CN114482021B - Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile - Google Patents

Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile Download PDF

Info

Publication number
CN114482021B
CN114482021B CN202111128287.2A CN202111128287A CN114482021B CN 114482021 B CN114482021 B CN 114482021B CN 202111128287 A CN202111128287 A CN 202111128287A CN 114482021 B CN114482021 B CN 114482021B
Authority
CN
China
Prior art keywords
pile
tank
soil
double
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111128287.2A
Other languages
Chinese (zh)
Other versions
CN114482021A (en
Inventor
袁连冲
吉锋
徐桂中
俞骏
沈朝晖
王山
王从友
宋文智
陈先勇
王希晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunshan Zhouzhuang Water Conservancy Water Station
Jiangsu Water Source Co ltd Of East Line Of South To North Water Transfer
Yancheng Institute of Technology
Shanghai Ershiye Construction Co Ltd
Original Assignee
Kunshan Zhouzhuang Water Conservancy Water Station
Jiangsu Water Source Co ltd Of East Line Of South To North Water Transfer
Yancheng Institute of Technology
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunshan Zhouzhuang Water Conservancy Water Station, Jiangsu Water Source Co ltd Of East Line Of South To North Water Transfer, Yancheng Institute of Technology, Shanghai Ershiye Construction Co Ltd filed Critical Kunshan Zhouzhuang Water Conservancy Water Station
Priority to CN202111128287.2A priority Critical patent/CN114482021B/en
Publication of CN114482021A publication Critical patent/CN114482021A/en
Application granted granted Critical
Publication of CN114482021B publication Critical patent/CN114482021B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a method for solidifying the soil at the bottom of a preset reverse frictional resistance combined pile and a formed filling pile, wherein a pile hole of the filling pile is formed in a foundation, a high-strength tank is placed at the bottom of the pile hole, a double-layer gas guide pipe is arranged on the surface of the tank, and the double-layer gas guide pipe extends out of the filling pile along the pile hole; pile body materials are injected into the pile holes to form piles; after the pile body of the filling pile is solidified for a plurality of days, air is injected into the inner structure of the tank through the double-layer air guide pipe, and the outer structure of the tank is vacuumized; after the bored concrete pile is solidified for a period of time, stopping injecting gas into the inner structure of the tank, and stopping vacuumizing the outer structure of the tank, so that soft soil at the bottom of the bored concrete pile is solidified; injecting a fluid gel material into the internal structure of the tank through the inner tube of the gas guide tube until the whole internal structure of the tank is filled; the invention can effectively improve the side friction resistance and pile end bearing force of the pile so as to achieve the purpose of improving the bearing capacity of the pile foundation.

Description

Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile
Technical Field
The invention relates to a method for consolidating soil at the bottom of a preset reverse frictional resistance combined pile and a formed cast-in-place pile, belongs to the technology of adding soft soil foundations, and can be used in the fields of hydraulic engineering, civil engineering and construction engineering and the like.
Background
Pile foundations are currently an important way to increase soft foundations. When the bearing capacity of the pile mainly comes from the bearing load of the pile foundation, the reaction force of the surrounding soil of the pile to the pile foundation comes from the friction force at the pile side and the end bearing force at the pile bottom. Under the general circumstances, pile foundation has the tendency of sinking when bearing the load, and the downward displacement takes place for the soil body around, and compressive strain takes place for the pile body itself, so the soil around the pile can produce ascending side friction to the pile body. The degree of the development of the side friction resistance of a certain depth position of the pile foundation is closely related to the strain of the depth pile foundation, and the larger the strain is, the larger the relative displacement between the depth pile body and the pile surrounding soil is, the more the side friction resistance of the pile surrounding soil is developed, and the larger the bearing capacity of the pile is. However, with a general pile, the strain of the pile gradually decreases along the depth, so that the side friction resistance tends to be exerted to a smaller and smaller extent along the depth, and cannot be fully exerted.
Meanwhile, the soil at the bottom of the pile can generate an upward supporting force, namely an end bearing force, on the pile; the exertion of the end bearing force of the pile end is often related to the weakness degree of the pile end soil, and the lower the water content of the pile end soil is, the harder the pile end soil is, and the larger the pile end bearing force is. Under practical conditions, for soft soil areas, pile end bearing force is smaller due to smaller soil intensity. In addition, for a bored pile, a certain amount of sediment is remained in the lower part of the hole in the process of boring, so that the pile end soil is extremely weak after pile forming, and the exertion of end bearing force is affected. The sum of upward side friction resistance and end bearing force generated by the pile surrounding soil and pile end soil to the pile is the bearing capacity of the pile.
Obviously, improving the side friction resistance and pile end bearing capacity of the pile is an important way for improving the bearing capacity of the pile.
Disclosure of Invention
The invention provides a method for combining preset reverse frictional resistance with pile bottom soil consolidation and a formed cast-in-place pile, which can effectively improve the side frictional resistance and pile end bearing force of the pile so as to achieve the aim of improving the bearing capacity of a pile foundation.
The technical scheme adopted for solving the technical problems is as follows:
the method for consolidating the preset reverse frictional resistance combined pile foundation soil specifically comprises the following steps:
step S1: driving a pile hole of a filling pile in a foundation, and performing hole forming operation;
step S2: placing a high-strength tank on the bottom of a pile hole, mounting a double-layer gas guide pipe on the surface of the tank, and extending the double-layer gas guide pipe out of the filling pile along the pile hole, wherein the tank is of a double-layer structure, the inner structure of the tank is communicated with the inner pipe of the double-layer gas guide pipe, and the outer structure of the tank is communicated with the outer pipe of the double-layer gas guide pipe;
step S3: injecting pile body materials into the pile holes to form piles;
step S4: after the pile body of the filling pile is solidified for a plurality of days, air is injected into the inner structure of the tank through the double-layer air guide pipe, and the outer structure of the tank is vacuumized;
step S5: stopping injecting air into the internal structure of the tank after the soft soil or the sediments at the bottom of the filling pile are solidified for a period of time, and stopping vacuumizing the external structure of the tank, so that the solidification of the soft soil or the sediments at the bottom of the filling pile is finished;
step S6: at this time, the internal structure of the tank is expanded, and a fluid gel material is injected into the internal structure of the tank through the inner tube of the gas guide tube until the whole internal structure of the tank is filled;
as a further preferred aspect of the present invention, the tank includes an inner structure and an outer structure, the outer structure is a permeable layer, the inner structure is an air tank body, and the permeable layer is wrapped outside the air tank body;
as a further preferred aspect of the present invention, the pile body material is concrete or solidified soil;
as a further preferable aspect of the present invention, in step S4, the setting time of the pile body of the cast-in-place pile is 28 days;
as a further preferable mode of the invention, the inner tube of the double-layer air duct is connected with a pneumatic pump, and the outer tube of the double-layer air duct is connected with a vacuum pump;
as a further preferable aspect of the present invention, in the step S5, the bottom soft soil or sediment consolidation time is 10-20 days;
the bored concrete pile formed based on the method for combining the preset reverse frictional resistance with the soil consolidation of the pile bottom comprises a bored concrete pile body, wherein the bottom in the pile body is provided with a tank gas filled with a fluid gel material;
the rest part of the pile body of the cast-in-place pile is filled with concrete or solidified soil.
Through the technical scheme, compared with the prior art, the invention has the following beneficial effects:
1. according to the invention, the tank is arranged at the bottom of the filling pile, after the tank is inflated in the tank, a lifting force can be generated on the bottom of the filling pile, and the surrounding soil of the pile forms upward side friction resistance to the pile, so that the side friction resistance of the bottom of the pile body is improved;
2. the invention is arranged at the bottom of the bored concrete pile and has a two-layer structure, negative pressure is formed in the pile bottom soil of the bored concrete pile when the outer layer is vacuumized, extrusion force is formed on the pile bottom by the inner layer inflation, and under the combined action of positive and negative pressure, the soft soil or sediment of the pile bottom is solidified, so that the strength of the soil body of the pile bottom is improved, and the bearing capacity of the pile body end is improved;
3. after the soft soil at the pile bottom is solidified, the inner structure of the tank is expanded, and the injected high-strength gel material forms an enlarged pile bottom at the pile end, so that the bearing capacity of the filling pile is further improved.
Drawings
The invention will be further described with reference to the drawings and examples.
FIG. 1 is a schematic diagram of a preferred embodiment of the present invention for pore forming and then placing in a high strength tank;
FIG. 2 is a schematic view of a preferred embodiment of the present invention after pile formation of cast-in-place pile material;
FIG. 3 is a schematic illustration of the pressurizing and evacuating through a double-layered airway in accordance with the preferred embodiment of the present invention;
FIG. 4 is a schematic view of the structure of the preferred embodiment of the present invention after filling with a high strength filling material;
fig. 5 is a schematic cross-sectional view of a double-layered airway provided by the present invention.
In the figure: 1 is a filling pile, 2 is a pile hole, 3 is a double-layer air duct, 4 is side friction resistance, 5 is high-strength tank, 6 is a fluidized gel material, 7 is lifting force, 8 is an outer pipe, and 9 is an inner pipe.
Detailed Description
The invention will now be described in further detail with reference to the accompanying drawings. In the description of the present application, it should be understood that the terms "left," "right," "upper," "lower," and the like indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, and are merely for convenience in describing the present invention and simplifying the description, rather than indicating or implying that the apparatus or element being referred to must have a specific orientation, be configured and operated in a specific orientation, and that "first," "second," etc. do not represent the importance of the components and therefore should not be construed as limiting the present invention. The specific dimensions adopted in the present embodiment are only for illustrating the technical solution, and do not limit the protection scope of the present invention.
The pile foundation is taken as an important mode for increasing the soft soil foundation, the bearing capacity of the pile foundation is improved, researches show that the bearing capacity influence factor of the pile foundation mainly comprises two points, the first is the side friction resistance of the pile, the factor influencing the exertion degree of the side friction resistance is mainly the strain of the pile foundation, and the more fully the side friction resistance is exerted, the larger the bearing capacity of the pile is; secondly, the pile end bearing force of the pile is the weakness degree of the pile end soil, and the main factor influencing the exertion of the pile end bearing force is that the greater the strength of the pile end soil is, the greater the end bearing force is.
In order to achieve the purpose of improving the bearing capacity of pile foundation, the application provides a method for solidifying the pile foundation soil by combining preset reverse frictional resistance, which can effectively improve the bearing capacity of a cast-in-place pile 1 and specifically comprises the following steps:
step S1: and driving a cast-in-place pile 1 in the foundation, performing hole forming operation (pipe sinking cast-in-place pile or drilling cast-in-place pile) on the cast-in-place pile, and forming a pile hole 2 in the cast-in-place pile.
Step S2: in fig. 1, a high-strength tank 5 is placed at the bottom of a pile hole, a double-layer gas-guide pipe 3 is installed on the surface of the tank, and the double-layer gas-guide pipe extends out of a filling pile along the pile hole, wherein the tank is of a double-layer structure, the tank is divided into an inner structure and an outer structure for convenience of explanation, the outer structure is a permeable layer, the inner structure is an air tank body, the permeable layer is wrapped outside the tank body, the tank body is communicated with an inner pipe 9 of the double-layer gas-guide pipe, the permeable layer of the tank is communicated with an outer pipe 8 of the double-layer gas-guide pipe (the inner pipe is used for high-pressure gas injection, and the outer pipe is used for vacuum gas extraction); the permeable layer is made of high-strength permeable material, and when the permeable layer is vacuumized, a drainage and air guide channel can be formed.
Step S3: and (3) injecting pile body materials into the pile holes, wherein the pile body materials are concrete or solidified soil, and the pile is formed as shown in fig. 2.
Step S4: after the pile body of the filling pile is solidified for a plurality of days (the hydration reaction time of cement is restricted to be 28 days), the inner pipe of the double-layer air guide pipe is connected with the pneumatic pump, the outer pipe of the double-layer air guide pipe is connected with the vacuum pump, and as shown in fig. 3, air is injected into the inner structure of the tank through the double-layer air guide pipe, and the outer structure of the tank is vacuumized; the air tank body is inflated to expand, so that the pile body has an upward lifting trend, the pile is upwards displaced relative to the soil, the surrounding soil of the pile generates downward side friction force 4 on the pile, and along with the expansion of the air tank body, the lifting force 7 is smaller than the side friction force of the pile, that is, the side friction force of the pile in the application is far greater than that of a traditional pile;
meanwhile, in the vacuumizing process of the permeable layer, vacuum negative pressure is transmitted to the pile bottom through the outer pipe, negative pressure is formed in pile bottom soil, besides, the tank body of air expands to form extrusion force on the pile bottom soil, a consolidation effect is formed on the pile end soil body under the combined action of positive and negative pressure, the strength of the pile bottom soil body is improved, the pile body bearing capacity is improved, water generated in the consolidation effect is discharged out of the pile body through the outer pipe, and the pile end soil body can be effectively reinforced again through negative pressure vacuum.
Step S5: after the soft soil or the sediment at the bottom of the bored concrete pile is solidified for a period of time, determining that the time for solidifying the soft soil or the sediment at the bottom is 10-20 days according to the soil property, stopping injecting gas into the inner structure of the tank, stopping vacuumizing the outer structure of the tank, namely stopping negative pressure solidification and inflation, and ending the solidification of the soft soil or the sediment at the bottom of the bored concrete pile.
Step S6: at this time, the internal structure of the tank is expanded, as shown in fig. 4, a fluidized gel material 6 is injected into the internal structure of the tank through the inner pipe of the gas guide pipe until the whole internal structure of the tank is filled, the solidified material is quickly solidified in a short time to form high-strength solid, and the gas tank is expanded due to solidification of pile bottom soil, so that the volume is larger than the diameter of the pile, and the quick solidification of the solidified material can form an enlarged pile bottom at the pile end, so that the bearing capacity of the pile is effectively improved; the method can also achieve an effect that when the original pile body is drilled, certain residues remain at the bottom of the hole, and the fluidized gel material can avoid the problem of weak soil at the pile end caused by the residues.
Finally, the main description is that the air pressure formed by injecting air into the air tank body through the air pressure pump needs to calculate the side friction resistance of the pile body in advance, and the concrete calculation mode of the side friction resistance needs to be calculated and set according to actual requirements, which is not described herein.
The cast-in-place pile formed according to the method comprises a cast-in-place pile body, wherein the bottom of the pile body is provided with a tank, and the tank is filled with fluid gel materials.
In summary, the pile bearing capacity is finally improved by improving the side friction resistance and the pile end bearing capacity of the pile.
It will be understood by those skilled in the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs. It will be further understood that terms, such as those defined in commonly used dictionaries, should be interpreted as having a meaning that is consistent with their meaning in the context of the prior art and will not be interpreted in an idealized or overly formal sense unless expressly so defined herein.
The meaning of "and/or" as referred to in this application means that each exists alone or both.
As used herein, "connected" means either a direct connection between elements or an indirect connection between elements via other elements.
With the above-described preferred embodiments according to the present invention as an illustration, the above-described descriptions can be used by persons skilled in the relevant art to make various changes and modifications without departing from the scope of the technical idea of the present invention. The technical scope of the present invention is not limited to the description, but must be determined according to the scope of claims.

Claims (6)

1. A method for solidifying the soil at the bottom of a preset reverse frictional resistance combined pile is characterized by comprising the following steps: the method specifically comprises the following steps: step S1: piling pile holes (2) of a filling pile (1) in a foundation, and performing hole forming operation;
step S2: placing a high-strength tank (5) at the bottom of a pile hole (2), mounting a double-layer air duct (3) on the surface of the tank, and extending the double-layer air duct (3) out of the filling pile (1) along the pile hole (2), wherein the tank is of a double-layer structure, the inner structure of the tank is communicated with an inner pipe (9) of the double-layer air duct (3), and the outer structure of the tank is communicated with an outer pipe (8) of the double-layer air duct (3);
step S3: injecting pile body materials into the pile holes (2) to form piles;
step S4: after the pile body of the filling pile (1) is solidified for a plurality of days, gas is injected into the inner structure of the tank through the double-layer gas guide pipe (3), and the outer structure of the tank is vacuumized;
step S5: stopping injecting air into the internal structure of the tank after the soft soil or the sediment at the bottom of the bored pile (1) is solidified for a period of time, and stopping vacuumizing the external structure of the tank, wherein the solidification of the soft soil or the sediment at the bottom of the bored pile (1) is finished;
step S6: at the moment, the inner structure of the tank is expanded, and a fluid gel material (6) is injected into the inner structure of the tank through an inner tube (9) of the gas guide tube until the whole inner structure of the tank is filled;
the tank comprises an inner structure and an outer structure, the outer structure is a permeable layer, the inner structure is an air tank body, and the permeable layer is wrapped outside the air tank body.
2. The method for consolidating pile foundation soil combined with preset reverse frictional resistance as claimed in claim 1, wherein: the pile body material is concrete or solidified soil.
3. The method for consolidating pile foundation soil combined with preset reverse frictional resistance as claimed in claim 1, wherein: in the step S4, the pile body solidification time of the cast-in-place pile (1) is 28 days.
4. The method for consolidating pile foundation soil combined with preset reverse frictional resistance as claimed in claim 1, wherein: the inner tube (9) of the double-layer air duct (3) is connected with a pneumatic pump, and the outer tube (8) of the double-layer air duct (3) is connected with a vacuum pump.
5. The method for consolidating pile foundation soil combined with preset reverse frictional resistance as claimed in claim 1, wherein: in the step S5, the consolidation time of soft soil or sediment at the bottom of the bored concrete pile (1) is 10-20 days.
6. Cast-in-place pile (1) formed on the basis of a method for consolidation of a preset reverse frictional resistance combined pile foundation soil according to any one of claims 1 to 5, characterized in that: comprises a filling pile (1) body, wherein the bottom of the pile body of the filling pile (1) is provided with an tank, and the tank is filled with a fluid gel material (6);
the rest part of the pile body of the filling pile (1) is filled with concrete or solidified soil.
CN202111128287.2A 2021-09-26 2021-09-26 Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile Active CN114482021B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111128287.2A CN114482021B (en) 2021-09-26 2021-09-26 Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111128287.2A CN114482021B (en) 2021-09-26 2021-09-26 Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile

Publications (2)

Publication Number Publication Date
CN114482021A CN114482021A (en) 2022-05-13
CN114482021B true CN114482021B (en) 2023-12-29

Family

ID=81491509

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111128287.2A Active CN114482021B (en) 2021-09-26 2021-09-26 Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile

Country Status (1)

Country Link
CN (1) CN114482021B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115879201B (en) * 2022-12-20 2023-09-05 同济大学 Analysis method for permanent pile casing and sediment solidification and lifting cast-in-place pile bearing capacity

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE9301035D0 (en) * 1993-03-28 1993-03-28 Soilex Ab PROCEDURES TO MAKE PILLOWS
WO1997043488A1 (en) * 1996-05-14 1997-11-20 Guoliang Zhang Method of constructing a pile structure and apparatus thereof
JPH11217827A (en) * 1998-01-30 1999-08-10 East Japan Railway Co Cast-in-place concrete pipe front end preparatory loading device, and execution method of cast-in-place concrete pile
JPH11217825A (en) * 1998-01-30 1999-08-10 East Japan Railway Co Cast-in-place concrete pipe front end preparatory loading device and execution method of cast-in-place concrete pile
JP2001214438A (en) * 2000-02-02 2001-08-07 East Japan Railway Co Method for construction cast-in-place concrete pile, and preload device onto ground under bottom of cast-in- place concrete pile.
JP2005220708A (en) * 2004-02-09 2005-08-18 East Japan Railway Co Tip-preloaded cast-in-place pile construction method, and pile tip preloading device
JP2006138100A (en) * 2004-11-11 2006-06-01 East Japan Railway Co Constructing method for tip-reinforcing cast-in-place pile
JP2017008490A (en) * 2015-06-17 2017-01-12 株式会社竹中工務店 Pile body construction method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10458088B2 (en) * 2017-09-14 2019-10-29 Jordan Alan Soil adaptive smart caisson
CN109469050A (en) * 2018-12-25 2019-03-15 高永光 Grout pile bottom is installed by hollow (hole) doughnut-shaped steel plate capsule (chamber) Post Grouting Technique

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE9301035D0 (en) * 1993-03-28 1993-03-28 Soilex Ab PROCEDURES TO MAKE PILLOWS
WO1997043488A1 (en) * 1996-05-14 1997-11-20 Guoliang Zhang Method of constructing a pile structure and apparatus thereof
JPH11217827A (en) * 1998-01-30 1999-08-10 East Japan Railway Co Cast-in-place concrete pipe front end preparatory loading device, and execution method of cast-in-place concrete pile
JPH11217825A (en) * 1998-01-30 1999-08-10 East Japan Railway Co Cast-in-place concrete pipe front end preparatory loading device and execution method of cast-in-place concrete pile
JP2001214438A (en) * 2000-02-02 2001-08-07 East Japan Railway Co Method for construction cast-in-place concrete pile, and preload device onto ground under bottom of cast-in- place concrete pile.
JP2005220708A (en) * 2004-02-09 2005-08-18 East Japan Railway Co Tip-preloaded cast-in-place pile construction method, and pile tip preloading device
JP2006138100A (en) * 2004-11-11 2006-06-01 East Japan Railway Co Constructing method for tip-reinforcing cast-in-place pile
JP2017008490A (en) * 2015-06-17 2017-01-12 株式会社竹中工務店 Pile body construction method

Also Published As

Publication number Publication date
CN114482021A (en) 2022-05-13

Similar Documents

Publication Publication Date Title
CN103233454B (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
JP5277174B2 (en) Method and apparatus for testing load bearing capacity using a ring cell
CN105908744B (en) Pore pressure counter-force construction method
CN106638552A (en) Permeable pipe pile system capable of accelerating consolidation and construction method thereof
JP5243669B1 (en) Method of tilting structure and improving ground
CN102011399A (en) PHC pile-based multiple high jet pedestal pile construction method
CN114482021B (en) Method for solidifying preset reverse friction combined pile foundation soil and formed cast-in-place pile
CN102808407B (en) Construction method of soft-foundation reinforced concrete cast-in-place pile
CN110700842A (en) Advanced grouting reinforcement method suitable for water-rich sand layer section of shield end
US11525231B2 (en) Double-spiral-tube structure, grouting and pile forming device and construction method for strengthening soft soil
CN114457790B (en) Pile forming device and pile forming method for cast-in-place piles in karst areas
KR101698457B1 (en) Multi pile construction method for strengthening weak soil
CN102134861B (en) Method for testing precast pile in soil body
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN105064332A (en) Construction method for bearing base piles of square pile bodies
US12012715B2 (en) Extensible shells and related methods for constructing a ductile support pier
JP6395238B1 (en) Ground reinforcement method and injection pipe device
CN204898670U (en) Counter -force steel -pipe pile pile pulling device and clear native device are pressed to hole
Bingjian Study of the pore water pressure variation rule in saturated soft soil caused by prestressed concrete pile penetration
CN214614009U (en) Be applied to soft soil foundation reinforced rubber bag formula slip casting compaction stake
CN204475337U (en) A kind of hole pressure counter-force steel pipe pile pile pulling device
CN201010902Y (en) Plastic tube with partially smooth and partially threaded surface used for cast-in-place concrete pile
CN114482057A (en) Control device and method for pile side grouting reinforcement of pipe pile foundation
JP5301059B1 (en) Method of tilting structure and improving ground
CN104294817A (en) Construction method for concrete pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant