365984U (en) | Fine pressure control drilling device | |
CN111058792A (en) | Coiled tubing perforation-free under-pressure operation-free well completion device and method | |
CN219795209U (en) | Self-checking packer | |
CN113669047B (en) | High-temperature high-pressure oil-gas well testing device and method | |
Shan et al. | Check for updates Preliminary Study on Oil Test and Completion Technology of Over 9000 m Deep Wells-Taking | |
CN217270111U (en) | Blowout guide casing head | |
Shan et al. | Preliminary Study on Oil Test and Completion Technology of Over 9000 m Deep Wells—Taking Guole X Well as an Example | |
CN119163363A (en) | A pressure-controlled drilling and grinding method for ultra-long horizontal section oil wells |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20250217 Address after: No. 12 Aiguo Road, Ranghu Road District, Daqing City, Heilongjiang Province, China 163453 Applicant after: Daqing Drilling Engineering Co.,Ltd. Country or region after: China Applicant after: CHINA NATIONAL PETROLEUM Corp. Address before: 163453 Heilongjiang Province, Daqing City Ranghulu District Central Plains Road No. 99 Applicant before: DAQING PETROLEUM ADMINISTRATION Co.,Ltd. Country or region before: China Applicant before: CHINA NATIONAL PETROLEUM Corp. |
|
TA01 | Transfer of patent application right |