CN203553760U - Tool specially for 500-kV electric transmission line spacer - Google Patents

Tool specially for 500-kV electric transmission line spacer Download PDF

Info

Publication number
CN203553760U
CN203553760U CN201320721363.5U CN201320721363U CN203553760U CN 203553760 U CN203553760 U CN 203553760U CN 201320721363 U CN201320721363 U CN 201320721363U CN 203553760 U CN203553760 U CN 203553760U
Authority
CN
China
Prior art keywords
pin
transmission line
tool
conductor spacer
pull rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320721363.5U
Other languages
Chinese (zh)
Inventor
张福宝
林仲良
郑庆佑
林晓光
郑奋成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Original Assignee
FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd, State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd filed Critical FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd
Priority to CN201320721363.5U priority Critical patent/CN203553760U/en
Application granted granted Critical
Publication of CN203553760U publication Critical patent/CN203553760U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Processing Of Terminals (AREA)

Abstract

The utility model relates to a tool specially for a 500-kV electric transmission line spacer. The tool comprises a cam wrench, a pull rod and a light pin; and one end of the pull rod is hinged with the cam wrench by a pin. A plurality of hole sites cooperating with the pin are arranged at the cam wrench. The other end of the pull rod is connected with one end of the light pin by a chain. And a plurality of insertion holes that are arranged into one row and cooperate with the light pin are arranged in the pull rod along the length direction. The provided tool has advantages of universality, high efficiency, and easy mastering and the like. Because of the multi-hole site adjustable cam wrench and the pull rod, disassembling and assembling requirements of spacers with different types and different dimensions can be met. The existing various special-purpose tools can be replaced by the pair of tools; and the tools can be carried conveniently by the installing personnel. On the basis of the lever crowbar principle, the operation method and the operation steps for spacer assembling and disassembling can be simplified, thereby substantially improving the work efficiency. The tool can be operated easily; and the principle is simple and the tool can be used for training easily.

Description

A kind of 500kV transmission line conductor spacer specific purpose tool
Technical field
The utility model relates to a kind of 500kV transmission line conductor spacer specific purpose tool.
Background technology
Along with the high speed development of power grid construction, on 500kV transmission line, use wire type variation, the sectional area of wire is also increasing, from initial 300,400 to 500,630, even 800 has.The also variation of different wires and different gold utensil manufacturer production conductor spacer model out, at present common 500kV transmission line conductor spacer model is kind more than ten nearly, and erector's utensil that every kind of conductor spacer is equipped with is all not quite similar, and dismounting complex operation.
The conventional special dismounting multiplexer of 500kV transmission line conductor spacer has three kinds (band pawl formula, centring types, telescopic) at present, because the variation of Work tool, staff is easily obscured for the Work tool carrying, if it is very heavy again that three kinds of instruments all take field high altitude to, greatly strengthened operating personnel's workload.And three kinds of conductor spacer specific purpose tools that use at present, the time of a conductor spacer of installation and removal needs 12~15 minutes.
Utility model content
The problem that the utility model exists for above-mentioned prior art is made improvement, and technical problem to be solved in the utility model is to provide the 500kV transmission line conductor spacer specific purpose tool that a kind of versatility is high, dismounting efficiency is high and processing ease is grasped.
In order to solve the problems of the technologies described above, the technical solution of the utility model is: a kind of 500kV transmission line conductor spacer specific purpose tool, comprise cam spanner, pull bar and light pin, described pull bar one end is hinged by pin and cam spanner, offers along its length the multiple equal jacks that can match with light pin of a row on described pull bar.
In further technical scheme, the described pull bar other end is connected with light pin one end by chain.
In further technical scheme, on described cam spanner, be provided with the multiple equal positions, hole that can match with pin.
Compared with prior art, the utlity model has following beneficial effect: (1) has versatility: the design adjustable cam spanner of multi-hole position and pull bar can meet the conductor spacer dismounting needs of different model and different size, as long as can substitute original multiple different specific purpose tool, installation personnel carrying portable, convenience once secondary 500kV transmission line conductor spacer specific purpose tool; (2) there is high efficiency: this 500kV transmission line conductor spacer specific purpose tool mainly utilizes lever crowbar principle, operation technique and the operating procedure of dismounting conductor spacer have been simplified, work efficiency is improved greatly, originally 12~15 minutes time of a conductor spacer of installation and removal, and only need now can complete for 2~3 minutes; (3) there is easy grasp: this 500kV transmission line conductor spacer specific purpose tool principle is simple, training use be easy to, general workman only need to see for 1 minute others demonstrate can learn operation.
Below in conjunction with the drawings and specific embodiments, the utility model is described in more detail.
Accompanying drawing explanation
Fig. 1 is the organigram of 500kV transmission line conductor spacer specific purpose tool.
Fig. 2 is the organigram after Fig. 1 cam spanner rotates counterclockwise.
Fig. 3 is the view that 500kV transmission line conductor spacer specific purpose tool is arranged on conductor spacer claw.
Fig. 4 is after Fig. 3 cam spanner rotates counterclockwise and the view of extracting conductor spacer pin.
Fig. 5 is the view after Fig. 4 cam spanner unclamps.
In figure: 1-cam spanner, 2-pin, 3-pull bar, 3-1-jack, 4-chain, 5-light pin, 6-conductor spacer claw, 7-conductor spacer pin.
Embodiment
As shown in Figure 1 and 2, a kind of 500kV transmission line conductor spacer specific purpose tool, comprise cam spanner 1, pull bar 3 and light pin 5, described pull bar 3 one end are hinged by pin 2 and cam spanner 1, offer along its length six jack 3-1 that all can match with light pin 5 of a row on described pull bar 3.
In the present embodiment, on described cam spanner 1, be provided with two positions, hole that all can match with pin 2.In order to facilitate light pin 5 to operate and to be difficult for losing, described pull bar 3 other ends are connected with light pin 5 one end by chain 4.
The utility model design adjustable cam spanner 1 of multi-hole position and pull bar 3, can meet the conductor spacer dismounting needs of different model and different size, as long as can substitute original multiple different specific purpose tool, installation personnel carrying portable, convenience once secondary 500kV transmission line conductor spacer specific purpose tool.
The using method of this 500kV transmission line conductor spacer specific purpose tool, carry out according to the following steps:
(1) by pull bar 3 and cam spanner 1 place's 90 degree states, and pull bar 3 is aimed in the through hole inserting in the middle of conductor spacer claw 6;
(2) light pin 5 is inserted in jack 3-1 corresponding on pull bar 3,500kV transmission line conductor spacer specific purpose tool installs and closes, as shown in Figure 3;
(3) counterclockwise 45 degree rotating cam spanners 1, with by the stressed conductor spacer pin 7 light pin 5 that is transferred to, conductor spacer pin 7 is not stressed can normally be extracted, as shown in Figure 4;
(4) extract conductor spacer pin 7, as shown in Figure 4;
(5) unclamp cam spanner 1, conductor spacer claw 6 unclamps naturally, as shown in Figure 5;
(6) conductor spacer dismounting is complete, takes out 500kV transmission line conductor spacer special;
(7) in like manner, installation steps order is contrary with dismounting step for conductor spacer installation method.
This 500kV transmission line conductor spacer specific purpose tool operation principle is simple, training use be easy to, general workman only need to see for 1 minute others demonstrate can learn operation.This 500kV transmission line conductor spacer specific purpose tool simplify the operation gimmick and operating procedure, work efficiency is improved greatly, originally utilize the time of a conductor spacer of existing instrument installation and removal to need 12~15 minutes, and utilize now this instrument only to need to complete for 2~3 minutes.
The foregoing is only preferred embodiment of the present utility model, all equalizations of doing according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.

Claims (3)

1. a 500kV transmission line conductor spacer specific purpose tool, it is characterized in that: comprise cam spanner, pull bar and light pin, described pull bar one end is hinged by pin and cam spanner, offers along its length the multiple equal jacks that can match with light pin of a row on described pull bar.
2. 500kV transmission line conductor spacer specific purpose tool according to claim 1, is characterized in that: the described pull bar other end is connected with light pin one end by chain.
3. 500kV transmission line conductor spacer specific purpose tool according to claim 1, is characterized in that: on described cam spanner, be provided with the multiple equal positions, hole that can match with pin.
CN201320721363.5U 2013-11-15 2013-11-15 Tool specially for 500-kV electric transmission line spacer Expired - Fee Related CN203553760U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320721363.5U CN203553760U (en) 2013-11-15 2013-11-15 Tool specially for 500-kV electric transmission line spacer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320721363.5U CN203553760U (en) 2013-11-15 2013-11-15 Tool specially for 500-kV electric transmission line spacer

Publications (1)

Publication Number Publication Date
CN203553760U true CN203553760U (en) 2014-04-16

Family

ID=50471829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320721363.5U Expired - Fee Related CN203553760U (en) 2013-11-15 2013-11-15 Tool specially for 500-kV electric transmission line spacer

Country Status (1)

Country Link
CN (1) CN203553760U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103560436A (en) * 2013-11-15 2014-02-05 国家电网公司 Special tool for 500kV electric transmission line spacing bar and application method thereof
CN116140958A (en) * 2022-12-13 2023-05-23 国家电网有限公司 Automatic alignment system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103560436A (en) * 2013-11-15 2014-02-05 国家电网公司 Special tool for 500kV electric transmission line spacing bar and application method thereof
CN103560436B (en) * 2013-11-15 2016-06-01 国家电网公司 The special dismantling devices of 500kV power transmission line spacer and using method thereof
CN116140958A (en) * 2022-12-13 2023-05-23 国家电网有限公司 Automatic alignment system
CN116140958B (en) * 2022-12-13 2024-05-10 国家电网有限公司 Automatic alignment system

Similar Documents

Publication Publication Date Title
CN204365899U (en) A kind of transmission line tower stay wire tools
CN201298694Y (en) Pin remover for anti-pollution insulator
CN203553760U (en) Tool specially for 500-kV electric transmission line spacer
CN202384627U (en) Multifunctional network cable tongs
CN204308817U (en) A kind of dual gauge box spanner assembly
CN201922399U (en) M spring leaf pin demounting device for insulator
CN203951020U (en) A kind of Multifunctional netting twine pincers
CN201900590U (en) Special wrench for high-tension line lead spacers
CN103560436A (en) Special tool for 500kV electric transmission line spacing bar and application method thereof
CN202123491U (en) Pin remover
CN103972755A (en) Wiring pincers for tapping terminal of transformer
CN206531992U (en) Optical cable opens cable and draws tool of exchanging work
CN203487881U (en) Unlocking device
CN203197832U (en) Locating pin pulling device
CN202302716U (en) Air filling tube for SF6 switch
CN203039294U (en) Working tool for live-line replacement of three-hole single connection plate linear insulator string
CN202190024U (en) Special vice for power transmission line checking and repair
CN206287065U (en) A kind of instrument of fast assembling-disassembling nut
CN103286724A (en) Simple folding type inner hexagon wrenches
CN204382175U (en) Incremental encoder tool special for dismounting
CN203932590U (en) Transformer tap terminals jointing clamp
CN204308875U (en) The adjustable antioverloading electroprobe of a kind of load
CN204205405U (en) The replaceable special pin pulling clamp of a kind of insulator R type pin
CN203386941U (en) Improved grounding wire wiring terminal
CN203125402U (en) Tool for mounting and dismounting round nut

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140416

Termination date: 20201115