CN114703855A - Device for improving post-grouting quality of cast-in-place pile and construction method - Google Patents

Device for improving post-grouting quality of cast-in-place pile and construction method Download PDF

Info

Publication number
CN114703855A
CN114703855A CN202210138744.4A CN202210138744A CN114703855A CN 114703855 A CN114703855 A CN 114703855A CN 202210138744 A CN202210138744 A CN 202210138744A CN 114703855 A CN114703855 A CN 114703855A
Authority
CN
China
Prior art keywords
grouting
pile
head
grouting pipe
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210138744.4A
Other languages
Chinese (zh)
Inventor
张水红
周叙伦
徐超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202210138744.4A priority Critical patent/CN114703855A/en
Publication of CN114703855A publication Critical patent/CN114703855A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to the technical field of building construction, and particularly relates to a device and a construction method for improving the post-grouting quality of a cast-in-place pile. The pile side grouting device comprises a steel reinforcement cage, a pile end grouting head, a pile side grouting head and a grouting pipe, wherein the grouting pipe comprises a first grouting pipe and a second grouting pipe, the first grouting pipe and the second grouting pipe are respectively connected with the pile end grouting head and the pile side grouting head, the first grouting pipe and the second grouting pipe are respectively fixed on the inner side and the outer side of the steel reinforcement cage, and grouting engineering can be simultaneously carried out on the ground and a side soil body through the matching of the pile end grouting head and the pile side grouting head. The pile end guniting head has the guniting and pressurizing effects, so that sediment and soil bodies near the pile end are compact, a 'bottom expanding' effect is generated, the end bearing capacity is improved, the pile side grout outlet can be bent and formed and is tightly attached to the side wall of the hole pile, grout can penetrate into soil bodies along the gap to fill the gap, the soil bodies are enabled to be consolidated, the soil body strength of a grouting area is improved, and the construction quality of post-grouting of a pile foundation and the bearing capacity of the pile foundation are improved.

Description

Device for improving post-grouting quality of cast-in-place pile and construction method
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a device and a construction method for improving the post-grouting quality of a cast-in-place pile.
Background
In the construction of buildings in China, a pile foundation is used as a structural form applied to the building foundation, the sediment at the bottom of a hole cannot be guaranteed to be removed by 100% to meet the design requirement no matter the current construction process of the cast-in-situ bored pile is a forward circulation method or a reverse circulation method, and the requirement cannot be met even if the hole is cleaned for the second time can be obtained from the results of the sediment thickness tester test and the static load detection.
Because the sediment at the bottom of the pile is thick, the bearing force at the pile end can not be fully exerted, which is particularly obvious for the pile with the pile end entering a compact sand layer. Therefore, how to solve the above problems and improve the vertical load capacity of the cast-in-situ bored pile becomes a practical problem to be solved in the engineering.
In the prior art, post grouting of a cast-in-situ bored pile basically belongs to the combination of split grouting and infiltration grouting. The so-called cleavage grouting is that high-pressure slurry of sub-shavings overcomes the initial pressure stress on the main stress surface of the soil body to cause cleavage damage to the soil body, the slurry permeates into soil body filling gaps along cleavage gaps and compacts pile side soil to promote the consolidation of the soil body so as to improve the soil body strength of a grouting area. If the grouting area is at the bottom of the pile, the grout is firstly split and permeated in the sediment area at the bottom of the pile, so that sediment and soil bodies near the end of the pile are compact, a bottom expanding effect is generated, the end bearing capacity is improved, and if the grouting area is at a certain part on the side of the pile, the diameter expanding effect is also generated at the certain part. The material is found out from the actual measurement of a large number of test piles, the end bearing capacity of the pile is improved after the pile bottom is grouted, and the side frictional resistance of the pile within the range of 5m above the end and even more is also greatly improved. If grouting is carried out on a certain section of the pile side, the friction resistance of the pile side within a certain range above the section is also obviously improved.
However, in the prior art, the grouting failure caused by the blockage of the grout outlet is easy to occur; pile side slip casting pipe ligature is in the steel reinforcement cage outside, often pours slip casting pipe and whitewashing head in concrete in the concrete placement construction, and the condition of jam appears very easily in the slip casting pipe.
Disclosure of Invention
In order to solve the technical problems, the invention belongs to the technical field of building construction, and particularly relates to a device for improving the post-grouting quality of a cast-in-place pile and a construction method.
The technical scheme adopted by the invention is as follows: the utility model provides a device of grouting quality behind improvement bored concrete pile, includes pile tip whitewashing head, stake side whitewashing head, steel reinforcement cage and slip casting pipe, its characterized in that: the grouting pipes comprise a first grouting pipe and a second grouting pipe, the first grouting pipe and the second grouting pipe are respectively arranged on the inner side and the outer side of the reinforcement cage, the first grouting pipe is connected with the pile end guniting head, and the second grouting pipe is connected with the pile side guniting head;
the pile end guniting head and the pile side guniting head can simultaneously spray grouting on soil bodies at the bottom of the reinforcement cage and on the side edge of the reinforcement cage.
Furthermore, the pile end guniting head is provided with a conical nozzle, the surface of the conical nozzle is provided with a plurality of grout outlets, and the conical nozzle is matched with the grout outlets to rapidly spray grouting grout and increase the spraying area of the grouting grout.
Furthermore, the pile side guniting head is provided with a flexible nozzle, and the flexible nozzle can adjust the grouting injection direction.
Furthermore, the grouting pipe is provided with a connecting sleeve, and the connecting sleeve can connect the first grouting pipe and the second grouting pipe with the pile end guniting head and the pile side guniting head respectively.
Further, the pile side guniting head is provided with a fixing device, and the fixing device can be connected with the second grouting pipe and fixes the pile side guniting head.
Furthermore, the pile end guniting head is provided with a plugging plate, and the plugging plate is arranged on the outer side of the conical nozzle and can adjust the opening and closing of the conical nozzle.
Further, the flexible nozzle is provided with a protective plug which can prevent the grouting from flowing back.
Further, the grouting pipe is provided with a fastener, and the fastener can fasten the grouting pipe on the reinforcement cage.
Further, a construction method of the device for improving the post-grouting quality of the cast-in-place pile is characterized by comprising the following steps:
placing the first grouting pipe on the inner side of the reinforcement cage, and placing the second grouting pipe on the outer side of the reinforcement cage;
the pile end guniting head is arranged at one end, close to the ground, of the first grouting pipe;
the pile side guniting head is installed at one end, close to the ground, of the second grouting pipe;
and the pile end guniting head and the pile side guniting head simultaneously carry out grouting and guniting on the ground and the side soil body to finish grouting.
The invention has the advantages and positive effects that: by adopting the technical scheme, the pile end guniting head adopts a conical structure, has guniting pressurization effect, and the grout is firstly split and permeated in a sediment zone at the bottom of the pile, so that sediment and soil bodies near the pile end are compact, a bottom expanding effect is generated, the end bearing capacity is improved, the problem that a grouting pipe is blocked by concrete is solved, and the construction quality of post-grouting of a pile foundation is improved.
The pile side grout outlet can be bent and formed by adopting the flexible high-pressure grout spraying port, the side wall of the hole pile can be tightly attached to the steel reinforcement cage when the steel reinforcement cage is placed, the grout can penetrate into a soil body along a gap to fill a gap, and pile side soil is compacted, so that the soil body is solidified, the soil body strength of a grouting area is improved, the construction quality of grouting after a pile foundation is improved, and the bearing capacity of the pile foundation is improved.
Drawings
FIG. 1 is a schematic view of a construction structure according to an embodiment of the present invention;
FIG. 2 is a schematic view of a grout tube according to an embodiment of the present invention;
FIG. 3 is a schematic view of a conical spray head according to an embodiment of the invention;
FIG. 4 is a schematic view of a flexible nozzle tip according to an embodiment of the present invention
In the figure:
1. reinforcing cage 2, pile end guniting head 3 and conical nozzle
4. Pile side guniting head 5, flexible nozzle 6 and sealing plug
7. Fixing device 8, slip casting pipe 9, first slip casting pipe
10. Second slip casting pipe 11, connecting sleeve 12 and fastener
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings in conjunction with the following detailed description. It should be understood that the description is intended to be exemplary only, and is not intended to limit the scope of the present invention. In addition, in the following description, descriptions of techniques for well-known structures are omitted so as to avoid unnecessarily obscuring the concepts of the present invention.
Embodiments of the present invention will be described below with reference to the accompanying drawings.
A device for improving the post-grouting quality of a cast-in-place pile and a construction method thereof comprise a reinforcement cage 1, a pile end grouting head 2, a conical nozzle 3, a pile side grouting head 4, a flexible nozzle 5, a sealing plug 6, a fixing device 7, a grouting pipe 8, a first grouting pipe 9, a second grouting pipe 10, a connecting sleeve 11 and a fastener.
As shown in fig. 1, in the embodiment of the present invention, a grouting pipe 8 is installed in a reinforcement cage 1, wherein the grouting pipe 8 is divided into a first grouting pipe 9 and a second grouting pipe 10, the first grouting pipe 9 is oppositely disposed at the inner side of the reinforcement cage 1, and the first grouting pipe 9 is fixed on the reinforcement cage 1 through a fastener 12; the second grouting pipe 10 is arranged on the outer side of the reinforcement cage 1, and the second grouting pipe 10 is fixed on the reinforcement cage 1 through a fastener 12; pile end grouting head 2 and pile side grouting head 4 are installed respectively to the one end that is close to ground at first slip casting pipe 9 and second slip casting pipe 10, and the grout is spouted from pile end shotcrete head 2 and pile side shotcrete head 4 through first slip casting pipe 9 and second slip casting pipe 10, realizes pouring simultaneously ground and side soil body, has improved the efficiency of construction, makes the slip casting process more convenient and the slip casting effect obtains showing and promotes.
Preferably, as shown in fig. 2, the grouting pipes 8 can be connected through connecting sleeves 11, so that the grouting pipes 8 can adapt to reinforcement cages 1 with different lengths, and the injection engineering of cast-in-place piles with different depths can be adapted through the matching connection between the connecting sleeves 11 and the grouting pipes 8
Preferably, as shown in fig. 3, the pile end grouting head 2 is connected with the first grouting pipe 9 through a connecting sleeve 11, the conical nozzle 3 is installed at the pile end grouting head 2, the surface of the conical nozzle 3 is provided with a plurality of grout outlets, the conical nozzle 3 can rapidly spray grouting grout and increase the spraying area of grouting grout by matching with the grout outlets, the construction efficiency of grouting on the ground is improved, and the coverage area is wide; the conical nozzle 3 is provided with the plugging plate, the plugging plate can close or open the conical nozzle 3 through opening and closing, and the plugging plate can prevent the blockage of the grouting pipe 8 caused by the backflow of slurry in the process of lowering the reinforcement cage 1, so that protective measures are provided for smooth construction and repeated use of the embodiment of the invention.
Preferably, as shown in fig. 4, the pile side guniting head 4 is also connected with a second grouting pipe 10 through a connecting sleeve 11, a flexible nozzle 5 is installed on the pile side guniting head 4, the nozzle direction of the flexible nozzle 5 can be adjusted, grouting is carried out towards a place needing construction, a sealing plug 6 is arranged at a nozzle of the flexible nozzle 5, the sealing plug 6 can prevent slurry from flowing back to cause blockage of the grouting pipe 8 in the lowering process of the reinforcement cage 1, and the sealing plug 6 can be pulled out of the nozzle in a pulling line mode after being lowered to a preset position. Protective measures are provided for smooth construction and repeated use of the embodiment of the invention; the pile side grouting head 4 is also provided with a fixing device 7, the fixing device 7 is connected with the fixing ring through a buckle to enable the flexible nozzle 5 to be fixed after being adjusted to a specified direction, so that the flexible nozzle 5 cannot be taken away from the specified direction along with a large amount of grouting injection processes, and the grouting efficiency of a soil body on the side is improved.
Example 1:
when the reinforcement cage 1 is manufactured, the first grouting pipe 9 and the second grouting pipe 10 are installed together, and the first grouting pipe 9 and the second grouting pipe 10 are respectively fixed on the inner side and the outer side of the reinforcement cage 1 through fasteners 12; a pile end guniting head 2 is arranged at one end of the first grouting pipe 9 close to the ground through a connecting sleeve 11, and a pile side guniting head 4 is arranged at one end of the second grouting pipe 10 close to the ground through the connecting sleeve 11; simultaneously, a conical nozzle 3 and a flexible nozzle 5 are respectively arranged on the pile end guniting head 2 and the pile side guniting head 4, the grouting direction of the flexible nozzle 5 is adjusted, a sealing plug is arranged at the nozzle of the flexible nozzle 5, the grouting direction of the flexible nozzle 5 is fixed through a fixing device, and a plugging plate is arranged on the outer side of the conical nozzle 3.
And (5) after the installation, lowering the reinforcement cage 1. After the pile foundation concrete is poured, the grouting operation is suitable for starting two days after the pile is formed, and is not suitable for exceeding 30 days after the pile is formed. The compound grouting sequence is that the pile side is firstly followed by the pile end, and the grouting interval of the pile end at the pile side is not less than 2 hours.
The embodiment of the invention has the advantages that: the pile end guniting head adopts a conical structure, has a guniting pressurization effect, and grout is firstly split and permeated in a sediment area at the bottom of a pile, so that sediment and soil bodies near the pile end are compact, a bottom expanding effect is generated, the end bearing capacity is improved, the problem that a grouting pipe is blocked by concrete is solved, and the construction quality of grouting after a pile foundation is improved.
The pile side grout outlet can be bent and formed by adopting the flexible high-pressure grout spraying port, the side wall of the hole pile can be tightly attached to the steel reinforcement cage when the steel reinforcement cage is placed, the grout can penetrate into a soil body along a gap to fill a gap, and pile side soil is compacted, so that the soil body is solidified, the soil body strength of a grouting area is improved, the construction quality of grouting after a pile foundation is improved, and the bearing capacity of the pile foundation is improved.
The embodiments of the present invention have been described in detail, but the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.

Claims (9)

1. The utility model provides a device of grouting quality behind improvement bored concrete pile, includes steel reinforcement cage, stake end whitewashing head, stake side whitewashing head and slip casting pipe, its characterized in that: the grouting pipes comprise a first grouting pipe and a second grouting pipe, the first grouting pipe and the second grouting pipe are respectively arranged on the inner side and the outer side of the reinforcement cage, the first grouting pipe is connected with the pile end guniting head, and the second grouting pipe is connected with the pile side guniting head;
the pile end guniting head and the pile side guniting head can simultaneously spray grouting on soil bodies at the bottom of the reinforcement cage and on the side edge of the reinforcement cage.
2. The device for improving the post-grouting quality of the cast-in-place pile according to claim 1, characterized in that: the pile end grouting head is provided with a conical nozzle, the surface of the conical nozzle is provided with a plurality of grout outlets, and the conical nozzle can be matched with the grout outlets to quickly spray grouting and increase the spraying area of the grouting.
3. The device for improving the post-grouting quality of the cast-in-place pile according to claim 1, characterized in that: the pile side guniting head is provided with a flexible nozzle, and the flexible nozzle can adjust the grouting injection direction.
4. The device for improving the post-grouting quality of the cast-in-place pile according to claim 1, characterized in that: the grouting pipe is provided with a connecting sleeve, and the first grouting pipe and the second grouting pipe can be connected with the pile end guniting head and the pile side guniting head respectively through the connecting sleeve.
5. The device for improving the post-grouting quality of the cast-in-place pile according to claim 1, characterized in that: the pile side guniting head is provided with a fixing device, and the fixing device can be connected with the second grouting pipe and fixes the pile side guniting head.
6. The device for improving the post-grouting quality of the cast-in-place pile according to claim 2, characterized in that: the pile end guniting head is provided with a plugging plate, and the plugging plate is arranged on the outer side of the conical nozzle and can adjust the opening and closing of the conical nozzle.
7. The apparatus for improving the post-grouting quality of a cast-in-place pile according to claim 3, wherein: the flexible nozzle is provided with a sealing plug which can prevent the backflow of the perfusion slurry.
8. The device for improving the post-grouting quality of the cast-in-place pile according to claim 4, characterized in that: the grouting pipe is provided with a fastener, and the fastener can fasten the grouting pipe on the reinforcement cage.
9. A method of constructing an apparatus for improving post-grouted pile grouting quality according to claim 1, wherein the method comprises the steps of:
placing the first grouting pipe on the inner side of the reinforcement cage, and placing the second grouting pipe on the outer side of the reinforcement cage;
the pile end guniting head is installed at one end, close to the ground, of the first grouting pipe;
the pile side guniting head is installed at one end, close to the ground, of the second grouting pipe;
and the pile end guniting head and the pile side guniting head simultaneously carry out grouting and guniting on the ground and the side soil body to finish grouting.
CN202210138744.4A 2022-02-15 2022-02-15 Device for improving post-grouting quality of cast-in-place pile and construction method Pending CN114703855A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210138744.4A CN114703855A (en) 2022-02-15 2022-02-15 Device for improving post-grouting quality of cast-in-place pile and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210138744.4A CN114703855A (en) 2022-02-15 2022-02-15 Device for improving post-grouting quality of cast-in-place pile and construction method

Publications (1)

Publication Number Publication Date
CN114703855A true CN114703855A (en) 2022-07-05

Family

ID=82167238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210138744.4A Pending CN114703855A (en) 2022-02-15 2022-02-15 Device for improving post-grouting quality of cast-in-place pile and construction method

Country Status (1)

Country Link
CN (1) CN114703855A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006307593A (en) * 2005-05-02 2006-11-09 Taisei Corp Grout pipe and grouting in cast-in-place concrete pile
CN101509352A (en) * 2009-03-11 2009-08-19 西南石油大学 Drill with flexible nozzle
CN104452746A (en) * 2013-09-23 2015-03-25 中国建筑股份有限公司上海分公司 Construction method for bored pile
CN214657036U (en) * 2021-02-23 2021-11-09 赵鹏举 High-pressure injection grouting spray head
CN217174793U (en) * 2022-02-15 2022-08-12 中冶天工集团有限公司 Device for improving post-grouting quality of cast-in-place pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006307593A (en) * 2005-05-02 2006-11-09 Taisei Corp Grout pipe and grouting in cast-in-place concrete pile
CN101509352A (en) * 2009-03-11 2009-08-19 西南石油大学 Drill with flexible nozzle
CN104452746A (en) * 2013-09-23 2015-03-25 中国建筑股份有限公司上海分公司 Construction method for bored pile
CN214657036U (en) * 2021-02-23 2021-11-09 赵鹏举 High-pressure injection grouting spray head
CN217174793U (en) * 2022-02-15 2022-08-12 中冶天工集团有限公司 Device for improving post-grouting quality of cast-in-place pile

Similar Documents

Publication Publication Date Title
CN104234055B (en) A kind of prefabricated pile post-grouting device and technique thereof
CN108457266B (en) Post-grouting device and method for pile side of cast-in-place pile
CN101761345A (en) Reinforcement device for tunnel top soil and construction method thereof
CN102777189A (en) Intermediate-jacking-station-free jacking construction device of ultra-long pipe roof and method thereof
CN201770981U (en) Tube-side injection grouting apparatus for simultaneous drilling pipe pile
CN104074190A (en) Secondary high-pressure grouting expansion bit anchor rod and construction method thereof
CN217174793U (en) Device for improving post-grouting quality of cast-in-place pile
CN202970719U (en) Relay chamber-free jacking construction device for ultra-long pipe roof
CN106838463B (en) The fastener inserts and usage of longitudinal overall stiffness after raising rectangular top plumber
CN207959225U (en) One kind is certainly into the pull-type steel sheet pile supporting construction of churning anchor
CN110004927A (en) Prestressing force miniature pile construction method
CN111042142B (en) Post-grouting construction and grouting failure processing device for pile end
CN111733894A (en) Anti-floating system of deep foundation pit underground structure and construction process
CN114703855A (en) Device for improving post-grouting quality of cast-in-place pile and construction method
CN211446931U (en) Grouting pipe structure of post-grouting bored pile in desert area
CN211368723U (en) Novel grouting pipe
WO2022134224A1 (en) Construction method for pre-stressed pull-resistant anchor rod of concrete expansion head
CN114525781A (en) Prestressed rod core bag grouting combined anti-floating component and construction method
CN212742508U (en) U-shaped reinforced concrete sheet pile for preventing seepage under soft soil foundation gate bottom plate
CN108301400B (en) Hollow drainage anchoring anti-slide pile and construction method thereof
CN113718752A (en) Ground diaphragm wall composite grouting method and grouting structure
CN109024622B (en) Use method of slope reinforcement rod piece
CN105672328B (en) Slip casting ductule resists the H profile steel foundation pit support device of earth lateral pressure
CN220620152U (en) Slope rock stratum reinforcing device
CN217870574U (en) Structure for applying locking steel sheet pile to water-stop curtain between piles

Legal Events