CN116537534A - Construction method of high and large formwork engineering supporting system - Google Patents
Construction method of high and large formwork engineering supporting system Download PDFInfo
- Publication number
- CN116537534A CN116537534A CN202310476882.8A CN202310476882A CN116537534A CN 116537534 A CN116537534 A CN 116537534A CN 202310476882 A CN202310476882 A CN 202310476882A CN 116537534 A CN116537534 A CN 116537534A
- Authority
- CN
- China
- Prior art keywords
- formwork
- column
- vertical
- support
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明涉及建筑施工技术领域,尤其涉及一种高大模板工程支撑系统施工方法,包括以下施工工序:模板支架搭设→墙、柱钢筋绑扎→墙、柱模板安装→梁、板模板安装→梁、板模板加固→模板安全检查→墙、柱混凝土浇筑→梁、板钢筋绑扎→梁、板混凝土浇筑及养护→模板拆除。采用本发明的施工方法搭建的支撑体系支撑更稳定,采用盘扣式支架搭设更快捷,且拆装容易,便于材料的周转使用,同时最大化保证支撑体系的牢固和人员的施工安全,最终提高建筑的施工质量。
The invention relates to the technical field of building construction, in particular to a construction method for a tall formwork engineering support system, which includes the following construction steps: formwork bracket erection → wall and column reinforcement binding → wall and column formwork installation → beam and slab formwork installation → beam and slab Formwork reinforcement → formwork safety inspection → wall and column concrete pouring → beam and slab reinforcement binding → beam and slab concrete pouring and maintenance → formwork removal. The support system built by the construction method of the present invention is more stable in support, and the use of the buckle-type support is faster to set up, and it is easy to disassemble and assemble, which is convenient for the turnover and use of materials. Construction quality of buildings.
Description
技术领域technical field
本发明涉及建筑施工技术领域,尤其涉及一种高大模板工程支撑系统施工方法。The invention relates to the technical field of building construction, in particular to a construction method for a tall formwork engineering support system.
背景技术Background technique
建筑模板是一种临时性支护结构,按设计要求制作,使混凝土结构、构件按规定的位置、几何尺寸成形,保持其正确位置,并承受建筑模板自重及作用在其上的外部荷载。进行模板工程的目的,是保证混凝土工程质量与施工安全、加快施工进度和降低工程成本。现浇混凝土结构工程施工用的建筑模板结构,主要由面板、支撑结构和连接件三部分组成。面板是直接接触新浇混凝土的承力板;支撑结构则是支承面板、混凝土和施工荷载的临时结构,保证建筑模板结构牢固地组合,做到不变形、不破坏;连接件是将面板与支撑结构连接成整体的配件The building formwork is a temporary support structure, which is manufactured according to the design requirements, so that the concrete structure and components are formed according to the specified position and geometric size, maintain their correct position, and bear the self-weight of the building formwork and the external load acting on it. The purpose of formwork engineering is to ensure the quality of concrete engineering and construction safety, speed up the construction progress and reduce engineering costs. The building formwork structure used in the construction of cast-in-place concrete structures is mainly composed of three parts: panels, support structures and connectors. The panel is the load-bearing slab that directly contacts the freshly poured concrete; the support structure is a temporary structure that supports the panel, concrete and construction loads, ensuring that the building formwork structure is firmly combined without deformation or damage; the connector is the connection between the panel and the support Fittings that join the structure into a whole
随着国民经济的快速发展和人民群众日益增长的物质文化生活需要,我国工程建设的规模不断扩大,体型亦不断增大和复杂,特别是一些公用设施要求的大空间、大跨度、新奇造型等,高大模板支撑系统在建筑施工领域的使用越来越广泛和频繁。水平混凝土构件模板支撑体系高度超过8m或跨度超过18m,施工总荷载大于15KN/㎡,或集中线荷载大于20KN/m的模板支撑体系均属于高大模板工程,实际施工中,高大模板支撑系统具有荷载大、高度高、多样性、复杂性及高危性等特点,过去几年发生的坍塌事故大多是由于在荷载作用下产生过大的变形或荷载,进而导致高大模板支撑体系失稳,导致建筑坍塌,严重影响着大型建筑的施工安全,因此,高大模板支撑系统的稳定性对工程建设的成功与否起到至关重要的作用。With the rapid development of the national economy and the increasing material and cultural needs of the people, the scale of my country's engineering construction has continued to expand, and its shape has also continued to increase and become more complex, especially for large spaces, large spans, and novel shapes required by some public facilities. Tall formwork support systems are used more and more widely and frequently in the field of building construction. The formwork support system of horizontal concrete members with a height of more than 8m or a span of more than 18m, a total construction load greater than 15KN/㎡, or a formwork support system with a concentrated line load greater than 20KN/m belongs to the tall formwork project. In actual construction, the tall formwork support system has load Large, high, diverse, complex, and high-risk. Most of the collapse accidents that occurred in the past few years were due to excessive deformation or load under load, which led to the instability of the tall formwork support system and the collapse of the building. , which seriously affects the construction safety of large buildings. Therefore, the stability of the tall formwork support system plays a vital role in the success of the project construction.
发明内容Contents of the invention
鉴于此,本发明的目的在于提供一种高大模板工程支撑系统施工方法,在遵循装拆方便、搭设灵活的原则下,保证整个支撑系统的稳定性,提高建筑的施工质量,保证施工安全。In view of this, the object of the present invention is to provide a construction method for a tall formwork engineering support system, which can ensure the stability of the entire support system, improve the construction quality of the building, and ensure construction safety under the principles of convenient assembly and disassembly and flexible erection.
为实现上述目的,本发明所采用的技术方案是:To achieve the above object, the technical solution adopted in the present invention is:
一种高大模板工程支撑系统施工方法,包括以下施工工序:A construction method for a tall formwork engineering support system, comprising the following construction procedures:
模板支架搭设→墙、柱钢筋绑扎→墙、柱模板安装→梁、板模板安装→梁、板模板加固→模板安全检查→墙、柱混凝土浇筑→梁、板钢筋绑扎→梁板混凝土浇筑及养护→模板拆除;Erection of formwork support→wall and column reinforcement binding→wall and column formwork installation→beam and slab formwork installation→beam and slab formwork reinforcement→formwork safety inspection→wall and column concrete pouring→beam and slab reinforcement binding→beam and slab concrete pouring and maintenance → Formwork removal;
所述模板支架为盘扣支架,搭设流程包括:放线定位→按定位放置可调底座→在可调底座上放置标准基座→在标准基座上安装扫地横杆→用钢卷尺和线绳将架体调直→用水准仪和线绳将架体调平→安装二步及以上立杆和横杆→安装斜拉杆→直至封顶安装端横杆和斜杆→安装U型顶托和主次楞;The formwork support is a buckle support, and the erection process includes: setting out wire positioning → placing the adjustable base according to the positioning → placing a standard base on the adjustable base → installing a sweeping bar on the standard base → using a steel tape measure and wire rope Straighten the frame body → level the frame body with a level and a wire rope → install the two-step and above vertical bar and cross bar → install the diagonal stay bar → until the top is installed, the cross bar and the inclined bar → install the U-shaped jacking and the primary and secondary Leng;
梁模板安装包括:弹梁轴线并复核→搭支模架→调整托梁→摆主梁→安放梁底模并固定→梁底起拱→扎梁筋→安侧模→侧模拉线支撑→复核梁模尺寸、标高、位置→与相邻模板连固;Beam formwork installation includes: spring beam axis and review→build formwork frame→adjust joist beam→swing main beam→place beam bottom formwork and fix it→beam bottom arching→beam reinforcement→install side formwork→side formstay cable support→recheck Beam formwork size, elevation, position → fasten with adjacent formwork;
柱板模板安装包括:检查底盘控制线→验收柱钢筋→合模→调整及校正→加固柱箍→拉通长线→自检整修;The installation of the column slab formwork includes: checking the chassis control line→checking the column reinforcement→closing the mold→adjusting and correcting→reinforcing the column hoop→pull through the long line→self-inspection and repair;
墙模板安装包括:检查墙位置墨线→安装就位→侧墙模板→钻对拉螺杆孔并装上穿墙螺杆→安装另一侧墙模板→钻对拉螺杆孔并对上穿墙螺杆→检查或调整竖向内楞方管间距→装水平双钢管外楞、临时固定穿墙螺杆→检查、调整模板垂直度并安装支撑→紧固穿墙螺杆螺帽→安装预留洞洞侧边模板。Wall formwork installation includes: check the position of the ink line on the wall → install it in place → side wall formwork → drill the opposite pull screw hole and install the through wall screw → install the other side wall formwork → drill the opposite pull screw hole and align the upper through wall screw → check Or adjust the vertical inner corrugated square tube spacing → install horizontal double steel pipe outer corrugated, temporarily fix the wall-through screw → check and adjust the verticality of the formwork and install the support → fasten the wall-through screw nut → install the side formwork with reserved holes.
进一步的,盘扣支架在安装时,先对可调底座进行定位、放样和摆放,然后在可调底座上安装起始杆并在起始杆上搭设首层水平横杆,并在首层水平横杆与起始杆的连接部位处安装首层立杆,之后在首层立杆的端部安装第二层水平横杆,然后在两层水平横杆之间安装首层竖向斜拉杆;按照上述顺序依次进行搭设,直至达到搭设高度后,在顶部的立杆端部安装顶托;每层竖向斜拉杆的安装方向相同。Further, when installing the pan buckle support, firstly position, stake out and place the adjustable base, then install the starting bar on the adjustable base and set up the first layer of horizontal bars on the starting bar, and place the first layer on the first layer Install the first layer of vertical bars at the connection between the horizontal bar and the starting bar, then install the second layer of horizontal bars at the end of the first layer of vertical bars, and then install the first layer of vertical diagonal rods between the two layers of horizontal bars ;Perform erection in sequence according to the above sequence until the erection height is reached, and then install jacking brackets at the ends of the vertical poles on the top; the installation direction of the vertical slanting rods on each layer is the same.
进一步的,在进行梁模板安装时,需要按照设计间距要求整齐铺好带槽矩形方管,然后铺设梁底模,铺设时先与柱头对接好并钉牢,并用方木作立档及立档支撑,用铁制侧模卡勾住梁侧模压脚,之后吊直梁侧模,最后进行固定。Furthermore, when installing the beam formwork, it is necessary to neatly lay out the rectangular square tubes with grooves according to the design spacing requirements, and then lay the bottom formwork of the beam. When laying, it should be butted with the column head and nailed firmly, and the square wood should be used as the stand and stand For support, hook the beam side formwork presser foot with iron side form clamps, then hang the beam side formwork straight, and finally fix it.
进一步的,梁跨度大于4米时,跨中梁底处进行起拱,主次梁交接时,先主梁起拱,后次梁起拱,起拱高度为梁跨度的1/1000~3/1000,在梁底模中间加一排立杆与高支模排架连接。Further, when the span of the beam is greater than 4 meters, the bottom of the mid-span beam is arched. When the primary and secondary beams are handed over, the main beam is arched first, and the secondary beam is arched. The arching height is 1/1000~3/ of the beam span 1000, add a row of vertical rods in the middle of the bottom formwork of the beam to connect with the high support formwork.
进一步的,梁侧模的上口设有纵向的通长托木,下口设置有纵向的通长夹木,通长托木与通长夹木之间设有竖向立档。Further, the upper opening of the beam side form is provided with a longitudinal full-length backer, the lower opening is provided with a longitudinal full-length clip, and a vertical stand is provided between the full-length backer and the full-length clip.
进一步的,在两个梁侧模处的两根立杆之间连接双槽钢托梁,双槽钢托梁由两根槽钢相对布置并采用高强螺栓连接组成,双槽钢托梁的上下两侧均设置有立杆圆盘,立杆圆盘与梁侧模处的立杆对应连接并与双槽钢托梁在上下方向上挡止配合;双槽钢托梁上于梁底模的位置设有至少两个生根件,生根件上设有可调上托,可调上托用于支撑梁下水平杆。Further, double-channel steel joists are connected between the two vertical poles at the side forms of the two beams. The double-channel steel joists are arranged opposite to each other and connected by high-strength bolts. The upper and lower sides of the double-channel steel joists Both sides are equipped with upright discs, which are connected to the uprights at the beam side molds and matched with the double-channel steel joists in the up and down direction; There are at least two rooting parts, and the rooting parts are provided with an adjustable upper support, which is used to support the lower horizontal bar of the beam.
进一步的,位于梁侧模的同一侧的与对应双槽钢托梁连接的立杆顶部共同连接一根通长顶托。Further, the tops of the vertical poles located on the same side of the beam side form and connected with the corresponding double-channel steel joists are jointly connected with a long jacking bracket.
进一步的,柱模板在安装时,柱模竖向次楞布置应贯穿整根柱长,在梁柱交接处不断开;柱模板的第一道柱箍离柱底不小于150mm,最下侧的两道柱箍的间距不小于500mm,在设置穿柱对拉螺栓时,上下相邻两根对拉螺栓的间距与相邻两道柱箍之间的间距相同,且对拉螺栓的数量与柱箍的数量相同。Further, when the column formwork is installed, the vertical secondary flute layout of the column formwork should run through the entire length of the column without breaking at the junction of beams and columns; the first column hoop of the column formwork is not less than 150mm from the bottom of the column, and the bottom The distance between the two column hoops is not less than 500mm. When setting the bolts that pass through the column, the distance between the upper and lower adjacent two opposite tension bolts is the same as the distance between the two adjacent column hoops, and the number of the opposite tension bolts is the same as that of the column. The number of hoops is the same.
进一步的,在混凝土浇筑施工前,在每个施工段上均设置多个检测点,用于检测模板支架的沉降和水平位移。Further, before the concrete pouring construction, multiple detection points are set on each construction section to detect the settlement and horizontal displacement of the formwork support.
本发明的有益效果是:The beneficial effects of the present invention are:
采用本发明的施工方法搭建的支撑体系支撑更稳定,采用盘扣式支架搭设更快捷,且拆装容易,便于材料的周转使用;而且支撑体系中的底座高度能够调节,能够保证对应层的杆件能够实现稳定的连接,支撑体系中设有多个监测点监测模板支架的变形、沉降和水平位移,从而便于人员实时进行监控并作出预警,最大化保证支撑体系的牢固和人员的施工安全,最终提高建筑的施工质量。The support system built by the construction method of the present invention has more stable support, and the use of the buckle-type bracket is faster to set up, and it is easy to disassemble and assemble, which is convenient for the turnover and use of materials; moreover, the height of the base in the support system can be adjusted to ensure that the poles of the corresponding layer The parts can be connected stably. There are multiple monitoring points in the support system to monitor the deformation, settlement and horizontal displacement of the formwork support, so that it is convenient for personnel to monitor and give early warning in real time, and to ensure the firmness of the support system and the construction safety of personnel to the greatest extent. Ultimately improving the construction quality of the building.
附图说明Description of drawings
图1是本发明的高大模板工程支撑系统施工方法中柱、剪力墙临空面模板安装示意图;Fig. 1 is the installation schematic diagram of column and shear wall free surface formwork in the tall formwork engineering support system construction method of the present invention;
图2是本发明的高大模板工程支撑系统施工方法中剪力墙模板支撑图;Fig. 2 is a shear wall formwork support figure in the tall formwork engineering support system construction method of the present invention;
图3是本发明的高大模板工程支撑系统施工方法中梁模板安装示意图;Fig. 3 is a schematic diagram of beam formwork installation in the construction method of the tall formwork engineering support system of the present invention;
图4是本发明的高大模板工程支撑系统施工方法中边跨梁模板的安装示意图;Fig. 4 is the installation schematic diagram of the side-span beam formwork in the construction method of the tall formwork engineering support system of the present invention;
图5是本发明的高大模板工程支撑系统施工方法中边跨梁模板工具式立柱支撑安装示意图;Fig. 5 is a schematic diagram of installation of side-span beam formwork tool type column support in the construction method of tall formwork engineering support system of the present invention;
图6为图5中A处细部做法节点大样图;Fig. 6 is a large sample diagram of the detail method node at A place in Fig. 5;
图7为图6中B处节点大样图;Figure 7 is a large sample diagram of the node at B in Figure 6;
图8为本发明的高大模板工程支撑系统施工方法中内墙柱用对拉螺栓示意图;Fig. 8 is a schematic diagram of the pull bolts used for the inner wall column in the construction method of the tall formwork engineering support system of the present invention;
图9为本发明的高大模板工程支撑系统施工方法中外墙柱用对拉螺栓示意图;Fig. 9 is a schematic diagram of the pull bolts used for the outer wall column in the construction method of the tall formwork engineering support system of the present invention;
图10是本发明的高大模板工程支撑系统施工方法中双槽钢托梁节点处的示意图;Fig. 10 is a schematic diagram of the node of the double-channel steel joist in the construction method of the tall formwork engineering support system of the present invention;
图11是图10中的双槽钢托梁与立杆圆盘连接的正立面大样图;Fig. 11 is a large sample diagram of the front elevation of the double-channel steel joist in Fig. 10 connected with the vertical pole disk;
图12是图10中的双槽钢托梁与立杆圆盘连接的平面大样图。Fig. 12 is a large plan view of the connection between the double-channel steel joist and the upright disc in Fig. 10 .
具体实施方式Detailed ways
下面结合附图及具体实施方式对本发明作进一步详细描述。The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
本发明的高大模板工程支撑系统施工方法的具体实施例:Specific embodiments of the construction method of the tall formwork engineering support system of the present invention:
本实施例以具体工程实例进行说明。高大模板工程支撑系统施工方法主要包括以下施工工序:This embodiment is described with a specific engineering example. The construction method of the support system of tall formwork engineering mainly includes the following construction procedures:
模板支架搭设→墙、柱钢筋绑扎→墙、柱模板安装→梁、板模板安装→梁、板模板加固→模板安全检查→墙、柱混凝土浇筑→梁、板钢筋绑扎→梁、板混凝土浇筑及养护→模板拆除。Erection of formwork support→wall and column reinforcement binding→wall and column formwork installation→beam and slab formwork installation→beam and slab formwork reinforcement→formwork safety inspection→wall and column concrete pouring→beam and slab reinforcement binding→beam and slab concrete pouring and Maintenance → formwork removal.
具体的,模板支架为盘扣支架,模板支架的高宽比控制在3以内,高宽比大于3的模板支架应采取与既有结构进行刚性连接等抗倾覆措施。对标准步距为1.5m的模板支架,应根据模板支架搭设高度、模板支架型号及立杆轴力设计值进行竖向斜杆布置。在进行模板支架设计时要严格按照规范进行计算操作;搭设时要保证横成向,纵成方,立杆杆身垂直。纵向水平杆平直,横向水平杆平齐,立杆间距、步距、纵距、横距等均要符合规范要求,保持架子整体牢固、稳定、安全、适用、美观。Specifically, the formwork support is a buckle support, the aspect ratio of the formwork support is controlled within 3, and the formwork support with an aspect ratio greater than 3 should take anti-overturning measures such as rigid connection with the existing structure. For the formwork support with a standard step distance of 1.5m, the vertical slanting rod arrangement should be carried out according to the erection height of the formwork support, the model of the formwork support and the design value of the axial force of the vertical pole. When designing the formwork support, the calculation operation must be performed in strict accordance with the specifications; when erecting, it must be ensured that the horizontal orientation, the vertical orientation, and the vertical pole shaft are vertical. The vertical horizontal bars are straight, and the horizontal horizontal bars are even. The distance between the vertical bars, the step distance, the vertical distance, and the horizontal distance must meet the requirements of the specification, so as to keep the whole shelf firm, stable, safe, applicable and beautiful.
水平剪刀撑采用普通钢管扣件式。架体搭设高度在8m及以上时,应在架体顶部、底部及竖向间隔不超过8m分别设置连续水平剪刀撑,剪刀撑的角度45°~60°。剪刀撑接长时应采用搭接,搭接长度不用小于1000mm,并应等距离设置不少于3个旋转扣件,剪刀撑旋转扣件固定在与之相交的水平杆或立杆上,旋转扣件中心线至主节点的距离不宜大于150mm。The horizontal scissor support adopts the ordinary steel pipe fastener type. When the height of the frame body is 8m and above, continuous horizontal scissor braces shall be installed at the top, bottom and vertical interval of no more than 8m respectively, and the angle of the scissor braces shall be 45°~60°. When the scissor brace is long, lap joints should be used. The lap length should not be less than 1000mm, and no less than 3 rotating fasteners should be installed at equal distances. The distance from the centerline of the fastener to the main node should not be greater than 150mm.
另外,每隔2层且不大于10m加设一道安全平网,安全网应符合以下规定:(1)安全网的材质、规格、要求及物理性能、耐火性、阻燃性应满足现行国家标准《安全网》GB5725的规定;(2)安全网搭设应牢固、严密、完整有效,易于拆卸。安全网的模板支架具有足够的强度和稳定性,挂设安全网时选择合适的挂点,避免锋利边角(如销子、花盘等位置);(3)平网的每个系结点的边绳应与模板支架靠紧,边绳的断裂张力不得小于7kN,系绳沿网边均匀分布,间距不得大于750mm;(4)钢结构厂房和框架结构及构筑物在作业层下部应设置安全网,落地式模板支架应采用模板支架,悬挑式平网支撑应采用直接不小于9.3mm的钢丝绳;(5)电梯井内平网网体与井壁的空隙不得大于25mm,安全网拉结应牢固;(6)安全网在贮运中,必须通风、遮光、隔热,同时要避免化学物品的侵蚀,搬运时禁止使用钩子,已使用过的安全网必须经过检查和试验合格后方可使用,超过使用期限的安全网严禁使用。In addition, a safety flat net shall be added every 2 floors and not greater than 10m. The safety net shall meet the following requirements: (1) The material, specifications, requirements and physical properties, fire resistance and flame retardancy of the safety net shall meet the current national standards The provisions of "Safety Net" GB5725; (2) The safety net should be firm, tight, complete and effective, and easy to disassemble. The formwork support of the safety net has sufficient strength and stability. When hanging the safety net, choose a suitable hanging point to avoid sharp corners (such as pins, faceplates, etc.); The side ropes should be close to the formwork support, the breaking tension of the side ropes should not be less than 7kN, and the tethers should be evenly distributed along the edge of the net, and the spacing should not be greater than 750mm; (4) Steel structure workshops, frame structures and structures should be equipped with safety nets at the lower part of the working layer , the floor-standing formwork support should use the formwork support, and the cantilevered flat net support should use a steel wire rope not less than 9.3mm in length; (5) The gap between the flat net body and the shaft wall in the elevator shaft should not be greater than 25mm, and the safety net tie should be firm (6) During storage and transportation, the safety net must be ventilated, shading, and heat-insulated, and at the same time avoid the erosion of chemicals. It is forbidden to use hooks during transportation. The safety net of expiry date is strictly prohibited.
基于上述要求,模板支架的搭设流程为:放线定位→按定位放置可调底座→在可调底座上放置标准基座→在标准基座上安装扫地横杆→用钢卷尺和线绳将架体调直→用水准仪和线绳将架体调平→安装二步及以上立杆和横杆→安装斜拉杆→直至封顶安装端横杆和斜杆→安装U型顶托和主次楞→检查验收。Based on the above requirements, the erection process of the formwork support is: setting out wires and positioning → placing the adjustable base according to the positioning → placing the standard base on the adjustable base → installing the sweeping bar on the standard base → using a steel tape measure and wire rope to fix the frame Straighten the body → level the frame with a level and a wire rope → install the two-step and above vertical bar and cross bar → install the diagonal stay → until the top is installed to install the cross bar and the inclined bar → install the U-shaped top bracket and the primary and secondary corrugations → Inspection and acceptance.
即先放线定位,然后按放线位置准确地确立摆放可调底座的位置,然后将标准基座放入可调底座;再用水平尺或水平仪调整整个基础部分的水平和垂直,挂线调整纵、横排标准基座是否在一条直线上,用钢卷尺检查每个方格的方正;检验合格后再进行上部标准层架体的搭设。在施工中随着架体的升高随时检查和校正架体的垂直度,控制在3‰内,锁销一定要打紧。That is, lay out the line first, then accurately establish the position of the adjustable base according to the position of the line, and then put the standard base into the adjustable base; then adjust the level and vertical of the entire base with a spirit level or spirit level, and hang the line Adjust whether the vertical and horizontal standard bases are in a straight line, and check the squareness of each square with a steel tape measure; after passing the inspection, erect the upper standard shelf body. During the construction, check and correct the verticality of the frame body at any time as the frame body rises, and control it within 3‰, and the lock pin must be tightened.
安装顺序的详细流程为:步骤一:定位、放样、摆放可调底座;步骤二:安放起始杆;步骤三:安放首层水平横杆;步骤四:安装首层立杆;步骤五:安装第二层水平横杆;步骤六:安装首层竖向斜拉杆;步骤七:依步骤五安装第三层横杆;步骤八:按步骤六组搭方式,和第一层相同方向搭接第二层斜杆,若第一层为逆时针方向组装,则第二层以上的斜杆同样需以逆时针方向组装;步骤九:立杆接长安装;步骤十:依次安装达到搭设高度后,安装顶托。The detailed process of the installation sequence is: Step 1: positioning, setting out, and placing the adjustable base; Step 2: placing the starting pole; Step 3: placing the horizontal bar on the first floor; Step 4: installing the vertical pole on the first floor; Step 5: Install the horizontal bar on the second layer; Step 6: Install the vertical slant bars on the first layer; Step 7: Install the horizontal bar on the third layer according to Step 5; Step 8: Lap in the same direction as the first layer according to the method of step 6 If the second layer of slanting rods is assembled in a counterclockwise direction, the slanting rods above the second layer must also be assembled in a counterclockwise direction; Step 9: The vertical rods are extended and installed; Step 10: Install in sequence after reaching the erection height , install the jacking.
模板支架搭设完成后,需在模板支架四周设置施工平台,并在边缘设置临边防护,来防止安全事故发生。搭设形式采用悬挑式施工平台及临边防护,使用盘扣式钢管支架配套的900mm三角架附着于模板支架上使悬挑防护形成一个稳定的结构,且需要保证临边防护高出施工人员作业层不少于1.2m,采用横杆上放置木跳板作为施工平台和施工通道。After the formwork support is erected, it is necessary to set up a construction platform around the formwork support, and set up marginal protection at the edge to prevent safety accidents. The erection form adopts the cantilevered construction platform and the edge protection. The 900mm tripod matched with the buckle-type steel pipe support is attached to the formwork support to form a stable structure for the cantilever protection, and it is necessary to ensure that the edge protection is higher than the construction personnel's work. The floor is not less than 1.2m, and wooden springboards are placed on the crossbars as construction platforms and construction passages.
为保证工人施工过程中上下架体及操作面的安全,特配置盘扣式钢管支架配套施工垂直通道,垂直通道的位置和数量根据工作面相应配置。垂直通道是将钢制成品楼梯挂在架体的横杆上。同时配置配套的楼梯扶手。施工垂直通道可与主架体相连接设置,不能与主架体连接的情况下必须4-6个步距进行抱柱拉结措施。In order to ensure the safety of the upper and lower frames and the operation surface of the workers during the construction process, the buckle-type steel pipe support is specially configured to support the construction of vertical passages, and the position and quantity of the vertical passages are configured according to the working surface. The vertical passage is to hang the steel finished stairs on the cross bar of the frame body. At the same time, it is equipped with matching stair handrails. The construction vertical channel can be connected with the main frame body. If it cannot be connected with the main frame body, 4-6 steps must be taken to hold the column and tie the knot.
盘扣式钢管支架的水平杆的模数为300mm,在施工过程中可能会遇到不满足300mm模数的连接位置,该位置无法通过盘扣式钢管支架配套的水平杆进行连接,需采用钢管扣件将两侧的模板支架连接成一个整体。连接位置位于模板支架的主节点横杆位置,每个主节点均需连接。The modulus of the horizontal bar of the buckle-type steel pipe support is 300mm. During the construction process, it may encounter a connection position that does not meet the modulus of 300mm. This position cannot be connected through the horizontal rod matching the buckle-type steel pipe support, and steel pipes are required. Fasteners connect the formwork supports on both sides into a whole. The connection position is located at the crossbar position of the main node of the template support, and each main node needs to be connected.
在遇到高低跨区域施工时,(1)当地基高差较小时,可利用可调底托的丝杠进行调整,可调底托的丝杆外露长度不大于300mm。(2)当地基高差较大时,可利用立杆1m、0.5m、0.25m节点位差配合可调底座进行调整。使高处架体和低处架体立杆连接盘在同一水平面,高处水平水平杆向低处延长两跨与立杆固定,并保证步距不得大于1.5m。When encountering high-low cross-area construction, (1) When the ground height difference is small, the screw of the adjustable bottom bracket can be used to adjust, and the exposed length of the screw rod of the adjustable bottom bracket is not more than 300mm. (2) When the ground height difference is large, it can be adjusted by using the 1m, 0.5m, 0.25m point difference of the vertical pole and the adjustable base. Make the connection plate of the vertical pole of the high frame body and the low frame body on the same horizontal plane, extend the horizontal horizontal bar of the high position to the lower position by two spans and fix it with the vertical pole, and ensure that the step distance shall not be greater than 1.5m.
当模板支架架体内部需设置与单支水平杆同宽的人行通道时,可间隔抽除第一层水平杆和竖向斜杆形成施工人员进出通道,与通道正交的两侧立杆间应设置竖向斜杆。通道洞口顶部应铺设封闭的防护板,并且两侧应封闭密目网防护。并延通道方向设置灯带用来指示施工人员进出及出现安全事故时及时按照正确方向撤离。When a walkway with the same width as a single horizontal bar needs to be set inside the formwork support frame, the horizontal bars and vertical slanting bars on the first layer can be removed at intervals to form a passageway for construction personnel, and the vertical bars on both sides orthogonal to the passageway Vertical bars should be set. A closed protective plate shall be laid on the top of the passage hole, and dense mesh protection shall be closed on both sides. And along the direction of the channel, a light belt is set to indicate the construction personnel to enter and exit and to evacuate in the correct direction in time when a safety accident occurs.
上述施工工序中,板模板的安装包括:(1)定位放线,根据定位桩点,投放出单体轴线,再由该轴线分尺定出墙线、梁线、渠道线,最后进一步弹出钢管搭设线。(2)架体搭设,包括:放置纵向扫地杆→自角部起依次向两边竖立底立杆,底端与纵向扫地杆扣接固定后、装设横向扫地杆也与立杆固定,每边竖起3~4根立杆后,随即装设第一步纵向平杆和横向平杆、校正立杆垂直和水平杆水平度使其符合要求后,插销连接,形成构架的起始段→按上述要求依次向前搭设,直至第一步支撑架交圈完成→第二步纵向水平杆→第二步横向水平杆,重复上述步骤直至设计标高。(3)核验标高,架体搭设完成后之后,及时核查正误。并由项目部技术人员核验收标高。In the above construction process, the installation of the slab formwork includes: (1) Positioning and setting out, according to the positioning pile points, the single axis is released, and then the axis is divided into wall lines, beam lines, and channel lines, and finally the steel pipe is further ejected Set up the line. (2) The erection of the frame body includes: placing the vertical sweeping rod → erecting the bottom vertical rod to both sides from the corner in turn, after the bottom end is buckled and fixed with the vertical sweeping rod, the horizontal sweeping rod is also fixed with the vertical rod, each side After erecting 3 to 4 vertical poles, install the first step of longitudinal flat poles and horizontal horizontal poles, correct the verticality of the vertical poles and the levelness of the horizontal poles to meet the requirements, and connect them with bolts to form the initial section of the frame→according to the above It is required to build forward in sequence until the first step of the supporting frame is completed → the second step is the vertical horizontal bar → the second step is the horizontal horizontal bar, and the above steps are repeated until the design elevation. (3) Check the elevation and check the correctness in time after the erection of the frame is completed. And the technical personnel of the project department will check the acceptance elevation.
板模安装时,应调整支撑体系的顶托标高,经复查无误后,安装横向主楞,再在横向主楞上铺设纵向次楞,调整横向次楞的位置及间距,最后铺设模板。楼板模板的安装,由四周向中心铺设,模板垂直于次楞方向铺齐,对于模板间的缝隙,用三合板补齐,当跨度≥4m时,按规范或设计要求起拱。板缝要求拼接严密,拼缝整齐。固定在模板上的预埋件和预留洞须安装牢固,位置准确。相邻梁板表面高低差控制在2mm以内,表面平整度控制在5mm以内。浇筑砼时,设置一组砼试块与已浇筑的砼同条件养护,作为拆模的依据。When the formwork is installed, the jacking elevation of the support system should be adjusted. After the review is correct, install the horizontal main flute, then lay the longitudinal secondary flute on the horizontal main flute, adjust the position and spacing of the horizontal secondary flute, and finally lay the formwork. The installation of the floor formwork shall be laid from all sides to the center, and the formwork shall be laid perpendicular to the direction of the secondary corrugation. For the gap between the formwork, it shall be filled with plywood. When the span is ≥ 4m, it shall be arched according to the specification or design requirements. The joints of the boards are required to be tightly spliced and the seams are neat. The embedded parts and reserved holes fixed on the formwork must be firmly installed and positioned accurately. The height difference between adjacent beam and slab surfaces shall be controlled within 2mm, and the surface flatness shall be controlled within 5mm. When pouring concrete, set up a group of concrete test blocks to be cured under the same conditions as the poured concrete, as the basis for removing the formwork.
柱模板的安装包括:检查底盘控制线→验收柱钢筋→合模→调整及校正→加固柱箍→拉通长线→自检整修→验收。先复核已弹出的柱的控制线,待钢筋经隐蔽验收后,可以封柱模,安装前清理干净柱内杂物,安装时要先吊直模板,然后上紧柱箍、穿墙螺杆。在封柱模时,可以将梁柱接头模板一起安装。为了保证混凝土的施工质量,柱箍采用方圆扣搭配£40×40×1.5mm带槽矩形方管使用。The installation of the column formwork includes: checking the chassis control line → checking the column reinforcement → closing the mold → adjusting and correcting → strengthening the column hoop → pulling through the long line → self-inspection and repair → acceptance. First check the control line of the ejected column. After the steel bar is concealed and accepted, the column formwork can be sealed, and the sundries in the column should be cleaned before installation. When sealing the column formwork, the beam-column joint formwork can be installed together. In order to ensure the construction quality of the concrete, the column hoops are used with square and round buckles and £40×40×1.5mm rectangular square pipes with grooves.
梁模板的安装包括:弹梁轴线并复核→搭支模架→调整托梁→摆主梁→安放梁底模并固定→梁底起拱→扎梁筋→安侧模→侧模拉线支撑(梁高加对拉螺栓)→复核梁模尺寸、标高、位置→与相邻模板连固。按设计间距要求整齐铺好40×40×1.5mm带槽矩形方管,随即铺设梁底模,铺设时应先与柱头对接好并钉牢,并用方木作立档及立档支撑,用使用铁制侧模卡勾住侧模压脚,之后吊直侧模,最后固定。另外,当梁跨度大于4米时,跨中梁底处应按规范要求起拱,主次梁交接时,应先主梁起拱,后次梁起拱,起拱高度宜为梁跨度的1/1000~3/1000。为了保证梁不出现下沉变形等质量事故,在大梁底模中间加一排立杆与高支模排架相连接。The installation of the beam formwork includes: springing the axis of the beam and checking it → setting up the formwork → adjusting the joist → placing the main beam → placing the bottom formwork of the beam and fixing it → arching the bottom of the beam → binding the beam reinforcement → installing the side formwork → side formwork support ( Beam height plus tension bolts) → check the size, elevation and position of the beam formwork → connect with the adjacent formwork. Lay 40×40×1.5mm rectangular square pipes with grooves neatly according to the design spacing requirements, and then lay the beam bottom mold. When laying, it should be connected with the column head and nailed firmly. The iron side form clamp hooks the side form presser foot, then hangs the side form straight, and finally fixes it. In addition, when the span of the beam is greater than 4 meters, the bottom of the mid-span beam should be arched according to the requirements of the code. When the primary and secondary beams are handed over, the main beam should be arched first, and the secondary beam should be arched. /1000~3/1000. In order to ensure that there are no quality accidents such as sinking and deformation of the beam, a row of vertical rods are added in the middle of the bottom formwork of the girder to connect with the high-support formwork bent frame.
墙模板的安装包括:检查墙位置墨线→安装就位→侧墙模板→钻对拉螺杆孔并装上穿墙螺杆→安装另一侧墙模板→钻对拉螺杆孔并对上穿墙螺杆→检查(或调整竖向内楞方管间距)→装水平双钢管外楞,临时固定穿墙螺杆→检查、调整模板垂直度,安装支撑→紧固穿墙螺杆螺帽→安装预留洞洞侧边模板→质量检查。The installation of the wall formwork includes: checking the position of the ink line on the wall→installing it in place→side wall formwork→drilling the opposite pull screw holes and installing the through-wall screws→installing the other side wall formwork→drilling the opposite pull screw holes and aligning the through-wall screws→ Check (or adjust the spacing between vertical inner corrugated square tubes) → install horizontal double steel pipes and outer corrugated pipes, temporarily fix the wall-through screw → check and adjust the verticality of the formwork, install the support → fasten the wall-through screw nut → install the side of the reserved hole Edge template → QA.
墙模板在安装时需要满足一下要求:(1)待钢筋绑扎、预埋件管道、预埋件等隐蔽工程验收合格后,方可进行立模。(2)按墙位置线安装就位一侧墙模板,安装临时拉杆或斜撑固定,钻对拉螺杆孔,穿墙螺栓。(3)清扫墙内杂物,再安装就位另一侧模板,钻对拉螺杆孔,对上并穿上对拉螺杆。内外模用15mm厚覆膜胶合板,3型扣件固定整齐,墙底部1/3部分螺杆加双螺帽,水平及竖向每隔45.5cm设置一道螺杆。(4)水构筑物外墙及有防水要求的内隔墙穿墙螺栓中部焊止水片,止水片用50×50×4扁钢钻孔套至螺栓中间,双面满焊,在焊接过程中,要严格控制焊接质量,不得有漏焊和沙眼,保证起到止水作用。墙厚通过螺杆的限位片控制。螺栓孔待拆除后凿除木垫片用防水砂浆抹平。(5)检查、校正模板垂直度。拉通长线,对每轴进行校正,并检查承重架和支撑系统固定是否牢固。墙模板安装完毕,检查一遍对拉螺栓是否紧固,模板拼缝及下口是否严密,办完预检手续。The wall formwork needs to meet the following requirements during installation: (1) The formwork can only be set up after the concealed works such as steel bar binding, embedded pipes, and embedded parts have passed the acceptance. (2) Install the side wall template in place according to the wall position line, install temporary pull rods or diagonal braces, drill holes for pull screw rods, and pass through wall bolts. (3) Clean up the sundries in the wall, then install the formwork on the other side, drill the hole for the pull screw, align and put on the pull screw. The inner and outer molds are made of 15mm thick film-coated plywood, and the type 3 fasteners are fixed neatly. The screw rods on the bottom 1/3 of the wall are equipped with double nuts, and a screw rod is installed every 45.5cm horizontally and vertically. (4) The outer wall of the water structure and the inner partition wall with waterproof requirements are welded with a water-stop sheet in the middle of the wall-penetrating bolt. The water-stop sheet is inserted into the middle of the bolt with a 50×50×4 flat steel drill hole, and the two sides are fully welded. During the welding process In the middle, the welding quality must be strictly controlled, and there must be no leakage of welding and trachoma, so as to ensure the function of water stop. The wall thickness is controlled by the limit plate of the screw. After the bolt holes are removed, the wooden spacers are chiseled and smoothed with waterproof mortar. (5) Check and correct the verticality of the template. Pull through the long wires, correct each axis, and check whether the load-bearing frame and support system are firmly fixed. After the wall formwork is installed, check whether the pull bolts are fastened, whether the joints of the formwork and the lower opening are tight, and complete the pre-inspection procedures.
另外,柱、墙模板施工构造还应符合下列要求:(1)柱模竖向次楞布置应贯穿整根柱长,在梁柱交接处不得断开,交接处梁净高≥600mm时,柱头位置应加设对拉螺栓。方柱四角竖向次楞木应对称对顶。(2)柱模第一道柱箍离柱底不小于150mm,最下两道柱箍的间距不小于500mm,当需设置穿柱对拉螺栓时,对拉螺栓沿柱高度方向的布置应与柱箍等距等量。(3)柱、墙临空面的模板面板与次楞应从楼面起向下延伸200mm,并在内模与楼面梁侧用2mm厚双面胶带封贴,具体如图1所示。再者,墙模第一道主楞离墙底不小于150mm,墙边第一列对拉螺栓离端头不宜>305mm。墙模主次楞、对拉螺栓间距应满足设计计算要求,且竖向次楞不宜>305mm;主楞不宜>455mm;对拉螺栓不宜>455×455mm。上部主体结构外墙柱、及其他有防水要求的墙体,采用三片止水型对拉螺栓,具体如图2所示。In addition, the construction structure of the column and wall formwork should also meet the following requirements: (1) The vertical secondary corrugated layout of the column formwork should run through the entire length of the column, and must not be disconnected at the junction of beams and columns. Add pull bolts. The vertical corrugated wood at the four corners of the square column should be topped symmetrically. (2) The distance between the first column hoop of the column formwork and the bottom of the column is not less than 150mm, and the distance between the bottom two column hoops is not less than 500mm. Column hoop isometric isometric. (3) The formwork panel and secondary flute on the empty side of the column and wall should extend 200mm downward from the floor, and seal the inner mold and the floor beam side with 2mm thick double-sided tape, as shown in Figure 1. Furthermore, the first main groove of the wall formwork should not be less than 150mm away from the bottom of the wall, and the distance between the first row of tension bolts at the side of the wall should not be greater than 305mm from the end. The primary and secondary corrugations and the distance between the tension bolts of the wall formwork shall meet the design calculation requirements, and the vertical secondary corrugation should not be greater than 305mm; the main corrugation should not be greater than 455mm; and the opposite tension bolts should not be greater than 455×455mm. For the outer wall columns of the upper main structure and other walls that require waterproofing, three pieces of water-stop type tension bolts are used, as shown in Figure 2.
梁模板施工构造应符合下列要求:(1)梁侧模上口应设置纵向通长托木,下口应设置纵向通长夹木且不得兼做梁底模主、次楞,托木与夹木间应设置竖向立档,其间距不应>800mm。梁面板的对接处应紧密,面板外侧应加设帮条木。(2)高度>400mm的梁,梁底模应设有主、次楞,不得随意取消次楞木而用纵向主楞木代替。采用传统安装法,次楞木间距应符合设计计算要求,且不宜>350mm;采用次楞平行于梁跨的纵向布置安装法,应符合图3的要求。(3)梁净高≥600mm时,应设置穿梁对拉螺栓,对拉螺栓固定应有两根并列通长的方木或双肢φ48.3×3.5mm钢管作支托,不得直接固定在梁侧面板上,可参考图3。The construction structure of the beam formwork shall meet the following requirements: (1) The upper opening of the beam side formwork shall be provided with a longitudinally long backer, and the lower opening shall be provided with a longitudinally long clip and shall not be used as the main and secondary sides of the bottom formwork of the beam, the backing and the clip. Vertical vertical shelves should be set between the woods, and the distance between them should not be greater than 800mm. The butt joints of beams and panels should be tight, and side bars should be added on the outside of the panels. (2) For beams with a height greater than 400mm, the bottom formwork of the beam shall be provided with main and secondary flute, and the secondary flute shall not be arbitrarily canceled and replaced by longitudinal main flute. If the traditional installation method is used, the spacing of the secondary flute wood should meet the design calculation requirements, and should not be greater than 350mm; if the vertical arrangement installation method of the secondary flute parallel to the beam span is adopted, it should meet the requirements of Figure 3. (3) When the net height of the beam is ≥ 600mm, it should be installed with cross-tension bolts through the beam. The cross-tension bolts should be fixed with two side-by-side square wood or double-leg φ48.3×3.5mm steel pipes as supports, and should not be directly fixed on the side of the beam. panel, refer to Figure 3.
再者,梁、板模板竖向支撑施工构造应符合下列要求:(1)梁模板支架立杆横向布置应对称,其数量、间距应符合设计计算要求,且数量不得<2根。(2)梁、板模板支架的扫地杆距楼地面高度,盘扣式钢管脚手架应不大于200mm。立杆上端包括顶托可调螺杆在内,伸出顶层水平杆长度大于相关规范的规定时,应增设水平杆。(3)有梁结构的梁、板模板支架立杆在水平方向应相互拉接。支撑高度大于3.5m的架体应按满堂架的要求设置竖向和水平剪刀撑。(4)边跨梁模板的横向立杆上方受力点应布置对称、合理。采用可调斜外立杆方式的,立杆上的每道水平拉杆应与结构模板支架的立杆相连接至少3道立杆,采用工具式立柱支撑方式的,应符合图4、图5、图6和图7所示的要求。Furthermore, the vertical support construction structure of the beam and slab formwork shall meet the following requirements: (1) The horizontal arrangement of the vertical poles of the beam formwork support shall be symmetrical, and the number and spacing shall meet the design calculation requirements, and the number shall not be less than 2. (2) The height of the sweeping pole of the beam and slab formwork support from the ground of the building, and the buckle-type steel pipe scaffolding should not be greater than 200mm. The upper end of the vertical pole includes the adjustable screw rod for jacking, and when the length of the horizontal pole on the top layer is longer than the relevant specifications, a horizontal pole should be added. (3) The beams and slab formwork support poles with beam structure should be connected to each other in the horizontal direction. For frames with a support height greater than 3.5m, vertical and horizontal scissor braces should be set according to the requirements of the full-scale frame. (4) The stress points above the horizontal poles of the side-span beam formwork should be arranged symmetrically and reasonably. If the adjustable inclined external pole is used, each horizontal tie rod on the pole shall be connected with the pole of the structural formwork support for at least 3 vertical poles. If the tool-type column support is used, it shall comply with Figure 4, Figure 5, Figures 6 and 7 show the requirements.
关于对拉螺栓,满足:(1)内墙柱使用M14的对拉螺栓,在对拉螺栓上套Φ14mm的硬塑料套管,在硬塑料套管两端与模板接触处分别套聚酯椎套,在聚酯椎套外加海绵止水垫,确保混凝土不漏浆。内墙柱用对拉螺栓的示意图如图8所示。(2)上部主体结构内墙加固使用三段式对拉螺栓,中间带有止水片。外墙、柱用对拉螺栓如图9所示。(3)支模对拉螺栓加固模板,其长度为墙厚(柱边长、梁宽)两端各加300mm长,止水螺栓则在中间加焊3mm厚50×50mm止水片,两端设限位片。Regarding the tension bolts, the following requirements are met: (1) M14 tension bolts are used for the inner wall columns, and Φ14mm hard plastic sleeves are placed on the tension bolts, and polyester cone sleeves are respectively placed at the contact points between the two ends of the hard plastic sleeve and the formwork , add a sponge water-stop pad to the polyester vertebral sleeve to ensure that the concrete does not leak. The schematic diagram of the pull bolts used for interior wall columns is shown in Figure 8. (2) The inner wall of the upper main structure is reinforced using three-section pull bolts with a water-stop sheet in the middle. The pull bolts used for external walls and columns are shown in Figure 9. (3) The formwork supports the tension bolts to reinforce the formwork. The length is 300mm at both ends of the wall thickness (column side length and beam width). Set limit piece.
在安装梁模板时,在两个梁侧模处的两根立杆之间连接双槽钢托梁,双槽钢托梁由两根槽钢相对布置并采用高强螺栓连接组成,高强螺栓起到连接以及限制双槽钢托梁位移的作用。双槽钢托梁的上下两侧均设置有立杆圆盘,立杆圆盘与梁侧模处的立杆对应连接并与双槽钢托梁在上下方向上挡止配合;双槽钢托梁上于梁底模的位置设有至少两个生根件,生根件上放置可调上托,将生根件放置在双槽钢托梁上,生根件上有连接盘,连接盘可防止生根件及上托侧倾,如图10、图11和图12所示。When installing the beam formwork, connect the double-channel steel joists between the two vertical poles at the two beam side forms. The double-channel steel joists are composed of two channel steels arranged opposite to each other and connected by high-strength bolts. The high-strength bolts play the role of connecting And the role of limiting the displacement of double channel steel joists. Both the upper and lower sides of the double-channel steel joist are provided with vertical rod discs, which are connected to the vertical rods at the side molds of the beams and matched with the double-channel steel joists in the up and down direction; the double-channel steel joists There are at least two rooting parts on the beam at the position of the bottom formwork of the beam. An adjustable upper support is placed on the rooting part, and the rooting part is placed on the double-channel steel joist. And the support side tilt, as shown in Figure 10, Figure 11 and Figure 12.
双槽钢托梁/方钢管横杆直接放置在立杆圆盘/长顶托圆盘上,双槽钢托梁距离立杆点的位置上有限位螺栓,不会出现托梁脱落,搭拆施工时只要将托梁斜着放入即可。The double-channel steel joist/square steel pipe cross bar is directly placed on the pole disc/long top support disc, and the position of the double-channel steel joist from the pole point is limited by the bolt, so that the joist will not fall off, and it will not be dismantled Just place the joists obliquely during construction.
长顶托使用说明如下:①通过旋转圆盘螺母,可以调节托梁/方钢管横杆的位置;②扳手大螺母放在立杆上端部,用来调节丝杠的伸出长度;③套筒盘可以通过旋转到合适位置,用于连接横杆和竖向斜杆,这样整体结构功用性增强。The instructions for using the long jack are as follows: ①The position of the joist/square steel bar can be adjusted by rotating the disc nut; ②The large nut of the wrench is placed on the upper end of the vertical bar to adjust the extension length of the screw; ③Sleeve The disc can be rotated to a suitable position for connecting the horizontal bar and the vertical slanting bar, so that the utility of the overall structure is enhanced.
由于高大模板支撑系统在混凝土浇筑过程中和浇筑后一段时间内,由于受压可能发生一定的沉降和位移,如变化过大可能发生垮塌事故,因此混凝土浇筑施工前在每施工段共布置七个监测点,设置高支模安全监测系统,主要监测的内容包括支架、模板沉降,支架位移和变形。Since the tall and large formwork support system may undergo certain settlement and displacement due to pressure during the concrete pouring process and for a period of time after the concrete pouring, and if the change is too large, a collapse accident may occur. The monitoring point is to set up a safety monitoring system for high formwork. The main monitoring contents include support, formwork settlement, support displacement and deformation.
高支模安全监测系统主要功能是对高大模板支撑系统的模板沉降、支架变形和立杆轴力的实时监测,可以实现实时监测、超限预警、危险报警、趋势预测的监测目标。除了能感知高支模外围情况,传感器的使用可方便监测支模体系的变化,提高监控水平。高支模实时监测警报系统,创新使用声光报警。当监测值超过预警值时,施工人员在作业时能从机器上读取预警信号。The main function of the high formwork safety monitoring system is to monitor the settlement of the formwork, the deformation of the support and the axial force of the vertical rod in the high formwork support system in real time, and can realize the monitoring goals of real-time monitoring, over-limit early warning, danger alarm, and trend prediction. In addition to being able to perceive the surrounding conditions of high formwork, the use of sensors can facilitate the monitoring of changes in the formwork system and improve the monitoring level. The real-time monitoring and alarm system of high-support molds innovatively uses sound and light alarms. When the monitoring value exceeds the warning value, construction personnel can read the warning signal from the machine during operation.
模板的拆除遵循先支后拆,后支先拆;先拆不承重的模板,后拆承重部分的模板;自上而下,支架先拆侧向支撑,后拆竖向支撑等原则。高大模架拆除,在平面上先拆除通道位置,再沿通道向两侧有序拆除,在立面上采用阶梯式拆除法,形成以支持区为出料口低点的坡度体系,拆除时保证人员作业处有水平安全网及木跳板,拆除下来的盘扣架、木枋、模板由人工向下传递,拆除的架料必须当天清理、堆码完成,否则不允许进行下一段架体拆除。The dismantling of the formwork follows the principle of supporting first and then dismantling, and dismantling the latter first; dismantling the non-load-bearing formwork first, and then dismantling the formwork of the load-bearing part; from top to bottom, first remove the lateral support of the bracket, and then remove the vertical support. To dismantle the tall formwork, remove the position of the channel first on the plane, and then remove it in an orderly manner along the channel to both sides. On the facade, a step-by-step demolition method is adopted to form a slope system with the support area as the lowest point of the outlet. There are horizontal safety nets and wooden springboards where personnel work. The dismantled racks, wooden beams, and formwork are passed down manually. The dismantled racks must be cleaned and stacked on the same day, otherwise the next section of racks is not allowed to be dismantled.
梁、板模板拆除时,先拆除支架部分水平拉杆和剪刀撑,以便作业,而后拆除梁侧模板上的水平钢管,轻撬梁侧模板,使之与混凝土表面脱离;下调支座顶托螺杆后,轻撬模板下的龙骨,使龙骨与模板分离,或用木锤轻击,拆下第一块,然后逐块逐段拆除。切不可用钢棍或铁锤猛击乱撬。每块模板拆下时,或用人工托扶放于地上,或将支座顶托螺杆再下调相当高度,以托住拆下的模板。严禁模板自由坠落于地面。拆除梁底模板的方法大致与楼板模板相同。但拆除跨度较大的梁底模板时,应从跨中开始下调支座顶托螺杆,然后向两端逐根下凋,拆除粱底模立杆时,亦从跨中向两端作业。When dismantling the beam and slab formwork, first remove the horizontal tie rods and scissors braces of the support part to facilitate the operation, then remove the horizontal steel pipes on the beam side formwork, lightly pry the beam side formwork to separate it from the concrete surface; , Gently pry the keel under the formwork to separate the keel from the formwork, or lightly tap with a wooden hammer to remove the first piece, and then remove it piece by piece. Do not use steel rods or hammers to slam and pry. When each formwork is disassembled, it can be placed on the ground with manual support, or the supporting screw rod of the support can be lowered to a certain height to support the dismantled formwork. It is strictly forbidden for the formwork to fall freely on the ground. The method of removing the beam bottom formwork is roughly the same as that of the floor formwork. However, when removing the beam bottom formwork with a large span, the support jacking screws should be lowered from the middle of the span, and then lowered one by one to both ends.
采用本发明的施工方法搭建的支撑体系支撑更稳定,采用盘扣式支架搭设更快捷,且拆装容易,便于材料的周转使用;而且支撑体系中的底座高度能够调节,能够保证对应层的杆件能够实现稳定的连接,支撑体系中设有多个监测点监测模板支架的变形、沉降和水平位移,从而便于人员实时进行监控并作出预警,最大化保证支撑体系的牢固和人员的施工安全,最终提高建筑的施工质量。The support system built by the construction method of the present invention has more stable support, and the use of the buckle-type bracket is faster to set up, and it is easy to disassemble and assemble, which is convenient for the turnover and use of materials; moreover, the height of the base in the support system can be adjusted to ensure that the poles of the corresponding layer The parts can be connected stably. There are multiple monitoring points in the support system to monitor the deformation, settlement and horizontal displacement of the formwork support, so that it is convenient for personnel to monitor and give early warning in real time, and to ensure the firmness of the support system and the construction safety of personnel to the greatest extent. Ultimately improving the construction quality of the building.
以上所述的本发明的实施方式,并不构成对本发明保护范围的限定。任何在本发明的精神和原则之内所作的修改、等同替换和改进等,均应包括在本发明的权利要求保护范围之内。The embodiments of the present invention described above are not intended to limit the protection scope of the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principle of the present invention shall be included in the protection scope of the claims of the present invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310476882.8A CN116537534A (en) | 2023-04-28 | 2023-04-28 | Construction method of high and large formwork engineering supporting system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310476882.8A CN116537534A (en) | 2023-04-28 | 2023-04-28 | Construction method of high and large formwork engineering supporting system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116537534A true CN116537534A (en) | 2023-08-04 |
Family
ID=87442861
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310476882.8A Withdrawn CN116537534A (en) | 2023-04-28 | 2023-04-28 | Construction method of high and large formwork engineering supporting system |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116537534A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117868483A (en) * | 2024-03-13 | 2024-04-12 | 山西冶金岩土工程勘察有限公司 | House building template and method |
| CN118390795A (en) * | 2024-05-08 | 2024-07-26 | 上海宝冶集团有限公司 | Template system for improving construction quality of roof ultra-long and ultra-high parapet concrete and construction method thereof |
| CN119434631A (en) * | 2025-01-08 | 2025-02-14 | 中建二局第一建筑工程有限公司 | A double-headed steel support beam replacing the bottom upright and its construction method |
| CN120119793A (en) * | 2025-05-14 | 2025-06-10 | 太行城乡建设集团有限公司 | A disc-type formwork frame erection structure and construction method thereof |
-
2023
- 2023-04-28 CN CN202310476882.8A patent/CN116537534A/en not_active Withdrawn
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117868483A (en) * | 2024-03-13 | 2024-04-12 | 山西冶金岩土工程勘察有限公司 | House building template and method |
| CN117868483B (en) * | 2024-03-13 | 2024-05-14 | 山西冶金岩土工程勘察有限公司 | House building template and method |
| CN118390795A (en) * | 2024-05-08 | 2024-07-26 | 上海宝冶集团有限公司 | Template system for improving construction quality of roof ultra-long and ultra-high parapet concrete and construction method thereof |
| CN119434631A (en) * | 2025-01-08 | 2025-02-14 | 中建二局第一建筑工程有限公司 | A double-headed steel support beam replacing the bottom upright and its construction method |
| CN119434631B (en) * | 2025-01-08 | 2025-04-25 | 中建二局第一建筑工程有限公司 | Double-head steel joist for replacing beam bottom upright rod and construction method thereof |
| CN120119793A (en) * | 2025-05-14 | 2025-06-10 | 太行城乡建设集团有限公司 | A disc-type formwork frame erection structure and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN116537534A (en) | Construction method of high and large formwork engineering supporting system | |
| CN109629810B (en) | Closed type overhanging scaffold and construction method | |
| CN103403277B (en) | precast wall panels | |
| CN104895318B (en) | Aluminum alloy template system and construction method of same | |
| CN113513160B (en) | Construction method of basement high and large formwork support system | |
| CN110952763A (en) | Construction method of externally-hung type externally-hung overhanging scaffold | |
| CN111779248B (en) | High formwork system and construction method thereof | |
| CN107246073A (en) | Core Walls Structure crossbar structure synchronous construction structure and method | |
| CN103452311A (en) | Method for erecting section steel cantilever structure support frame | |
| CN110607905A (en) | An all-steel support reinforcement formwork system and construction method | |
| CN212507296U (en) | High formwork system | |
| CN115627912A (en) | Construction method of assembled externally-mounted flower basket type overhanging scaffold | |
| CN114775979A (en) | Assembly operation frame device for safety production training | |
| CN116254995A (en) | A large-span cantilevered concrete beam-slab support structure and its construction method | |
| CN116696055B (en) | Construction decoration method for cantilever structure of flat roof framework layer | |
| CN116657875B (en) | Cantilever steel structure construction platform with formwork system and construction method | |
| CN111608376B (en) | Comprehensive construction method for shaping component | |
| CN103147573A (en) | Natatorium roof beam slab high formwork construction method | |
| CN219863953U (en) | A cantilevered protective frame for housing construction projects | |
| CN116591462A (en) | A formwork-free structure and construction method for narrow space structural slab reverse construction method | |
| CN211666225U (en) | Externally hung type externally hung overhanging scaffold | |
| CN212053723U (en) | Fastener type combined steel pipe stair | |
| CN111608377B (en) | Comprehensive construction method for building overhanging scaffold | |
| CN210086818U (en) | A kind of roof floating plate formwork structure | |
| CN222893950U (en) | High-altitude large-span overhanging base |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WW01 | Invention patent application withdrawn after publication | ||
| WW01 | Invention patent application withdrawn after publication |
Application publication date: 20230804 |