CN114412152A - Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project - Google Patents

Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project Download PDF

Info

Publication number
CN114412152A
CN114412152A CN202210097895.XA CN202210097895A CN114412152A CN 114412152 A CN114412152 A CN 114412152A CN 202210097895 A CN202210097895 A CN 202210097895A CN 114412152 A CN114412152 A CN 114412152A
Authority
CN
China
Prior art keywords
vertical
construction
scaffolding
horizontal
pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210097895.XA
Other languages
Chinese (zh)
Inventor
蒙晓莲
刘国林
李顺明
周毅鹏
方楷滨
李建斌
蔡甲锟
李明
李相宏
莫承谦
高�豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Rongxiang Architectural Engineering Co ltd
Zhongzhao Construction Engineering Group Co ltd
Original Assignee
Guangzhou Rongxiang Architectural Engineering Co ltd
Zhongzhao Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Rongxiang Architectural Engineering Co ltd, Zhongzhao Construction Engineering Group Co ltd filed Critical Guangzhou Rongxiang Architectural Engineering Co ltd
Priority to CN202210097895.XA priority Critical patent/CN114412152A/en
Publication of CN114412152A publication Critical patent/CN114412152A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/20Stiff scaffolding clamps for connecting scaffold members of common shape for ends of members only, e.g. for connecting members in end-to-end relation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The invention discloses a construction method for constructing an I-steel scaffold by a large-span overhanging structure of a high-rise cluster project, which comprises the following steps: 1) arranging a plurality of horizontal cantilever beams; 2) arranging a plurality of groups of upright rod assemblies; 3) arranging a first cross bar and a second cross bar; 4) arranging a shear support assembly; 5) wall connecting construction; 6) unloading construction; 7) arranging a scaffold board and a foot baffle board; 8) arranging a protective guard; 9) and after the building construction is finished, dismantling the outer scaffold of the cantilever beam. The cantilever structure scaffold is adopted to replace a high-rise building to erect construction from the ground, and the defects that the full scaffold is high in material consumption, long in installation and disassembly time, long in time consumption, high in cost, difficult in installation and disassembly, high in danger, large in material investment and the like are overcome. Compared with the traditional inclined stay rope 'embedded ring' of the cantilever frame, the labor is saved, the inclined stay rope can be recycled for many times, the length of the pull rod can be adjusted at any time to ensure the stability of the frame body, and the I-shaped steel can be reused.

Description

高层集群项目大跨度悬挑结构施工工字钢脚手架的工法Construction method of I-beam scaffolding for large-span cantilevered structures in high-rise cluster projects

技术领域technical field

本发明涉及工程施工技术领域,特别是涉及高层集群项目大跨度悬挑结构施工工字钢脚手架的工法。The invention relates to the technical field of engineering construction, in particular to a construction method for constructing I-beam scaffolding with a large-span cantilever structure of a high-rise cluster project.

背景技术Background technique

外脚手架一般是在建筑物外围搭设的脚手架,在施工过程中,搭设脚手架的速度、质量是建筑施工的关键控制点。现有的外脚手架与楼体外墙没有连接,导致外脚手架搭设不稳固,质量难以保证,同时,现有的外脚手架搭设的施工方法速度较慢。External scaffolding is generally a scaffolding erected on the periphery of a building. During the construction process, the speed and quality of erecting the scaffolding are the key control points of building construction. The existing external scaffolding is not connected to the outer wall of the building, which results in unstable erection of the external scaffolding and difficulty in ensuring the quality. At the same time, the existing construction method for erecting the external scaffolding is relatively slow.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于至少解决现有技术中存在的技术问题之一,为此,本发明提出一种高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,包括如下步骤:The purpose of the present invention is to solve at least one of the technical problems existing in the prior art, for this reason, the present invention proposes a construction method for constructing I-beam scaffolding with a large-span cantilever structure of a high-rise cluster project, comprising the following steps:

1)设置多个水平悬挑梁,水平悬挑梁采用工字钢,水平悬挑梁远离楼体外墙的一端连接斜吊钢绳,斜吊钢绳的另一端位于水平悬挑梁的上方且与楼体外墙连接;1) Set up a plurality of horizontal cantilever beams, the horizontal cantilever beam is made of I-beam, the end of the horizontal cantilever beam far from the outer wall of the building is connected to the oblique hanging steel rope, and the other end of the oblique hanging steel rope is located above the horizontal cantilever beam and connected to the outer wall of the building;

2)设置多组立杆组件:立杆组件包括平行且间隔设置的外立杆以及内立杆,内立杆与楼体外墙相对设置,外立杆和内立杆通过横向扫地杆连接,多组立杆组件通过纵向扫地杆连接,立杆组件设于水平悬挑梁上,立杆组件的数量与水平悬挑梁的数量相同且一对一设置;2) Set up multiple sets of vertical pole components: the vertical pole components include external vertical poles and internal vertical poles arranged in parallel and at intervals, the internal vertical poles are arranged opposite to the outer wall of the building, and the external vertical poles and the internal vertical poles are connected by horizontal sweeping poles. The vertical pole components are connected by longitudinal sweeping poles, the vertical pole components are arranged on the horizontal cantilever beams, and the number of vertical pole components is the same as that of the horizontal cantilever beams and is arranged one-to-one;

3)设置第一横杆和第二横杆:在立杆组件的高度方向间隔的设置多个第一横杆和多个第二横杆,第一横杆的两端分别与外立杆和内立杆连接,第二横杆连接于外立杆上,第二横杆的端部位于第一横杆和外立杆的交接处,第一横杆设于第二横杆的上方;3) Setting up the first crossbar and the second crossbar: a plurality of first crossbars and a plurality of second crossbars are arranged at intervals in the height direction of the vertical rod assembly, and the two ends of the first crossbar are The inner vertical bar is connected, the second horizontal bar is connected to the outer vertical bar, the end of the second horizontal bar is located at the junction of the first horizontal bar and the outer vertical bar, and the first horizontal bar is arranged above the second horizontal bar;

4)设置剪力撑组件:外立杆的外侧立面上连接有剪力撑组件,沿外立杆的外侧立面的全宽和全高且由底至顶连续设置垂直剪力撑组件;4) Set up shear brace components: shear brace components are connected to the outer elevation of the outer pole, and vertical shear brace components are continuously arranged along the full width and height of the outer elevation of the outer pole and from the bottom to the top;

5)连墙施工:立杆组件与楼体外墙预埋的连墙件拉结固定连接;5) Connecting wall construction: The vertical rod components are tied and fixedly connected with the connecting wall parts embedded in the outer wall of the building;

6)卸荷施工:在斜吊钢绳与楼体外墙连接的强度达到设计强度的100%后,卸载斜吊钢绳;6) Unloading construction: After the strength of the connection between the inclined hanging steel rope and the outer wall of the building reaches 100% of the design strength, unload the inclined hanging steel rope;

7)设置脚手板和挡脚板:内立杆上连接有挡脚板,挡脚板位于内立杆与楼体外墙之间,内立杆和外立杆之间铺设有脚手板,脚手板设于第一横杆上;7) Set up the scaffolding board and the toeboard: the inner pole is connected with a toeboard, the toeboard is located between the inner pole and the outer wall of the building, and a scaffolding board is laid between the inner pole and the outer pole, and the scaffolding board is set on the first floor. on a crossbar;

8)设置防护栏:外立杆上固设防护栏杆,外立杆的外侧立面满挂密目式安全网;8) Set up guardrails: guardrails are fixed on the outer poles, and the outer facades of the outer poles are covered with dense mesh safety nets;

9)楼体施工完成后,拆除悬挑梁外脚手架:先拆脚手板、挡脚板和剪力撑组件,而后拆第一横杆、第二横杆和立杆组件。9) After the construction of the building is completed, remove the outer scaffolding of the cantilever beam: first remove the scaffolding board, toe board and shear brace components, and then remove the first cross bar, second cross bar and vertical bar components.

有益效果:通过采用悬挑结构脚手架代替了高层建筑物从地面搭设施工,解决了满堂脚手架耗材大,安拆时间长、耗时长、成本高、安拆困难、危险性高、材料投入较大等缺陷。与传统做法的悬挑架的斜拉绳“预埋环”对比,即省工又可多次周转利用,可随时调节拉杆长短以确保架体的稳定性,工字钢可重复利用。Beneficial effects: The use of cantilevered structure scaffolding replaces the construction of high-rise buildings from the ground, which solves the problem of large consumables for full-scale scaffolding, long installation and dismantling time, long time, high cost, difficult installation and dismantling, high risk, and large material investment, etc. defect. Compared with the "pre-embedded ring" of the cable-stayed rope of the traditional cantilever frame, it saves labor and can be used multiple times. The length of the tie rod can be adjusted at any time to ensure the stability of the frame body, and the I-beam can be reused.

在本发明的一些实施例中,步骤1)中,水平悬挑梁的外挑长度为1300mm、锚固长度为2000mm时,采用20a号工字钢。In some embodiments of the present invention, in step 1), when the overhang length of the horizontal cantilever beam is 1300mm and the anchoring length is 2000mm, 20a I-beam is used.

在本发明的一些实施例中,步骤1)中,水平悬挑梁的外挑长度为2000mm、锚固长度为3000mm时,采用25a号工字钢。In some embodiments of the present invention, in step 1), when the overhang length of the horizontal cantilever beam is 2000mm and the anchoring length is 3000mm, 25a I-beam is used.

在本发明的一些实施例中,步骤2)中,控制各内立杆和各外立杆的垂直偏差为≤100mm。In some embodiments of the present invention, in step 2), the vertical deviation of each inner pole and each outer pole is controlled to be ≤100 mm.

在本发明的一些实施例中,步骤3)中,第一横杆的两端分别远离内立杆和外立杆伸长长度为150mm。In some embodiments of the present invention, in step 3), the two ends of the first transverse rod are respectively away from the inner and outer vertical rods by an extension length of 150 mm.

在本发明的一些实施例中,步骤4)中,剪力撑组件搭设的角度为45°~60°。In some embodiments of the present invention, in step 4), the angle at which the shear brace assembly is erected is 45°˜60°.

在本发明的一些实施例中,步骤4)中,设置完成剪力撑组件后,在悬挑梁外脚手架的两端开口处设置横向斜撑,横向斜撑在同一节间,由底至顶呈之字型连续布设。In some embodiments of the present invention, in step 4), after the shear bracing assembly is completed, transverse diagonal bracing is set at the openings at both ends of the outer scaffold of the cantilever beam, and the horizontal diagonal bracing is in the same section, from bottom to top Laid out continuously in a zigzag pattern.

在本发明的一些实施例中,步骤5)中,立杆组件与楼体外墙预埋的连墙件拉结的拉结点设置在第一横杆和第二横杆接点的300mm范围内。In some embodiments of the present invention, in step 5), the tie point between the vertical rod assembly and the pre-embedded connecting wall member on the outer wall of the building is set within 300 mm of the junction of the first crossbar and the second crossbar.

在本发明的一些实施例中,步骤7)中,挡脚板为冲压钢板,挡脚板的高度为180mm。In some embodiments of the present invention, in step 7), the foot guard is a stamped steel plate, and the height of the foot guard is 180 mm.

在本发明的一些实施例中,步骤2)中,在水平悬挑梁上焊接外径为25mm的定位钢筋,立杆组件套座在定位钢筋外。In some embodiments of the present invention, in step 2), a positioning steel bar with an outer diameter of 25 mm is welded on the horizontal cantilever beam, and the vertical rod assembly is seated outside the positioning steel bar.

附图说明Description of drawings

下面结合附图对本发明作进一步说明,显而易见地,下面描述中的附图是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。The present invention will be further described below in conjunction with the accompanying drawings. Obviously, the accompanying drawings in the following description are some embodiments of the present invention. For those of ordinary skill in the art, under the premise of no creative work, they can also follow these drawings. Figure to obtain additional drawings.

图1是本发明实施例的施工平面示意图;Fig. 1 is the construction plan schematic diagram of the embodiment of the present invention;

图2是本发明实施例设有横向斜撑的的示意图;Fig. 2 is the schematic diagram that the embodiment of the present invention is provided with horizontal diagonal brace;

图3是本发明实施例的结构示意图;3 is a schematic structural diagram of an embodiment of the present invention;

图4是本发明实施例设有剪力撑组件的结构示意图。FIG. 4 is a schematic structural diagram of a shear brace assembly according to an embodiment of the present invention.

附图标记:Reference number:

10-水平悬挑梁;10-Horizontal cantilever beam;

20-斜吊钢绳;20- oblique hanging steel rope;

31-外立杆;31-outer pole;

32-内立杆;32 - inner pole;

33-横向扫地杆;33- Lateral sweeping rod;

34-纵向扫地杆;34-Longitudinal sweeping rod;

35-第一横杆;35 - the first crossbar;

36-第二横杆;36 - second crossbar;

37-剪力撑组件;37 - Shear brace assembly;

41-挡脚板;41 - foot guard;

42-脚手板;42 - Scaffolding board;

43-安全网;43 - safety net;

44-横向斜撑;44- Lateral diagonal brace;

45-连墙件;45-connecting wall parts;

46-防护栏杆;46 - protective railing;

47-木枋;47 - Wood Fang;

50-剪力撑组件搭设的角度。50 - The angle at which the shear brace assembly is erected.

具体实施方式Detailed ways

为了使本领域技术人员更好地理解本发明的技术方案,下面结合附图对本发明进行详细描述,本部分的描述仅是示范性和解释性,不应对本发明的保护范围有任何的限制作用。In order to make those skilled in the art better understand the technical solutions of the present invention, the present invention will be described in detail below with reference to the accompanying drawings. The description in this part is only exemplary and explanatory, and should not have any limiting effect on the protection scope of the present invention. .

需要理解的是,本文中,术语“上”、“下”、“左”、“右”、“前”、“后”、“底”、“顶”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It is to be understood that, herein, the terms "upper", "lower", "left", "right", "front", "rear", "bottom", "top", "inner", "outer", etc. refer to The orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation or be constructed in a specific orientation. and operation, and therefore should not be construed as limiting the present invention.

本文中,术语“第一”、“第二”等是用于区别不同对象,而不是用于描述特定顺序。本文中,如果有描述到“若干”、“多个”,若干的含义是一个或者多个,多个的含义是两个以上,大于、小于、超过等理解为不包括本数,以上、以下、以内等理解为包括本数。Herein, the terms "first", "second", etc. are used to distinguish different objects, rather than to describe a particular order. In this article, if there is a description of "several" and "multiple", the meaning of several is one or more, the meaning of multiple is two or more, greater than, less than, exceeding, etc. are understood as not including this number, above, below, Within, etc., are understood to include this number.

需要说明的是,在本文中,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。本发明的描述中,除非另有明确的限定,设置、安装、连接等词语应做广义理解,所属技术领域技术人员可以结合技术方案的具体内容合理确定上述词语在本发明中的具体含义。It should be noted that, herein, the terms "comprising", "comprising" or any other variation thereof are intended to encompass non-exclusive inclusion, such that a process, method, article or device comprising a series of elements includes not only those elements, It also includes other elements not expressly listed or inherent to such a process, method, article or apparatus. In the description of the present invention, unless otherwise clearly defined, words such as setting, installation, connection should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meaning of the above words in the present invention in combination with the specific content of the technical solution.

本部分将详细描述本发明的具体实施例,本发明之较佳实施例在附图中示出,附图的作用在于用图形补充说明书文字部分的描述,使人能够直观地、形象地理解本发明的每个技术特征和整体技术方案,但其不能理解为对本发明保护范围的限制。This part will describe the specific embodiments of the present invention in detail, and the preferred embodiments of the present invention are shown in the accompanying drawings. Each technical feature and overall technical solution of the invention should not be construed as limiting the protection scope of the invention.

参照图1至图4,本发明实施例提出一种高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,包括如下步骤:1 to 4 , an embodiment of the present invention proposes a method for constructing I-beam scaffolding with a large-span cantilever structure for a high-rise cluster project, including the following steps:

1)设置多个水平悬挑梁10,水平悬挑梁10采用工字钢,水平悬挑梁10远离楼体外墙的一端连接斜吊钢绳20,斜吊钢绳20的另一端位于水平悬挑梁10的上方且与楼体外墙连接。外立杆31位置设两根斜拉钢丝绳。1) Set up a plurality of horizontal cantilever beams 10, the horizontal cantilever beam 10 adopts I-beam, the end of the horizontal cantilever beam 10 away from the outer wall of the building is connected to the oblique hanging steel rope 20, and the other end of the oblique hanging steel rope 20 is located in the horizontal suspension. The top of the cantilever beam 10 is connected to the outer wall of the building. Two diagonal-pulling steel wire ropes are arranged at the position 31 of the outer pole.

在一些实施例中,水平悬挑梁10的外挑长度为1300mm、锚固长度为2000mm时,采用20a号工字钢。In some embodiments, when the overhang length of the horizontal cantilever beam 10 is 1300mm and the anchoring length is 2000mm, 20a I-beam is used.

在另一些实施例中,水平悬挑梁10的外挑长度为2000mm、锚固长度为3000mm时,采用25a号工字钢,立杆组件为由内至外依次设置的内立杆32、中立杆以及外立杆31,即三层立杆。In other embodiments, when the overhang length of the horizontal cantilever beam 10 is 2000mm and the anchoring length is 3000mm, 25a I-beam is used, and the vertical rod components are the inner vertical rods 32 and neutral rods arranged in sequence from the inside to the outside. And the outer pole 31, that is, the three-layer pole.

2)设置多组立杆组件:立杆组件包括平行且间隔设置的外立杆31以及内立杆32,内立杆32与楼体外墙相对设置,外立杆31和内立杆32通过横向扫地杆33连接,多组立杆组件通过纵向扫地杆34连接,立杆组件设于水平悬挑梁10上,在水平悬挑梁10上焊接外径为25mm的定位钢筋,立杆组件套座在定位钢筋外,以确保架体的稳定。立杆组件的数量与水平悬挑梁10的数量相同且一对一设置。控制各内立杆32和各外立杆31的垂直偏差≤100mm。2) Set up multiple groups of vertical rod assemblies: the vertical rod assemblies include parallel and spaced outer vertical rods 31 and inner vertical rods 32, the inner vertical rods 32 are arranged opposite to the outer wall of the building, and the outer vertical rods 31 and the inner vertical rods 32 pass through the horizontal The sweeping rod 33 is connected, and multiple sets of vertical pole assemblies are connected by the longitudinal sweeping rod 34. The vertical pole assembly is arranged on the horizontal cantilever beam 10, and the positioning steel bar with an outer diameter of 25mm is welded on the horizontal cantilever beam 10, and the vertical pole assembly is sleeved. Outside the positioning steel bars to ensure the stability of the frame body. The number of the vertical rod assemblies is the same as that of the horizontal cantilever beams 10 and is arranged one-to-one. The vertical deviation of each inner pole 32 and each outer pole 31 is controlled to be less than or equal to 100mm.

水平悬挑梁10须保证有足够的锚固强度和截面抗屈曲能力,水平悬挑梁10的纵向间距与立杆组件的纵向间距相同。外立杆31和内立杆32均分别由多根立杆件拼接连接而成,各立杆件之间采用对接接头连接。外立杆31和内立杆32与第一横杆35采用直角扣件连接,置接头位置交错布置,两个相邻立杆的接头避免出现在同步同跨内,并在高度方向错开的距离不小于50cm;各接头中心距主节点的距离不大于60cm。The horizontal cantilever beam 10 must ensure sufficient anchoring strength and section buckling resistance, and the longitudinal spacing of the horizontal cantilever beam 10 is the same as that of the vertical rod assembly. The outer vertical rod 31 and the inner vertical rod 32 are respectively formed by splicing and connecting a plurality of vertical rod pieces, and the vertical rod pieces are connected by butt joints. The outer vertical rod 31 and the inner vertical rod 32 are connected with the first cross rod 35 by right-angle fasteners, and the joint positions are arranged in a staggered manner. The joints of two adjacent vertical rods are avoided to appear in the same span and are staggered in the height direction. Not less than 50cm; the distance between the center of each joint and the main node is not more than 60cm.

3)设置第一横杆35和第二横杆36:在立杆组件的高度方向间隔的设置多个第一横杆35和多个第二横杆36,第一横杆35的两端分别与外立杆31和内立杆32连接,在一些实施例中,第一横杆35的两端分别远离内立杆32和外立杆31伸长长度为150mm。第二横杆36连接于外立杆31上,第二横杆36的端部位于第一横杆35和外立杆31的交接处,第一横杆35设于第二横杆36的上方,以形成空间结构整体受力。3) Setting the first cross bar 35 and the second cross bar 36: a plurality of first cross bars 35 and a plurality of second cross bars 36 are arranged at intervals in the height direction of the vertical bar assembly, and the two ends of the first cross bar 35 are respectively In connection with the outer vertical rod 31 and the inner vertical rod 32 , in some embodiments, the two ends of the first transverse rod 35 are respectively away from the inner vertical rod 32 and the outer vertical rod 31 by an extension length of 150 mm. The second horizontal bar 36 is connected to the outer vertical bar 31 , the end of the second horizontal bar 36 is located at the junction of the first horizontal bar 35 and the outer vertical bar 31 , and the first horizontal bar 35 is arranged above the second horizontal bar 36 , in order to form the overall force of the space structure.

4)设置剪力撑组件37:外立杆31的外侧立面上连接有剪力撑组件37,剪力撑组件37沿外立杆31的外侧立面的全宽和全高且由底至顶连续设置垂直剪力撑组件37。继续参照图4,具体地,剪力撑组件搭设的角度50为45°~60°。4) Set up the shear support assembly 37: the outer vertical rod 31 is connected with the shear support assembly 37, and the shear support assembly 37 is along the full width and height of the outer vertical rod 31 from the bottom to the top. Vertical shear brace assemblies 37 are provided in series. Continuing to refer to FIG. 4 , specifically, the angle 50 at which the shear brace assembly is erected is 45°˜60°.

可以理解的是,第一剪力撑杆和第二剪力撑杆均分别由多根撑杆件接长拼接而成,并采用旋转扣件固定,旋转扣件中心线离主节点的距离不大于100mm。It can be understood that the first shear strut and the second shear strut are formed by splicing a plurality of struts respectively, and are fixed by rotating fasteners, and the distance between the center line of the rotating fasteners and the main node is different. greater than 100mm.

可以理解的是,设置完成剪力撑组件37后,在悬挑梁外脚手架的两端开口处设置横向斜撑44,横向斜撑44在同一节间,由底至顶呈之字型连续布设。横向斜撑44采用旋转扣件固定在与之相较的第一横杆35上。在一些实施例中,当横向斜撑44在一跨内跨越两个步距时,在相交的第二横杆36处增设一根第一横杆35,将横向斜撑44固定在增设的第一横杆35的伸出端上。It can be understood that, after the shearing support assembly 37 is installed, transverse diagonal braces 44 are arranged at the openings at both ends of the outer scaffold of the cantilever beam, and the transverse diagonal braces 44 are arranged continuously in a zigzag pattern from the bottom to the top in the same section. . The transverse diagonal brace 44 is fixed on the corresponding first transverse rod 35 by a rotating fastener. In some embodiments, when the transverse diagonal brace 44 spans two steps in a span, a first cross bar 35 is added at the intersecting second cross bar 36 to fix the transverse diagonal brace 44 on the added second cross bar 36 . On the protruding end of a cross bar 35.

5)连墙施工:立杆组件与楼体外墙预埋的连墙件45拉结固定连接。可以理解的是,预埋的连墙件45为钢管或钢筋。连墙件45按楼体每层三跨设置,竖向为每层设置。在转角范围内和顶部处加密,即在转角一米以内按垂直方向按每层设一个拉结点。5) Connecting wall construction: The vertical rod components are connected with the connecting wall parts 45 embedded in the outer wall of the building. It can be understood that the embedded connecting wall member 45 is a steel pipe or a steel bar. The connecting wall pieces 45 are arranged on each floor and three spans of the building body, and are arranged vertically on each floor. Encrypt in the corner range and at the top, that is, set up a pull node on each layer in the vertical direction within one meter of the corner.

拉结点应保证牢固,防止其移动变形,立杆组件与楼体外墙预埋的连墙件45拉结的拉结点设置在第一横杆35和第二横杆36接点的300mm范围内,超过此长度时,增加一道拉结点,将连墙件45拉通与内立杆32和外立杆31连结牢固。The tie point should be firm to prevent it from moving and deforming. The tie point between the vertical rod assembly and the connecting wall piece 45 embedded in the outer wall of the building is set within 300mm of the connection point between the first crossbar 35 and the second crossbar 36. , when this length is exceeded, a pull node is added to pull the connecting wall piece 45 through and connect the inner pole 32 and the outer pole 31 firmly.

6)卸荷施工:在斜吊钢绳20与楼体外墙连接的强度达到设计强度的100%后,卸载斜吊钢绳20。6) Unloading construction: After the strength of the connection between the inclined hanging steel rope 20 and the outer wall of the building reaches 100% of the design strength, the inclined hanging steel rope 20 is unloaded.

7)设置脚手板42和挡脚板41:内立杆32上连接有挡脚板41,挡脚板41位于内立杆32与楼体外墙之间。内立杆32和外立杆31之间铺设有脚手板42,脚手板42设于第一横杆35上。可以理解的是,脚手板42为兜底网。需要理解的是,兜底网为常用件,本领域技术人员有能力根据实际需求选择规格、型号和参数。脚手板42必须满铺到位,不留空位。可以理解的是,挡脚板41为冲压钢板,挡脚板41的高度为180mm。7) Setting up the scaffolding plate 42 and the foot retaining plate 41: the inner vertical rod 32 is connected with the foot retaining plate 41, and the foot retaining plate 41 is located between the inner vertical rod 32 and the outer wall of the building. A scaffolding board 42 is laid between the inner vertical rod 32 and the outer vertical rod 31 , and the scaffolding board 42 is arranged on the first horizontal rod 35 . It can be understood that the scaffolding board 42 is a bottom net. It should be understood that the pocket bottom net is a common part, and those skilled in the art are capable of selecting specifications, models and parameters according to actual needs. The scaffolding 42 must be fully laid in place, leaving no space. It can be understood that the foot guard 41 is a stamped steel plate, and the height of the foot guard 41 is 180 mm.

8)设置防护栏:外立杆31上固设防护栏杆46,外立杆31的外侧立面满挂密目式安全网43。优选地,挂密目式安全网43为18#铁丝张挂安全网43。防护栏杆46设置为1.2m高。悬挑梁外脚手架的内侧形成临边的,在悬挑梁外脚手架的内侧设置0.9m的防护栏杆46和18cm高的踢脚杆。8) Setting up guardrails: guardrails 46 are fixed on the outer poles 31 , and the outer facades of the outer poles 31 are covered with dense mesh type safety nets 43 . Preferably, the hanging security mesh 43 is an 18# iron wire hanging safety net 43 . The guardrail 46 is set to be 1.2m high. The inner side of the outer scaffolding of the cantilever beam forms the edge, and the inner side of the outer scaffolding of the cantilever beam is provided with a 0.9m protective railing 46 and a 18cm high skirting bar.

悬挑梁外脚手架在底层外立杆31与建筑物边线之间范围内全部采用模板及木枋47进行封闭,并设180mm高的挡脚板41,防止坠物伤人。在操作层设水平兜网,并满铺脚手板42,安全网43接口处必须连接严密。安全网43必须与结构连接严密牢固。严禁使用损坏和腐朽的安全网43。悬挑梁外脚手架的底部及侧面用夹板硬密封。The outer scaffolding of the cantilever beam is completely enclosed by formwork and wooden beams 47 within the range between the bottom outer pole 31 and the building sideline, and a 180mm high foot plate 41 is set to prevent falling objects from hurting people. A horizontal pocket net is set on the operation layer, and the scaffolding board 42 is fully covered, and the interface of the safety net 43 must be tightly connected. The safety net 43 must be tightly connected to the structure. Damaged and decayed safety nets are strictly prohibited43. The bottom and sides of the cantilever beam outer scaffold are hard sealed with plywood.

9)楼体施工完成后,拆除悬挑梁外脚手架:拆除方向按照楼层从上到下循环拆除。拆架时应划分作业区,周围设绳绑围栏或竖立警戒标志,地面应设专人指挥,禁止非作业人员进入。9) After the construction of the building is completed, remove the outer scaffolding of the cantilever beams: the removal direction is circularly removed from top to bottom according to the floor. When dismantling the frame, the work area should be divided, and ropes should be tied around the fence or a warning sign should be erected. The ground should be commanded by a special person, and non-operating personnel should not be allowed to enter.

拆架程序应遵守由上而下,先搭后拆的原则,先拆脚手板42、挡脚板41和剪力撑组件37,而后拆第一横杆35、第二横杆36和立杆组件等。The dismantling procedure should follow the principle of top-to-bottom, build first and then dismantle, first dismantle the scaffolding plate 42, the baffle plate 41 and the shear brace assembly 37, and then dismantle the first cross bar 35, the second cross bar 36 and the vertical bar assembly Wait.

不准分立面拆架或在上下两步同时进行拆架。做到一步一清、一杆一清。拆外立杆31和内立杆32时,要先抱住立杆再拆开最后两个扣。拆除第一横杆35、横向斜撑44、剪刀撑组件时,应先拆中间扣件,然后托住中间,再解端头扣。所有连墙件45等必须随悬挑梁外脚手架拆除同步下降,严禁先将连墙件45整层或数层拆除后再拆悬挑梁外脚手架,分段拆除高差不应大于2步,如高差大于2步,应增设连墙件45加固。It is not allowed to dismantle the rack separately or to dismantle the rack in two steps at the same time. Do it one step at a time, one shot at a time. When disassembling the outer pole 31 and the inner pole 32, you must first hold the pole and then disassemble the last two buckles. When removing the first cross bar 35, the transverse diagonal brace 44 and the scissor brace assembly, the middle fastener should be removed first, then hold the middle, and then unfasten the end fasteners. All connecting wall parts 45 must be lowered synchronously with the removal of the outer scaffolding of the cantilever beam. It is strictly forbidden to first remove the whole or several layers of the connecting wall parts 45 and then remove the outer scaffolding of the cantilever beam. If the height difference is greater than 2 steps, the connecting wall piece 45 should be added for reinforcement.

拆除后架体的稳定性不被破坏,如附墙杆被拆除前,应加设临时支撑防止变形,拆除各标准节时,应防止失稳。After dismantling, the stability of the frame body will not be damaged. For example, before the wall-attaching rods are dismantled, temporary supports should be added to prevent deformation. When the standard sections are dismantled, instability should be prevented.

当悬挑梁外脚手架拆至下部最后一根立杆时,应先在适当位置搭临时抛撑加固,后拆连墙件45。When the outer scaffolding of the cantilever beam is dismantled to the last pole at the lower part, it should be temporarily reinforced at the appropriate position, and then the connecting wall piece 45 should be dismantled.

拆除过程中,要把同一种部件集中分类堆放,然后使用垂直运输设备运制地面,不得散乱搬运,以免部件变形和受损。During the dismantling process, the same type of parts should be piled up in a centralized manner, and then transported to the ground using vertical transport equipment.

水平悬挑梁10的拆除主要借助塔吊这一有力工具进行辅助拆除。当架体拆到水平悬挑梁10处时,首先将吊环安装在设为工字钢的水平悬挑梁10两端的1/3-1/4处,慢慢提升使吊环牢固、钢丝绳拉紧后,在确保安全可靠的前提下先拆除悬挑端的斜吊钢绳20,再将水平悬挑梁10固定压环钢筋、楔子拆除。The removal of the horizontal cantilever beam 10 is mainly assisted by a tower crane, a powerful tool. When the frame body is disassembled to the horizontal cantilever beam 10, first install the lifting ring at 1/3-1/4 of the two ends of the horizontal cantilever beam 10 set as I-beam, and slowly lift it to make the lifting ring firm and the wire rope tight. After that, under the premise of ensuring safety and reliability, first remove the inclined hanging steel rope 20 at the cantilever end, and then remove the fixed pressure ring reinforcement bars and wedges of the horizontal cantilever beam 10.

本发明悬挑梁外脚手架搭设施工方法技术措施为,利用建筑物的避雷系统,利用主楼外架四角立杆,用A12圆钢连通第一横杆35与建筑物的结构柱中的避雷钢筋,形成避雷网络,并检测接地电阻不大于4Ω。The technical measures of the construction method and technical measures for the erection of the outer scaffolding of the cantilever beam of the present invention are: using the lightning protection system of the building, using the four corner vertical poles of the outer frame of the main building, and using A12 round steel to connect the first cross bar 35 with the lightning protection steel bars in the structural columns of the building, A lightning protection network is formed, and the detection grounding resistance is not greater than 4Ω.

定期检查悬挑梁外脚手架,发现问题和隐患,在施工作业前及时维修加固,以达到坚固稳定,确保施工安全。Regularly inspect the outer scaffolding of the cantilever beams, find problems and hidden dangers, and repair and reinforce them in time before construction operations to achieve firmness and stability and ensure construction safety.

悬挑梁外脚手架严禁钢竹、钢木混搭,禁止扣件、绳索、铁丝、竹篾、塑料篾混用。The scaffolding outside the cantilever beam is strictly prohibited from mixing steel, bamboo, steel and wood, and the mixing of fasteners, ropes, iron wires, bamboo strips, and plastic strips is prohibited.

严禁脚手板42存在探头板,铺设脚手板42以及多层作业时,应尽量使施工荷载内、外传递平衡。It is strictly forbidden to have probe plates on the scaffolding board 42. When laying the scaffolding board 42 and multi-layer operations, the internal and external transmission of the construction load should be balanced as much as possible.

保证悬挑梁外脚手架体的整体性,不得与井架、升降机一并拉结,不得截断架体。To ensure the integrity of the outer scaffolding body of the cantilever beam, it shall not be tied together with the derrick and the elevator, and the frame body shall not be cut off.

严格控制施工荷载,脚手板42不得集中堆料施荷,施工荷载不得大于3kN/m2,确保较大安全储备。Strictly control the construction load, the scaffolding board 42 shall not be piled up and the construction load shall not be greater than 3kN/m2, so as to ensure a large safety reserve.

施工时只允许一层结构及装修同时作业,或装修施工时同时作业层数不超过二层。During construction, only one-story structure and decoration are allowed to operate at the same time, or the number of simultaneous operation layers during decoration construction shall not exceed two.

当作业层高出其下连墙件45的3.6m以上、且其上尚无连墙件45时,应采取适当的临时撑拉措施。When the working floor is more than 3.6m higher than the lower connecting wall piece 45 and there is no connecting wall piece 45 on it, appropriate temporary stretching measures should be taken.

各作业层之间设置可靠的防护栅栏,防止坠落物体伤人。Reliable protective fences are set between each working layer to prevent falling objects from hurting people.

同一幢建筑的悬挑梁外脚手架搭设的基础标高起始不相同时,必须在较高的标高位置的第一道水平杆进行闭合交圈设置。When the foundation elevations of the cantilever beams and the outer scaffolding of the same building are not the same, the first horizontal pole at the higher elevation must be set in a closed circle.

本发明悬挑梁外脚手架拆除安全技术措施为,拆架前,全面检查拟拆悬挑梁外脚手架,根据检查结果,拟订出作业计划。The safety technical measures for the dismantling of the outer scaffolding of the cantilever beam of the present invention are as follows: before the dismantling, the outer scaffolding of the cantilever beam to be dismantled is comprehensively inspected, and an operation plan is drawn up according to the inspection results.

拆架时应划分作业区,周围设绳绑围栏或竖立警戒标志,地面应设专人指挥,禁止非作业人员进入。When dismantling the frame, the work area should be divided, and ropes should be tied around the fence or a warning sign should be erected. The ground should be commanded by a special person, and non-operating personnel should not be allowed to enter.

拆立杆时,必需安排两个工人合作拆除一根立杆,要先抱住立杆再拆开最后两个扣件,拆除第一横杆35、横向斜撑44、剪力撑组件37时,应先拆除中间扣件,然后托住中间,再解端头扣件。When dismantling the pole, it is necessary to arrange two workers to cooperate to dismantle a pole. First, hold the pole and then disassemble the last two fasteners. The middle fastener should be removed first, then hold the middle, and then unfasten the end fasteners.

连墙件45应随拆除进度逐层拆除,拆抛撑时,应用临时撑支住,然后才能拆除。The connecting wall piece 45 shall be removed layer by layer with the progress of removal, and shall be supported by temporary supports before being removed.

通过采用工字钢的水平悬挑梁10,增强了外脚手架基底的稳固性;设置斜吊钢绳20实现了增加水平悬挑梁10的强度;通过设置第一横杆35位于第二横杆36的上方加强了整个架体的强度;沿外立杆31的外侧立面的全宽和全高且由底至顶连续设置剪力撑组件37,进一步加强了架体的强度;采用本发明的搭设施工方法实现了提高施工速度,增强施工的质量的效果。By using the horizontal cantilever beam 10 of I-beam, the stability of the outer scaffold base is enhanced; the installation of the inclined hanging steel rope 20 can increase the strength of the horizontal cantilever beam 10; The upper part of 36 strengthens the strength of the entire frame body; along the full width and height of the outer elevation of the outer vertical rod 31 and from the bottom to the top, the shear brace assembly 37 is continuously arranged to further strengthen the strength of the frame body; The construction method has achieved the effect of improving the construction speed and enhancing the quality of construction.

本发明悬挑结构脚手架替代了高层建筑物从地面搭设施工,解决了满堂脚手架耗材大,安拆时间长、耗时长、成本高、安拆困难、危险性高、材料投入较大等缺陷。与传统做法的悬挑架的斜拉绳“预埋环”对比,即省工又可多次周转利用,可随时调节拉杆长短以确保架体的稳定性,工字钢可重复利用。本发明为解决多个超长悬挑结构施工问题,设计了悬挑长度达3.6m,锚固在主体结构的工字钢悬挑架体平台。本发明为解决悬挑宽度不一的屋檐结构,选择合理可重复利用、自由组合成多种宽度的工字刚架体结构。本发明为解决悬挑结构高度的多样化,选用了合适的架体上拉或下撑方式,提高支撑架体的适用性,安全性。The scaffold of the cantilever structure of the invention replaces the construction of high-rise buildings from the ground, and solves the defects of large consumables, long installation and disassembly time, long time, high cost, difficult installation and disassembly, high risk, and large material investment. Compared with the "pre-embedded ring" of the cable-stayed rope of the traditional cantilever frame, it saves labor and can be used multiple times. The length of the tie rod can be adjusted at any time to ensure the stability of the frame body, and the I-beam can be reused. In order to solve the construction problems of a plurality of super-long cantilever structures, the invention designs an I-beam cantilever frame platform with a cantilever length of 3.6 m and anchored on the main structure. In order to solve the eaves structure with different cantilever widths, the present invention selects an I-shaped rigid frame body structure which can be reasonably reused and freely combined into various widths. In order to solve the diversification of the height of the cantilevered structure, the present invention selects a suitable way of pulling up or supporting the frame body so as to improve the applicability and safety of the supporting frame body.

本文中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实例的说明只是用于帮助理解本发明的方法及其核心思想。以上仅是本发明的优选实施方式,应当指出,由于文字表达的有限性,而客观上存在无限的具体结构,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进、润饰或变化,也可以将上述技术特征以适当的方式进行组合;这些改进润饰、变化或组合,或未经改进将发明的构思和技术方案直接应用于其它场合的,均应视为本发明的保护范围。Specific examples are used herein to illustrate the principles and implementations of the present invention, and the descriptions of the above examples are only used to help understand the method and the core idea of the present invention. The above are only the preferred embodiments of the present invention. It should be pointed out that, due to the limitation of written expressions, there are objectively infinite specific structures. For those of ordinary skill in the art, without departing from the principles of the present invention, Several improvements, modifications or changes can also be made, and the above-mentioned technical features can also be combined in an appropriate manner; these improvements, modifications, changes or combinations, or the concept and technical solutions of the invention are directly applied to other occasions without improvement, All should be regarded as the protection scope of the present invention.

Claims (10)

1.高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于,包括如下步骤:1. the construction method of the large-span cantilever structure construction I-beam scaffolding of high-rise cluster project, is characterized in that, comprises the steps: 1)设置多个水平悬挑梁:水平悬挑梁采用工字钢,水平悬挑梁远离楼体外墙的一端连接斜吊钢绳,斜吊钢绳的另一端位于水平悬挑梁的上方且与楼体外墙连接;1) Set up multiple horizontal cantilever beams: I-beams are used for horizontal cantilever beams, and one end of the horizontal cantilever beam far from the outer wall of the building is connected to the oblique hanging steel rope, and the other end of the oblique hanging steel rope is located above the horizontal cantilever beam and connected to the outer wall of the building; 2)设置多组立杆组件:立杆组件包括平行且间隔设置的外立杆以及内立杆,内立杆与楼体外墙相对设置,外立杆和内立杆通过横向扫地杆连接,多组立杆组件通过纵向扫地杆连接,立杆组件设于水平悬挑梁上,立杆组件的数量与水平悬挑梁的数量相同且一对一设置;2) Set up multiple sets of vertical pole components: the vertical pole components include external vertical poles and internal vertical poles arranged in parallel and at intervals, the internal vertical poles are arranged opposite to the outer wall of the building, and the external vertical poles and the internal vertical poles are connected by horizontal sweeping poles. The vertical pole components are connected by longitudinal sweeping poles, the vertical pole components are arranged on the horizontal cantilever beams, and the number of vertical pole components is the same as that of the horizontal cantilever beams and is arranged one-to-one; 3)设置第一横杆和第二横杆:在立杆组件的高度方向间隔的设置多个第一横杆和多个第二横杆,第一横杆的两端分别与外立杆和内立杆连接,第二横杆连接于外立杆上,第二横杆的端部位于第一横杆和外立杆的交接处,第一横杆设于第二横杆的上方;3) Setting the first crossbar and the second crossbar: a plurality of first crossbars and a plurality of second crossbars are arranged at intervals in the height direction of the vertical rod assembly, and the two ends of the first crossbar are respectively connected with the outer vertical rod and the outer vertical rod. The inner vertical bar is connected, the second horizontal bar is connected to the outer vertical bar, the end of the second horizontal bar is located at the junction of the first horizontal bar and the outer vertical bar, and the first horizontal bar is arranged above the second horizontal bar; 4)设置剪力撑组件:外立杆的外侧立面上连接有剪力撑组件,沿外立杆的外侧立面的全宽和全高且由底至顶连续设置垂直剪力撑组件;4) Set up shear brace components: shear brace components are connected to the outer elevation of the outer pole, and vertical shear brace components are continuously arranged along the full width and height of the outer elevation of the outer pole and from the bottom to the top; 5)连墙施工:立杆组件与楼体外墙预埋的连墙件拉结固定连接;5) Connecting wall construction: The vertical rod components are tied and fixedly connected with the connecting wall parts embedded in the outer wall of the building; 6)卸荷施工:在斜吊钢绳与楼体外墙连接的强度达到设计强度的100%后,卸载斜吊钢绳;6) Unloading construction: After the strength of the connection between the inclined hanging steel rope and the outer wall of the building reaches 100% of the design strength, unload the inclined hanging steel rope; 7)设置脚手板和挡脚板:内立杆上连接有挡脚板,挡脚板位于内立杆与楼体外墙之间,内立杆和外立杆之间铺设有脚手板,脚手板设于第一横杆上;7) Set up the scaffolding board and the toeboard: the inner pole is connected with a toeboard, the toeboard is located between the inner pole and the outer wall of the building, and a scaffolding board is laid between the inner pole and the outer pole, and the scaffolding board is set on the first floor. on a crossbar; 8)设置防护栏:外立杆上固设防护栏杆,外立杆的外侧立面满挂密目式安全网;8) Set up guardrails: guardrails are fixed on the outer poles, and the outer facades of the outer poles are covered with dense mesh safety nets; 9)楼体施工完成后,拆除悬挑梁外脚手架:先拆脚手板、挡脚板和剪力撑组件,而后拆第一横杆、第二横杆和立杆组件。9) After the construction of the building is completed, remove the outer scaffolding of the cantilever beam: first remove the scaffolding board, toe board and shear brace components, and then remove the first cross bar, second cross bar and vertical bar components. 2.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤1)中,水平悬挑梁的外挑长度为1300mm、锚固长度为2000mm时,采用20a号工字钢。2. the construction method of high-rise cluster project large-span cantilever structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 1), when the overhang length of horizontal cantilever beam is 1300mm, the anchoring length is 2000mm , using 20a I-beam. 3.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤1)中,水平悬挑梁的外挑长度为2000mm、锚固长度为3000mm时,采用25a号工字钢。3. the construction method of high-rise cluster project large-span cantilever structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 1), when the overhang length of horizontal cantilever beam is 2000mm, the anchoring length is 3000mm , using 25a I-beam. 4.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤2)中,控制各内立杆和各外立杆的垂直偏差为≤100mm。4. the construction method of high-rise cluster project large-span cantilevered structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 2), control the vertical deviation of each inner pole and each outer pole to be ≤ 100mm . 5.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤3)中,第一横杆的两端分别远离内立杆和外立杆伸长长度为150mm。5. the construction method of high-rise cluster project large-span cantilevered structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 3), the two ends of the first crossbar are respectively away from the inner pole and the outer pole The elongation length is 150mm. 6.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤4)中,剪力撑组件搭设的角度为45°~60°。6. The method for constructing I-beam scaffolding with a large-span cantilevered structure of a high-rise cluster project according to claim 1, characterized in that: in step 4), the angle at which the shear brace assembly is erected is 45° to 60°. 7.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤4)中,设置完成剪力撑组件后,在悬挑梁外脚手架的两端开口处设置横向斜撑,横向斜撑在同一节间,由底至顶呈之字型连续布设。7. the construction method of high-rise cluster project large-span cantilevered structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 4), after setting and completing the shear brace assembly, in two parts of the cantilever beam outer scaffolding. Horizontal diagonal bracing is arranged at the end opening, and the horizontal diagonal bracing is arranged continuously in a zigzag pattern from bottom to top. 8.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤5)中,立杆组件与楼体外墙预埋的连墙件拉结的拉结点设置在第一横杆和第二横杆接点的300mm范围内。8. the construction method of high-rise cluster project large-span cantilevered structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 5), vertical rod assembly and the pre-buried connecting wall piece of building outer wall are tied together. The tie point is set within 300mm of the junction of the first crossbar and the second crossbar. 9.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤7)中,挡脚板为冲压钢板,挡脚板的高度为180mm。9. The construction method of the large-span cantilevered structure construction I-beam scaffolding of high-rise cluster project according to claim 1, is characterized in that: in step 7), the toe plate is a stamped steel plate, and the height of the toe plate is 180mm. 10.根据权利要求1所述的高层集群项目大跨度悬挑结构施工工字钢脚手架的工法,其特征在于:步骤2)中,在水平悬挑梁上焊接外径为25mm的定位钢筋,立杆组件套座在定位钢筋外。10. the construction method of high-rise cluster project large-span cantilevered structure construction I-beam scaffolding according to claim 1, is characterized in that: in step 2), welding on the horizontal cantilever beam is the positioning steel bar with an outer diameter of 25mm, vertical The rod assembly is seated outside the positioning reinforcement.
CN202210097895.XA 2022-01-27 2022-01-27 Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project Pending CN114412152A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210097895.XA CN114412152A (en) 2022-01-27 2022-01-27 Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210097895.XA CN114412152A (en) 2022-01-27 2022-01-27 Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project

Publications (1)

Publication Number Publication Date
CN114412152A true CN114412152A (en) 2022-04-29

Family

ID=81279274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210097895.XA Pending CN114412152A (en) 2022-01-27 2022-01-27 Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project

Country Status (1)

Country Link
CN (1) CN114412152A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114991460A (en) * 2022-07-07 2022-09-02 中建二局第三建筑工程有限公司 Truss track overhanging I-steel installation method
CN115977373A (en) * 2022-12-27 2023-04-18 上海建工五建集团有限公司 Enclosure structure and construction method of a ring-type scaffolding

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11190126A (en) * 1997-12-26 1999-07-13 Taisei Corp Scaffolding brackets for wall tethering on scaffolds
CN105971274A (en) * 2016-06-13 2016-09-28 中国建筑第二工程局有限公司 Cantilever support frame formwork system and construction method thereof
CN109629810A (en) * 2018-12-29 2019-04-16 杭州江润科技有限公司 Closed builder's jack system and construction method
CN110952763A (en) * 2019-11-21 2020-04-03 成都建工第二建筑工程有限公司 Construction method of externally-hung type externally-hung overhanging scaffold

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11190126A (en) * 1997-12-26 1999-07-13 Taisei Corp Scaffolding brackets for wall tethering on scaffolds
CN105971274A (en) * 2016-06-13 2016-09-28 中国建筑第二工程局有限公司 Cantilever support frame formwork system and construction method thereof
CN109629810A (en) * 2018-12-29 2019-04-16 杭州江润科技有限公司 Closed builder's jack system and construction method
CN110952763A (en) * 2019-11-21 2020-04-03 成都建工第二建筑工程有限公司 Construction method of externally-hung type externally-hung overhanging scaffold

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蓝媚,张保志,叶茂: "悬挑外脚手架在高层建筑中的设计与施工", 广东土木与建筑, vol. 27, no. 10, 15 October 2020 (2020-10-15), pages 65 - 68 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114991460A (en) * 2022-07-07 2022-09-02 中建二局第三建筑工程有限公司 Truss track overhanging I-steel installation method
CN115977373A (en) * 2022-12-27 2023-04-18 上海建工五建集团有限公司 Enclosure structure and construction method of a ring-type scaffolding

Similar Documents

Publication Publication Date Title
CN103452311B (en) A kind of erection method of shaped steel suspended structural support frame
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN110952763A (en) Construction method of externally-hung type externally-hung overhanging scaffold
CN113513160B (en) Construction method of basement high and large formwork support system
CN111779248B (en) High formwork system and construction method thereof
CN114412152A (en) Construction method for constructing I-steel scaffold by large-span overhanging structure of high-rise cluster project
CN111576832A (en) Construction system and construction method of cantilever multi-bent
CN112252698A (en) Super high-rise large cantilever steel truss construction platform
CN105839907A (en) Suspension type steel platform scaffold foundation and method for mounting same
CN111005547B (en) Construction method of outer scaffold of two-way bending and twisting staggered floor elevation
CN116696055A (en) Construction decoration method for cantilever structure of flat roof framework layer
CN115627912A (en) Construction method of assembled externally-mounted flower basket type overhanging scaffold
CN214696763U (en) Super high-rise large cantilever steel truss construction platform
CN116537534A (en) Construction method of high and large formwork engineering supporting system
CN214834781U (en) Supporting vertical pipe structure in multi-stair-section stair formwork supporting system
CN114775979A (en) Assembly operation frame device for safety production training
CN213174700U (en) Building block type splicing operation frame
CN111677259B (en) High-rise Bailey truss cantilever construction method
CN115095118A (en) Method for constructing coke quenching tower by suspended integrally-installed support
CN111608377B (en) Comprehensive construction method for building overhanging scaffold
CN111962850A (en) Construction method of overhanging scaffold
CN221664328U (en) Edge protection device suitable for steel structure system steel bar truss building carrier plate
CN110593411B (en) Construction method of high-rise high-altitude suspended large-span beam
CN222375922U (en) Used for the construction support frame of reinforced concrete lower hanging plate and upper flap plate at the edge of steel structure
CN219931554U (en) Cantilever steel structure construction platform with formwork system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220429