CN114633768A - Carrier cable laying and braiding method - Google Patents
Carrier cable laying and braiding method Download PDFInfo
- Publication number
- CN114633768A CN114633768A CN202210131838.9A CN202210131838A CN114633768A CN 114633768 A CN114633768 A CN 114633768A CN 202210131838 A CN202210131838 A CN 202210131838A CN 114633768 A CN114633768 A CN 114633768A
- Authority
- CN
- China
- Prior art keywords
- rope
- cable
- steel wire
- steel
- wire rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009954 braiding Methods 0.000 title claims abstract description 25
- 238000000034 method Methods 0.000 title claims abstract description 18
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 58
- 239000010959 steel Substances 0.000 claims abstract description 58
- 230000000087 stabilizing effect Effects 0.000 claims abstract description 4
- 238000003466 welding Methods 0.000 claims abstract description 4
- 239000000835 fiber Substances 0.000 claims description 3
- 238000004804 winding Methods 0.000 claims description 2
- 238000009940 knitting Methods 0.000 abstract description 8
- 238000009435 building construction Methods 0.000 abstract description 2
- 239000011111 cardboard Substances 0.000 description 3
- 239000004677 Nylon Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 229920001778 nylon Polymers 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61B—RAILWAY SYSTEMS; EQUIPMENT THEREFOR NOT OTHERWISE PROVIDED FOR
- B61B12/00—Component parts, details or accessories not provided for in groups B61B7/00 - B61B11/00
- B61B12/007—Cable tensioning devices
Landscapes
- Engineering & Computer Science (AREA)
- Transportation (AREA)
- Mechanical Engineering (AREA)
- Ropes Or Cables (AREA)
Abstract
The invention relates to the technical field of building construction, and discloses a carrying cable laying and braiding method, which comprises the following steps: s1, placing the steel wire rope on a cable tray frame at a station according to the rope outlet direction of the steel wire rope, flatly cushioning and compacting the bottom of the cable tray frame, slowly jacking the steel wire rope by using a jack, leaving 10-20 cm from the original support, leveling a rope releasing central shaft, welding the cable tray frames at two sides by using channel steel or a round pipe to form a firm whole, and stabilizing the cable tray frame by using a chain block in the opposite direction of the rope outlet direction of the steel wire rope; s2, lifting a rope releasing working rope onto a bracket rope supporting wheel on a line from a lower station to an upper station by using a cargo rope traction rope as a traction rope when releasing the steel rope of the passenger ropeway; s3, at the lower station, one end of the cable releasing working rope is braided with the steel wire rope of the cableway; when the method is adopted to knit the steel cable, the tightness is controlled uniformly during knitting through the arrangement of the clamping plate clamps and the auxiliary action of the anti-reverse device, and the strength of the ropeway after knitting is higher.
Description
Technical Field
The invention relates to the technical field of building construction, in particular to a method for laying and braiding a carrying cable.
Background
Cableways are commonly used to transport passengers or materials. There are two types of cableways, reciprocating type and circulating type. The former hangs a passenger carriage on the carrying cable at both sides of the line bracket, and is dragged by one or two traction cables to move back and forth along the line; the latter is respectively hung with a plurality of passenger carriages or hanging chairs on the steel wire ropes at two sides of the line bracket at equal intervals, and the steel wire ropes are driven by a driver to circularly run.
However, when the carrying rope is manufactured, the steel cable needs to be braided to improve the firmness of the cableway, and the carrying rope is usually braided by a braiding machine, so that the braiding mode is simple, the tension degree is not uniformly controlled, and the braided strength is low.
Therefore, there is a need to provide a carrier rope laying braiding method that solves the above-mentioned problems.
Disclosure of Invention
The invention aims to provide a carrying cable laying and braiding method to solve the problems in the background technology.
Based on the above thought, the invention provides the following technical scheme: a carrier rope laying braiding method, comprising the steps of:
s1, placing the steel wire rope on a cable tray frame at a station according to the rope outlet direction of the steel wire rope, flatly cushioning and compacting the bottom of the cable tray frame, slowly jacking the steel wire rope by using a jack, leaving 10-20 cm from the original support, leveling a rope releasing central shaft, welding the cable tray frames at two sides by using channel steel or a round pipe to form a firm whole, and stabilizing the cable tray frame by using a chain block in the opposite direction of the rope outlet direction of the steel wire rope;
s2, lifting a rope releasing working rope onto a bracket rope supporting wheel on a line from a lower station to an upper station by using a cargo rope traction rope as a traction rope when releasing the steel rope of the passenger ropeway;
s3, at the lower station, one end of the cable releasing working rope is braided with the steel wire rope of the cableway, and the other end of the cable releasing working rope winds into the winch drum;
s4, starting a winch, and drawing a working rope to release the steel rope of the cableway;
and S5, tightening the cable by using a motorized winch, stopping for 72 hours after the tension reaches the design tension, and if the design tension is reduced, tightening again until the design tension is reached, and then braiding.
As a further scheme of the invention, the braiding length of the carrying cable and the working cable comprises a core-spun length and an inserting length, the core-spun length is not less than 12 meters, the inserting length is not less than 2 meters, and the joint position is protected by a steel anchor head.
As a further scheme of the invention, 30 meters of the carrying cable is reserved before the carrying cable is applied, a first anti-rotation is carried out, then a second anti-rotation is carried out at intervals of 60 meters, when the first anti-rotation device reaches the upper station port, the first anti-rotation device is detached, when the second anti-rotation device reaches the upper station port, the second anti-rotation device is detached, and then the first anti-rotation device is installed on the other side.
As a further scheme of the invention, when the carrying cable is tensioned, a steel wire rope is hung on one side of the carrying cable from the center of the driving wheel to 40 meters upwards, a pulley block is hung on the other side of the carrying cable from the center of the driving wheel to the equipment foundation, the pulley block is hung on the other side of the carrying cable from the center of the driving wheel to the card board, a pulley block is hung from the card board and the pulley block from the center of the driving wheel to the 35 meters upwards, the steel wire rope is wound around the pulley block, and a weight not less than 60Kg is hung at the position of the card board and the pulley block to serve as an anti-reversion device.
As a further aspect of the invention, the steel core and the fiber core are joined to each other inside the braided joint.
Compared with the prior art, the invention has the beneficial effects that: when the method is adopted to knit the steel cable, the tightness is controlled uniformly during knitting through the arrangement of the clamping plate clamps and the auxiliary action of the anti-reverse device, and the strength of the ropeway after knitting is higher.
Detailed Description
1) The method is characterized in that the rope releasing traction force is correctly and reasonably calculated, a large-tonnage winch which can meet the production requirement is selected, the maximum traction force of the cableway during rope releasing is about 6.5 tons, and a 16-ton winch is used for traction.
2) Placing the steel wire rope on a cable tray frame at an upper station according to the rope outlet direction of the steel wire rope, leveling and compacting the bottom of the cable tray frame, slowly jacking the steel wire rope by using a jack, leaving 10-20 cm away from the original support, leveling a rope releasing central shaft, welding the cable tray frames at two sides by using channel steel or a circular pipe to form a firm whole, and stabilizing the cable tray frame by using 2 chain blocks of 5 tons in the opposite direction of the rope outlet direction of the steel wire rope; the brake device selects logs or brake tapes, 2 chain blocks of 5 tons are used for adjustment, and the effectiveness of the brake device is guaranteed; the brake operator is provided with the interphone, and can contact other related personnel at any time.
3) The freight cable traction cable with the diameter phi of 22 is used as a traction cable when the steel cable of the passenger ropeway is released;
4) lifting the cable releasing working rope with the diameter phi of 22 to a support cable supporting wheel on a line from a lower station to an upper station;
5) at the lower station, one end of a cable releasing working rope with the diameter phi of 22 is braided with a steel wire rope of the cableway (the braiding length of a carrying rope and the working rope comprises a core-spun length and an inserting length, the core-spun length is not less than 12 m, the inserting length is not less than 2 m, the joint position is protected by a steel anchor head), and the other end of the cable releasing working rope is wound into a winch roller with the length of 16T;
6) according to the actual situation on site, the nylon guide wheels are reasonably arranged so as to guide the cableway steel wire rope into a correct cableway line, so that the safety of releasing the steel wire rope is ensured, and meanwhile, the steel wire rope can be well protected;
7) after all the parts are ready and are checked to be correct, starting a 16T winch and drawing a phi 22 working rope to discharge a steel rope of the cableway;
8) in order to prevent the steel wire rope from rotating in the releasing process and change the lay length of the steel wire rope, a first anti-rotation is added for about 30 meters of the carrying rope before releasing, and a second anti-rotation is added for about 60 meters. It should be noted in particular that the antirotation is handled in time at the entrance and exit, the first antirotation device being removed when it reaches the entrance of the station. When the second anti-rotation device reaches the upper standing port, the second anti-rotation device is detached, and then the first anti-rotation device is installed on the other side. According to the position and the distance of the braided rope, the reversing wheel is arranged at a proper bracket position, so that the carrying rope has enough braided rope length after passing through the driving wheel at a lower station.
9) In the process of releasing the cable, a specially-assigned person is required to track the knitting heads of the two cables so as to strengthen the protection of the cableway steel wire rope;
10) and determining the actual braiding form and tensioning of the carrying rope according to the actual terrain condition. When the carrying rope is tensioned, a clamp plate clip is arranged at one side of the carrying rope 40 meters upwards from the center of the driving wheel, a steel wire rope with the multiplying power i equal to 2 and phi 36 is hung, and the other end of the steel wire rope is connected with an equipment foundation. The other side is hung on a pulley block on the basis of equipment, and the pulley block is hung on a clamping plate clip 35 meters upwards from the center of the driving wheel. And (3) penetrating and winding the pulley block by using a steel wire rope with the diameter of 11, wherein the multiplying power i is 20. And weights not lower than 60Kg are hung at the positions of the board card and the pulley block to serve as anti-reverse devices. The rope was tightened with a motorized winch to the designed tension. And after the tension force reaches the design tension force, the tension force stays for 72 hours. If the design tension drops, tensioning is performed again. And knitting is carried out until the tension is designed.
11) And (4) knitting construction is carried out on the cableway steel wire rope according to the standard requirement, and the carrying rope is knitted under the guidance of an outside engineer. And measuring the tension state actual length. And measuring the braiding length of the carrying rope, measuring the actual length required by braiding the carrying rope according to the tension state, and cutting off redundant parts. After the braiding length is measured, the length of the splicing section is divided, marked and braided. When the traction rope is tensioned in the knotting process, a special clamp which does not damage the traction rope must be used, and a common U-shaped rope clamp is strictly forbidden. Secondly, the length of the braided joint is not less than 1000 days for the freight cableway. For passenger ropeways, when the total filament number of the steel wire ropes is smaller than or equal to 114, the total filament number is not smaller than 1200 d; when the total filament number of the steel wire rope is more than 114, the total filament number is preferably (1300-1500) d. And the length of the index between two braided joints without braiding is not less than 3600 d. Fourthly, the appearance of the braided joint is perfectly round and full, the pressure head is smooth, the lay length is uniform, and the tightness is consistent. The diameter increase rate of the braided joint is not more than 10% when d is not more than 28mm, not more than 9% when d is 29-38 mm, and not more than 8% when d is 39-48 mm. Fifthly, knitting the inside of the joint, wherein the steel core and the fiber core are mutually connected. Sixthly, when the track of the tensioning trolley is long, the tensioning trolley is located at a designed given position after the traction cable is in place. If there is no given position, the tensioning trolley should be located at about 1/3-2/5 strokes from the front end of the track.
Claims (5)
1. A carrying cable laying and braiding method is characterized by comprising the following steps:
s1, placing the steel wire rope on a cable tray frame in an upper station according to the direction of the steel wire rope going out, flatly filling and compacting the bottom of the cable tray frame, slowly jacking the steel wire rope by using a jack, leaving 10-20 cm from the original support, leveling a cable laying central shaft, welding the cable tray frames on two sides by using channel steel or a circular tube to form a firm whole, and stabilizing the cable tray frame by using a chain block in the direction opposite to the direction of the steel wire rope going out;
s2, lifting a rope releasing working rope onto a bracket rope supporting wheel on a line from a lower station to an upper station by using a cargo rope traction rope as a traction rope when releasing the steel rope of the passenger ropeway;
s3, at the lower station, braiding one end of a rope releasing working rope with a steel wire rope of the cableway, and winding the other end of the rope releasing working rope into a winch roller;
s4, starting a winch, and drawing the working rope to discharge the steel rope of the cableway;
and S5, tightening the cable by using a motorized winch, stopping for 72 hours after the tension reaches the design tension, and if the design tension is reduced, tightening again until the design tension is reached, and then braiding.
2. A carrier rope laying braiding method according to claim 1, wherein: the braiding length of the carrying cable and the working cable comprises a core-spun length and an inserting length, the core-spun length is not less than 12 m, the inserting length is not less than 2 m, and the joint position is protected by a steel anchor head.
3. A carrier rope laying braiding method according to claim 2, wherein: the carrying cable is reserved 30 meters before being released, a first rotation preventing is added, a second rotation preventing is added at intervals of 60 meters, when the first rotation preventing device reaches the opening of the upper station, the first rotation preventing device is detached, when the second rotation preventing device reaches the opening of the upper station, the second rotation preventing device is detached, and then the first rotation preventing device is installed on the other side.
4. A carrier rope laying braiding method according to claim 3, wherein: when the carrying cable is tensioned, a steel wire rope is hung on one side of the carrying cable from the center of the driving wheel to 40 meters upwards, the other end of the carrying cable is connected with the equipment foundation, a pulley block is hung on the other side of the carrying cable from the equipment foundation, the pulley block is hung on the clamping plate from the center of the driving wheel to 35 meters upwards, the steel wire rope penetrates around the pulley block, and a weight not lower than 60Kg is hung at the positions of the clamping plate and the pulley block to serve as an anti-reversion device.
5. A carrier rope laying braiding method according to claim 1, wherein: the steel core and the fiber core are connected with each other inside the braided joint.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210131838.9A CN114633768A (en) | 2022-02-14 | 2022-02-14 | Carrier cable laying and braiding method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210131838.9A CN114633768A (en) | 2022-02-14 | 2022-02-14 | Carrier cable laying and braiding method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114633768A true CN114633768A (en) | 2022-06-17 |
Family
ID=81946491
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210131838.9A Pending CN114633768A (en) | 2022-02-14 | 2022-02-14 | Carrier cable laying and braiding method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114633768A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106184237A (en) * | 2015-05-08 | 2016-12-07 | 中国石油化工股份有限公司天然气川气东送管道分公司 | A kind of Light-duty Quick-installation cableway |
CN108082194A (en) * | 2017-12-26 | 2018-05-29 | 浙江省送变电工程有限公司 | A kind of 6 tonnes of heavy cableways and its installation method |
CN108930180A (en) * | 2018-08-18 | 2018-12-04 | 贵州钢绳股份有限公司 | Manned wire rope for cableway splice and installation method |
CN109554968A (en) * | 2019-01-14 | 2019-04-02 | 中国十七冶集团有限公司 | The device and its construction method of the carrying rope laying of aerial cableway |
CN109677423A (en) * | 2019-01-04 | 2019-04-26 | 扬州市百思特机械设备有限公司 | A kind of coal mine mixing tunnel enclosed systemic circulation overhead passenger cableway |
US20200232160A1 (en) * | 2017-07-21 | 2020-07-23 | Fatzer Ag | Sheathing element and method for splicing a rope |
-
2022
- 2022-02-14 CN CN202210131838.9A patent/CN114633768A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106184237A (en) * | 2015-05-08 | 2016-12-07 | 中国石油化工股份有限公司天然气川气东送管道分公司 | A kind of Light-duty Quick-installation cableway |
US20200232160A1 (en) * | 2017-07-21 | 2020-07-23 | Fatzer Ag | Sheathing element and method for splicing a rope |
CN108082194A (en) * | 2017-12-26 | 2018-05-29 | 浙江省送变电工程有限公司 | A kind of 6 tonnes of heavy cableways and its installation method |
CN108930180A (en) * | 2018-08-18 | 2018-12-04 | 贵州钢绳股份有限公司 | Manned wire rope for cableway splice and installation method |
CN109677423A (en) * | 2019-01-04 | 2019-04-26 | 扬州市百思特机械设备有限公司 | A kind of coal mine mixing tunnel enclosed systemic circulation overhead passenger cableway |
CN109554968A (en) * | 2019-01-14 | 2019-04-02 | 中国十七冶集团有限公司 | The device and its construction method of the carrying rope laying of aerial cableway |
Non-Patent Citations (1)
Title |
---|
吕进,李政彬: "客运架空索道钢丝绳的编结" * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11014776B2 (en) | Cable recovery machine | |
US3519101A (en) | Construction elevator system | |
CN102040173B (en) | Steel wire rope pre-tightening device | |
CN107299595B (en) | Bridge prestressed pipe pulls out pipe and wears to restraint platform truck | |
CN113756201B (en) | T-structure continuous beam prestressed steel strand pulling method and pulling device thereof | |
CN113789720A (en) | Construction method of carbon fiber inhaul cable | |
US20080308362A1 (en) | Cable management assembly and method for construction elevator systems | |
CN111874745A (en) | High-speed rail trackless constant-tension contact line erecting technology and device | |
CN109554968B (en) | Device for laying carrier cable of aerial cableway and construction method thereof | |
CN114633768A (en) | Carrier cable laying and braiding method | |
CN107176548B (en) | A kind of cable crane overhead traveling crane closed circulation trailer system and traction method | |
CN220182628U (en) | Capacity-expansion anti-winding traction equipment | |
CN107324231A (en) | Endless rope winch wire rope distributing technique | |
US2971255A (en) | Method of spinning cables for suspension bridges | |
CN111469717A (en) | No-crossing arrangement construction method for contact net at No. 42 turnout | |
CN113699889A (en) | Construction method for erecting main cable strand in space of three-tower self-anchored suspension bridge | |
CN214112345U (en) | High-speed railway trackless constant tension carrier cable erecting device | |
CN114408449B (en) | Belt replacing device for belt conveyor under limited space condition | |
CN112339617A (en) | High-speed rail trackless constant-tension carrier cable erecting technology and device | |
CN112290457A (en) | Construction method of carbon fiber composite core wire | |
CN106890869B (en) | Prestressed reinforcement integral paying-off device and method | |
CN212424976U (en) | High-speed railway trackless constant tension contact line erecting device | |
CN110713092B (en) | Hoisting method and hoisting mechanism for elevator synthetic fiber rope | |
CN108930180A (en) | Manned wire rope for cableway splice and installation method | |
JP2003128367A (en) | Rope extension method at climbing of lifting device and its auxiliary device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220617 |