CN114525806A - Iron tower single-pile combined foundation and construction method thereof - Google Patents

Iron tower single-pile combined foundation and construction method thereof Download PDF

Info

Publication number
CN114525806A
CN114525806A CN202210332625.2A CN202210332625A CN114525806A CN 114525806 A CN114525806 A CN 114525806A CN 202210332625 A CN202210332625 A CN 202210332625A CN 114525806 A CN114525806 A CN 114525806A
Authority
CN
China
Prior art keywords
foundation
tower
pile
foot
iron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210332625.2A
Other languages
Chinese (zh)
Inventor
郭艳军
李晔
吴数伟
刘泉
刘杰
李果
安宁
刘华峰
张勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Electric Power Design and Consulting Co Ltd
Original Assignee
Sichuan Electric Power Design and Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Electric Power Design and Consulting Co Ltd filed Critical Sichuan Electric Power Design and Consulting Co Ltd
Priority to CN202210332625.2A priority Critical patent/CN114525806A/en
Publication of CN114525806A publication Critical patent/CN114525806A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Foundations (AREA)

Abstract

本发明涉及铁塔施工领域,公开了一种铁塔基础及其施工方法。该铁塔单桩联合基础包括一根基桩和多根塔脚连接梁,所述基桩位于多根塔脚连接梁的中间,各所述塔脚连接梁一端均与基桩相连接、另一端向外发散延伸形成延伸部,所述延伸部设置有用于连接铁塔腿的塔脚连接结构。该铁塔单桩联合基础仅在铁塔中心开挖和浇筑一个基础,此基础大大减少基础占地及开挖,减少场地条件对于铁塔基础的限制,同时降低铁塔基础对周边的影响和破坏,能够有效解决城市地下管线多、山区四个独立基础建设困难、保护区动土区域限制、冻胀对基础上拔影响大等难题。

Figure 202210332625

The invention relates to the field of iron tower construction, and discloses an iron tower foundation and a construction method thereof. The single-pile combined foundation of the iron tower includes a foundation pile and a plurality of tower foot connecting beams, the foundation pile is located in the middle of the plurality of tower foot connecting beams, one end of each tower foot connecting beam is connected with the foundation pile, and the other end is connected to the foundation pile. The outer divergent extension forms an extension part, and the extension part is provided with a tower foot connection structure for connecting the iron tower legs. The single-pile combined foundation of the tower only excavates and pours one foundation in the center of the tower. This foundation greatly reduces the land occupation and excavation of the foundation, reduces the restrictions on the tower foundation due to site conditions, and reduces the impact and damage of the tower foundation on the surrounding area, which can effectively Solve the problems of many urban underground pipelines, difficulties in four independent infrastructure construction in mountainous areas, restrictions on the ground breaking area of protected areas, and frost heave has a great impact on the foundation pull.

Figure 202210332625

Description

铁塔单桩联合基础及其施工方法Iron tower monopile combined foundation and its construction method

技术领域technical field

本发明涉及铁塔基础领域,尤其是一种铁塔基础及其施工方法。The invention relates to the field of iron tower foundation, in particular to an iron tower foundation and a construction method thereof.

背景技术Background technique

输电线路的铁塔最常见的为四腿铁塔,现有的四腿铁塔基础常规采用每个塔腿下一个基础的方式,将铁塔上的荷载传递到地基中,如公告号为CN203411988U的实用新型专利,但随着线路建设,存在以下几种情况四腿铁塔塔腿采用独立基础难于建设的困难:The most common type of iron tower for transmission lines is a four-legged iron tower. The existing four-legged iron tower foundation routinely adopts the method of one foundation for each tower leg to transfer the load on the iron tower to the foundation, such as the utility model patent with the announcement number CN203411988U , but with the construction of the line, there are the following difficulties in the construction of the four-legged tower with an independent foundation:

1、沿城市及城市周边道路建设的四腿铁塔,因路边下埋设有市政水电管线,无法建设四个基础;1. The four-legged iron towers built along the city and the surrounding roads of the city cannot build four foundations because of the municipal water and electricity pipelines buried under the roadside;

2、线路经过生态环境保护区、水源地、水产养殖基地等对动土区域及范围均有限制,四腿基础无法满足要求;2. The route passes through ecological environmental protection areas, water sources, aquaculture bases, etc., which have restrictions on the area and scope of ground breaking, and the four-leg foundation cannot meet the requirements;

3、山区水电送出线路场地狭窄,孤立山包或悬崖边无法建设四个独立基础;3. The site of the hydropower transmission line in the mountainous area is narrow, and four independent foundations cannot be built on the isolated hill or cliff;

4、生态环境脆弱的高原或戈壁场地,建设四个独立基础对塔基环境破坏严重,无法满足环水保要求;4. In the plateau or Gobi site with fragile ecological environment, the construction of four independent foundations will seriously damage the environment of the tower base and cannot meet the requirements of environmental protection and water protection;

5、地质条件坚硬,地基开挖困难,采用小截面独立基础机械开挖空间受限,采用大截面独立基础造成投资增加;5. The geological conditions are hard and the foundation excavation is difficult. The use of small-section independent foundations is limited in mechanical excavation space, and the use of large-section independent foundations results in increased investment;

6、地质条件差,地形坡度大的塔位采用四个独立基础开挖风险高,且环境破坏大;6. The geological conditions are poor, the tower site with large terrain slope adopts four independent foundations, the risk of excavation is high, and the environmental damage is large;

7、冻胀等级和深度较大区域,四腿独立基础中冻胀力对基础上拔影响较大,造成工程量大幅增加;以上问题目前常用的基础型式均难以解决。7. In areas with large frost heave grades and depths, the frost heave force in the four-leg independent foundation has a greater impact on the uplift of the foundation, resulting in a substantial increase in the amount of work; the above problems are currently difficult to solve with the commonly used foundation types.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题是提供一种铁塔单桩联合基础及其施工方法,减少场地条件对于铁塔基础的限制,同时降低铁塔基础对周边的影响。The technical problem to be solved by the present invention is to provide an iron tower single-pile combined foundation and a construction method thereof, which can reduce the limitation of site conditions on the iron tower foundation, and at the same time reduce the influence of the iron tower foundation on the surrounding.

本发明公开的铁塔单桩联合基础,包括一根基桩和多根塔脚连接梁,所述基桩位于多根塔脚连接梁的中间,各所述塔脚连接梁一端均与基桩相连接、另一端向外发散延伸形成延伸部,所述延伸部设置有用于连接铁塔腿的塔脚连接结构。The single-pile combined foundation for an iron tower disclosed by the invention comprises a foundation pile and a plurality of tower foot connecting beams, the foundation pile is located in the middle of the plurality of tower foot connecting beams, and one end of each tower foot connecting beam is connected with the foundation pile , the other end diverges and extends outward to form an extension part, and the extension part is provided with a tower foot connection structure for connecting the iron tower legs.

优选地,所述基桩的底部设置有基础扩大头。Preferably, the bottom of the foundation pile is provided with a foundation enlargement head.

优选地,所述塔脚连接梁水平设置。Preferably, the tower foot connecting beams are arranged horizontally.

优选地,所述塔脚连接梁从基桩至延伸部倾斜向上设置。Preferably, the tower foot connecting beam is inclined upward from the foundation pile to the extension part.

优选地,各所述塔脚连接梁连接于基桩的同一水平高度上。Preferably, each of the tower foot connecting beams is connected to the same level of the foundation piles.

优选地,各所述塔脚连接梁连接于基桩的不同水平高度上。Preferably, each of the tower foot connecting beams is connected to the foundation piles at different levels.

优选地,所述塔脚连接结构为地脚螺栓,所述地脚螺栓底部连接有锚板,所述锚板位于塔脚连接梁的钢筋下方。Preferably, the connection structure of the tower foot is an anchor bolt, and the bottom of the anchor bolt is connected with an anchor plate, and the anchor plate is located under the reinforcing bars of the connecting beam of the tower foot.

优选地,所述塔脚连接梁为混凝土或者型钢材料。Preferably, the tower foot connecting beam is made of concrete or profiled steel.

所述的铁塔单桩联合基础的施工方法,包括如下步骤:The construction method of the single-pile combined foundation of the iron tower comprises the following steps:

设计铁塔单桩联合基础;Design the monopile joint foundation of the tower;

按照基桩的设计开挖基坑,并开挖塔脚连接梁的沟槽;Excavate the foundation pit according to the design of the foundation pile, and excavate the groove for connecting the beam at the foot of the tower;

绑扎钢筋,设置塔脚连接梁,完成后按铁塔根开固定预埋地脚螺栓作为塔脚连接结构,支立模板,浇筑混凝土形成铁塔单桩联合基础。Bind steel bars, set up connecting beams at the tower foot, and then open and fix the pre-buried anchor bolts as the tower foot connection structure according to the tower root, erect the formwork, and pour concrete to form the iron tower single pile joint foundation.

优选地,在设计铁塔单桩联合基础时,在塔脚连接梁的塔脚连接结构上加载荷载,根据铁塔各工况计算的上拔力最不利、下压力最不利、水平力最不利情况确定加载荷载的大小和方向。Preferably, when designing the combined foundation of the iron tower, load the load on the tower foot connection structure of the tower foot connecting beam, and determine the most unfavorable uplift force, the most unfavorable down pressure and the most unfavorable horizontal force calculated according to the working conditions of the iron tower. The magnitude and direction of the loading load.

优选地,在设计铁塔单桩联合基础时,根据年平均气温条件计算基础作用力,以此基础作用力计算塔脚连接梁挠度,设计塔脚连接梁预抬值大于计算出的塔脚连接梁挠度。Preferably, when designing the single-pile combined foundation of the iron tower, the basic force is calculated according to the annual average temperature condition, and the deflection of the tower foot connecting beam is calculated based on the basic force, and the pre-lift value of the designed tower foot connecting beam is greater than the calculated tower foot connecting beam. deflection.

本发明的有益效果是:本申请的铁塔单桩联合基础仅在铁塔中心开挖和浇筑一个基础,此基础大大减少基础占地及开挖,减少场地条件对于铁塔基础的限制,同时降低铁塔基础对周边的影响和破坏,能够有效解决背景技术中所述的城市地下管线多、山区四个独立基础建设困难、保护区动土区域限制、冻胀对基础上拔影响大等难题。The beneficial effects of the present invention are as follows: the combined foundation of the iron tower single pile of the present application only excavates and pours a foundation in the center of the iron tower, which greatly reduces the land occupation and excavation of the foundation, reduces the limitation of site conditions on the iron tower foundation, and reduces the iron tower foundation at the same time. The impact and damage on the surrounding area can effectively solve the problems mentioned in the background art, such as many urban underground pipelines, difficulty in constructing four independent infrastructures in mountainous areas, restrictions on ground breaking area in protected areas, and large impact of frost heave on foundation pull.

附图说明Description of drawings

图1是本申请的一种实施方式的示意图;1 is a schematic diagram of an embodiment of the present application;

图2是本申请的另一种实施方式的图;Figure 2 is a diagram of another embodiment of the application;

图3是本申请的计算示例示意图。FIG. 3 is a schematic diagram of a calculation example of the present application.

附图标记:基础扩大头1,基桩2,塔脚连接梁3,塔脚连接结构4。Reference numerals: foundation expansion head 1, foundation pile 2, tower foot connecting beam 3, tower foot connecting structure 4.

具体实施方式Detailed ways

下面对本发明进一步说明。The present invention is further described below.

本发明公开的铁塔单桩联合基础,包括一根基桩2和多根塔脚连接梁3,所述基桩2位于多根塔脚连接梁3的中间,各所述塔脚连接梁3一端均与基桩2相连接、另一端向外发散延伸形成延伸部,所述延伸部设置有用于连接铁塔腿的塔脚连接结构4。The iron tower single-pile combined foundation disclosed in the present invention includes a foundation pile 2 and a plurality of tower foot connecting beams 3, the foundation pile 2 is located in the middle of the plurality of tower foot connecting beams 3, and each tower foot connecting beam 3 has one end at one end. It is connected with the foundation pile 2, and the other end diverges and extends outward to form an extension portion, and the extension portion is provided with a tower foot connection structure 4 for connecting the iron tower legs.

其中,塔脚连接梁3上的塔脚连接结构4用于连接铁塔的塔脚,塔脚连接结构4通常为地脚螺栓,也可采用现有的其他连接方式,塔脚连接梁3的数量可根据塔脚数量确定,目前绝大多数铁塔塔脚为四个,即塔脚连接梁3的数量通常也为四个,整个基础的基桩2数量则仅为一个,其位于各个塔脚连接梁3的中间位置,各个塔脚的作用力通过塔脚连接梁3传递至基桩2处,由基桩2稳定承受。由于仅设置一个基桩2,因此,减少场地条件对于铁塔基础的限制,同时降低铁塔基础对周边的影响和破坏。Among them, the tower foot connection structure 4 on the tower foot connection beam 3 is used to connect the tower foot of the tower. The tower foot connection structure 4 is usually an anchor bolt, and other existing connection methods can also be used. The number of tower foot connection beams 3 It can be determined according to the number of tower feet. At present, most iron towers have four tower feet, that is, the number of tower foot connecting beams 3 is usually four, and the number of foundation piles 2 of the entire foundation is only one, which is located at the connection of each tower foot. At the middle position of the beam 3, the acting force of each tower foot is transmitted to the foundation pile 2 through the tower foot connecting beam 3, and the foundation pile 2 is stably borne. Since only one foundation pile 2 is set, the limitation of site conditions on the iron tower foundation is reduced, and the influence and damage of the iron tower foundation on the surrounding area are also reduced.

该铁塔单桩联合基础的施工方法,包括如下步骤:The construction method of the single-pile combined foundation of the iron tower includes the following steps:

设计铁塔单桩联合基础;Design the monopile joint foundation of the tower;

按照基桩2的设计开挖基坑,并开挖塔脚连接梁3的沟槽;Excavate the foundation pit according to the design of the foundation pile 2, and excavate the groove of the tower foot connecting beam 3;

绑扎钢筋,设置塔脚连接梁3,完成后按铁塔根开固定预埋地脚螺栓作为塔脚连接结构4,支立模板,浇筑混凝土形成铁塔单桩联合基础。Bind the steel bars, set the tower foot connecting beam 3, and fix the pre-buried anchor bolts according to the tower root as the tower foot connection structure 4, erect the formwork, and pour concrete to form the iron tower single pile joint foundation.

设计时,需要兼顾考虑铁塔和场地条件,基础既要达到铁塔的安装需求,又要与场地条件相适配,场地条件包含周边环境、地质地形等方面因素;开挖基坑和沟槽时,可以采用机械或者人工开挖,由于所需基坑和沟槽相对面积较小,因此可以一定程度上降低工程量。塔脚连接梁3为混凝土或者型钢材料。若塔脚连接梁3采用混凝土,则塔脚连接梁3也要绑扎钢筋,基桩2和塔脚连接梁3的钢筋可以分开绑扎,不过优选方式是基桩2钢筋与塔脚连接梁3钢筋同时绑扎,并保证有效锚固连接,若塔脚连接梁3采用型钢,可以将型钢与基桩2钢筋连接,保证稳定性。支立模板时,模板需要固定牢固,可采取措施保证基桩2和塔脚连接梁3尺寸及钢筋保护层厚度。优选的,模板固定后复核基桩2高程、塔脚连接梁3高程及方向、基础根开、地脚螺栓根开等尺寸,复核无误后浇筑基础混凝土,混凝土应边浇筑边振捣,地脚螺栓周围混凝土浇筑振捣需保证地脚螺栓位置不变,混凝土浇筑完成后再复核基桩 2高程、塔脚连接梁3高程及方向、基础根开、地脚螺栓根开等尺寸,无误后按相应规范进行混凝土养护。When designing, it is necessary to take into account the iron tower and site conditions. The foundation must not only meet the installation requirements of the iron tower, but also be adapted to the site conditions. The site conditions include the surrounding environment, geological topography and other factors; when excavating foundation pits and trenches, Mechanical or manual excavation can be used. Since the relative area of the required foundation pit and trench is relatively small, the amount of engineering can be reduced to a certain extent. The tower foot connecting beam 3 is made of concrete or profiled steel. If the tower foot connecting beam 3 is made of concrete, the tower foot connecting beam 3 should also be bound with steel bars, and the steel bars of the foundation pile 2 and the tower foot connecting beam 3 can be bound separately, but the preferred way is that the foundation pile 2 steel bar and the tower foot connecting beam 3 steel bars At the same time, it is bound to ensure the effective anchoring connection. If the connecting beam 3 of the tower foot is made of profiled steel, the profiled steel can be connected to the reinforcement of the foundation pile 2 to ensure stability. When the formwork is erected, the formwork needs to be fixed firmly, and measures can be taken to ensure the size of the foundation pile 2 and the connecting beam 3 at the tower foot and the thickness of the steel protective layer. Preferably, after the formwork is fixed, check the elevation of the foundation pile 2, the elevation and direction of the connecting beam 3 at the tower foot, the foundation root opening, the root opening of the anchor bolts and other dimensions, and pour the foundation concrete after the review is correct. For concrete pouring and vibrating around the bolts, it is necessary to ensure that the position of the anchor bolts remains unchanged. After the concrete is poured, the elevation of foundation pile 2, the elevation and direction of tower foot connecting beam 3, the opening of the foundation, and the opening of the anchor bolts should be checked. Concrete curing according to relevant specifications.

基桩2的稳定性尤为重要,为提高基桩2的稳定性,在本申请的优选实施方式中,所述基桩2的底部设置有基础扩大头1,基础扩大头1可以提高基桩2受力性能,无论是基础的受压、上拔、受弯性能都能提升。基础扩大头1本身可以不配置钢筋,但是需要通过钢筋和混凝土与基桩2浇筑为一体。The stability of the foundation pile 2 is particularly important. In order to improve the stability of the foundation pile 2, in the preferred embodiment of the present application, a foundation enlargement head 1 is provided at the bottom of the foundation pile 2, and the foundation enlargement head 1 can improve the foundation pile 2. The force performance, whether it is the basic compression, pull-up, and bending performance, can be improved. The foundation enlargement head 1 itself may not be equipped with reinforcement, but it needs to be poured together with the foundation pile 2 through reinforcement and concrete.

基础主要受压和受弯,仅在铁塔前后侧均上拔的情况下存在上拔荷载,绝大部分为受压,因此,通常情况下,塔脚连接梁3可以水平设置也可以从基桩2至延伸部倾斜向上设置,同时,所述塔脚连接梁3可连接于基桩2的同一水平高度上,也可以连接于基桩2的不同水平高度上,具体可以根据需求搭配,例如,各个塔脚连接梁3的延伸部根据地形和铁塔需求可以设置为不同的高度,如图1所示,当塔脚连接梁3连接于基桩2的同一水平高度上时,可以通过调整塔脚连接梁3的长度和倾斜角度来调整延伸部的高度,进而调整塔脚连接结构4 的高度和位置以适配塔脚,如图2所示,当塔脚连接梁3为水平设置时,可以通过调整各个塔脚连接梁3的连接高度和长度,来调整塔脚连接结构4的高度和位置以适配塔脚。The foundation is mainly subjected to compression and bending. There is a pull-up load only when the front and rear sides of the tower are pulled up. 2. The extension part is inclined upward, and at the same time, the tower foot connecting beam 3 can be connected to the same level of the foundation pile 2, or can be connected to the different levels of the foundation pile 2, which can be matched according to the needs, for example, The extension of each tower foot connecting beam 3 can be set to different heights according to the terrain and the requirements of the iron tower. As shown in Figure 1, when the tower foot connecting beam 3 is connected to the same level of the foundation pile 2, the tower foot can be adjusted by adjusting the height of the tower foot connecting beam 3. The length and inclination angle of the connecting beam 3 are used to adjust the height of the extension, and then the height and position of the tower foot connecting structure 4 are adjusted to fit the tower foot. As shown in Figure 2, when the tower foot connecting beam 3 is set horizontally, it can be By adjusting the connection height and length of each tower foot connecting beam 3, the height and position of the tower foot connecting structure 4 are adjusted to fit the tower foot.

在设计铁塔单桩联合基础时,在塔脚连接梁3的塔脚连接结构4上加载荷载,根据铁塔各工况计算的上拔力最不利、下压力最不利、水平力最不利情况确定加载荷载的大小和方向,从而保证基础的稳定性。When designing the single-pile combined foundation of the iron tower, load the load on the tower foot connection structure 4 of the tower foot connection beam 3, and determine the load according to the most unfavorable uplift force, the most unfavorable down pressure and the most unfavorable horizontal force calculated under each working condition of the iron tower. The magnitude and direction of the load to ensure the stability of the foundation.

如图3所示,某110kV直线塔同一工况下四个塔腿作用力如下:As shown in Figure 3, the acting forces of the four tower legs of a 110kV linear tower under the same working condition are as follows:

腿号Leg number 竖向力(kN)Vertical force (kN) X向水平力(kN)X-direction horizontal force (kN) Y向水平力(kN)Y-direction horizontal force (kN) AA -111.84-111.84 4.34.3 -13.66-13.66 BB 330.26330.26 -31.09-31.09 -31.57-31.57 CC 61.3261.32 -7.8-7.8 -9.71-9.71 DD -387.56-387.56 -35.04-35.04 -35.65 -35.65

上表荷载为最大上拔和最大下压荷载工况对应各塔腿上的基础作用力,竖向力负值表示下压,正值表示上拔。将上表中ABCD四个荷载加载图3中相应塔腿上,计算出桩基受力和横梁受力,然后根据桩基础规范和混凝土规范计算计算桩基2和塔脚连接梁3规格,包括截面尺寸和钢筋数量等,最终确定出桩基2直径为1.2m,钢筋采用26根22mm,塔脚连接梁3尺寸规格为根部高0.9m,宽0.6m,上下平面各6根28mm钢筋。The loads in the table above are the maximum uplift and maximum downforce load conditions corresponding to the foundation forces on each tower leg. The negative value of the vertical force indicates the downforce, and the positive value indicates the uplift. Load the four loads ABCD in the above table on the corresponding tower legs in Figure 3, calculate the pile foundation force and the beam force, and then calculate the pile foundation 2 and the tower foot connecting beam 3 specifications according to the pile foundation specification and concrete specification, including Section size and the number of steel bars, etc., the diameter of the pile foundation 2 is 1.2m, 26 steel bars of 22mm are used, the size of the connecting beam 3 of the tower foot is 0.9m high and 0.6m wide at the root, and there are 6 steel bars of 28mm on the upper and lower planes.

为了保证连接横梁受力后不因向下挠曲影响塔脚高度,在设计铁塔单桩联合基础时,根据年平均气温条件计算最大基础作用力,以此最大基础作用力计算塔脚连接梁3挠度,将计算出的塔脚连接梁3挠度作为设计塔脚连接梁3的预抬值。通过设计的塔脚连接梁3的预抬值,可以确保塔脚连接梁3在承受荷载后,处于准确高度位置,保证塔脚高度位置准确。In order to ensure that the height of the tower foot will not be affected by the downward deflection of the connecting beam after being stressed, when designing the combined foundation of the single pile of the iron tower, the maximum foundation force is calculated according to the annual average temperature condition, and the connection beam 3 at the tower foot is calculated based on the maximum foundation force. Deflection, take the calculated deflection of the connecting beam 3 at the tower foot as the pre-lift value of the connecting beam 3 at the tower foot. Through the designed pre-lift value of the tower foot connecting beam 3, it can be ensured that the tower foot connecting beam 3 is in an accurate height position after bearing the load, and the height position of the tower foot is accurate.

同样以图3所示的110kV直线塔为例,计算挠度的工况条件为风速5m/s,导地线不覆冰,年平均气温为5℃,此塔年平均温下作用力为:Also taking the 110kV linear tower shown in Figure 3 as an example, the working conditions for calculating the deflection are that the wind speed is 5m/s, the ground wire is not covered with ice, and the annual average temperature is 5℃. The force at the annual average temperature of this tower is:

腿号Leg number 竖向力(kN)Vertical force (kN) X向水平力(kN)X-direction horizontal force (kN) Y向水平力(kN)Y-direction horizontal force (kN) AA -3.91-3.91 0.150.15 -0.48-0.48 BB 11.5611.56 -1.09-1.09 -1.11-1.11 CC 2.152.15 -0.27-0.27 -0.34-0.34 DD -13.56-13.56 -1.23-1.23 -1.25 -1.25

最终计算出塔脚连接梁3的预抬值为8mm,在直线塔中,因风荷载计算方向不同,各塔腿均会出现相同的最大荷载,因此各个塔脚连接梁3的预抬值相同。Finally, the pre-lift value of the connecting beam 3 at the tower foot is calculated to be 8 mm. In a straight tower, due to the different calculation directions of the wind load, each tower leg will have the same maximum load, so the pre-lift value of the connecting beam 3 at the tower foot is the same. .

塔脚连接结构4通常为地脚螺栓,地脚螺栓需要一定的锚固长度,从而保证受力性能,为了避免因地脚螺栓锚固长度而引起塔脚连接梁3高度增加,所述地脚螺栓底部连接有锚板,所述锚板位于塔脚连接梁3的钢筋下方,通过锚板承受地脚螺栓的上拔力。The tower foot connection structure 4 is usually an anchor bolt, and the anchor bolt needs a certain anchoring length to ensure the mechanical performance. An anchor plate is connected, and the anchor plate is located below the steel bar of the connecting beam 3 at the tower foot, and the anchor plate bears the pulling force of the anchor bolt.

Claims (10)

1.铁塔单桩联合基础,其特征在于,包括一根基桩(2)和多根塔脚连接梁(3),所述基桩(2)位于多根塔脚连接梁(3)的中间,各所述塔脚连接梁(3)一端均与基桩(2)相连接、另一端向外发散延伸形成延伸部,所述延伸部设置有用于连接铁塔腿的塔脚连接结构(4)。1. an iron tower monopile combined foundation, is characterized in that, comprises a foundation pile (2) and a plurality of tower foot connecting beams (3), and the described foundation pile (2) is located in the middle of a plurality of tower foot connecting beams (3), One end of each of the tower foot connecting beams (3) is connected with the foundation pile (2), and the other end diverges and extends outward to form an extension portion, and the extension portion is provided with a tower foot connection structure (4) for connecting the tower legs. 2.如权利要求1所述的铁塔单桩联合基础,其特征在于:所述基桩(2)的底部设置有基础扩大头(1)。2. The iron tower monopile combined foundation according to claim 1, characterized in that: the bottom of the foundation pile (2) is provided with a foundation enlargement head (1). 3.如权利要求1所述的铁塔单桩联合基础,其特征在于:所述塔脚连接梁(3)水平设置或者从基桩(2)至延伸部倾斜向上设置。3. The iron tower monopile combined foundation according to claim 1, wherein the tower foot connecting beam (3) is arranged horizontally or inclined upward from the foundation pile (2) to the extension portion. 4.如权利要求1-3任一项所述的铁塔单桩联合基础,其特征在于:各所述塔脚连接梁(3)连接于基桩(2)的同一水平高度上。4. The iron tower monopile combined foundation according to any one of claims 1-3, characterized in that: each of the tower foot connecting beams (3) is connected to the same level of the foundation piles (2). 5.如权利要求1-4任一项所述的铁塔单桩联合基础,其特征在于:各所述塔脚连接梁(3)连接于基桩(2)的不同水平高度上。5. The iron tower monopile combined foundation according to any one of claims 1-4, characterized in that: each of the tower foot connecting beams (3) is connected to the foundation piles (2) at different levels. 6.如权利要求1所述的铁塔单桩联合基础,其特征在于:所述塔脚连接结构(4)为地脚螺栓,所述地脚螺栓底部连接有锚板,所述锚板位于塔脚连接梁(3)的钢筋下方。6 . The combined foundation of iron tower monopiles according to claim 1 , wherein the tower foot connection structure (4) is an anchor bolt, and the bottom of the anchor bolt is connected with an anchor plate, and the anchor plate is located in the tower. 7 . The feet are connected below the reinforcing bars of the beam (3). 7.如权利要求1所述的铁塔单桩联合基础,其特征在于:所述塔脚连接梁(3)为混凝土或者型钢材料。7. The iron tower monopile combined foundation according to claim 1, wherein the tower foot connecting beam (3) is made of concrete or profiled steel. 8.如权利要求1-7任一项所述的铁塔单桩联合基础的施工方法,其特征在于,包括如下步骤:8. the construction method of the iron tower monopile combined foundation as described in any one of claim 1-7, is characterized in that, comprises the steps: 设计铁塔单桩联合基础;Design the monopile joint foundation of the tower; 按照基桩(2)的设计开挖基坑,并开挖塔脚连接梁(3)的沟槽;Excavate the foundation pit according to the design of the foundation pile (2), and excavate the groove of the connecting beam (3) at the foot of the tower; 绑扎钢筋,设置塔脚连接梁(3),完成后按铁塔根开固定预埋地脚螺栓作为塔脚连接结构(4),支立模板,浇筑混凝土形成铁塔单桩联合基础。Bind the steel bars, set the tower foot connecting beam (3), and after completion, press the iron tower to open and fix the pre-buried anchor bolts as the tower foot connection structure (4), erect the formwork, and pour concrete to form the iron tower single pile joint foundation. 9.如权利要求8所述的施工方法,其特征在于,在设计铁塔单桩联合基础时,在塔脚连接梁(3)的塔脚连接结构(4)上加载荷载,根据铁塔各工况计算的上拔力最不利、下压力最不利、水平力最不利情况确定加载荷载的大小和方向,计算出桩基(2)和塔脚连接梁(3)受力,然后根据桩基础规范和混凝土规范计算桩基(2)和塔脚连接梁(3)规格。9. The construction method according to claim 8, characterized in that, when designing an iron tower monopile combined foundation, a load is loaded on the tower foot connection structure (4) of the tower foot connection beam (3), according to each working condition of the iron tower The calculated uplift force is the most unfavorable, the downward pressure is the most unfavorable, and the horizontal force is the most unfavorable situation. Determine the magnitude and direction of the loading load, calculate the force of the pile foundation (2) and the connecting beam (3) at the tower foot, and then according to the pile foundation specification and The concrete specification calculates the specification of the pile foundation (2) and the connecting beam (3) at the tower foot. 10.如权利要求8或9所述的施工方法,其特征在于,在设计铁塔单桩联合基础时,根据年平均气温条件计算基础作用力,以基础作用力计算塔脚连接梁(3)挠度,将计算出的塔脚连接梁(3)挠度作为设计塔脚连接梁(3)的预抬值。10. The construction method according to claim 8 or 9, characterized in that, when designing the combined foundation of the iron tower single pile, the foundation force is calculated according to the annual average temperature condition, and the deflection of the connecting beam (3) at the foot of the tower is calculated with the foundation force. , and take the calculated deflection of the connecting beam (3) at the tower foot as the pre-lift value of the connecting beam (3) at the designed tower foot.
CN202210332625.2A 2022-03-31 2022-03-31 Iron tower single-pile combined foundation and construction method thereof Pending CN114525806A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210332625.2A CN114525806A (en) 2022-03-31 2022-03-31 Iron tower single-pile combined foundation and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210332625.2A CN114525806A (en) 2022-03-31 2022-03-31 Iron tower single-pile combined foundation and construction method thereof

Publications (1)

Publication Number Publication Date
CN114525806A true CN114525806A (en) 2022-05-24

Family

ID=81627326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210332625.2A Pending CN114525806A (en) 2022-03-31 2022-03-31 Iron tower single-pile combined foundation and construction method thereof

Country Status (1)

Country Link
CN (1) CN114525806A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117266224A (en) * 2023-10-16 2023-12-22 中工国际工程股份有限公司 A construction method and structure for transmission line tower foundation in coastal beach areas

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0828096A (en) * 1994-07-13 1996-01-30 Yua Tec:Kk Method and device for assembling steel tower on the ground
FR2845705A1 (en) * 2002-10-15 2004-04-16 Ineo Reseaux Haute Tension Pylon foundation reinforcing procedure uses concrete blocks connected to outside plate anchors by tensioned cables
CN201605594U (en) * 2010-03-09 2010-10-13 王蓉 Self-balancing cross base of iron tower for power transmission line
CN102425188A (en) * 2011-09-07 2012-04-25 中国电力科学研究院 A height-adjustable pole tower foundation and its adjustment method
CN202247935U (en) * 2011-09-20 2012-05-30 中国电力工程顾问集团西南电力设计院 +/- 800 KV extra-high voltage direct-current large-span cast-in-place pile foundation
CN203411988U (en) * 2013-07-03 2014-01-29 国家电网公司 Independent medium-sized pile foundation
CN104499501A (en) * 2014-12-08 2015-04-08 国家电网公司 Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line
CN205134352U (en) * 2015-10-29 2016-04-06 国网浙江省电力公司绍兴供电公司 Bored pile basis is united to only post of narrow ji ta
CN205777813U (en) * 2016-07-11 2016-12-07 四川电力设计咨询有限责任公司 Be suitable to the electric power pylon of mountain terrain
CN106480899A (en) * 2016-09-12 2017-03-08 安徽华电工程咨询设计有限公司 A kind of full landform self-balancing column foot attachment structure
CN106522260A (en) * 2016-12-29 2017-03-22 西安建筑科技大学 Iron tower foundation for frozen soil foundation
JP2018021322A (en) * 2016-08-02 2018-02-08 東京電力ホールディングス株式会社 Pile foundation and tower reconstruction method
CN207277393U (en) * 2017-09-12 2018-04-27 广东电网有限责任公司湛江供电局 A kind of novel reinforced structure on transmission line of electricity rigidity ladder basis
CN207775920U (en) * 2017-12-21 2018-08-28 贵州电力设计研究院 A kind of mountain area electric power pylon strengthening of foundation device
CN109594579A (en) * 2018-02-11 2019-04-09 乌鲁木齐智源易通智能科技有限公司 Transmission line tower foundation and its reinforcement means
CN208830341U (en) * 2018-09-11 2019-05-07 中原豫安建设工程有限公司 A kind of electric power pylon foundation reinforcing structure
CN111851725A (en) * 2020-06-17 2020-10-30 浙江耀厦控股集团有限公司 Sequential construction method of super-long stiff suspension multilayer structure
CN212358363U (en) * 2019-12-30 2021-01-15 广州珠江建设发展有限公司 Suspended tower crane foundation
CN113373996A (en) * 2021-07-21 2021-09-10 徐州中国矿大岩土工程新技术发展有限公司 Uneven settlement adjusting device for iron tower column base and underpinning and lifting construction method
CN115928785A (en) * 2022-12-20 2023-04-07 重庆大学 Wind power ladder-type prefabricated foundation suitable for mountainous areas and its assembling method

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0828096A (en) * 1994-07-13 1996-01-30 Yua Tec:Kk Method and device for assembling steel tower on the ground
FR2845705A1 (en) * 2002-10-15 2004-04-16 Ineo Reseaux Haute Tension Pylon foundation reinforcing procedure uses concrete blocks connected to outside plate anchors by tensioned cables
CN201605594U (en) * 2010-03-09 2010-10-13 王蓉 Self-balancing cross base of iron tower for power transmission line
CN102425188A (en) * 2011-09-07 2012-04-25 中国电力科学研究院 A height-adjustable pole tower foundation and its adjustment method
CN202247935U (en) * 2011-09-20 2012-05-30 中国电力工程顾问集团西南电力设计院 +/- 800 KV extra-high voltage direct-current large-span cast-in-place pile foundation
CN203411988U (en) * 2013-07-03 2014-01-29 国家电网公司 Independent medium-sized pile foundation
CN104499501A (en) * 2014-12-08 2015-04-08 国家电网公司 Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line
CN205134352U (en) * 2015-10-29 2016-04-06 国网浙江省电力公司绍兴供电公司 Bored pile basis is united to only post of narrow ji ta
CN205777813U (en) * 2016-07-11 2016-12-07 四川电力设计咨询有限责任公司 Be suitable to the electric power pylon of mountain terrain
JP6834226B2 (en) * 2016-08-02 2021-02-24 東京電力ホールディングス株式会社 Pile foundation and tower rebuilding method
JP2018021322A (en) * 2016-08-02 2018-02-08 東京電力ホールディングス株式会社 Pile foundation and tower reconstruction method
CN106480899A (en) * 2016-09-12 2017-03-08 安徽华电工程咨询设计有限公司 A kind of full landform self-balancing column foot attachment structure
CN106522260A (en) * 2016-12-29 2017-03-22 西安建筑科技大学 Iron tower foundation for frozen soil foundation
CN207277393U (en) * 2017-09-12 2018-04-27 广东电网有限责任公司湛江供电局 A kind of novel reinforced structure on transmission line of electricity rigidity ladder basis
CN207775920U (en) * 2017-12-21 2018-08-28 贵州电力设计研究院 A kind of mountain area electric power pylon strengthening of foundation device
CN109594579A (en) * 2018-02-11 2019-04-09 乌鲁木齐智源易通智能科技有限公司 Transmission line tower foundation and its reinforcement means
CN208830341U (en) * 2018-09-11 2019-05-07 中原豫安建设工程有限公司 A kind of electric power pylon foundation reinforcing structure
CN212358363U (en) * 2019-12-30 2021-01-15 广州珠江建设发展有限公司 Suspended tower crane foundation
CN111851725A (en) * 2020-06-17 2020-10-30 浙江耀厦控股集团有限公司 Sequential construction method of super-long stiff suspension multilayer structure
CN113373996A (en) * 2021-07-21 2021-09-10 徐州中国矿大岩土工程新技术发展有限公司 Uneven settlement adjusting device for iron tower column base and underpinning and lifting construction method
CN115928785A (en) * 2022-12-20 2023-04-07 重庆大学 Wind power ladder-type prefabricated foundation suitable for mountainous areas and its assembling method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙树礼: "高速铁路桥梁设计与实践 第二版", 31 December 2021, 中国铁道出版社, pages: 691 *
孙珍茂;赵庆斌;: "陡峻山区输电铁塔与基础连接形式设计研究", 四川电力技术, no. 02, pages 63 - 66 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117266224A (en) * 2023-10-16 2023-12-22 中工国际工程股份有限公司 A construction method and structure for transmission line tower foundation in coastal beach areas

Similar Documents

Publication Publication Date Title
CN104532868B (en) High abrupt change shape sloped region bridge anchor pull-type high cap pile group basis construction method
CN110206038A (en) Supporting construction and construction method at a kind of concave foundation pit external corner
CN111779025A (en) In-situ protection structure crossing foundation pit municipal pipe network box culvert and construction method
CN102900095A (en) Transmission tower plate-type single rope foundation structure
CN210288470U (en) High side slope retaining structure of filling
CN114525806A (en) Iron tower single-pile combined foundation and construction method thereof
CN111058463A (en) Rock steep slope high cantilever slope-collecting reinforcing structure and construction method
CN105297763A (en) Assembled type flexible half-excavation foundation for electric transmission lines in mountainous areas
CN203498841U (en) Inclined pile vertical anchor rod supporting structure used for foundation pit supporting
CN205171537U (en) Mountain area transmission line assembled flexibility is partly drawn and is dug basis
CN210395410U (en) Transmission tower pile foundation suitable for mountain area precipitous topography area horizontal stock
CN208167505U (en) It is a kind of to hold the Abutment Reinforcement structure for tilting a miniature clump of piles using end
CN220433745U (en) Structure for resisting floating by supporting piles during construction of cyclone well
CN203498842U (en) Pile beam vertical anchor supporting system used for foundation pit supporting
CN209066472U (en) Mountain area transmission line of electricity tower foundation and transmission line of electricity
CN206408631U (en) Anchored Sheet Pile Wall for Excavation system for closing on existing underground structure
CN208088318U (en) Stake top counterfort wall supporting construction
CN217923719U (en) Combined type keeps off native supporting construction
CN206385549U (en) For soft stratum close to underground structure foundation pit supporting system
CN105442615A (en) Inverted-Y-shaped supporting structure for foundation pit engineering and construction method of inverted-Y-shaped supporting structure
CN216839479U (en) A kind of foundation pit supporting bent frame for weak foundation of hydraulic engineering
CN205502070U (en) A dual -purpose underground gallery structure
CN205839765U (en) A kind of soft soil foundation pit Retaining Structure with Double-row Piles considering soil arch and deformation space effect
CN205062763U (en) Arch dam reinforced structure
CN223434154U (en) Steel platform structure of power transmission tower leg

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220524

RJ01 Rejection of invention patent application after publication