Prior art keywords
level
grid
area
boundary
rate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210078020.5A
Other languages
Chinese (zh)
Other versions
CN114445359B (en
Inventor
刘臻
姚云宵
吴咏炜
李杨峰
杨愉存
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Xinguang Data Technology Co ltd
Original Assignee
Shanghai Xinguang Data Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Xinguang Data Technology Co ltd filed Critical Shanghai Xinguang Data Technology Co ltd
Priority to CN202210078020.5A priority Critical patent/CN114445359B/en
Publication of CN114445359A publication Critical patent/CN114445359A/en
Application granted granted Critical
Publication of CN114445359B publication Critical patent/CN114445359B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T7/00Image analysis
    • G06T7/0002Inspection of images, e.g. flaw detection
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/29Geographical information databases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/20Finite element generation, e.g. wire-frame surface description, tesselation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2207/00Indexing scheme for image analysis or image enhancement
    • G06T2207/30Subject of image; Context of image processing
    • G06T2207/30168Image quality inspection
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention discloses a system and a method for controlling the quality of an electronic map in a grid data system, which comprises the following steps: submitting each level grid boundary drawn in the electronic map; automatically performing quality inspection on submitted grid boundaries of all levels, performing validity check on the grid boundaries of a certain level, detecting whether the coverage rate of the grid boundaries of the level is greater than or equal to a corresponding threshold value, whether the overlapping rate is less than or equal to the corresponding threshold value and whether the overflow rate is less than or equal to the corresponding threshold value when the check is passed, if yes, passing the quality inspection, updating the grid boundaries of the level passing the quality inspection to the current version, and otherwise, rejecting to perform border drawing again; summarizing the grid boundaries of all levels passed by all quality tests to obtain the latest current version electronic map; automatically submitting the latest electronic map of the current version when the submission time reaches the set time; checking the latest electronic map of the current version, waiting for release when the checking is passed, and else, refusing to draw the border again; and automatically releasing the latest current version of the electronic map which is effective when the release effective time reaches the set time.

Description

Electronic map quality control system and method in grid data system
Technical Field
The invention relates to the technical field of grid data systems, in particular to a system and a method for controlling the quality of an electronic map in a grid data system.
Background
In the existing conventional administrative management system (province-city-district/county-town-village), an electronic map of a certain version can be submitted to be immediately effective after being drawn and subjected to manual quality inspection, and the drawn electronic map under the conventional administrative management system cannot realize automatic quality inspection and other operations, so that the effective electronic map is inaccurate, and time and labor are consumed for manual quality inspection.
Disclosure of Invention
Aiming at the problems and the defects in the prior art, the invention provides a system and a method for controlling the quality of an electronic map in a grid data system.
The invention solves the technical problems through the following technical scheme:
the invention provides an electronic map quality control system in a grid data system, which is characterized by comprising a boundary submitting module, a quality inspection module, a version summarizing module, a version submitting module, a version auditing module and a version validating module;
the boundary submitting module is used for submitting the grid boundaries of all levels under a grid data system drawn in the electronic map by a user;
the quality inspection module is used for automatically performing quality inspection on the grid boundary of each level below the highest level in the submitted levels, performing validity check on the grid boundary of a certain level based on a boundary validity rule, calculating the coverage rate, the overlapping rate and the overflow rate of the grid boundary of the level when the check is passed, detecting whether the coverage rate of the grid boundary of the level is greater than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, if yes, passing the quality inspection, updating the grid boundary of the level passing the quality inspection to the electronic map of the current version, and if not, sending information that the quality inspection is not passed and rejecting to perform boundary drawing again;
the version summarizing module is used for summarizing the grid boundaries of all levels passed by the quality inspection drawn by all users to obtain the latest current version electronic map;
the version submitting module is used for automatically submitting the latest current version electronic map when the submitting time reaches the set version submitting deadline;
the version auditing module is used for an administrator to audit the latest current version of the electronic map, and when the audit is passed, the version auditing module sends out information that the audit is passed and the release is effective, and when the audit is not passed, the version auditing module sends out information that the audit is not passed and the border drawing is rejected;
the version release module is used for automatically releasing the latest current version electronic map which is effective when the release effective time reaches the set version release effective time.
Preferably, the quality inspection module is configured to calculate a coverage rate of the hierarchical grid boundary: traversing all grid boundaries of the level to obtain a residual uncovered area uncovered by the grid boundary of the level in the grid boundary of the last level corresponding to the level, calculating a gap rate between the area of the residual uncovered area and the area of the grid boundary area of the last level corresponding to the level, and calculating the coverage rate to be 1-gap rate;
the quality inspection module is used for calculating the overlapping rate of the grid boundary of the level: traversing the pairwise combination of all grid boundaries of the level to obtain all intersection regions corresponding to the pairwise combination, taking a union set of all the intersection regions to obtain an overlapping region, and calculating the overlapping rate, namely the area of the overlapping region of the level/the area of the grid boundary region of the last level corresponding to the level;
the quality inspection module is used for calculating the overflow rate of the grid boundary of the level: traversing all grid boundaries of the level to obtain all boundary boundaries of the grid boundary of the level overflowing the grid boundary of the previous level corresponding to the level, taking and collecting the areas formed by all the boundary boundaries to obtain an overflow area, and calculating the overflow rate which is the area of the overflow area of the level/the area of the grid boundary area of the previous level corresponding to the level.
The invention also provides a method for controlling the quality of the electronic map in the grid data system, which is characterized by comprising the following steps:
s1, submitting the grid boundaries of each hierarchy under the grid data system drawn in the electronic map by a user;
s2, automatically performing quality inspection on the grid boundary of each level below the highest level in the submitted levels, performing validity inspection on the grid boundary of the level based on a boundary validity rule aiming at the grid boundary of a certain level, calculating the coverage rate, the overlapping rate and the overflow rate of the grid boundary of the level when the verification is passed, detecting whether the coverage rate of the grid boundary of the level is more than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, if yes, passing the quality inspection, updating the grid boundary of the level passing the quality inspection to the electronic map of the current version, and if not, sending information that the quality inspection is not passed and refusing to perform boundary drawing again;
s3, summarizing the grid boundaries of each level passed by the quality inspection drawn by each user to obtain the latest current version electronic map;
s4, automatically submitting the latest electronic map of the current version when the submission time reaches the set version submission deadline;
s5, the manager audits the electronic map of the latest current version, sends information that the audit is passed and the issuance is effective when the audit is passed, and sends information that the audit is not passed and the boundary drawing is carried out again when the audit is not passed;
and S6, automatically releasing and validating the latest current version electronic map when the release validation time reaches the set version release validation time.
Preferably, in step S2, the coverage of the hierarchical grid boundary is calculated: traversing all grid boundaries of the level to obtain a residual uncovered area uncovered by the grid boundary of the level in the grid boundary of the last level corresponding to the level, calculating a gap rate between the area of the residual uncovered area and the area of the grid boundary area of the last level corresponding to the level, and calculating the coverage rate to be 1-gap rate;
calculating the overlapping rate of the boundary of the hierarchical grid: traversing the pairwise combination of all grid boundaries of the level to obtain all intersection areas corresponding to the pairwise combination, taking a union set of all the intersection areas to obtain an overlapping area, and calculating the overlapping rate which is the area of the overlapping area of the level/the area of the grid boundary area of the previous level corresponding to the level;
calculating the overflow rate of the boundary of the hierarchical grid: and traversing all the grid boundaries of the level to obtain all the out-bound boundaries of the grid boundaries of the level overflowing the grid boundaries of the previous level corresponding to the level, taking a union set of the areas formed by all the out-bound boundaries to obtain an overflow area, and calculating the overflow rate which is the area of the overflow area of the level/the area of the grid boundary area of the previous level corresponding to the level.
On the basis of the common knowledge in the field, the above preferred conditions can be combined randomly to obtain the preferred embodiments of the invention.
The positive progress effects of the invention are as follows:
the invention obtains the latest current version electronic map through boundary submission, automatic boundary quality inspection, automatic version summarization, automatic version submission, version verification and automatic version validation operation of the grid boundary under the drawn grid data system, and the latest current version electronic map is generated accurately, and is time-saving and labor-saving.
Drawings
Fig. 1 is a schematic structural diagram of an electronic map quality control system in a mesh data system according to a preferred embodiment of the invention.
FIG. 2 is a flowchart illustrating a method for controlling quality of an electronic map in a grid data system according to a preferred embodiment of the present invention.
FIG. 3 is a schematic diagram of the intersection regions S1, S2 and S3 in accordance with the preferred embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention.
As shown in fig. 1, the present embodiment provides an electronic map quality control system in a grid data system, which includes a boundary submitting module 1, a quality inspection module 2, a version summarizing module 3, a version submitting module 4, a version auditing module 5, and a version validating module 6.
The boundary submitting module 1 is used for submitting the grid boundaries of each level under a grid data system drawn in the electronic map by a user.
The grid data system is a space system, is an extension of a conventional administrative system (province-city-district/county-town-village), and supports adding, canceling or modifying the hierarchy and creating corresponding boundaries on the basis of the administrative hierarchy.
For example: the hierarchy under the grid data system is two hierarchies, namely a region A and a part A1, A2, A3 and A4 below the region A, and a region B and a part B1, B2, B3 and B4 below the region B. The user 1 draws the polygonal grid boundaries of the A1 town, the A2 town, the A3 town and the A4 town under the A area in the electronic map, and clicks a submit button to submit after drawing; the user 2 draws the polygonal grid boundaries of the B1 town, the B2 town, the B3 town and the B4 town under the B region in the electronic map, and clicks the submit button to submit after drawing.
The quality inspection module 2 is used for automatically performing quality inspection on the grid boundary of each level below the highest level in the submitted levels, performing validity check on the grid boundary of a certain level based on a boundary validity rule, calculating the coverage rate, the overlapping rate and the overflow rate of the grid boundary of the level when the check is passed, detecting whether the coverage rate of the grid boundary of the level is greater than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, if yes, passing the quality inspection, updating the grid boundary of the level passing the quality inspection to the electronic map of the current version, and if not, sending information that the quality inspection is not passed and rejecting to perform boundary drawing again.
For example: automatically performing quality inspection on the submitted town level grid boundary, performing validity check on the town level grid boundary (A1 town, A2 town, A3 town and A4 town) based on the boundary validity rule, calculating the coverage rate, the overlapping rate and the overflow rate of the town level grid boundary when the verification is passed, detecting whether the coverage rate of the town level grid boundary is more than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, when the coverage rate of the grid boundary (A1 town, A2 town, A3 town and A4 town) of the town level is more than or equal to the corresponding coverage rate threshold value, the coverage rate is less than or equal to the corresponding overlap rate threshold value, and the overflow rate is less than or equal to the corresponding overflow rate threshold value, the quality detection is passed, and updating the grid boundaries (A1 town, A2 town, A3 town and A4 town) of the town level passed by the quality inspection to the electronic map of the current version.
Legality checking is performed on the mesh boundaries (B1 town, B2 town, B3 town and B4 town) of the town level based on a boundary legality rule aiming at the mesh boundaries of the town level, calculating the coverage rate, the overlapping rate and the overflow rate of the town level grid boundary when the verification is passed, detecting whether the coverage rate of the town level grid boundary is more than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, when the coverage rate of the grid boundary (B1 town, B2 town, B3 town and B4 town) of the town level is more than or equal to the corresponding coverage rate threshold value, the coverage rate is less than or equal to the corresponding overlap rate threshold value, and the overflow rate is less than or equal to the corresponding overflow rate threshold value, the quality detection is passed, and updating the grid boundaries (B1 town, B2 town, B3 town and B4 town) of the town level passed by the quality inspection to the current version electronic map.
The quality inspection module 2 is configured to calculate a coverage rate of the hierarchical grid boundary: traversing all the grid boundaries of the level to obtain a residual uncovered area uncovered by the grid boundary of the level in the grid boundary of the previous level corresponding to the level, calculating the gap rate between the area of the residual uncovered area and the area of the grid boundary area of the previous level corresponding to the level, and calculating the coverage rate to be 1-gap rate.
The quality inspection module 2 is configured to calculate an overlapping rate of the grid boundary of the hierarchy: traversing the pairwise combination of all grid boundaries of the level to obtain all intersection regions corresponding to the pairwise combination, taking a union set of all the intersection regions to obtain an overlapping region, and calculating the overlapping rate which is the area of the overlapping region of the level/the area of the grid boundary region of the previous level corresponding to the level.
For example: traversing the pairwise combination of all the mesh boundaries of the town level to obtain all the intersection regions S1, S2 and S3 corresponding to the pairwise combination, taking a union of the intersection regions S1, S2 and S3 to obtain an overlapping region (see a dash region), and calculating the overlapping rate of the town level mesh boundary, which is the area of the town level overlapping region (the dash region)/the area of the mesh boundary region of the a region.
The quality inspection module 2 is used for calculating the overflow rate of the grid boundary of the level: and traversing all the grid boundaries of the level to obtain all the out-bound boundaries of the grid boundaries of the level overflowing the grid boundaries of the previous level corresponding to the level, taking a union set of the areas formed by all the out-bound boundaries to obtain an overflow area, and calculating the overflow rate which is the area of the overflow area of the level/the area of the grid boundary area of the previous level corresponding to the level.
The version summarizing module 3 is used for summarizing the grid boundaries of all levels passed by the quality control drawn by all users so as to obtain the latest current version electronic map.
For example: the grid boundaries of A1 town, A2 town, A3 town and A4 town under the A region where the quality inspection passes drawn by the user 1 and the grid boundaries of B1 town, B2 town, B3 town and B4 town under the B region where the quality inspection passes drawn by the user 2 are summarized, so that the latest current version electronic map is obtained.
The version submitting module 4 is used for automatically submitting the latest current version electronic map when the submitting time reaches the set version submitting deadline.
The version auditing module 5 is used for the manager to audit the latest current version of the electronic map, and when the audit is passed, the version auditing module sends out the information that the audit is passed and the release is effective, and when the audit is not passed, the version auditing module sends out the information that the audit is not passed and the border drawing is rejected.
The version release module 6 is used for automatically releasing the latest current version electronic map when the release effective time reaches the set version release effective time.
As shown in fig. 2, the embodiment further provides a method for controlling quality of an electronic map in a grid data system, which includes the following steps:
and S1, submitting the grid boundaries of each hierarchy under the grid data system drawn in the electronic map by the user.
S2, automatically performing quality inspection on submitted grid boundaries of each hierarchy, performing validity check on the grid boundaries of a certain hierarchy based on a boundary validity rule, calculating the coverage rate, the overlapping rate and the overflow rate of the hierarchy grid boundaries when the check is passed, detecting whether the coverage rate of the grid boundaries of the hierarchy is greater than or equal to the corresponding coverage rate threshold, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold, and whether the overflow rate is less than or equal to the corresponding overflow rate threshold, if yes, passing the quality inspection, updating the grid boundaries of the hierarchy passing the quality inspection to the electronic map of the current version, and if not, sending out information that the quality inspection is not passed and rejecting to perform boundary drawing again.
In step S2, the coverage of the hierarchical grid boundary is calculated: traversing all grid boundaries of the level to obtain a residual uncovered area uncovered by the grid boundary of the level in the grid boundary of the previous level corresponding to the level, calculating a gap rate between the area of the residual uncovered area and the area of the grid boundary area of the previous level corresponding to the level, and calculating the coverage rate which is 1-gap rate.
Calculating the overlapping rate of the boundary of the hierarchical grid: traversing the pairwise combination of all grid boundaries of the level to obtain all intersection areas corresponding to the pairwise combination, taking a union set of all the intersection areas to obtain an overlapping area, and calculating the overlapping rate which is the area of the overlapping area of the level/the area of the grid boundary area of the previous level corresponding to the level.
Calculating the overflow rate of the boundary of the hierarchical grid: and traversing all the grid boundaries of the level to obtain all the out-bound boundaries of the grid boundaries of the level overflowing the grid boundaries of the previous level corresponding to the level, taking a union set of the areas formed by all the out-bound boundaries to obtain an overflow area, and calculating the overflow rate which is the area of the overflow area of the level/the area of the grid boundary area of the previous level corresponding to the level.
And S3, summarizing the grid boundaries of all levels passed by the quality control drawn by all users to obtain the latest current version electronic map.
And S4, automatically submitting the latest electronic map of the current version when the submission time reaches the set version submission deadline.
And S5, the manager audits the electronic map of the latest current version, sends information that the audit is passed and the issuance is effective when the audit is passed, and sends information that the audit is not passed and the boundary drawing is carried out again when the audit is not passed.
And S6, automatically releasing and validating the latest current version electronic map when the release validation time reaches the set version release validation time.
While specific embodiments of the invention have been described above, it will be appreciated by those skilled in the art that these are by way of example only, and that the scope of the invention is defined by the appended claims. Various changes and modifications to these embodiments may be made by those skilled in the art without departing from the spirit and scope of the invention, and these changes and modifications are within the scope of the invention.

Claims (4)

1. An electronic map quality control system in a grid data system is characterized by comprising a boundary submitting module, a quality inspection module, a version summarizing module, a version submitting module, a version checking module and a version validating module;
the boundary submitting module is used for submitting the grid boundaries of all levels under a grid data system drawn in the electronic map by a user;
the quality inspection module is used for automatically performing quality inspection on the grid boundary of each level below the highest level in the submitted levels, performing validity check on the grid boundary of a certain level based on a boundary validity rule, calculating the coverage rate, the overlapping rate and the overflow rate of the grid boundary of the level when the check is passed, detecting whether the coverage rate of the grid boundary of the level is greater than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, if yes, passing the quality inspection, updating the grid boundary of the level passing the quality inspection to the electronic map of the current version, and if not, sending information that the quality inspection is not passed and rejecting to perform boundary drawing again;
the version summarizing module is used for summarizing the grid boundaries of all levels passed by the quality inspection drawn by all users to obtain the latest current version electronic map;
the version submitting module is used for automatically submitting the latest current version electronic map when the submitting time reaches the set version submitting deadline;
the version auditing module is used for an administrator to audit the latest current version of the electronic map, and when the audit is passed, the version auditing module sends out information that the audit is passed and the release is effective, and when the audit is not passed, the version auditing module sends out information that the audit is not passed and the border drawing is rejected;
the version release module is used for automatically releasing the latest current version electronic map which is effective when the release effective time reaches the set version release effective time.
2. The system of claim 1, wherein the quality inspection module is configured to calculate the coverage of the grid boundary: traversing all grid boundaries of the level to obtain a residual uncovered area uncovered by the grid boundary of the level in the grid boundary of the last level corresponding to the level, calculating a gap rate between the area of the residual uncovered area and the area of the grid boundary area of the last level corresponding to the level, and calculating the coverage rate to be 1-gap rate;
the quality inspection module is used for calculating the overlapping rate of the grid boundary of the level: traversing the pairwise combination of all grid boundaries of the level to obtain all intersection areas corresponding to the pairwise combination, taking a union set of all the intersection areas to obtain an overlapping area, and calculating the overlapping rate which is the area of the overlapping area of the level/the area of the grid boundary area of the previous level corresponding to the level;
the quality inspection module is used for calculating the overflow rate of the grid boundary of the level: and traversing all the grid boundaries of the level to obtain all the out-bound boundaries of the grid boundaries of the level overflowing the grid boundaries of the previous level corresponding to the level, taking a union set of the areas formed by all the out-bound boundaries to obtain an overflow area, and calculating the overflow rate which is the area of the overflow area of the level/the area of the grid boundary area of the previous level corresponding to the level.
3. A method for controlling the quality of an electronic map in a grid data system is characterized by comprising the following steps:
s1, submitting the grid boundaries of each hierarchy under the grid data system drawn in the electronic map by a user;
s2, automatically performing quality inspection on the grid boundary of each level below the highest level in the submitted levels, performing validity inspection on the grid boundary of the level based on a boundary validity rule aiming at the grid boundary of a certain level, calculating the coverage rate, the overlapping rate and the overflow rate of the grid boundary of the level when the verification is passed, detecting whether the coverage rate of the grid boundary of the level is more than or equal to the corresponding coverage rate threshold value, whether the overlapping rate is less than or equal to the corresponding overlapping rate threshold value and whether the overflow rate is less than or equal to the corresponding overflow rate threshold value, if yes, passing the quality inspection, updating the grid boundary of the level passing the quality inspection to the electronic map of the current version, and if not, sending information that the quality inspection is not passed and refusing to perform boundary drawing again;
s3, summarizing the grid boundaries of each level passed by the quality inspection drawn by each user to obtain the latest current version electronic map;
s4, automatically submitting the latest electronic map of the current version when the submission time reaches the set version submission deadline;
s5, the manager audits the electronic map of the latest current version, sends out information that the audit is passed and the release is effective when the audit is passed, and sends out information that the audit is not passed and the border drawing is carried out again when the audit is not passed;
and S6, automatically releasing and validating the latest current version electronic map when the release validation time reaches the set version release validation time.
4. The method for controlling the quality of an electronic map in a mesh data system according to claim 3, wherein in step S2, the coverage of the hierarchical mesh boundary is calculated as: traversing all grid boundaries of the level to obtain a residual uncovered area uncovered by the grid boundary of the level in the grid boundary of the last level corresponding to the level, calculating a gap rate between the area of the residual uncovered area and the area of the grid boundary area of the last level corresponding to the level, and calculating the coverage rate to be 1-gap rate;
calculating the overlapping rate of the grid boundary of the hierarchy: traversing the pairwise combination of all grid boundaries of the level to obtain all intersection areas corresponding to the pairwise combination, taking a union set of all the intersection areas to obtain an overlapping area, and calculating the overlapping rate which is the area of the overlapping area of the level/the area of the grid boundary area of the previous level corresponding to the level;
calculating the overflow rate of the boundary of the hierarchical grid: and traversing all the grid boundaries of the level to obtain all the out-bound boundaries of the grid boundaries of the level overflowing the grid boundaries of the previous level corresponding to the level, taking a union set of the areas formed by all the out-bound boundaries to obtain an overflow area, and calculating the overflow rate which is the area of the overflow area of the level/the area of the grid boundary area of the previous level corresponding to the level.
CN202210078020.5A 2022-01-24 2022-01-24 Electronic map quality control system and method in grid data system Active CN114445359B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210078020.5A CN114445359B (en) 2022-01-24 2022-01-24 Electronic map quality control system and method in grid data system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210078020.5A CN114445359B (en) 2022-01-24 2022-01-24 Electronic map quality control system and method in grid data system

Publications (2)

Publication Number Publication Date
CN114445359A true CN114445359A (en) 2022-05-06
CN114445359B CN114445359B (en) 2023-09-08

Family

ID=81369818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210078020.5A Active CN114445359B (en) 2022-01-24 2022-01-24 Electronic map quality control system and method in grid data system

Country Status (1)

Country Link
CN (1) CN114445359B (en)

Citations (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11328378A (en) * 1998-05-13 1999-11-30 Hitachi Ltd Method and device for updating map information
US20040135705A1 (en) * 2003-01-07 2004-07-15 Masaharu Umezu Map data processing apparatus and center system
US20080040030A1 (en) * 2006-08-11 2008-02-14 Denso Corporation Map display system
WO2008023877A1 (en) * 2006-08-21 2008-02-28 Electronics And Telecommunications Research Institute Method for updating map data of terminal based on route area, and server using the same
US20080082260A1 (en) * 2006-10-03 2008-04-03 Denso Corporation Map data utilization apparatus
KR20080079346A (en) * 2006-12-28 2008-09-01 에스케이에너지 주식회사 System and merhod for map uapdate, storage medium recording that method program, user termianl
CN101421586A (en) * 2006-09-01 2009-04-29 爱信艾达株式会社 Map updating system
US20090171976A1 (en) * 2007-12-27 2009-07-02 Hitachi, Ltd. Map Data Delivering Device, Communication Terminal, and Map Delivering Method
US20090265105A1 (en) * 2008-04-21 2009-10-22 Igt Real-time navigation devices, systems and methods
JP2013228701A (en) * 2012-03-28 2013-11-07 Giken Shoji International Co Ltd Map mesh data generation system and mesh data generation method
US20160047658A1 (en) * 2013-04-16 2016-02-18 Denso Corporation Map data storage device, map data processing device, and map data updating system
JP2017116823A (en) * 2015-12-25 2017-06-29 株式会社トヨタマップマスター Map update device, map update method, computer program, and recording medium for recording computer program
CN107273486A (en) * 2017-06-12 2017-10-20 江苏省基础地理信息中心 Map updating method and device
JP2018004791A (en) * 2016-06-29 2018-01-11 アイシン・エィ・ダブリュ株式会社 Server device, communication terminal, information distribution system, and computer program
CN107992522A (en) * 2017-11-06 2018-05-04 腾讯科技(深圳)有限公司 A kind of image processing method, device and terminal device
US20190043251A1 (en) * 2017-08-04 2019-02-07 Walmart Apollo, Llc Systems, devices, and methods for generating a dynamic three dimensional communication map
CN109635060A (en) * 2018-11-27 2019-04-16 平安科技(深圳)有限公司 Shared map publishing method and apparatus
CN110741224A (en) * 2017-06-12 2020-01-31 松下知识产权经营株式会社 System and method for dynamically authenticating map data using blockchains
CN110941686A (en) * 2018-09-25 2020-03-31 北京京东尚科信息技术有限公司 Positioning map processing method and device
US20200402394A1 (en) * 2019-06-20 2020-12-24 Here Global B.V. Adjusting historical probe data for new road geometry
US20200408557A1 (en) * 2019-06-28 2020-12-31 Gm Cruise Holdings Llc Augmented 3d map
CN112325873A (en) * 2021-01-04 2021-02-05 炬星科技(深圳)有限公司 Environment map autonomous updating method, equipment and computer readable storage medium
CN112612860A (en) * 2020-12-09 2021-04-06 卡斯柯信号有限公司 Automatic electronic map pushing method based on train position
CN113160594A (en) * 2020-01-23 2021-07-23 丰田自动车株式会社 Change point detection device and map information distribution system
US20210302170A1 (en) * 2020-03-31 2021-09-30 Gm Cruise Holdings Llc Map maintenance and verification

Patent Citations (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11328378A (en) * 1998-05-13 1999-11-30 Hitachi Ltd Method and device for updating map information
US20040135705A1 (en) * 2003-01-07 2004-07-15 Masaharu Umezu Map data processing apparatus and center system
US20080040030A1 (en) * 2006-08-11 2008-02-14 Denso Corporation Map display system
WO2008023877A1 (en) * 2006-08-21 2008-02-28 Electronics And Telecommunications Research Institute Method for updating map data of terminal based on route area, and server using the same
CN101421586A (en) * 2006-09-01 2009-04-29 爱信艾达株式会社 Map updating system
US20080082260A1 (en) * 2006-10-03 2008-04-03 Denso Corporation Map data utilization apparatus
KR20080079346A (en) * 2006-12-28 2008-09-01 에스케이에너지 주식회사 System and merhod for map uapdate, storage medium recording that method program, user termianl
US20090171976A1 (en) * 2007-12-27 2009-07-02 Hitachi, Ltd. Map Data Delivering Device, Communication Terminal, and Map Delivering Method
US20090265105A1 (en) * 2008-04-21 2009-10-22 Igt Real-time navigation devices, systems and methods
JP2013228701A (en) * 2012-03-28 2013-11-07 Giken Shoji International Co Ltd Map mesh data generation system and mesh data generation method
US20160047658A1 (en) * 2013-04-16 2016-02-18 Denso Corporation Map data storage device, map data processing device, and map data updating system
JP2017116823A (en) * 2015-12-25 2017-06-29 株式会社トヨタマップマスター Map update device, map update method, computer program, and recording medium for recording computer program
JP2018004791A (en) * 2016-06-29 2018-01-11 アイシン・エィ・ダブリュ株式会社 Server device, communication terminal, information distribution system, and computer program
CN107273486A (en) * 2017-06-12 2017-10-20 江苏省基础地理信息中心 Map updating method and device
CN110741224A (en) * 2017-06-12 2020-01-31 松下知识产权经营株式会社 System and method for dynamically authenticating map data using blockchains
US20190043251A1 (en) * 2017-08-04 2019-02-07 Walmart Apollo, Llc Systems, devices, and methods for generating a dynamic three dimensional communication map
CN107992522A (en) * 2017-11-06 2018-05-04 腾讯科技(深圳)有限公司 A kind of image processing method, device and terminal device
CN110941686A (en) * 2018-09-25 2020-03-31 北京京东尚科信息技术有限公司 Positioning map processing method and device
CN109635060A (en) * 2018-11-27 2019-04-16 平安科技(深圳)有限公司 Shared map publishing method and apparatus
US20200402394A1 (en) * 2019-06-20 2020-12-24 Here Global B.V. Adjusting historical probe data for new road geometry
US20200408557A1 (en) * 2019-06-28 2020-12-31 Gm Cruise Holdings Llc Augmented 3d map
CN113160594A (en) * 2020-01-23 2021-07-23 丰田自动车株式会社 Change point detection device and map information distribution system
US20210302170A1 (en) * 2020-03-31 2021-09-30 Gm Cruise Holdings Llc Map maintenance and verification
CN112612860A (en) * 2020-12-09 2021-04-06 卡斯柯信号有限公司 Automatic electronic map pushing method based on train position
CN112325873A (en) * 2021-01-04 2021-02-05 炬星科技(深圳)有限公司 Environment map autonomous updating method, equipment and computer readable storage medium

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
DOUGLAS L. VANDEGRAFT: "A boundary delineation system for the bureau of ocean energy management", 《OCEANS 2017 - ANCHORAGE》 *
曾文华, 王友富: "基于Java的网络电子地图发布系统设计", 计算机应用, no. 06 *
胡晓东;梁姗;袁武;陆忠华;: "混合重叠网格通信优化算法", 计算机系统应用, no. 12 *

Also Published As

Publication number Publication date
CN114445359B (en) 2023-09-08

Similar Documents

Publication Publication Date Title
WO2017084345A1 (en) Method and device for form verification
US20190026261A1 (en) Methods and systems for validating multiple methods of input using a unified rule set
US20080201780A1 (en) Risk-Based Vulnerability Assessment, Remediation and Network Access Protection
US20060004614A1 (en) Content management system
US11366745B2 (en) Testing program code created in a development system
US11544409B2 (en) Data processing systems and methods for automatically protecting sensitive data within privacy management systems
CN104363112B (en) A kind of parameter management method and device
CN110474911A (en) Trusted end-user recognition methods, device, equipment and computer readable storage medium
US8473377B2 (en) Data management system
WO2019028411A1 (en) Data processing systems for prioritizing data subject access requests for fulfillment and related methods
US8874463B2 (en) Trouble ticket management system
CN114511235A (en) Process evaluation method and system
CN114445359A (en) Electronic map quality control system and method in grid data system
CN117495544A (en) Sandbox-based wind control evaluation method, sandbox-based wind control evaluation system, sandbox-based wind control evaluation terminal and storage medium
CN111045725B (en) Control method and device of code management system and storage medium
US8495542B2 (en) Automated management of verification waivers
US11507358B2 (en) Method and apparatus for change automation
JP2019508760A (en) Form information input method, apparatus, server, and storage medium
CN112016885A (en) Data processing method and device
JP2008052347A (en) Document processor and document processing program
CN105791335A (en) Information processing method and device
CN115037557B (en) Temporary identity authentication method and device for user access application
CN108984503B (en) Fool-proof method and system for page input box and related components
CN113010491B (en) Cloud-based data management method and system
CN112966244B (en) Multi-dimensional power grid information system access control method, system and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant