CN106184237A - A kind of Light-duty Quick-installation cableway - Google Patents
A kind of Light-duty Quick-installation cableway Download PDFInfo
- Publication number
- CN106184237A CN106184237A CN201510232182.XA CN201510232182A CN106184237A CN 106184237 A CN106184237 A CN 106184237A CN 201510232182 A CN201510232182 A CN 201510232182A CN 106184237 A CN106184237 A CN 106184237A
- Authority
- CN
- China
- Prior art keywords
- cableway
- light
- hoist engine
- holder device
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
The present invention relates to a kind of Light-duty Quick-installation cableway, including power control unit, holder device, carriage device, described power control unit includes hoist engine, secondary hoist engine, switch board, described holder device includes upper bracket and the lower carriage being arranged on different geographical height, described upper bracket is connected with lower carriage by hauling rope, described carriage device includes roller, adapter, support, chain block, described roller is connected by adapter and two supports of cross-like, described hoist engine and secondary hoist engine are connected with hauling rope respectively, described entablature is slidably connected with described hauling rope by roller, described sill is connected with described carrier cable.The present invention provides a kind of Light-duty Quick-installation cableway, solve existing cableway to fixedly mount, reclaim difficulty, the technical problem of construction period length, Light-duty Quick-installation cableway can be with Fast Installation in the complicated landform such as mountain stream, river, cliff, it is also possible to the goods and materials conveying when emergency relief or temporary construction.
Description
Technical field
The present invention relates to a kind of transport cableway, in particular, the present invention relates to be applied to the one of goods transport field
Light-duty Quick-installation cableway.
Background technology
Along with new technique, the progress of new technology, the application of cableway is more and more extensive, the manufacture of cableway simultaneously
Technology is more ripe, and it is more and more comprehensive that it makes specification accordingly.Such as, classify according to cableway, have specially
Door, for the manned sightseeing cableway in famous mountains and great rivers, also has the timber skidding ropeway being exclusively used in forest harvesting, the most useful
Simple slip rope crossed a river in remote mountain areas etc..Wherein simple slip rope, it is simply that fixing between upper and lower two ends
Steel cable, relies on the natural-drop of different terrain, become can across mountain, the various complicated landform of Yue He, adaptation
Means of transport.
Certain above-mentioned slip rope is higher for the requirement of landform, and the manned/loading cableway of complexity may prolong continuous thousands of
Rice, will cross multiple hilltop, so needing the structural system of complexity, controlling system.But no matter simple in construction or
Complexity, above-mentioned cableway all plays important transportation function, and playing other vehicles in express zone can not replace
The effect in generation.
Cableway, as the effective means of transport of one, has its limitation on using at present, i.e. can only fix and make
With, and the construction period is long, reclaims more difficulty.So cableway is built mostly has large area felling demand
Forest zone, or the sightseeing scenic spot that flow of personnel amount is bigger.
A kind of cableway can be designed, be applicable not only to major part landform, assemble simple, all right after use
Again reclaim?Design one can Fast Installation, reclaim simple cableway, be instantly in cableway development course urgently
The technical problem that need to solve.
Summary of the invention
It is an advantage of the invention to provide a kind of Light-duty Quick-installation cableway, solving existing cableway can only fix
Install, reclaim difficult, construction period length technical problem.
The above-mentioned purpose of the present invention and other purposes solve by the following technical programs:
The present invention provides a kind of Light-duty Quick-installation cableway, including power control unit, holder device, carriage device,
Described power control unit includes hoist engine, secondary hoist engine, switch board, described hoist engine, secondary hoist engine and control
Cabinet processed is successively set on the smooth ground of geographical position lower end, and described holder device includes being arranged on different geography
The upper bracket of height and lower carriage, described upper bracket is connected with lower carriage by hauling rope, described carriage device bag
Including roller, adapter, support, chain block, described roller is connected with crossbeam by the adapter of cross-like,
Described crossbeam includes entablature and sill, it is characterised in that:
Described hoist engine and secondary hoist engine are connected with a hauling rope respectively;
The top of described holder device is provided with angle pulley or corner block;
By being wrapped in leading of described angle pulley or corner block foreign steamer external diameter between described upper bracket and lower carriage
Straw line is connected;
By taking turns holding of external diameter in being wrapped in described angle pulley or corner block between described upper bracket and lower carriage
Power rope is connected;
Described entablature is slidably connected with described hauling rope by roller, and described sill is connected with described carrier cable.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that described storage rope device is fixedly installed on by frame
On the ground of described lower carriage side.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that described tension regulator is fixed on described lower
The top of frame, described tension regulator is connected with described carrier cable.
The present invention provide a kind of Light-duty Quick-installation cableway, it is preferable that described storage rope device by cordage with described
Draught control mechanism connects.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that described holder device is herringbone, described
Rack device is fixed on the ground by lower margin, and described holder device is connected triangular in shape with described side tension cords.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that described holder device is by lambdoid bracing frame
Composition, is provided with the tension ropes of intersection between support frame as described above.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that be provided with vertical between described holder device
Two stabiliser bars, are separately positioned on the symmetric position of described lambdoid bracing frame.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that described chain block is by vertical attachment means
Being connected with described sill, described chain block is connected with material by steel wire rope.
The present invention provide a kind of Light-duty Quick-installation cableway, it is preferable that one end of material by safety line with described on
Support connects.
A kind of Light-duty Quick-installation cableway that the present invention provides, it is preferable that described holder device is articulated structure, described
The weight of the parts of holder device both less than equal to 50kg, the height of described holder device be 6.5m-7.5m,
Width is 3.5m-4.5m, and model chosen respectively by described hoist engine and secondary hoist engine is the special of 1T and 0.5T standard
With hoist engine, material fed distance is 0-200m.
Advantages of the present invention and having the beneficial effects that:
1, cableway is manufactured into Portable detachable, standard product by the present invention first, it is adaptable to emergency relief, river
The manpower of the landform such as stream, mountain stream or Material Transportation;
2, a kind of Light-duty Quick-installation cableway that the present invention provides, sets up the time short, and single component weight is light, is suitable for
Manpower transport, it is adaptable to the area that plant equipment cannot arrive.
3, a kind of Light-duty Quick-installation this cableway of cableway that the present invention provides, carrier cable, hauling rope use super high molecular weight
Polyethylene fibre rope, replaces traditional structure steel wire rope, and therefore cable body is soft, lightweight, adds that quick support is
Heretofore described cableway is suitable to artificial fast erecting in the wild.
Accompanying drawing explanation
Carry out the preferred embodiment of the present invention below in conjunction with the accompanying drawings describing in detail or preferably, wherein,
Fig. 1 is the total arrangement structural representation of the present invention;
Fig. 2 is the partial enlarged drawing of Fig. 1;
Fig. 3 is the structural representation of holder device;
Fig. 4 is the structural scheme of mechanism of carriage device;
Power control unit-1, hoist engine-11, secondary hoist engine-12, switch board-13, holder device-2, upper
Frame-21, lower carriage-22, bracing frame-23, tension ropes-24, stabiliser bar-25, carriage device-3, roller-31,
Adapter-32, crossbeam-33, entablature-331, sill-332, chain block-34, hauling rope-4, carrier cable
-5, Chu Shengqi-6, tension regulator-7, lower margin-8, side tension cords-9, safety line-10.
Detailed description of the invention
The present invention provides a kind of Light-duty Quick-installation cableway, including power control unit 1, holder device 2, carriage device
3, power control unit includes hoist engine 11, secondary hoist engine 12, switch board 13, hoist engine 11, secondary hoist engine
12 and switch board 13 be successively set on the smooth ground of geographical position lower end, holder device 2 includes being arranged on
The upper bracket 21 of different geographical height and lower carriage 22, upper bracket 21 is by hauling rope 4 with lower carriage 23 even
Connecing, carriage device 3 includes roller 31, adapter 32, crossbeam 33, chain block 34, and roller 31 is by handing over
Forked adapter 32 is connected with crossbeam 33, and crossbeam 33 includes entablature 331 and sill 332, its feature
It is:
Hoist engine 11 and secondary hoist engine 12 are connected with a hauling rope 4 respectively;
The top of holder device 2 is provided with angle pulley or corner block;
By being wrapped in angle pulley or the traction of corner block foreign steamer external diameter between upper bracket 21 and lower carriage 22
Rope 4 is connected;
By taking turns the load of external diameter in being wrapped in angle pulley or corner block between upper bracket 21 and lower carriage 22
Rope 5 is connected;
Entablature 331 is slidably connected with hauling rope 4 by roller 31, and sill 332 is connected with carrier cable 5.
Preferably, storage rope device 6 is fixedly installed on the ground of lower carriage 22 side by frame.
Preferably, tension regulator 7 is fixed on the top of lower carriage 22, tension regulator 7 and carrier cable 5
Connect.
Preferably, storage rope device 6 is connected with tension regulator 7 by cordage.
Preferably, holder device 2 is in herringbone, and holder device 2 is fixed on the ground by lower margin 8, support
Device 2 is connected triangular in shape with side tension cords 9.
Preferably, holder device 2 is made up of lambdoid bracing frame 23, is provided with intersection between bracing frame 23
Tension ropes 24.
Preferably, it is provided with vertical two piece stabiliser bar 25 between holder device 2, is separately positioned on lambdoid
The symmetric position of bracing frame 23.
Preferably, chain block 34 is connected with sill 332 by vertical attachment means, and chain block 34 leads to
Cross steel wire rope to be connected with material.
Preferably, one end of material is connected with upper bracket 21 by safety line 10.
Preferably, holder device 2 is articulated structure, and the weight of the parts of holder device 2 is both less than equal to
50kg, the height of holder device 2 is 6.5m-7.5m, width is 3.5m-4.5m, hoist engine 11 and secondary hoist engine
12 choose the special hoist engine that model is 1T and 0.5T standard respectively, and material fed distance is 0-200m.
The present invention provides a kind of Light-duty Quick-installation cableway, its technical scheme and corresponding technique effect as follows:
1. a kind of Light-duty Quick-installation cableway provided with reference to the accompanying drawing 1-3 present invention, uses single-point reciprocating cargo ropeway
Basic structure, but compare with standard single-point reciprocating cargo ropeway, in order to Fast Installation, holder device
2 by being constituted with the metal structure of fast assembling-disassembling, and holder device 2 each component part deadweight no more than
50Kg, meets artificial carrying on mountain pass.Holder device 2, in herringbone, is connected with side tension cords 9 and collectively forms
One stable gusseted.Side tension cords 9 undertakes the main pulling force of cableway carrier cable 5, and adjustable length is permissible
According to field landform, it is bundled on the rock of thick trees, projection or the most architectural, otherwise can only use
Anchorage is fixedly connected with the ground.
Carrier cable 5 is arranged between upper bracket 21 and lower carriage 22, and carrier cable 5 uses superhigh molecular weight polyethylene
Alkene cordage, effect acts as the slideway that carriage device 3 moves.The surface of carrier cable 5 is through polyureas or other sprays
Painting processes so that cable body closely and has good anti-wear performance.The quality of cordage only has the 1/7 of steel wire rope to arrive
1/8, it is suitable for a dead lift and installation.
Hauling rope 4 uses superhigh molecular weight polyethylene fibers rope, hoist engine 11 and secondary hoist engine 12 respectively with one
Root hauling rope 4 connects, and therefore the upper and lower operation of hauling rope 4 all uses power traction, to ensure at upper bracket 21
With the height between lower carriage 22 is not enough to rely on gravity to use when making suspension hook glide.Equally, hoist engine 11,
The deadweight of secondary hoist engine 12 building block is less than 50Kg.
2. storage rope device 6 is fixedly installed on lower carriage 22 one end by frame, and tension regulator 7 is fixed on lower carriage
The top of 22, tension regulator 7 is connected with carrier cable 5, and storage rope device 6 and tension regulator 7 are for adjusting at any time
Accurate distance between the joint degree of speeding of carrier cable 5 and upper bracket 21 and lower carriage 22.
With reference to accompanying drawing 4:
3. roller 31 is connected by adapter and two supports of cross-like, and the upper end of carriage device 3 relies on roller
31 roll walking on carrier cable 5, and carrier cable 5 bears overwhelming majority gravity.Entablature 331 is by roller 31
Being slidably connected with hauling rope 4, hauling rope 4 trailer wagon device 3 walks up and down.Chain block 34 is by vertical
Attachment means is connected with sill 332, and chain block 34 is connected with material by steel wire rope, facilitates rising of material
Hang and unload, it is also possible to transporting when apparatus needs holding level.
The concrete steps installed: be transported to the parts of Light-duty Quick-installation cableway rapidly specify position, assemble complete
After, outside taking turns in carrier cable 5 is wrapped in angle pulley or corner block, upper bracket 21 and lower carriage 22 are connected
Get up, start tension regulator 7, tighten up carrier cable 5.While tightening up carrier cable 5, two end supports are stood
Rise (pulling up).Range estimation support and horizontal plane are substantially vertical.
After installation, a full and down workpiece is hung in examination, and whether range estimation can pass through whole barriers, regulates carrier cable
The degree of speeding of 5, it is ensured that all workpiece can smooth delivery of power, both can normally use.
In conjunction with specific embodiments the technical scheme in the present invention is further understood that
Embodiment: QKS-1-200 type fast installation cableway
One, cableway parameter
Q: light-duty;K: quick mounting type;S: single fulcrum list rope reversible tramway;1 conveying articles weight
0-1 ton, 200 effective fed distance 20 meters-200 meters.
Two, runway structures form
Cableway pattern: single fulcrum list rope reversible tramway;
The speed of service: the maximal rate of operation is 2.5m/s, putting rope speed is 2.5m/s;
Carrier cable: φ 24mm super-high wear-resistant ultra-high molecular weight polyethylene rope, safety coefficient take > 2.5, Chu Shengqi
One (200), special tension regulator one (15 tons)
Holder device: integrally assembled type steel structure support, bracing frame height divides 5 joints, high 7.0m, the width of support
Spend about 4.0m.
Hauling rope: super-high wear-resistant φ 12mm ultra-high molecular weight polyethylene rope (special), safety coefficient takes > 2.5;
1, special hoist engine (1 ton), secondary 1, hoist engine (0.5 ton);
Three, operation instruction
Cableway addressing: the selection to aerial cableway should follow following principle: first reply decorating position carries out scene
On-site inspection, and, centre minimum according to aerial cableway span do not have smooth former of obvious ridge, two ends physical features
The most preferentially choose;Cableway two ends should be able to allow people to pass through, it is possible to removes and unloads primary goods and lay cable;Traction
Rope 4 and cable are together laid, and avoiding trees etc. as far as possible can affect the barrier of cable body tensioning lift-off, if must
The little scope trees in local must can be carried out migration process by the woods etc..
Basis is with fixing: in the fixation procedure of cableway agent structure, for improving installation rate, it should as far as possible
Utilize site environment, be fixed such as thick trees, stump, the rock of projection or firm building etc.,
Fixture stress should be not less than 13 tons.
For not highlighting rock, mild heavy soil layer etc., it is impossible to find the distinguishingly condition of fixing side tension cords 9,
Must be according to the making situation of micro-judgment ground.According to practical situation, utilize the rock anchors and quick hardening cement carried
Ground is quickly fixed, or makes soil layer foundation pile, the geomatics engineer of specialty must be had if desired to do correct
Anticipation, in use, it should test ground load-bearing.
Holder device is installed: selected basis, is all transported by the parts of holder device 2 grade and puts in place.First,
The most fixing ground of holder device 2 is made according to size.The pre-buried upper bracket of ground 21 and the axle of lower carriage 22
Hole line, range estimation substantially to keep vertical with carrier cable 5.Ground, after quick hardening cement fastens substantially, starts group
Dress holder device 2.
When assembling holder device 2, the direction of holder device 2 is that top is outside, i.e. close to earth anchor.By side tension cords
The tops of 9 link earth anchors and supports, and long needed for estimating side tension cords 9 according to the angle of side tension cords 9 with horizontal plane
Degree, the length of regulation side tension cords 9, make holder device 2 will not tumble to offside when erecting.Holder device 2 is pacified
Load after admittedly completing, the tension ropes 24 of intersection be set between the lambdoid bracing frame 23 of holder device 2,
By holder device 2 tensioning, its tensioning degree should not rock with two timbering with rafter arch sets's framves 23, do not bend and be as the criterion.
Carrier cable is installed: while holder device 2 transports appointment position, put a diameter 4mm in advance
Superhigh molecular weight polyethylene fibers rope, artificial directly carrier cable 5 and hauling rope 4 being dragged to specifies position.
Carrier cable 5 and hauling rope 4 are connected with related device, simply fix.
Holder device erects and tensioning: above-mentioned steps carries out complete, check errorless after, can be energized startup elevator
The slow tensioning carrier cable 5 of machine 11, utilizes the tensile force of carrier cable 5 upper bracket 21 and lower carriage 22 to be erected.
Adjusting the tension force of side tension cords 9, (can make weight by oneself, simple test is hung down to keep holder device 2 and horizontal vertical
Straight degree).By suitable for hauling rope 4 tensioning, during the hoisting of hauling rope 4, should ensure that hauling rope 4 does not comes off,
The most do not hang over branch or dolly side.
Trail run adjusts with degree of speeding: the size of the degree of speeding of carrier cable 5 is the basis that can cableway normally work, and speeds
Degree is too big, in transportation, because of being acted on by load, hopper or by material and equipment easy be spanned
Thing collides;Degree of speeding is the least, then, under the effect of load, carrier cable 5 stress can be significantly increased, and reduces rope
The launch weight in road.Therefore, when setting up cableway, the degree of speeding of cableway should be increased as far as possible, it is ensured that material passes through
?.For barriers such as indivedual prominent rocks, trees, if desired, above-mentioned barrier is removed.
In view of above principle, cableway is when trail run first, and the material examination of optional 1.05 tons is hung, and emphasis should be examined
Look into holder device 2, related fittings, side tension cords 9 and the firmness of other vitals, regulate load
The degree of speeding of rope 5, whether range estimation material waits enough passes through.The degree of speeding of carrier cable 5 cannot be less than 4 meters.
Suspended object material (controllable distance) in short distance is run for several times repeatedly, normal operation, then can be normal
Use Light-duty Quick-installation cableway.
Cableway reclaims and maintenance: when this cableway reclaims, checks and identifies the damaged condition of parts, eliminate in time
Undesirable parts, the dust of the piece surface that clears all, it is coated with lubricating oil to operating position.
Vanning is with the minimum principle that takes up room, and parts should conveniently be dismantled, it is simple to transport, each parts of casing
It is not more than 50kg, after being numbered, is put in the fixed position in case, convenient access.
For the characteristic that holding cableway entirety is succinct, practical, light, in terms of electrical control, also take the simplest
Single design, installs concentratedly the device of electrical control in switch board 13, meets the needs of controllable property.
According to technical scheme, in the case of the connotation not changing the present invention, this area general
Logical technical staff can propose multiple frame modes of the present invention.Therefore detailed description below and accompanying drawing are only
It is that technical scheme is illustrated, and is not to be construed as the whole of the present invention or is considered as this
Defining or limiting of bright technical scheme.
Claims (10)
1. a Light-duty Quick-installation cableway, including power control unit (1), holder device (2), dolly dress
Putting (3), described power control unit (1) includes hoist engine (11), secondary hoist engine (12), switch board
(13), described hoist engine (11), secondary hoist engine (12) and switch board (13) are successively set on geography
On the smooth ground of position lower end, described holder device (2) include being arranged on different geographical height upper
Frame (21) and lower carriage (22), described upper bracket (21) is by hauling rope (4) and lower carriage (22)
Connecting, described carriage device (3) includes roller (31), adapter (32), crossbeam (33), pulls
Calabash (34), described roller (31) is connected with crossbeam (33) by the adapter (32) of cross-like,
Described crossbeam (33) includes entablature (331) and sill (332), it is characterised in that:
Described hoist engine (11) and secondary hoist engine (12) are connected with a hauling rope (4) respectively;
The top of described holder device (2) is provided with angle pulley or corner block;
By being wrapped in described angle pulley or turning between described upper bracket (21) and lower carriage (22)
The hauling rope (4) of coaster foreign steamer external diameter is connected;
By being wrapped in described angle pulley or turning between described upper bracket (21) and lower carriage (22)
In coaster, the carrier cable (5) of wheel external diameter is connected;
Described entablature (331) is slidably connected with described hauling rope (4) by roller (31), described
Sill (332) is connected with described carrier cable (5).
A kind of Light-duty Quick-installation cableway the most according to claim 1, it is characterised in that described storage rope device (6)
It is fixedly installed on the ground of described lower carriage (22) side by frame.
A kind of Light-duty Quick-installation cableway the most according to claim 2, it is characterised in that described tension regulator
(7) top of described lower carriage (22), described tension regulator (7) and described carrier cable (5) it are fixed on
Connect.
A kind of Light-duty Quick-installation cableway the most according to claim 3, it is characterised in that described storage rope device (6)
It is connected with described tension regulator (7) by cordage.
A kind of Light-duty Quick-installation cableway the most according to claim 1, it is characterised in that described holder device (2)
In herringbone, described holder device (2) is fixed on the ground by lower margin (8), described holder device (2)
It is connected triangular in shape with described side tension cords (9).
A kind of Light-duty Quick-installation cableway the most according to claim 5, it is characterised in that described holder device (2)
It is made up of lambdoid bracing frame (23), between support frame as described above (23), is provided with the tension ropes (24) of intersection.
A kind of Light-duty Quick-installation cableway the most according to claim 6, it is characterised in that described holder device (2)
Between be provided with vertical two piece stabiliser bar (25), be separately positioned on the right of described lambdoid bracing frame (23)
Claim position.
A kind of Light-duty Quick-installation cableway the most according to claim 1, it is characterised in that described chain block (34)
Be connected with described sill (332) by vertical attachment means, described chain block (34) by steel wire rope with
Material connects.
A kind of Light-duty Quick-installation cableway the most according to claim 1, it is characterised in that one end of material is passed through
Safety line (10) is connected with described upper bracket (21).
A kind of Light-duty Quick-installation cableway the most according to claim 1, it is characterised in that described holder device (2)
For articulated structure, the weight of the parts of described holder device (2) is both less than equal to 50kg, and described rack-mounted
The height putting (2) is 6.5m-7.5m, width is 3.5m-4.5m, described hoist engine (11) and secondary hoist engine
(12) choosing the special hoist engine that model is 1T and 0.5T standard respectively, material fed distance is 0-200m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510232182.XA CN106184237A (en) | 2015-05-08 | 2015-05-08 | A kind of Light-duty Quick-installation cableway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510232182.XA CN106184237A (en) | 2015-05-08 | 2015-05-08 | A kind of Light-duty Quick-installation cableway |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106184237A true CN106184237A (en) | 2016-12-07 |
Family
ID=57460210
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510232182.XA Pending CN106184237A (en) | 2015-05-08 | 2015-05-08 | A kind of Light-duty Quick-installation cableway |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106184237A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107792790A (en) * | 2017-10-16 | 2018-03-13 | 中国化学工程第十四建设有限公司 | Installation and application for the aerial cableway of mountain region construction material transport |
CN108797347A (en) * | 2018-07-20 | 2018-11-13 | 中交武汉港湾工程设计研究院有限公司 | Cycle is drawn into anchor system |
CN110182226A (en) * | 2019-06-13 | 2019-08-30 | 福建农林大学 | Double carrying circulation traction multispan cableway sport cars and application method |
CN110510527A (en) * | 2019-08-01 | 2019-11-29 | 中国建筑土木建设有限公司 | Installation system of high slope variable cross-section slope precast block and construction method thereof |
CN113844467A (en) * | 2021-10-22 | 2021-12-28 | 西北农林科技大学 | Hillside orchard transportation cableway with height-adjustable hanging boxes |
CN114633768A (en) * | 2022-02-14 | 2022-06-17 | 北京城建集团有限责任公司 | Carrier cable laying and braiding method |
CN115045175A (en) * | 2022-06-30 | 2022-09-13 | 徐少钢 | Temporary explosion-proof suspended ropeway bridge formed by single steel rope |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0678061B2 (en) * | 1990-04-27 | 1994-10-05 | ▲うお▼谷鉄工株式会社 | Cable carrier |
CN201209090Y (en) * | 2008-03-07 | 2009-03-18 | 中铁十三局集团有限公司 | Ropeway cable crane using single machine traction and lifting at steep terrain |
CN201494438U (en) * | 2009-10-13 | 2010-06-02 | 中国石油天然气股份有限公司 | Simple fast-assembling cableway for maintenance and emergency repair of mountain pipeline |
CN102020206A (en) * | 2010-12-17 | 2011-04-20 | 长江水利委员会长江勘测规划设计研究院 | Ropeway transport system of long-span steep terrain wind power device |
CN102654102A (en) * | 2011-03-01 | 2012-09-05 | 周振文 | Self-control kite group generator |
CN103171975A (en) * | 2013-01-17 | 2013-06-26 | 广东安元矿业技术服务有限公司 | Method for transporting slope engineering material |
CN204821555U (en) * | 2015-05-08 | 2015-12-02 | 中国石油化工股份有限公司天然气川气东送管道分公司 | Light -duty fast -assembling cableway |
-
2015
- 2015-05-08 CN CN201510232182.XA patent/CN106184237A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0678061B2 (en) * | 1990-04-27 | 1994-10-05 | ▲うお▼谷鉄工株式会社 | Cable carrier |
CN201209090Y (en) * | 2008-03-07 | 2009-03-18 | 中铁十三局集团有限公司 | Ropeway cable crane using single machine traction and lifting at steep terrain |
CN201494438U (en) * | 2009-10-13 | 2010-06-02 | 中国石油天然气股份有限公司 | Simple fast-assembling cableway for maintenance and emergency repair of mountain pipeline |
CN102020206A (en) * | 2010-12-17 | 2011-04-20 | 长江水利委员会长江勘测规划设计研究院 | Ropeway transport system of long-span steep terrain wind power device |
CN102654102A (en) * | 2011-03-01 | 2012-09-05 | 周振文 | Self-control kite group generator |
CN103171975A (en) * | 2013-01-17 | 2013-06-26 | 广东安元矿业技术服务有限公司 | Method for transporting slope engineering material |
CN204821555U (en) * | 2015-05-08 | 2015-12-02 | 中国石油化工股份有限公司天然气川气东送管道分公司 | Light -duty fast -assembling cableway |
Non-Patent Citations (1)
Title |
---|
李金赐: "装配式索道在输电线路工程中的应用", 《电力与电工》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107792790A (en) * | 2017-10-16 | 2018-03-13 | 中国化学工程第十四建设有限公司 | Installation and application for the aerial cableway of mountain region construction material transport |
CN108797347A (en) * | 2018-07-20 | 2018-11-13 | 中交武汉港湾工程设计研究院有限公司 | Cycle is drawn into anchor system |
CN110182226A (en) * | 2019-06-13 | 2019-08-30 | 福建农林大学 | Double carrying circulation traction multispan cableway sport cars and application method |
CN110510527A (en) * | 2019-08-01 | 2019-11-29 | 中国建筑土木建设有限公司 | Installation system of high slope variable cross-section slope precast block and construction method thereof |
CN110510527B (en) * | 2019-08-01 | 2024-07-26 | 中国建筑土木建设有限公司 | Installation system of high-side-slope variable-section side-slope precast block and construction method thereof |
CN113844467A (en) * | 2021-10-22 | 2021-12-28 | 西北农林科技大学 | Hillside orchard transportation cableway with height-adjustable hanging boxes |
CN114633768A (en) * | 2022-02-14 | 2022-06-17 | 北京城建集团有限责任公司 | Carrier cable laying and braiding method |
CN115045175A (en) * | 2022-06-30 | 2022-09-13 | 徐少钢 | Temporary explosion-proof suspended ropeway bridge formed by single steel rope |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106184237A (en) | A kind of Light-duty Quick-installation cableway | |
CN201494438U (en) | Simple fast-assembling cableway for maintenance and emergency repair of mountain pipeline | |
CN202090286U (en) | Traction system suitable for self-anchored type double cable plane suspension bridge | |
CN104695752B (en) | Rapid rush-repair Tower System and its erection method | |
CN206706584U (en) | Pier arch rib in the asymmetric button lashed cable cable system installation Multi-arch bridge of middle pier | |
CN101476293A (en) | Non-stand construction method for large bridge arch rib | |
CN101446066B (en) | Erection method of stiffening girder of suspension bridge and device thereof | |
CN105620493B (en) | A kind of novel rapid-installation freight ropeway | |
CN105113803B (en) | High-altitude sliding hoisting device of corridor truss of mountain and implementing method of high-altitude sliding hoisting device | |
US20190039629A1 (en) | Integrated bollard, anchor, and tower (ibat) apparatus and method | |
CN106245527B (en) | A kind of erection method of dicyclic suspender and Long span cat road track cable | |
CN109371854A (en) | The method of cable crane construction large-span suspension bridge stiff girder | |
CN105442446B (en) | Hanging basket for detecting and maintaining anchor mooring heads of boom and stay cable of bridge | |
CN204821555U (en) | Light -duty fast -assembling cableway | |
CN104494602A (en) | Construction method for transmission line project material transport by prefabricated cableway | |
CN109853393A (en) | A kind of the hanging cable construction system and its construction method of king-tower vertical transfer cable-stayed bridge | |
CN103626042A (en) | Cableway transport lifting device | |
CN105735103A (en) | Portable quick installation can dismantle bridge on foot | |
CN105275251A (en) | Railway existing line overhead line system hard crossbeam erection method | |
CN107476195A (en) | A kind of suspension bridge transports the fortune beam tackle system of stiff girder | |
CN107022958A (en) | The method in cable-stayed bridge across girder is installed using cable crane | |
CN207091932U (en) | A kind of equipment of aerial trackless erecting suspension bridge stiff girder | |
CN109291938A (en) | A kind of four rope freight ropeway systems with pulley-type self balancing device | |
CN110886188A (en) | Large-span suspension bridge stiffening beam erecting system and use method thereof | |
CN110820555A (en) | Bridge maintenance vehicle and method for avoiding bridge pier by maintenance platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161207 |
|
RJ01 | Rejection of invention patent application after publication |