CN114482083A - Anti-slide pile construction method for existing road widening section cutting rock slope - Google Patents

Anti-slide pile construction method for existing road widening section cutting rock slope Download PDF

Info

Publication number
CN114482083A
CN114482083A CN202011151246.0A CN202011151246A CN114482083A CN 114482083 A CN114482083 A CN 114482083A CN 202011151246 A CN202011151246 A CN 202011151246A CN 114482083 A CN114482083 A CN 114482083A
Authority
CN
China
Prior art keywords
slide
pile
piles
numbered
resistant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011151246.0A
Other languages
Chinese (zh)
Other versions
CN114482083B (en
Inventor
刘永松
董俭召
章儒愿
刘波
何政明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202011151246.0A priority Critical patent/CN114482083B/en
Publication of CN114482083A publication Critical patent/CN114482083A/en
Application granted granted Critical
Publication of CN114482083B publication Critical patent/CN114482083B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a cut rock slope slide-resistant pile construction method of an existing road widening section, which is characterized in that slide-resistant piles are numbered sequentially from 1 to N and are divided into odd-numbered slide-resistant piles and even-numbered slide-resistant piles; firstly, excavating odd-number anti-slide piles, drilling rocks around pile holes by using a water mill drilling machine during excavation, and crushing centers by using a blasting mode; after the odd-numbered anti-slide piles are completed, excavating the soil body in front of the piles to the slope bottom, then excavating the underground sections of the even-numbered anti-slide piles, wherein the excavating mode is consistent with that of the odd-numbered anti-slide piles; and finally, pouring the ground sections of the anti-slide piles with even numbers in a mode of erecting the formwork on the ground. The invention adopts jumping pile excavation, and the ground section of the even number piles constructed in the later period adopts a mode of on-ground vertical mold cast-in-place, thereby greatly shortening the construction period and saving the construction cost; the pile hole excavation adopts the mode of combining the water mill drilling machine and the micro-blasting excavation, is not limited by a construction site, and has small influence on the road traffic.

Description

Anti-slide pile construction method for existing road widening section cutting rock slope
Technical Field
The invention belongs to the technical field of road construction, relates to roadbed protection support engineering, and particularly relates to a method for constructing anti-slide piles on existing road widening section cutting rock slopes.
Background
In the existing highway widening project, for cutting rock slope, in order to prevent the slope from collapsing, single-row anti-slide piles are required to be arranged along the slope bottom outside the roadbed widening line.
One of the conventional anti-slide pile construction modes is a manual hole digging and blasting matched mode, the mode is convenient to construct, large equipment is not needed, the requirement on a field is low, the labor intensity is high, the single pile construction speed is low, and the safety of the existing expressway is greatly influenced; the other type is a mechanical hole digging construction mode, a rotary drilling rig is usually adopted, the construction is fast, the labor intensity is low, the influence on the existing expressway is small, the requirement on the field is high, the use of large equipment is limited, and the method is not suitable for the construction of the anti-slide pile of the cut rock slope of the widening section of the existing expressway.
Disclosure of Invention
The invention aims to provide a construction method of the slide-resistant pile suitable for the existing road widening section cutting rock slope, which aims at the limitation of slide-resistant pile construction in the prior art, reduces the influence of construction on the existing road traffic, improves the construction efficiency and shortens the construction period.
The technical scheme of the invention is as follows:
a cut rock slope slide-resistant pile construction method for an existing road widening section is characterized by comprising the following steps:
(1) before the anti-slide pile construction, excavating the corresponding section of cutting to the elevation of the anti-slide pile top, completing the corresponding upper slope protection and drainage engineering construction, and ensuring the stability of the upper slope;
(2) pile position measurement lofting is carried out, the position of the slide-resistant pile is determined, the slide-resistant piles are sequentially numbered from 1 to N, and the slide-resistant pile is divided into an odd-numbered slide-resistant pile and an even-numbered slide-resistant pile;
(3) excavating odd-number anti-slide piles: firstly, drilling peripheral rocks of a pile hole by using a water mill drilling machine, separating the central rocks of the pile hole from the peripheral rocks, simultaneously forming a free face for blasting excavation, punching the central rocks of the pile hole to be used as blast holes, installing explosives for blasting, and ventilating and discharging slag after blasting is finished; repeating the working procedures until the pile hole is excavated to the designed elevation of the pile bottom; after the pore-forming quality is detected to be qualified, installing odd-number slide-resistant pile reinforcement cages and pouring odd-number slide-resistant pile concrete;
(4) after the odd-number anti-slide piles are detected to be completely qualified and the concrete strength reaches 100% of the designed strength, excavating the inter-pile and pre-pile soil bodies of the finished odd-number anti-slide piles to the slope bottom;
(5) after the soil body is excavated, excavating underground sections of even-numbered anti-slide piles, wherein the excavation mode is consistent with that of odd-numbered anti-slide piles; after the pore-forming quality is detected to be qualified, installing an underground section reinforcement cage of the even-numbered anti-slide pile, reserving a lengthening part, and pouring underground section concrete of the even-numbered anti-slide pile;
(6) and installing the upper section reinforcement cage of the even-numbered anti-slide pile, installing a template, and pouring the upper section concrete of the even-numbered anti-slide pile to complete the construction of all anti-slide piles.
The invention adopts jumping pile excavation on the construction process, wherein odd piles are excavated firstly, and even piles are excavated later. The self-stability capability of the rock slope and the resisting effect of the odd piles constructed in the early stage on the slope are fully utilized, soil bodies between piles and in front of the piles are excavated after the odd piles are excavated, the ground sections of the even piles constructed in the later stage are adjusted to be in-situ cast by the ground vertical formwork, the construction period is greatly shortened, and the construction cost is saved.
According to the invention, a mode of combining a water mill drilling machine and micro-blasting excavation is adopted during pile hole excavation, the rocks around the pile hole are drilled by the water mill drilling machine, the original rocks outside the pile hole are not damaged, the rocks around the pile are in a stable state, and the pile hole can be ensured not to collapse without constructing a retaining wall; the water mill drilling machine belongs to small-sized equipment and is not limited by a construction site; the blasting function is to break the middle rock for slag tapping, so the number of blastholes and the explosive amount are only one third of the total blasting scheme, the blasting noise is small, the scattered objects are easy to control, and the influence on the existing expressway is small.
Drawings
FIG. 1 is a flow chart of the construction of the present invention;
FIG. 2 is a schematic diagram of a pile top cutting slope excavation structure;
fig. 3 is a schematic view of the arrangement of slide resistant piles;
FIG. 4 is a schematic diagram of excavation construction of odd-numbered slide-resistant piles;
FIG. 5 is a schematic diagram of a state that a water mill drills to drill a core of rock around a pile hole;
FIG. 6 is a schematic view of the shot hole distribution on a core;
FIG. 7 is a schematic view of the structure of the excavation of the soil body in front of the pile;
FIG. 8 is a schematic view of a construction structure of a lower section of an even-numbered slide-resistant pile;
fig. 9 is a schematic construction structure of an upper section of an even-numbered slide-resistant pile.
Detailed Description
The construction process of the invention is shown in figure 1, and the concrete construction process is as follows:
(1) as shown in fig. 2, before the anti-slide pile 1 is constructed, the cut slope 2 of the corresponding section is excavated to the elevation of the top of the anti-slide pile, so that the corresponding protection and drainage engineering construction of the upper slope is completed, and the stability of the upper slope is ensured;
(2) as shown in fig. 3, pile position measurement lofting is performed, the position of each slide-resistant pile 1 is determined, the slide-resistant piles are numbered sequentially from 1 to N, and the slide-resistant piles are divided into odd-numbered slide-resistant piles 11 and even-numbered slide-resistant piles 12;
(3) as shown in fig. 4, 5 and 6, excavating the odd-numbered slide-resistant piles 11: firstly, drilling peripheral rocks 3 of a pile hole by using a water mill drilling machine, separating the central rocks of the pile hole from the peripheral rocks, simultaneously forming a free face for blasting excavation, then drilling holes on the central rocks of the pile hole to be used as blast holes 4, installing explosives for blasting, and after blasting is finished, discharging slag by using a slag discharging machine; repeating the working procedures until the pile hole is excavated to the designed elevation of the pile bottom; after the pore-forming quality is detected to be qualified, installing odd-number slide-resistant pile reinforcement cages and pouring odd-number slide-resistant pile concrete;
(4) as shown in fig. 7, after all the odd-numbered anti-slide piles are detected to be qualified and the concrete strength reaches 100% of the designed strength, excavating inter-pile and pre-pile soil bodies 5 of the finished odd-numbered anti-slide piles to the slope bottom;
(5) as shown in fig. 8, after the soil body is excavated, excavating the underground sections 121 of the even-numbered anti-slide piles 12 in a manner consistent with that of the odd-numbered anti-slide piles; after the pore-forming quality is detected to be qualified, installing an underground section reinforcement cage of the even-numbered anti-slide pile, reserving a lengthening part, and pouring underground section concrete of the even-numbered anti-slide pile;
(6) as shown in fig. 9, the reinforcement cage of the upper section 122 of the even-numbered slide-resistant pile is installed, the formwork is installed, and the concrete of the upper section of the even-numbered slide-resistant pile is poured to complete the construction of all the slide-resistant piles.
During concrete construction, in order to increase the downward pressure of the water mill drilling machine and accelerate the drilling progress, a fulcrum reaction frame can be erected at a proper position at the top of the water mill drilling machine, and a back pressure fulcrum effect is provided for the drilling machine.
The diameter of a drill hole of the adopted water mill drilling machine is 16cm, and the depth of the drill hole is 70 cm; the blast holes are arranged in a rectangular shape, the distance is 40cm, the depth is 100cm, the diameter is 50mm, and the charge of each blast hole is 100 g.
In order to improve the construction efficiency, the longitudinal length of a construction section can be 10-15 m, and the same procedure of adjacent sections is carried out in a staggered mode, so that the flow process is formed.
Excavating the soil body before the pile section by section from two ends of the construction section to the middle; considering that the lower side slope is rock, the slope rate of the lower side slope is implemented according to the ratio of 1:0, and the excavation amount of the mountain is reduced.

Claims (3)

1. A cut rock slope slide-resistant pile construction method for an existing road widening section is characterized by comprising the following steps:
(1) before the anti-slide pile construction, excavating the corresponding section of cutting to the elevation of the anti-slide pile top, completing the corresponding upper slope protection and drainage engineering construction, and ensuring the stability of the upper slope;
(2) pile position measurement lofting is carried out, the position of the slide-resistant pile is determined, the slide-resistant piles are sequentially numbered from 1 to N, and the slide-resistant pile is divided into an odd-numbered slide-resistant pile and an even-numbered slide-resistant pile;
(3) excavating odd-number anti-slide piles: firstly, drilling peripheral rocks of a pile hole by using a water mill drilling machine, separating the central rocks of the pile hole from the peripheral rocks, simultaneously forming a free face for blasting excavation, punching the central rocks of the pile hole to be used as blast holes, installing explosives for blasting, and ventilating and discharging slag after blasting is finished; repeating the working procedures until the pile hole is excavated to the designed elevation of the pile bottom; after the pore-forming quality is detected to be qualified, installing odd-number slide-resistant pile reinforcement cages and pouring odd-number slide-resistant pile concrete;
(4) after the odd-number anti-slide piles are detected to be completely qualified and the concrete strength reaches 100% of the designed strength, excavating the inter-pile and pre-pile soil bodies of the finished odd-number anti-slide piles to the slope bottom;
(5) after the soil body is excavated, excavating underground sections of even-numbered anti-slide piles, wherein the excavation mode is consistent with that of odd-numbered anti-slide piles; after the pore-forming quality is detected to be qualified, installing an underground section reinforcement cage of the even-numbered anti-slide pile, reserving a lengthening part, and pouring underground section concrete of the even-numbered anti-slide pile;
(6) and installing the upper section reinforcement cage of the even-numbered anti-slide pile, installing a template, and pouring the upper section concrete of the even-numbered anti-slide pile to complete the construction of all anti-slide piles.
2. The existing road widening section cutting rock slope slide-resistant pile construction method according to claim 1, characterized in that: the diameter of a drill hole of the water mill drilling machine is 16cm, and the depth of the drill hole is 70 cm; the blast holes are arranged in a rectangular shape, the distance is 40cm, the depth is 100cm, the diameter is 50mm, and the charge of each blast hole is 100 g.
3. The existing road widening section cutting rock slope slide-resistant pile construction method according to claim 1, characterized in that: excavating the soil body before the pile section by section from two ends of the construction section to the middle; considering that the lower side slope is rock, the slope rate of the lower side slope is implemented according to the ratio of 1:0, and the excavation amount of the mountain is reduced.
CN202011151246.0A 2020-10-25 2020-10-25 Construction method for cutting rock slope slide-resistant pile of existing road widening section Active CN114482083B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011151246.0A CN114482083B (en) 2020-10-25 2020-10-25 Construction method for cutting rock slope slide-resistant pile of existing road widening section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011151246.0A CN114482083B (en) 2020-10-25 2020-10-25 Construction method for cutting rock slope slide-resistant pile of existing road widening section

Publications (2)

Publication Number Publication Date
CN114482083A true CN114482083A (en) 2022-05-13
CN114482083B CN114482083B (en) 2024-04-26

Family

ID=81471317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011151246.0A Active CN114482083B (en) 2020-10-25 2020-10-25 Construction method for cutting rock slope slide-resistant pile of existing road widening section

Country Status (1)

Country Link
CN (1) CN114482083B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0470401A (en) * 1990-07-10 1992-03-05 Kensetsu Kiso Eng Co Ltd Road widening construction
CN205314116U (en) * 2016-01-13 2016-06-15 重庆交通大学 Continuous type of combined type drilling cling compound structure
US20190127941A1 (en) * 2017-10-31 2019-05-02 Earth, Inc. Sheet pile retaining wall system
CN110670605A (en) * 2019-09-16 2020-01-10 中冶交通建设集团有限公司 Mountain road slope reinforcing method
CN110820726A (en) * 2019-11-18 2020-02-21 中国葛洲坝集团路桥工程有限公司 Pile foundation pore-forming method in environment where disturbance is not suitable for surrounding of hard rock in mountainous area
CN211472527U (en) * 2019-11-20 2020-09-11 中铁十二局集团第一工程有限公司 Highway reconstruction and extension engineering high slope construction safety protection structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0470401A (en) * 1990-07-10 1992-03-05 Kensetsu Kiso Eng Co Ltd Road widening construction
CN205314116U (en) * 2016-01-13 2016-06-15 重庆交通大学 Continuous type of combined type drilling cling compound structure
US20190127941A1 (en) * 2017-10-31 2019-05-02 Earth, Inc. Sheet pile retaining wall system
CN110670605A (en) * 2019-09-16 2020-01-10 中冶交通建设集团有限公司 Mountain road slope reinforcing method
CN110820726A (en) * 2019-11-18 2020-02-21 中国葛洲坝集团路桥工程有限公司 Pile foundation pore-forming method in environment where disturbance is not suitable for surrounding of hard rock in mountainous area
CN211472527U (en) * 2019-11-20 2020-09-11 中铁十二局集团第一工程有限公司 Highway reconstruction and extension engineering high slope construction safety protection structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林同立: "改扩建高速公路路堑边坡拓宽方案对比分析", 《矿冶工程》, vol. 34, no. 6, pages 18 - 21 *

Also Published As

Publication number Publication date
CN114482083B (en) 2024-04-26

Similar Documents

Publication Publication Date Title
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN109139104B (en) Drainage construction method for tunnel penetrating through clastic rock steep-dip reverse-thrust water-rich fault
CN106930276B (en) The construction method of the deep hole blasting of rotary digging bored concrete pile and conduit rotary digging removing obstacles
CN107905799B (en) Reinforced structure of high-speed rail tunnel bottom water passing karst cave and construction method thereof
CN104153352A (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN102071683A (en) Water drill dug pile construction method
CN104532818A (en) Treatment method for strip mine goaf
CN105649012A (en) Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN110821500B (en) Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum
CN110847929B (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN110863832B (en) Large-section tunnel stability control construction method for penetrating through earth-rock boundary stratum
CN111023930B (en) Tunnel step excavation method
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN105019431B (en) Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method
CN104846811A (en) Construction method of carrier pile of various technical line productions
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN112281897A (en) Construction method of bridge pile foundation
CN114482083B (en) Construction method for cutting rock slope slide-resistant pile of existing road widening section
CN113847029B (en) Surrounding column extraction method for underground mine high and large point column
CN216159751U (en) Anti-slide pile hole digging construction structure
CN113737781B (en) Combined type hole digging pile construction structure and construction method thereof
CN109113054A (en) A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment
CN113006802A (en) Tunnel reverse step excavation construction method suitable for thin overburden stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant