CN114541401A CN202210240496.4A CN202210240496A CN114541401A CN 114541401 A CN114541401 A CN 114541401A CN 202210240496 A CN202210240496 A CN 202210240496A CN 114541401 A CN114541401 A CN 114541401A
Authority
CN
China
Prior art keywords
threaded
cbs
concrete construction
vegetation concrete
belt pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210240496.4A
Other languages
Chinese (zh)
Other versions
CN114541401B (en
Inventor
王强
张志杰
陈强
冉东虎
潘金土
包小红
段伟明
查凯燊
景东红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202210240496.4A priority Critical patent/CN114541401B/en
Publication of CN114541401A publication Critical patent/CN114541401A/en
Application granted granted Critical
Publication of CN114541401B publication Critical patent/CN114541401B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P60/00Technologies relating to agriculture, livestock or agroalimentary industries
    • Y02P60/20Reduction of greenhouse gas [GHG] emissions in agriculture, e.g. CO2

Abstract

The invention discloses a CBS vegetation concrete construction device and a method thereof, belonging to the field of ecological restoration engineering. A CBS vegetation concrete construction device comprises a guide post, at least two fixing parts and a conversion part; three driving grooves which are arranged in a delta shape are formed in the circumferential side surface of the guide post, and two threaded shafts are fixedly arranged on the wall of each driving groove; and the two threaded shafts are not connected with each other; the conversion part comprises a rotary table, three threaded connecting shafts and two supporting blocks; the rotary table is positioned between the two threaded shafts; the construction positions are distributed on the air, the fixed parts are used for laying the preset positions, so that when construction is started, each device can have a better construction environment and is suitable for different rules required in each procedure during construction, then the rotary table is rotated, one of the fixed parts is rotated, the device is fixed, the construction equipment is fixed, and multiple effects are achieved.

Description

CBS vegetation concrete construction device and method thereof
Technical Field
The invention relates to the field of ecological restoration engineering, in particular to a CBS vegetation concrete construction device and a method thereof.
Background
Ecological restoration refers to a process that helps restore and manage ecological integrity, including key ranges of biodiversity, ecological processes and structures, regional and historical relationships, and variability of sustainable cultural practices. The ecological restoration is to stop the artificial interference to the ecological system to reduce the load pressure, and evolve in an orderly direction by depending on the self-regulation capacity and the self-organization capacity of the ecological system, or gradually restore the destroyed ecological system or develop the ecological system in a virtuous circle direction by utilizing the self-restoration capacity of the ecological system and assisting artificial measures; mainly aims to the recovery and reconstruction work of natural ecosystems damaged under the influence of natural mutation and human activity.
The vegetation concrete is a new ecological protection technology for protecting and greening the rock slope by adopting a specific concrete formula and mixing plant green seeds. The polymer granules are widely applied to the artificial soil technology in engineering practice, stabilize the slope, restore the exposed mountain and make contribution to restoring ecological balance.
There are a plurality of step processes when carrying out ecological restoration engineering among the prior art, thereby through the construction of the thereby completion CBS vegetation concrete of a series of operations, but every process is all separately carried out in this kind of technique to be convenient for practice thrift the cost and construct, because various construction equipment all need install, dismantle and match when the construction, be inconvenient for shorten the time limit for a project.
Disclosure of Invention
Aiming at the problems in the prior art, the first purpose of the invention is to provide a CBS vegetation concrete construction device, which can distribute construction positions on the air and ground firstly, then lay the construction positions at preset positions by using a fixed part, so that each device can have a better construction environment when starting construction, and is suitable for different rules required in each process when in construction.
The second purpose of the invention is to provide a use method of the CBS vegetation concrete construction device, so that each construction tool can have a better construction space and operation space, and the use of workers is convenient.
In order to solve the above problems, the present invention adopts the following technical solutions.
A CBS vegetation concrete construction device comprises a guide post, at least two fixing parts and a conversion part; three driving grooves which are arranged in a delta shape are formed in the circumferential side surface of the guide post, and two threaded shafts are fixedly arranged on the wall of each driving groove; and the two threaded shafts are not connected with each other; the conversion part comprises a rotary table, three threaded connecting shafts and two supporting blocks; the rotary table is positioned between the two threaded shafts; the guide column is divided into two parts, the rotary table is rotatably arranged between the two parts of the guide column, all driving grooves are equally divided into the two parts by the rotary table, each threaded connecting shaft connects two threaded shafts, and two supporting blocks are fixedly arranged on the two threaded connecting shafts; and is fixedly connected to the turntable; one of the two fixing parts is in threaded connection with one of the threaded shafts; another and the threaded connection axle threaded connection who does not install the supporting shoe, through the distribution of carrying out the construction position on the air earlier, then utilize the fixed part to carry out preset position and lay, when making the beginning construction, each equipment can have better construction environment, be applicable to the different rules that require in every process during the construction, then utilize the rotation of revolving stage, make one of them fixed part rotate, form and fix and the fixed of construction equipment to device self, accomplish the effect of killing more, and then utilize the threaded connection axle to supply, make the fixed part can remove and can not receive the interference, thereby accomplish the position of device and predetermine, make things convenient for follow-up construction.
Furthermore, one plane of each guide post is fixedly provided with a connecting shaft; the other plane is rotatably provided with a handle; the handle and the connecting shaft are in threaded fit, a plurality of guide columns are connected to complete large-area laying, and the handle and the connecting shaft are in threaded fit to complete connection, so that connection can be closely and conveniently achieved.
Further, the fixing part comprises a fixing plate, a driving component, a stretching deformation component and a clamping fixing component; in drive assembly set up the fixed plate, tensile deformation subassembly setting kept away from the one side of guide post at the fixed plate, centre gripping fixed subassembly installs at tensile deformation subassembly downside, through carrying out whole drive to the fixed plate for the construction is preset the position and is adjusted the convenience.
Furthermore, the driving assembly comprises a split plate, a crank rocker, a belt pulley, a driving wheel and a transmission cavity; the transmission cavity is arranged in the fixed plate, the opening plate is detachably arranged in the transmission cavity, and the belt pulley is rotatably arranged on the side wall of the transmission cavity; the driving wheel is rotatably arranged in the transmission cavity, the belt pulley is connected with the driving wheel through a belt, the crank rocker is matched with the driving wheel in a manner that inner teeth and outer teeth can be separated, and the crank rocker is slidably arranged on the open-close plate; and the crank part extends to the outside of the open-close plate, the fixed plate is driven by the crank rocker to transmit power to the belt pulley, and then the integral movement of the fixed plate is realized, so that the adjustment of the preset position for construction is facilitated.
Furthermore, the stretching deformation assembly comprises a limit nail, a hollow block, at least two bulges and a gooseneck pipe; one end of the gooseneck is fixedly arranged at the lower side of the fixed plate, the other end of the gooseneck is fixedly arranged in the hollow block, and one of the two bulges is fixedly arranged on the hollow block; the other one is fixedly arranged at the lower side of the fixed plate, and the limit screw is connected to the hollow block in a threaded manner; and with protruding screw-thread fit, accomodate and emit the gooseneck through utilizing being connected and separating between hollow block and the fixed plate to it is fixed on ground or to the angle change that carries out the construction after the fixed of construction equipment to correspond to make the device whole.
Further, the clamping and fixing assembly comprises a three-grab chuck, a piercing nail and a guide line; the three-jaw chuck is rotatably installed at the lower end of the hollow block, the piercing nail is fixedly installed at the top end of the clamping jaw of the three-jaw chuck, the guide lines are arranged on the side face of the clamping jaw, and the piercing nail and the guide lines are arranged on the clamping jaw of the three-jaw chuck, so that the three-jaw chuck is more convenient to fix the ground.
Furthermore, the threaded connecting shaft comprises a threaded connecting shaft body, a pair of spring columns and a pair of clamping grooves; the pair of spring posts slide respectively through the spring and are arranged at two ends of the threaded connecting shaft body in a rotating mode, a pair of clamping grooves are formed in one surfaces, close to the threaded connecting shaft, of the two threaded shafts respectively, and the spring posts are connected and disconnected, so that the movable connecting rod can be supported and is convenient to maintain.
Furthermore, the driving groove is internally provided with a size mark, so that the use of workers can be facilitated.
Further, the fixed part also comprises a transmission belt pulley; the diameter of driving pulley is greater than the belt pulley, and the diameter of drive wheel is less than the belt pulley, and driving pulley is connected with belt pulley belt, and driving pulley cooperates through the separable mode of inside and outside tooth with the crank rocker, carries out the contrast with the belt pulley through the diameter of driving pulley and drive wheel for big or small two kinds appear in the drive ratio, then realizes coarse adjustment and fine setting, and the meticulous size of cooperation construction reduces error and artificial consumption.
Further, a use method of the CBS vegetation concrete construction device is characterized in that:
the first step is as follows: rotating the rotary table, and then realizing the exchange of the threaded connecting shafts, so that one fixed part rotates ninety degrees;
the second step is that: and fixing the other fixing part on the ground, and connecting the tool to be constructed with the fixing part rotated by ninety degrees.
Compared with the prior art, the invention has the advantages that:
(1) this scheme is through earlier carrying out the distribution of construction position on the air, then utilize the fixed part to carry out preset position and lay, when making the beginning construction, each equipment can have better construction environment, be applicable to the different rules that require in every process during the construction, then utilize the rotation of revolving stage, make one of them fixed part rotate, it is fixed and to the fixed of construction equipment to form to device self, accomplish many effects of killing one's birds, and then utilize the threaded connection axle to supply, make the fixed part can remove can not receive the interference, thereby the position of accomplishing the device is predetermine, make things convenient for follow-up construction.
(2) This scheme is through utilizing the crank rocker to drive the fixed plate, gives the belt pulley with power transmission, then realizes the moving as a whole of fixed plate to the adjustment of position is predetermine in convenient construction.
(3) This scheme is accomodate the gooseneck and is emitted through the connection between hollow block and the fixed plate of utilization and separation to the angle that corresponds to make the device whole fixed or carry out the construction after fixing construction equipment changes on ground.
(4) This scheme is through seting up on the clamping jaw of three chucks and prick nail and direction line for can be more convenient when carrying out ground fixed, the diameter of belt drive wheel and drive wheel carries out the contrast with the belt pulley, makes the transmission ratio big or small two kinds appear, then realizes coarse adjusting and fine adjustment, and the meticulous size of cooperation construction reduces error and artificial consumption.
(5) This scheme is through connecting a plurality of guide posts and accomplish laying of large tracts of land, utilizes the handle and links up the screw-thread fit of axle and then accomplishes the connection for it can closely be convenient to connect.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the turntable after rotation;
FIG. 3 is a schematic view of the fixing portion of FIG. 2 according to the present invention;
FIG. 4 is a schematic representation of the tension deformable member of FIG. 3 after deformation in accordance with the present invention;
FIG. 5 is a schematic view of the internal structure of FIG. 3 according to the present invention;
FIG. 6 is a schematic view of the drive assembly of FIG. 5 according to the present invention;
FIG. 7 is a schematic view of the present invention at the location of the clamping fixture assembly of FIG. 5;
FIG. 8 is a schematic view of the invention at the location of the threaded connection shaft of FIG. 1;
FIG. 9 is a schematic view of an assembly structure of two devices according to the present invention.
The reference numbers in the figures illustrate:
the device comprises a guide post 1, a handle 11, a connecting shaft 12, a fixing part 2, a fixing plate 21, a driving component 22, a split plate 221, a crank rocker 222, a belt pulley 223, a driving wheel 224, a transmission cavity 226, a stretching deformation component 23, a limit nail 231, a hollow block 232, a bulge 234, a gooseneck 233, a transmission belt pulley 225, a clamping and fixing component 5, a three-grab chuck 51, a piercing nail 52, a guide line 53, a conversion part 3, a driving groove 4, a threaded shaft 41, a rotary table 31, a threaded connecting shaft 34, a supporting block 32, a spring post 35 and a clamping groove 36.
Detailed Description
Referring to fig. 1-9, a CBS vegetation concrete construction device includes a guide post 1, at least two fixing portions 2 and a transformation portion 3; three driving grooves 4 which are arranged in a shape of a Chinese character 'pin' are formed in the circumferential side surface of the guide column 1, and two threaded shafts 41 are fixedly arranged on the wall of each driving groove 4; and the two threaded shafts 41 are not connected to each other; the conversion part 3 comprises a rotary table 31, three threaded connecting shafts 34 and two supporting blocks 32; the turntable 31 is located between the two threaded shafts 41; the guide column 1 is divided into two parts, the rotary table 31 is rotatably arranged between the two parts of the guide column 1, all the driving grooves 4 are divided into two parts by the rotary table 31, each threaded connecting shaft 34 connects two threaded shafts 41, and two supporting blocks 32 are fixedly arranged on two of the threaded connecting shafts 34; and is fixedly connected to the turntable 31; one of the two fixing portions 2 is screwed with one of the threaded shafts 41; another and threaded connection axle 34 threaded connection who does not install supporting shoe 32, through the distribution of carrying out the construction position on the air earlier, then utilize the fixed part to carry out preset position and lay, when making the beginning construction, each equipment can have better construction environment, be applicable to the different rules that require in every process during the construction, then utilize the rotation of revolving stage 31, make one of them fixed part 2 rotate, form the fixed and construction equipment's of device self fixing, accomplish the effect of killing more, and then utilize threaded connection axle 34 to supply, make fixed part 2 can remove and can not receive the interference, thereby accomplish the position of device and predetermine, make things convenient for follow-up construction.
As shown in fig. 1 to 9, one of the planes of the guide post 1 is fixedly provided with an engaging shaft 12; the other plane is rotatably provided with a handle 11; handle 11 and the cooperation of linking 12 screw threads are through connecting the completion large tracts of land to a plurality of guide posts and lay, utilize the screw-thread fit of handle 11 and linking 12 and then accomplish to connect for it can closely be convenient to connect. The fixing part 2 comprises a fixing plate 21, a driving component 22, a stretching deformation component 23 and a clamping fixing component 5; in drive assembly 22 set up fixed plate 21, tensile deformation subassembly 23 sets up the one side of keeping away from guide post 1 at fixed plate 21, and the fixed subassembly 5 of centre gripping is installed at tensile deformation subassembly 23 downside, through carrying out whole drive to fixed plate 21 for the construction is preset the position and is adjusted the convenience.
As shown in fig. 1-6, the driving assembly 22 includes a clutch plate 221, a crank rocker 222, a pulley 223, a driving wheel 224, and a transmission cavity 226; the transmission cavity 226 is arranged in the fixed plate 21, the opening plate 221 is detachably arranged in the transmission cavity 226, and the belt pulley 223 is rotatably arranged on the side wall of the transmission cavity 226; the crank rocker 222 is matched with the driving wheel 224 in a separable mode through internal and external teeth, and the crank rocker 222 is slidably arranged on the open-close plate 221; and the crank part extends to the outside of the open-close plate 221, the fixed plate 21 is driven by the crank rocker 222, the power is transmitted to the belt pulley 223, and then the integral movement of the fixed plate 21 is realized, thereby facilitating the adjustment of the preset construction position.
As shown in fig. 2-7, the stretch-deforming assembly 23 includes a stop pin 231, a hollow block 232, at least two projections 234, and a gooseneck 233; one end of the gooseneck 233 is fixedly arranged at the lower side of the fixed plate 21, the other end is fixedly arranged in the hollow block 232, and one of the two bulges 234 is fixedly arranged on the hollow block 232; the other is fixedly arranged at the lower side of the fixed plate 21, and a limit nail 231 is connected to the hollow block 232 in a threaded manner; and is screw-engaged with the boss 234 to accommodate and release the gooseneck 233 by coupling and decoupling the hollow block 232 with the fixing plate 21, thereby corresponding to the change of the angle at which the entire apparatus is fixed to the ground or the construction is performed after the fixing of the construction equipment.
As shown in fig. 1 to 7, the holding fixture assembly 5 includes a three-grip chuck 51, piercing pins 52, and guide threads 53; the three-grip chuck 51 is rotatably arranged at the lower end of the hollow block 232, the puncturing nail 52 is fixedly arranged at the top end of the clamping jaw of the three-grip chuck 51, the guide lines 53 are arranged on the side surface of the clamping jaw, and the puncturing nail 52 and the guide lines 53 are arranged on the clamping jaw of the three-grip chuck 51, so that the ground fixing can be more convenient. The threaded connection shaft 34 includes a threaded connection shaft body, a pair of spring posts 35, and a pair of snap grooves 36; a pair of spring post 35 slides respectively through the spring and ann changes at threaded connection axle body both ends, and a pair of joint groove 36 is seted up respectively in two threaded shaft 41 one sides that are close to threaded connection axle 34, connects and breaks off through a pair of spring post 35 for the removal can be supported, and convenient the maintenance. The driving groove 4 is internally provided with a size mark, so that the use of workers can be facilitated.
As shown in fig. 2-8, the fixed part 2 further comprises a driving pulley 225; the diameter of the transmission belt wheel 225 is larger than that of the belt wheel 223, the diameter of the driving wheel 224 is smaller than that of the belt wheel 223, the transmission belt wheel 225 is in belt connection with the belt wheel 223, the transmission belt wheel 225 is matched with the crank rocker 222 in a mode that inner teeth and outer teeth can be separated, the transmission ratio is two in size through the comparison between the diameters of the transmission belt wheel 225 and the driving wheel 224, then coarse adjustment and fine adjustment are achieved, fine sizes of construction are matched, and errors and labor consumption are reduced.
The use method of the CBS vegetation concrete construction device is characterized in that:
the first step is as follows: rotating the turntable 31 and then effecting the exchange of the threaded connection shafts 34 so that one of the fixed parts 2 rotates ninety degrees;
the second step is that: another fixing part 2 is fixed on the ground, and a tool to be constructed is connected to the fixing part 2 rotated by ninety degrees
As shown in fig. 1-8, when in use, the device is moved to a preset position by presetting a position, then the crank rocker 222 is pushed to make the crank rocker 222 and the transmission belt pulley 225 complete internal tooth engagement, then the crank rocker 222 is rotated to make the belt pulley 223 rotate, then the fixed part 2 moves integrally, the matching dimension completes coarse adjustment, then the crank rocker 222 is moved to be engaged with the driving wheel 224 internal tooth, thereby the crank rocker 222 is rotated to complete fine adjustment, a specified position is reached, then the three clamping jaws of the three-jaw chuck 51 move towards the middle part, then the three clamping jaws are combined to complete forming a shape of a nail and rotate in alignment with the ground, and the three-jaw chuck 51 is rotated integrally, so that the formed nail can be drilled into the ground.
As shown in fig. 2 to 8, the rotary table 31 is rotated to rotate one of the fixing portions 2 by ninety degrees, and then the limit nail 231 is removed, so that the gooseneck 233 is released and is not stored, and then the construction equipment or material is clamped by the three-grip chuck 51 and is constructed by being matched with the gooseneck 233.
When the connection is required, as shown in fig. 9, it is sufficient to rotate the handle 11 so that the coupling shaft 12 is connected to the guide post 1.

Claims (10)

1. The utility model provides a CBS vegetation concrete construction equipment which characterized in that: comprises a guide post (1), at least two fixed parts (2) and a conversion part (3);
three driving grooves (4) which are arranged in a shape of a Chinese character 'pin' are formed in the circumferential side surface of the guide column (1), and two threaded shafts (41) are fixedly mounted on the wall of each driving groove (4); and the two threaded shafts (41) are not connected to each other;
the conversion part (3) comprises a rotary table (31), three threaded connecting shafts (34) and two supporting blocks (32);
the turntable (31) is located between two threaded shafts (41); the guide column (1) is divided into two parts, the rotary table (31) is rotatably installed between the two parts of the guide column (1), all driving grooves (4) are equally divided into the two parts by the rotary table (31), each threaded connecting shaft (34) connects two threaded shafts (41), and two supporting blocks (32) are fixedly installed on the two threaded connecting shafts (34); and is fixedly connected to the turntable (31);
one of the two fixing parts (2) is in threaded connection with one of the threaded shafts (41); and the other one is in threaded connection with a threaded connection shaft (34) which is not provided with the supporting block (32).
2. The CBS vegetation concrete construction device of claim 1, wherein: one plane of the guide post (1) is fixedly provided with a connecting shaft (12) respectively; the other plane is rotatably provided with a handle (11);
the handle (11) is in threaded fit with the connecting shaft (12).
3. The CBS vegetation concrete construction device of claim 1, wherein: the fixing part (2) comprises a fixing plate (21), a driving component (22), a stretching deformation component (23) and a clamping fixing component (5);
the driving assembly (22) is arranged in the fixing plate (21), the stretching deformation assembly (23) is arranged on one surface, far away from the guide column (1), of the fixing plate (21), and the clamping fixing assembly (5) is installed on the lower side of the stretching deformation assembly (23).
4. The CBS vegetation concrete construction device of claim 3, wherein: the driving assembly (22) comprises an opening plate (221), a crank rocker (222), a belt pulley (223), a driving wheel (224) and a transmission cavity (226);
the transmission cavity (226) is arranged in the fixing plate (21), the opening plate (221) is detachably arranged in the transmission cavity (226), and the belt pulley (223) is rotatably arranged on the side wall of the transmission cavity (226); the crank rocker (222) is matched with the driving wheel (224) in a separable mode through inner and outer teeth, and the crank rocker (222) is slidably arranged on the opening plate (221); and a crank part extending to the outside of the opening plate (221).
5. The CBS vegetation concrete construction device of claim 3, characterized in that: the stretching deformation assembly (23) comprises a limit nail (231), a hollow block (232), at least two protrusions (234) and a gooseneck (233);
one end of the gooseneck (233) is fixedly arranged at the lower side of the fixed plate (21), the other end of the gooseneck is fixedly arranged in the hollow block (232), and one of the two bulges (234) is fixedly arranged on the hollow block (232); the other one is fixedly arranged at the lower side of the fixed plate (21), and a limit nail (231) is connected to the hollow block (232) in a threaded manner; and is threadedly engaged with the boss (234).
6. The CBS vegetation concrete construction device of claim 3, wherein: the clamping and fixing assembly (5) comprises a three-grab chuck (51), piercing nails (52) and guide threads (53);
the three-grab chuck (51) is rotatably arranged at the lower end of the hollow block (232), the piercing nail (52) is fixedly arranged at the top end of the clamping jaw of the three-grab chuck (51), and the guide lines (53) are arranged on the side surface of the clamping jaw.
7. The CBS vegetation concrete construction device of claim 1, wherein: the threaded connecting shaft (34) comprises a threaded connecting shaft body, a pair of spring columns (35) and a pair of clamping grooves (36);
the pair of spring columns (35) are respectively arranged at two ends of the threaded connecting shaft body in a sliding mode through springs, and the pair of clamping grooves (36) are respectively formed in one surfaces, close to the threaded connecting shaft (34), of the two threaded shafts (41).
8. The CBS vegetation concrete construction device of claim 1, wherein: and size marks are arranged in the driving grooves (4).
9. The CBS vegetation concrete construction device of claim 4, wherein: the fixed part (2) further comprises a transmission belt pulley (225); the diameter of the transmission belt pulley (225) is larger than that of the belt pulley (223), the diameter of the driving wheel (224) is smaller than that of the belt pulley (223), the transmission belt pulley (225) is in belt connection with the belt pulley (223), and the transmission belt pulley (225) is matched with the crank rocker (222) in a mode that inner teeth and outer teeth can be separated.
10. The use method of the CBS vegetation concrete construction device according to any one of claims 1 to 9, wherein:
the first step is as follows: rotating the turntable (31) and then effecting an exchange of the threaded connection shafts (34) so that one of the fixed parts (2) rotates ninety degrees;
the second step is that: the other fixing part (2) is fixed on the ground, and a tool to be constructed is connected with the fixing part (2) which rotates ninety degrees.
CN202210240496.4A 2022-03-10 2022-03-10 CBS vegetation concrete construction device and method thereof Active CN114541401B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210240496.4A CN114541401B (en) 2022-03-10 2022-03-10 CBS vegetation concrete construction device and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210240496.4A CN114541401B (en) 2022-03-10 2022-03-10 CBS vegetation concrete construction device and method thereof

Publications (2)

Publication Number Publication Date
CN114541401A true CN114541401A (en) 2022-05-27
CN114541401B CN114541401B (en) 2023-10-24

Family

ID=81663877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210240496.4A Active CN114541401B (en) 2022-03-10 2022-03-10 CBS vegetation concrete construction device and method thereof

Country Status (1)

Country Link
CN (1) CN114541401B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4984680A (en) * 1988-10-26 1991-01-15 Shibuya Kogyo Co., Ltd. Article transfer apparatus with clamper
JP2003184025A (en) * 2001-12-17 2003-07-03 Sato Road Co Ltd Method for constructing porous concrete slope face
CN108004900A (en) * 2018-01-03 2018-05-08 黄远明 A kind of environmental and ecological prosthetic appliance that filling can be dug to eco-concrete slope surface
CN112854255A (en) * 2021-01-12 2021-05-28 中建长远建设有限公司 Anchor rod structure and construction method of ecological slope protection of plant-growing concrete
ZA202101674B (en) * 2020-09-15 2021-10-27 Univ Qingdao Agricultural Overflow protection device for vegetation growing recycled eco-concrete pouring on slope

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4984680A (en) * 1988-10-26 1991-01-15 Shibuya Kogyo Co., Ltd. Article transfer apparatus with clamper
JP2003184025A (en) * 2001-12-17 2003-07-03 Sato Road Co Ltd Method for constructing porous concrete slope face
CN108004900A (en) * 2018-01-03 2018-05-08 黄远明 A kind of environmental and ecological prosthetic appliance that filling can be dug to eco-concrete slope surface
ZA202101674B (en) * 2020-09-15 2021-10-27 Univ Qingdao Agricultural Overflow protection device for vegetation growing recycled eco-concrete pouring on slope
CN112854255A (en) * 2021-01-12 2021-05-28 中建长远建设有限公司 Anchor rod structure and construction method of ecological slope protection of plant-growing concrete

Also Published As

Publication number Publication date
CN114541401B (en) 2023-10-24

Similar Documents

Publication Publication Date Title
CN201960568U (en) Reversible mechanical paws
NO20083656L (en) Method and apparatus for connection and release of threaded rudders
NO20150916A1 (en) Apparatus and method for applying torque to a first tube against a second tube
CN111364685B (en) Device for connecting steel bar sleeve and construction method
KR20160039180A (en) Device for handling drill string components in respect of a rock drill rig and rock drill rig
CN111236865B (en) Shackle tongs and method capable of realizing automatic screwing-on and unscrewing of sucker rod
CN101781975B (en) Screwing and buckling clamp for connecting and disassembling drill rod and sleeve pipe
CN114541401A (en) CBS vegetation concrete construction device and method thereof
CN112192469B (en) Automobile tire clamping and fixing device
CN116837840A (en) Flood prevention equipment for hydraulic engineering and application method thereof
CN106555482B (en) A kind of masonry constructional column bar planting device
CN215467733U (en) Municipal works cable device of flare-outing
CN201705247U (en) Spinning wrench used for mounting or dismounting drilling rod and casing
CN213153195U (en) Positioning device is used in ornamental trees and shrubs maintenance convenient to installation
CN107009292A (en) A kind of fast fixture for frock
CN106737344A (en) Screw bolt dismantling device and its application method
CN204235111U (en) A kind of pressure reducer assembly machine
CN112962604B (en) Pile cutter for building disassembly
CN111886980B (en) Rice planting equipment
CN203553760U (en) Tool specially for 500-kV electric transmission line spacer
CN219719274U (en) Warmhouse booth temperature regulating device
CN214035576U (en) Automatic disassembling and assembling mechanism applied to drill rod
CN212849675U (en) Electronic engineering cable strutting arrangement
CN211135817U (en) Simple fastening thread repairing device
CN114809701B (en) Sleeve type reinforcing device for power transmission tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant