CN107489396A - A kind of towed cementing method of small borehole bushing window sidetracking well - Google Patents

A kind of towed cementing method of small borehole bushing window sidetracking well Download PDF

Info

Publication number
CN107489396A
CN107489396A CN201710845719.9A CN201710845719A CN107489396A CN 107489396 A CN107489396 A CN 107489396A CN 201710845719 A CN201710845719 A CN 201710845719A CN 107489396 A CN107489396 A CN 107489396A
Authority
CN
China
Prior art keywords
short
well
circuit cycle
drilling fluid
towed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710845719.9A
Other languages
Chinese (zh)
Other versions
CN107489396B (en
Inventor
张德荣
蒲阳凤
孔春岩
孙林平
吴思梦
杨之豪
岳华伟
谢武君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Petroleum University
Original Assignee
Southwest Petroleum University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Petroleum University filed Critical Southwest Petroleum University
Priority to CN201710845719.9A priority Critical patent/CN107489396B/en
Publication of CN107489396A publication Critical patent/CN107489396A/en
Application granted granted Critical
Publication of CN107489396B publication Critical patent/CN107489396B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices, or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • E21B21/08Controlling or monitoring pressure or flow of drilling fluid, e.g. automatic filling of boreholes, automatic control of bottom pressure
    • E21B21/085Underbalanced techniques, i.e. where borehole fluid pressure is below formation pressure
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices, or the like
    • E21B33/14Methods or devices for cementing, for plugging holes, crevices, or the like for cementing casings into boreholes

Abstract

The present invention relates to a kind of towed cementing method of small borehole bushing window sidetracking well, belong to petroleum gas cementing technology field, its technical scheme is:Intelligent short-circuit cycle pipe nipple is together entered into well with well cementation tubing string;Former drilling fluid is injected, cleans annular space, is then implanted sequentially conventional very low-density drilling fluid (or clear water), insulating liquid, cement mortar and the former drilling fluid of specified quantitative;Open short-circuit cycle passage, conventional very low-density drilling fluid (or clear water) is entered annular space, when conventional very low-density drilling fluid (or clear water) completely by after, closing short-circuit cycle passage;Cement mortar is pressed into annular space using pressure differential, forms towed well cementation.The advantage of the invention is that:By reducing annulus fluid density, the stagnation pressure reduction for being subject to shaft bottom, shaft bottom is prevented by pressure break, drastically increase the one-time success rate of small borehole bushing window sidetracking well well cementation, ensure that cementing quality, reduce cost, avoid the pollution of oil-gas Layer.

Description

A kind of towed cementing method of small borehole bushing window sidetracking well
Technical field
The present invention relates to a kind of towed cementing method of small borehole bushing window sidetracking well, belongs to petroleum gas well cementation skill Art field.
Background technology
In the drilling engineering of petroleum industry, cementing technology is that the barefoot interval cementing sealing that will be drilled is formed and can installed The well of development equipment, cementing operation are that the cement mortar prepared is injected into well and sleeve pipe after setting of casing in the well being drilled Annular space, Hou Ning, form firm cement sheath.Small borehole bushing window sidetracking well is to make use of cased wellbores more than casing damaged well section From the offset well or adjustment well of the oil reservoir with a certain distance from casing damaged well section, it has drill change again with original ground DP technology flow The features such as small investment, quick, well life-span suitable with the new well life-span.Slim Hole Sidetracking Technology is that China middle and later periods oil field is used to solve Deformation well, accident well, deepened well and the important means for recovering production capacity with Development volue on old block.Due to small borehole bushing Annular clearance is small when window sidetracking well is cemented the well, flow resistance is big, and one side displacement efficiency is poor, easy channelling, serious reduces well cementation matter Amount, another aspect bottom pressure is larger, excessive bottom pressure fractured well bottom often, causes cement mortar to miss, and causes well cementation to be lost Lose, can only subsequently take perforation to squeeze and block up to remedy, considerably increase well cementation cost, while cement mortar intrusion payzone can pollute oil gas Layer, the rate of oil and gas recovery is reduced, so bottom pressure problems of too urgent need to resolve when small borehole bushing window sidetracking well is cemented the well.Mesh Before, solve small borehole bushing window sidetracking well well cementation circulation problems frequently with low-density Antileakage Cement Slurry technology in casing and cementing, But low-density cement mortar price is high, substantially increases well cementation cost.Meanwhile the density of cement mortar is lower, the performance of Behavior of Hardened Cement Paste is got over Difference, reduce cementing quality, it is impossible to reach preferably well cementation effect.Therefore, towed cementing method can be effective from technique The difficulty such as leakage, displacement efficiency difference caused by solution small borehole bushing window sidetracking well annular clearance is small, flow resistance is big, pump pressure is high Topic.
The content of the invention
The defects of it is an object of the invention to overcome prior art, spy provide a kind of small borehole bushing window sidetracking well traction Formula cementing method, it has construction is simple, and reliability is high, practical, can effectively solve the problem that small borehole bushing window sidetracking well The problems such as leakage, of poor quality, cost is high, pollution oil-gas Layer in well cementing operation.
The purpose of the present invention is achieved through the following technical solutions:A kind of towed well cementation of small borehole bushing window sidetracking well Method, it comprises the following steps:
A, intelligent short-circuit cycle pipe nipple top connects drill string I, and bottom connects drill string II, together enters well with well cementation tubing string, and ensure Intelligent short-circuit cycle pipe nipple is at the 50m-100m of extension hanger upper end;
B, former drilling fluid, cleaning well cementation tubing string and annular space are circulated, ensures that well cementation tubing string inner passage and annulus access are unimpeded It is without hindrance;
C, the conventional very low-density drilling fluid (or clear water) of specified quantitative is injected into well cementation tubing string, former drilling fluid is replaced, pushes away Dynamic intelligence decoding glue core I moves downward, and when intelligently decoding glue core I reaches the ad-hoc location of intelligent short-circuit cycle pipe nipple, intelligence is short Road circulating sub receives decoding open signal I, and control short-circuit cycle passage is opened;
D, after the completion of conventional very low-density drilling fluid (or clear water) is injected, start to inject into well cementation tubing string successively and isolate Liquid and cement mortar, intelligence decoding glue core II is promoted to move downward;
E, after the completion of cement mortar injection, former drilling fluid is injected into well cementation tubing string;
F, when intelligence decoding glue core II reaches the ad-hoc location of intelligent short-circuit cycle pipe nipple, intelligent short-circuit cycle pipe nipple receives Shutdown signal II is decoded, control short-circuit cycle passage is closed;
G, continue to inject former drilling fluid into well cementation tubing string, promote cement mortar to enter annular space, until top cement plug bruising, stop Pump, Hou Ning.
The described liquid for being used to replace former drilling fluid is conventional very low-density drilling fluid (or clear water), is injected conventional special low The amount of density drilling fluid (or clear water) can just be full of intelligent short-circuit cycle pipe nipple upper end annular space.
Described short-circuit cycle passage connects well cementation tubing string inner passage and annular space, makes under intelligent short-circuit cycle pipe nipple (6a) The passage short circuit at end, ensure the ring that conventional very low-density drilling fluid (or clear water) smoothly can enter more than intelligent short-circuit cycle pipe nipple It is empty.
Described intelligent short-circuit cycle pipe nipple carries out open and close and acted twice:Triggered for the first time by intelligence decoding glue core I, intelligence The control system of energy short-circuit cycle pipe nipple receives identification decoding open signal I, control short-circuit cycle passage opening;Lean on intelligence for the second time Glue core II can be decoded to trigger, the control system of intelligent short-circuit cycle pipe nipple receives identification decoding shutdown signal II, and control short circuit follows Ring passage is closed.
Described intelligence decoding glue core I and the center of intelligence decoding glue core II are hollow, can be passed through for liquid.
Described short-circuit cycle passage is closed when going into the well.
A kind of described towed cementing method of small borehole bushing window sidetracking well, utilizes the fluid column and ring cemented the well in tubing string The pressure differential formed between empty fluid column, cement mortar is pressed into by annular space based on self-balancing principle, forms towed well cementation.
Compared with prior art, the beneficial effects of the invention are as follows:Replaced using conventional very low-density drilling fluid (or clear water) Former drilling fluid, due to Action of Gravity Field during well cementation, head of liquid is cemented the well in tubing string less than head of liquid in well cementation tubing string in annular space Pressure differential is automatically formed between fluid column and annular space fluid column, to reach pressure balance, cement mortar is formed towed automatically into annular space Well cementation, the stagnation pressure reduction for being subject to shaft bottom, effectively prevent shaft bottom by pressure break, guarantee cementing quality.The Small Well can effectively be overcome The problem such as leakage, displacement efficiency difference caused by eye casing window sidetracking well well cementation annular clearance is small, flow resistance is big, pump pressure is high, And then improve cementing quality, success rate of cementing the well and the target for reducing cost.
Brief description of the drawings
Fig. 1 is the view for circulating former drilling fluid.
Fig. 2 is the view for injecting conventional very low-density drilling fluid (or clear water).
Fig. 3 is the view for injecting insulating liquid.
Fig. 4 is the view for injecting cement mortar.
Fig. 5 is the view of bottom plug rupture of membranes.
Fig. 6 is the view of top cement plug bruising.
In figure:1-top cement plug, 2-bottom plug, 3-intelligence decoding glue core II, 4-intelligence decoding glue core I, 5-drill string I, 6a-intelligent short-circuit cycle pipe nipple, 6b-short-circuit cycle passage, 7-drill string II, 8-extension hanger, 9-sleeve pipe, 10-ring Sky, 11-barefoot interval, 12-float collar, 13-guide shoe, 14-former drilling fluid, 15-conventional very low-density drilling fluid (or it is clear Water), 16-insulating liquid, 17-cement mortar.
Embodiment
In order that technical characteristic, purpose and the beneficial effect of the present invention can be more clearly understood, with reference to embodiment The present invention will be further described in detail.But the part of the embodiment of the described simply present invention, do not include all implementing Example, it is impossible to be interpreted as the limitation to the scope of the present invention.
A kind of towed cementing method of small borehole bushing window sidetracking well, its specific operating procedure are:
A, the top of drill string I 5 connects cementing head, and the bottom of drill string I 5 connects intelligent short-circuit cycle pipe nipple 6a, intelligent short-circuit cycle pipe nipple 6a bottoms connect drill string II 7, and the bottom of drill string II 7 connects extension hanger 8, the bottom female connector tubing string of extension hanger 8, and casing string includes set Pipe 9, float collar 12 and guide shoe 13, by casing string tripping in barefoot interval 11;
B, pitching is built the pressure, and packer is realized and set;
C, continue to suppress, suppress logical ball seat, establish normal circulation;
D, former drilling fluid 14, cleaning well cementation tubing string and annular space 10 are circulated, ensures that well cementation tubing string inner passage is logical with annular space 10 Road is unblocked;
E, the conventional very low-density drilling fluid (or clear water) 15 of specified quantitative is injected into well cementation tubing string, promotes intelligence decoding glue Core I 4 moves downward, and when intelligently decoding glue core I 4 reaches intelligent short-circuit cycle pipe nipple 6a ad-hoc location, intelligent short-circuit cycle is short Save 6a and receive decoding open signal I, control short-circuit cycle passage 6b is opened;
F, after the completion of conventional very low-density drilling fluid (or clear water) 15 is injected, start to inject specified quantitative into well cementation tubing string Insulating liquid 16 and cement mortar 17, intelligence decoding glue core II 3 is promoted to move downward;
G, when the ad-hoc location for intelligently decoding the intelligent short-circuit cycle pipe nipple 6a of the arrival of glue core II 3, intelligent short-circuit cycle pipe nipple 6a receives decoding shutdown signal II, and control short-circuit cycle passage 6b is closed;
H, inject after the completion of cement mortar 17, injecting former drilling fluid 14 into well cementation tubing string is circulated, the rupture of membranes of bottom plug 2, Annular space 10 between the sleeve pipe 9 of cement mortar 17 and barefoot interval 11, cement mortar 17 replace former drilling fluid 14;
I, until the bruising of top cement plug 1, geostatic pressure rise certain value quickly, the signal instruction cement mortar 17 has replaced Position, construction terminate;
J, termination of pumping, Hou Ning.
The great representativeness of above example, has simple to operate, securely and reliably, can realize stable well cementation effect, carry High cementing quality, has saved well cementation cost, can preferably realize cementing method of the present invention.

Claims (7)

1. a kind of towed cementing method of small borehole bushing window sidetracking well, it is characterised in that it comprises the following steps:
a:Drill string I (5) top connects cementing head, and drill string I (5) bottom connects intelligent short-circuit cycle pipe nipple (6a), and intelligent short-circuit cycle is short Section (6a) bottom connects drill string II (7), and drill string II (7) bottom connects extension hanger (8), extension hanger (8) bottom female connector tubing string, Casing string includes sleeve pipe (9), float collar (12) and guide shoe (13), by casing string tripping in barefoot interval (11), and ensures intelligent short circuit Circulating sub (6a) is at extension hanger (8) upper end 50m-100m;
b:Former drilling fluid (14), cleaning well cementation tubing string and annular space (10) are circulated, ensures well cementation tubing string inner passage and annular space (10) Passage is unblocked;
c:The conventional very low-density drilling fluid (or clear water) (15) of specified quantitative is injected into well cementation tubing string, promotes intelligence decoding glue core I (4) move downward, and when intelligently decoding glue core I (4) reaches the ad-hoc location of intelligent short-circuit cycle pipe nipple (6a), intelligent short circuit follows Ring pipe nipple (6a) receives decoding open signal I, and control short-circuit cycle passage (6b) is opened;
d:When conventional very low-density drilling fluid (or clear water) (15) inject after the completion of, start to well cementation tubing string in be implanted sequentially it is specific The insulating liquid (16) and cement mortar (17) of amount, intelligence decoding glue core II (3) is promoted to move downward;
e:When intelligently decoding glue core II (3) reaches the ad-hoc location of intelligent short-circuit cycle pipe nipple (6a), intelligent short-circuit cycle pipe nipple (6a) receives decoding shutdown signal II, and control short-circuit cycle passage (6b) is closed;
f:Inject after the completion of cement mortar (17), injecting former drilling fluid (14) into well cementation tubing string is circulated, and promotes cement mortar (17) annular space (10) is entered;
g:After top cement plug (1) bruising, termination of pumping, Hou Ning.
A kind of 2. towed cementing method of small borehole bushing window sidetracking well according to claim 1, it is characterised in that:With It is conventional very low-density drilling fluid (or clear water) (15) in the liquid of the former drilling fluid (14) of replacement, the conventional very low-density of injection bores The amount of well liquid (or clear water) (15) can just be full of intelligent short-circuit cycle pipe nipple (6a) upper end annular space (10).
A kind of 3. towed cementing method of small borehole bushing window sidetracking well according to claim 1, it is characterised in that:It is short Road circulation canal (6b) connects well cementation tubing string inner passage and annular space (10), makes the passage of intelligent short-circuit cycle pipe nipple (6a) lower end Short circuit.
A kind of 4. towed cementing method of small borehole bushing window sidetracking well according to claim 1, it is characterised in that:Gu Intelligent short-circuit cycle pipe nipple (6a) progress open and close act twice during well, for the first time by intelligently decoding glue core I (4) triggering, intelligence The control system of energy short-circuit cycle pipe nipple (6a) receives identification decoding open signal I, control short-circuit cycle passage (6b) opening;The Secondary to be triggered by intelligently decoding glue core II (3), the control system of intelligent short-circuit cycle pipe nipple (6a), which receives identification decoding and closed, to be believed Number II, control short-circuit cycle passage (6b) is closed.
A kind of 5. towed cementing method of small borehole bushing window sidetracking well according to claim 1, it is characterised in that:Intelligence It is hollow that the center of glue core I (4) and intelligence decoding glue core II (3), which can be decoded,.
A kind of 6. towed cementing method of small borehole bushing window sidetracking well according to claim 1, it is characterised in that:It is short Road circulation canal (6b) is closed when going into the well.
A kind of 7. towed cementing method of small borehole bushing window sidetracking well according to claim 1, it is characterised in that:Profit With the pressure differential between the fluid column and annular space (10) fluid column in well cementation tubing string, cement mortar (17) is pressed into by ring based on self-balancing principle Empty (10), form towed well cementation.
CN201710845719.9A 2017-09-19 2017-09-19 A kind of towed cementing method of small borehole bushing window sidetracking well Active CN107489396B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710845719.9A CN107489396B (en) 2017-09-19 2017-09-19 A kind of towed cementing method of small borehole bushing window sidetracking well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710845719.9A CN107489396B (en) 2017-09-19 2017-09-19 A kind of towed cementing method of small borehole bushing window sidetracking well

Publications (2)

Publication Number Publication Date
CN107489396A true CN107489396A (en) 2017-12-19
CN107489396B CN107489396B (en) 2019-07-19

Family

ID=60651739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710845719.9A Active CN107489396B (en) 2017-09-19 2017-09-19 A kind of towed cementing method of small borehole bushing window sidetracking well

Country Status (1)

Country Link
CN (1) CN107489396B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108979583A (en) * 2018-07-12 2018-12-11 马弘毅 A kind of sidetracked hole layer and section cementing unit and application method
CN109403916A (en) * 2018-12-05 2019-03-01 田振林 A kind of thermally conductive well shaft fixing technology of geothermal well
CN111706259A (en) * 2020-07-14 2020-09-25 中国石油集团渤海钻探工程有限公司 Method for solving casing deformation by sidetracking old well paste-salt section reaming unfixed well
CN112943161A (en) * 2021-01-14 2021-06-11 中国石油天然气股份有限公司 Side drilling is exempted from to hang and can be lost hand well cementation well completion device
CN114109309A (en) * 2020-08-28 2022-03-01 中国石油化工股份有限公司 Underground infinite-stage fracturing sliding sleeve

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5301760A (en) * 1992-09-10 1994-04-12 Natural Reserves Group, Inc. Completing horizontal drain holes from a vertical well
CN1621658A (en) * 2003-11-28 2005-06-01 大港油田集团有限责任公司 Well cementing technology by center tube replacing elutriation method
CN1632278A (en) * 2003-12-24 2005-06-29 大港油田集团有限责任公司 Big tail pipe side drilling well cementing technology
CN103362473A (en) * 2012-10-24 2013-10-23 中国石油化工股份有限公司 Graded variable density well cementation technology
CN104963653A (en) * 2015-07-24 2015-10-07 中石化华东石油工程有限公司 Cementing technology for 5.5-cun sleeve windowed side drilled slim hole
CN106223917A (en) * 2016-08-01 2016-12-14 中国石油集团川庆钻探工程有限公司工程技术研究院 A kind of side tracked slim hole layered fracturing pipe string and method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5301760A (en) * 1992-09-10 1994-04-12 Natural Reserves Group, Inc. Completing horizontal drain holes from a vertical well
US5301760C1 (en) * 1992-09-10 2002-06-11 Natural Reserve Group Inc Completing horizontal drain holes from a vertical well
CN1621658A (en) * 2003-11-28 2005-06-01 大港油田集团有限责任公司 Well cementing technology by center tube replacing elutriation method
CN1632278A (en) * 2003-12-24 2005-06-29 大港油田集团有限责任公司 Big tail pipe side drilling well cementing technology
CN103362473A (en) * 2012-10-24 2013-10-23 中国石油化工股份有限公司 Graded variable density well cementation technology
CN104963653A (en) * 2015-07-24 2015-10-07 中石化华东石油工程有限公司 Cementing technology for 5.5-cun sleeve windowed side drilled slim hole
CN106223917A (en) * 2016-08-01 2016-12-14 中国石油集团川庆钻探工程有限公司工程技术研究院 A kind of side tracked slim hole layered fracturing pipe string and method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张凯等: "国内外小井眼固井技术研究现状", 《钻采工艺》 *
张文泽等: "开窗侧钻小井眼、小间隙井", 《化学工程师》 *
蒋海涛等: "小井眼开窗侧钻井固井工艺技术", 《石油钻采工艺》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108979583A (en) * 2018-07-12 2018-12-11 马弘毅 A kind of sidetracked hole layer and section cementing unit and application method
CN108979583B (en) * 2018-07-12 2020-11-17 福州宇卓科技有限公司 Sidetracking well layering and segmenting cementing device and using method
CN109403916A (en) * 2018-12-05 2019-03-01 田振林 A kind of thermally conductive well shaft fixing technology of geothermal well
CN111706259A (en) * 2020-07-14 2020-09-25 中国石油集团渤海钻探工程有限公司 Method for solving casing deformation by sidetracking old well paste-salt section reaming unfixed well
CN114109309A (en) * 2020-08-28 2022-03-01 中国石油化工股份有限公司 Underground infinite-stage fracturing sliding sleeve
CN112943161A (en) * 2021-01-14 2021-06-11 中国石油天然气股份有限公司 Side drilling is exempted from to hang and can be lost hand well cementation well completion device

Also Published As

Publication number Publication date
CN107489396B (en) 2019-07-19

Similar Documents

Publication Publication Date Title
CN107489396B (en) A kind of towed cementing method of small borehole bushing window sidetracking well
CN101864921B (en) Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN201705219U (en) Lateral drilling gravel pack completion string
CN103867119B (en) Coal seam reservoirs completion remodeling method
CN105756650B (en) It is a kind of that the outer method altered and realize horizontal well fracturing is managed using mixing diverting agent closure
CN109653707B (en) Method for dewatering and increasing oil by filling packing body particles in oil and gas well of fractured oil and gas reservoir
CN101787854A (en) Subsection well completion system of bottom water reservoir horizontal well
CN106555565A (en) A kind of low pressure and easy leaking loses the cementing method that well positive injection is instead squeezed
CN110424912A (en) Method, the row's of returning service unit and the completion structure of tubing string replacement filling layer are not changed
CN102182421A (en) Segmented water plugging method of liquid bridge plug of horizontal well
CN103452531B (en) Oil pipe under underbalance, no killing well gaslift, turn the method for taking out, examining pump and maintenance oil pipe
CN101532375B (en) Method for recycling for failure of stage cementing unit and sealed circulation device
CN201738822U (en) String for upper horizontal well cementation and lower screen pipe gravel pack completion
CN105178910A (en) Water-plugging process tubing string and method of horizontal wells
CN103670271A (en) Dual-cycle relay coal bed well drilling method
CN108625841A (en) A kind of refracturing method that the sealing of horizontal well annular space is made with pitching sliding sleeve connection
CN103470221B (en) Method made by the connection that pump was taken out and examined to oil pipe under underbalance, no killing well gaslift, axle
CN108049816A (en) The narrow pressure window well four of deep water opens time Casing Program Design Method
CN108049817A (en) The narrow pressure window well five of deep water opens time Casing Program Design Method
CN103711473A (en) Double-circulation relay type method for drilling and completing coal seam composite well
CN106337667A (en) Dual-opening horizontal well cementation and completion construction method
CN110067528A (en) A kind of injecting cement in oil well method and single current cementing tool
AU2021104224A4 (en) Sectional Cementing Technology for Deep Trona Drilling and Mining
CN105178905A (en) Process tubing string and method for integrated setting and channeling testing of bridge plugs of horizontal wells
CN201381824Y (en) Sealed circulation device for stage-cementing device invalidation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhang Derong

Inventor after: Zhao Lu

Inventor after: Pu Yangfeng

Inventor after: Kong Chunyan

Inventor after: Sun Linping

Inventor after: Wu Simeng

Inventor after: Yang Zhihao

Inventor after: Yue Huawei

Inventor after: Xie Wujun

Inventor before: Zhang Derong

Inventor before: Pu Yangfeng

Inventor before: Kong Chunyan

Inventor before: Sun Linping

Inventor before: Wu Simeng

Inventor before: Yang Zhihao

Inventor before: Yue Huawei

Inventor before: Xie Wujun

CB03 Change of inventor or designer information