CN114320493B - Undisturbed switching method between 9H-cascade combined circulating unit booster units - Google Patents

Undisturbed switching method between 9H-cascade combined circulating unit booster units Download PDF

Info

Publication number
CN114320493B
CN114320493B CN202210042619.3A CN202210042619A CN114320493B CN 114320493 B CN114320493 B CN 114320493B CN 202210042619 A CN202210042619 A CN 202210042619A CN 114320493 B CN114320493 B CN 114320493B
Authority
CN
China
Prior art keywords
supercharger
natural gas
volume
minimum
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210042619.3A
Other languages
Chinese (zh)
Other versions
CN114320493A (en
Inventor
任渊源
袁勤勇
李硕平
刘建波
丁雁湘
徐红波
郭凯凯
钱晓栋
陈青
马炜晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd
Original Assignee
China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd filed Critical China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd
Priority to CN202210042619.3A priority Critical patent/CN114320493B/en
Publication of CN114320493A publication Critical patent/CN114320493A/en
Application granted granted Critical
Publication of CN114320493B publication Critical patent/CN114320493B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/16Combined cycle power plant [CCPP], or combined cycle gas turbine [CCGT]

Landscapes

  • Supercharger (AREA)

Abstract

The invention discloses a non-interference switching method between 9H-cascade circulating unit booster units, which comprises the following steps: firstly, the pressure requirement of a gas engine inlet on natural gas and the technical parameters of a supercharger are required to be clarified; the minimum allowable pressure of the outlet of the booster is reversely pushed under the pressure condition of the lowest value or lower than the natural pressure range of the inlet of the fuel module of the combustion engine, the minimum buffer volume under the corresponding condition is calculated, and then the calculated minimum buffer volume is optimally reduced; setting a realization scheme of the buffer volume according to the buffer volume obtained after optimization; and finally, considering potential influencing factors of undisturbed switching of the supercharger and optimizing or adjusting, wherein the specific implementation scheme comprises a pipe capacity buffer scheme and a compression buffer tank scheme, the pipe capacity buffer scheme is realized by properly increasing the distance between the supercharger and a combustion engine room and properly increasing the pipe diameter to meet the requirement of minimum buffer volume, and the compression buffer tank scheme is realized by adding a compression buffer tank with a certain volume.

Description

Undisturbed switching method between 9H-cascade combined circulating unit booster units
Technical Field
The invention relates to the technical field of combined cycle power plant construction, in particular to a non-interference switching method between 9H-cascade combined cycle units and booster units.
Background
The 9H-level gas-steam combined cycle unit is the gas turbine unit with the highest capacity and highest efficiency worldwide at present. The design scale of the Bakistan certain combined cycle power station project (hereinafter referred to as the Bakistan project) is 1 set of 9H-level two-to-one gas-steam combined cycle unit, which comprises 2 sets of GE 9HA.01 gas turbine generator sets, 2 sets of three-pressure, reheat and natural circulation zone SCR waste heat boilers and 1 set of three-pressure, reheat and pure condensing steam turbine generator sets, and natural gas and light diesel dual fuel are used for combustion. The output of the gas turbine is 406.732MW, the output of the steam turbine is 418.391MW, the total output of the combined cycle is about 1.9MW, and the net efficiency of the combined cycle whole plant reaches 63.04%. The total contractual (EPC) contract of the buckstan project puts very strict demands on the performance and reliability of the main and auxiliary machines, for example, the provision of a buffer volume is required, so that the gas engine can be switched undisturbed between the natural gas superchargers under any load conditions, and the load of the gas engine is not reduced.
The power industry standard of China, namely, the design rule of a gas-steam combined cycle power plant (DL/T5174-2003) is as follows: when the supercharger needs to be arranged, one supercharger is preferably arranged for each set of gas turbines, and most of domestic power plants are not provided with the supercharger, so that the regulations are followed. The method is based on the consideration that most domestic combined cycle power plants are peak shaving units, and the reliability of a common booster is high (the availability of a common centrifugal booster in the power plant can reach more than 99.35%, the forced outage time is 29.7 hours/year, and the average time between two faults is more than 5.85 years). The foreign gas turbine power stations are required to carry basic load, and the reliability requirement of the unit is high, so that the booster is usually configured according to 2×100% of the whole plant capacity or 3×50% of the whole plant capacity, namely, the natural gas system is provided with a standby booster, and therefore, the higher requirement is put on the switching working condition of the booster. The working booster is stopped, the standby booster needs a certain time until the working booster is fully loaded, and the 'undisturbed switching' means that the combustion engine is ensured to maintain the full-load stable operation in the process of switching the working booster to the standby booster, which is still a problem which is still not considered in China. However, the requirements for realizing undisturbed switching among superchargers are met in a plurality of foreign combined cycle power station projects, and therefore, an implementation scheme for realizing undisturbed switching is needed.
Disclosure of Invention
The invention aims at solving the technical problems of the prior art, and provides the undisturbed switching method between the 9H-cascade combined cycle units, which can greatly save engineering investment, improve system reliability and effectively solve the undisturbed switching problem of the booster units.
The invention aims to accomplish the following technical scheme, and discloses a non-interference switching method between 9H-cascade circulating unit booster units, which comprises the following steps:
1) The method comprises the steps of determining the pressure requirement of a gas engine inlet on natural gas and the technical parameters of a supercharger; the natural gas pressure range of the inlet of the 9H-level gas turbine fuel module is 3.64 MPa.a-4.05 MPa.a, and the supercharger comprises a working supercharger and a standby supercharger;
2) Calculating a minimum buffer volume; the natural gas operating pressure in the pipeline is continuously reduced until the minimum pressure allowed by the natural gas at the inlet of the combustion engine is reduced in the process of stopping the working booster and starting the standby booster, and the standby booster is started to reach full load and put into use at the moment; under a certain gas storage volume of the pipeline, the pressure reduction process can enable the pipeline to release natural gas, and enable the gas turbine to maintain full-load operation in the switching time, and the minimum gas storage volume is the minimum buffer volume;
the minimum buffer volume calculation formula is as follows:
wherein: v (V) min For minimum buffer volume, m 3 The method comprises the steps of carrying out a first treatment on the surface of the Q is natural gas mass flow: kg/s; t is the time required for switching the supercharger, s; ρ 1 To natural gas density at normal operating pressure, kg/m 3 ;ρ 0 To allow natural gas density at minimum pressure kg/m 3
3) At or below the lowest value of the range of natural gas pressures at the inlet of the fuel module of the combustion engine, back-pushing the lowest allowable pressure at the outlet of the supercharger and calculating the minimum buffer volume under the corresponding conditions;
4) Further optimizing and reducing the calculated minimum buffer volume;
5) Setting a realization scheme of the buffer volume according to the buffer volume obtained after optimization;
6) The potential influencing factors of the undisturbed switching of the supercharger are considered and optimized or adjusted.
Further, in step 5), the implementation scheme of the buffer volume includes a tube-volume buffer scheme and a compression buffer tank scheme, wherein the Guan Rong buffer scheme is as follows: on the premise of reasonable total plane arrangement, the distance between the supercharger and the combustion engine room is properly increased, and the pipe diameter is properly increased, so that the volume of a pipeline between the supercharger and the fuel module of the combustion engine meets the optimized minimum buffer volume requirement; the compression buffer tank scheme meets the optimized minimum buffer volume requirement by additionally installing a compression buffer tank device.
Further, the compression buffer tank scheme comprises the following contents:
a) When the unit normally operates, the front and rear isolation valves of the compressor are opened, the compressor works to compress and boost natural gas from the natural gas main pipe to a set pressure, the isolation valves are closed, and the compressor stops operating;
b) When the unit booster is required to be switched, the isolation valve behind the compression buffer tank is opened, the natural gas is decompressed to the set pressure through the decompression valve, and the natural gas is continuously supplied to the gas turbine until the unit booster completes the switching process;
since the temperature of the natural gas will rise after passing through the compressor, the minimum buffer volume calculation formula is adjusted as follows:
wherein T is 1 K is the temperature of natural gas in the compression buffer tank; t (T) 0 Temperature of 273K at standard state; the minimum buffer volume, i.e. the compressed buffer tank volume, which meets the requirements, can be calculated by equation (2).
The beneficial technical effects of the invention are as follows: according to the method, the undisturbed switching problem among the booster sets is converted into the calculation and optimization of the minimum buffer volume, and the optimal calculation of the minimum buffer volume and the research on the start-stop mode of the booster are provided, so that the undisturbed switching among the 9H-cascade combined cycle booster sets can be realized through the buffer of the pipeline volume.
Drawings
FIG. 1 is a schematic system diagram of a natural gas pressurization unit for the Bakistan project;
fig. 2 is a schematic system diagram of a natural gas compression buffer tank.
Detailed Description
The present invention will be further described with reference to the drawings and examples below in order to more clearly understand the objects, technical solutions and advantages of the present invention to those skilled in the art.
The invention discloses a non-interference switching method between 9H-cascade combined cycle units and a booster unit, which comprises the following steps:
1) The method comprises the steps of determining the pressure requirement of a gas engine inlet on natural gas and the technical parameters of a supercharger; the natural gas pressure range of the inlet of the 9H-level gas turbine fuel module is 3.64 MPa.a-4.05 MPa.a, and the supercharger comprises a working supercharger and a standby supercharger;
2) Calculating a minimum buffer volume; the natural gas operating pressure in the pipeline is continuously reduced until the minimum pressure allowed by the natural gas at the inlet of the combustion engine is reduced in the process of stopping the working booster and starting the standby booster, and the standby booster is started to reach full load and put into use at the moment; under a certain gas storage volume of the pipeline, the pressure reduction process can enable the pipeline to release natural gas, and enable the gas turbine to maintain full-load operation in the switching time, and the minimum gas storage volume is the minimum buffer volume;
the minimum buffer volume calculation formula is as follows:
wherein: v (V) min For minimum buffer volume, m 3 The method comprises the steps of carrying out a first treatment on the surface of the Q is natural gas mass flow: kg/s; t is the time required for switching the supercharger, s; ρ 1 To natural gas density at normal operating pressure, kg/m 3 ;ρ 0 To allow natural gas density at minimum pressure kg/m 3
3) At or below the lowest value of the range of natural gas pressures at the inlet of the fuel module of the combustion engine, back-pushing the lowest allowable pressure at the outlet of the supercharger and calculating the minimum buffer volume under the corresponding conditions;
4) Further optimizing and reducing the calculated minimum buffer volume;
5) Setting a realization scheme of the buffer volume according to the buffer volume obtained after optimization;
6) The potential influencing factors of the undisturbed switching of the supercharger are considered and optimized or adjusted.
In step 5), the implementation scheme of the buffer volume includes a tube-volume buffer scheme and a compression buffer tank scheme, wherein the Guan Rong buffer scheme is as follows: on the premise of reasonable total plane arrangement, the distance between the supercharger and the combustion engine room is properly increased, and the pipe diameter is properly increased, so that the volume of a pipeline between the supercharger and the fuel module of the combustion engine meets the optimized minimum buffer volume requirement; the compression buffer tank scheme meets the optimized minimum buffer volume requirement by additionally installing a compression buffer tank device. The compression buffer tank scheme comprises the following contents:
a) When the unit normally operates, the front and rear isolation valves of the compressor are opened, the compressor works to compress and boost natural gas from the natural gas main pipe to a set pressure, the isolation valves are closed, and the compressor stops operating;
b) When the unit booster is required to be switched, the isolation valve behind the compression buffer tank is opened, the natural gas is decompressed to the set pressure through the decompression valve, and the natural gas is continuously supplied to the gas turbine until the unit booster completes the switching process;
since the temperature of the natural gas will rise after passing through the compressor, the minimum buffer volume calculation formula is adjusted as follows:
wherein T is 1 K is the temperature of natural gas in the compression buffer tank; t (T) 0 Temperature of 273K at standard state; the minimum buffer volume, i.e. the compressed buffer tank volume, which meets the requirements, can be calculated by equation (2).
Examples:
take a buckstan certain combined cycle plant project as an example (hereinafter referred to as buckstan project). The principle system of the supercharging unit in the natural gas pressure regulating station of the Pakistan project is shown in fig. 1, and mainly comprises 3 sets of supercharger systems corresponding to 100% of the natural gas consumption of one combustion engine, wherein #1 and #3 supercharger sets are normally operated and respectively supplied to #1 combustion engine and #2 combustion engine, the #2 supercharger sets are standby superchargers, and the branches of the 3 sets of supercharger sets are connected in parallel. Each supercharger branch is provided with a front safety cut-off valve, a rear safety cut-off valve, a front manual isolation valve and a rear manual isolation valve. The safety shut-off valve is supplied by a supercharger supplier along with a supercharger body system and used for safely shutting off when the supercharger starts and stops, the front and rear manual isolating valves are used for on-line maintenance isolation when the working supercharger fails, and the safety valve is used for protecting the supercharger and a downstream pipeline system.
And a pneumatic switching valve is also arranged between the 3 booster branch outlets. And when the #1 and #3 booster units normally operate, the pneumatic switching valve is closed. When the failure of the #1 booster unit needs to be switched to the operation of the #2 booster unit, the front and rear safety cut-off valves of the #1 booster unit are automatically closed along with the closing of the booster, the standby #2 booster is started, when the parameters meet the requirements, the pneumatic switching valve on the side of the #1 booster is opened, and natural gas at the outlet of the #2 booster is merged into the outlet branch of the original #1 booster. The fault switching mode of the #3 booster unit is the same.
Firstly, determining the pressure requirement of a fuel engine inlet on natural gas and the technical parameters of a supercharger; gas turbine inlet natural gas pressure requirement: the range and fluctuation of the natural gas pressure at the inlet of the GE company 9HA.01 are required to be certain, and if the pressure is lower than the minimum value or the pressure fluctuation speed exceeds a certain range, the gas engine can jump, and the specific requirements are as follows: (1) gas turbine fuel module inlet natural gas pressure range: 3.64 MPa.a-4.05 MPa.a; (2) transient: the maximum feed gas pressure change rate at the gas turbine inlet is limited to 1% change rate per second or 5% step. A limit of 1% change rate per second is applicable from minimum operating pressure to maximum operating pressure. The 5% step change limit applies to a range of 95% from minimum to maximum operating pressure and no more than a 5% step change can occur in 5 seconds; (3) steady state: the pressure change amplitude at any operating point at the inlet of the gas turbine fuel module should not exceed + -1% of the point pressure, and the average pressure change rate should be less than 0.25%/sec.
Supercharger technical parameters: the centrifugal supercharger has the advantages of small structure size, large exhaust gas amount, no wearing parts such as air valves, long continuous operation period, stable air supply and the like, thereby being widely applied to high-capacity gas pipelines and large-scale gas turbine power plants. The bacheltein project supercharger selects a centrifugal supercharger with 3X 50% of total plant natural gas consumption, two working and one standby. The specific selection parameters are shown in the following table:
table 1 natural gas booster selection parameters
After determining the pressure requirement of the gas engine inlet on the natural gas and the technical parameters of the supercharger, the minimum buffer volume can be calculated according to the formula (1), wherein the calculation comprises the calculation under the lowest pressure of 3.64MPa.a of the fuel module inlet and the calculation under the lowest pressure of 2.8MPa.a of the fuel module inlet.
(1) Calculation of the fuel module inlet minimum pressure at 3.64 mpa.a: the minimum allowable pressure of the outlet of the reverse booster is 4.098MPa.a, and the resistance conditions of each section are shown in the following table:
TABLE 2 resistance conditions for each section of Natural gas System
The standby booster takes 60 seconds to start from warm standby to full load operation, depending on the warranty value of the typical booster manufacturer. The minimum buffer volume calculated under this condition is shown in the following table:
TABLE 3 minimum buffer volume calculation Table-1
It is clear that substantially no pipe capacity of about 3700m3 is provided within the plant to meet the minimum buffer capacity requirements.
(2) Calculation of the minimum fuel module inlet pressure at 2.8 mpa.a: the pen managed to optimize from the "minimum pressure allowed" point of view, since the lower the "minimum pressure allowed" is, the more natural gas can be released from the existing tube volume for the fuel of the combustion engine during the turbocharger switching. According to further cooperation with a main engine plant, the 'gas engine jump pressure set value' of the inlet of the natural gas fuel module is 2.8MPa.a, and is greatly lower than the minimum pressure of 3.64MPa.a required normally. The minimum allowable pressure is 3.258MPa.a (considering the resistance 0.458 MPa) from the engine trip pressure 2.8MPa.a back-pushing booster outlet, and the minimum buffer volume is calculated under this condition as shown in the following table:
table 4 minimum buffer volume calculation table-2
Therefore, the minimum buffer volume is calculated to be 212.5m under the scheme 3
Further optimized reduction of minimum buffer volume:
to further reduce the minimum buffer volume and reduce the difficulty of undisturbed switching of the supercharger, we have further studied the time required for switching the supercharger. Through deep matching with a buckstan project supercharger manufacturer, the auxiliary supercharger can be started from a warm standby state to full-load operation within 30 seconds. The minimum buffer volume was further reduced to 107m3 by calculation in the same manner as in the previous section, and it was recommended that the actual buffer volume be considered to be not less than 118m3 (10% of the desired amount was considered).
After the minimum buffer volume is further optimized and reduced, the implementation scheme of considering the buffer volume can be correspondingly:
(1) Scheme one: guan Rong buffer regimen;
the distance between the outlet of the supercharger and the combustion engine room is longer, and the distance generally passes through the factory pipe frame (or the factory direct burial section), the front-mounted module of the fuel of the combustion engine and the pipeline from the front-mounted module to the fuel module of the combustion engine, so that the distance between the supercharger and the combustion engine room can be properly increased and the pipe diameter can be properly increased on the premise of reasonable total plane arrangement in the feasibility research and preliminary design stage of the power station, and the pipeline volume (including the internal volume of equipment such as a filter) between the supercharger and the fuel module of the combustion engine meets the requirement of the minimum buffer volume 118m 3.
In addition to meeting the undisturbed switching between superchargers, a suitable increase of the volume of this portion of the pipe has the following advantages:
when the gas engine is in load shedding, the natural gas flow rate is reduced from 100% to 30% within 1 second, and the pressure in the pipeline after the supercharger is possibly increased due to the delay of the action time of the supercharger and a valve thereof, so that the gas engine can be jumped. Properly increasing the tube volume contributes to stability under this condition.
The control system of the gas turbine needs to receive an online real-time signal of the heat value instrument so as to timely track the change of the heat value of the natural gas and timely perform combustion adjustment. Since the heat meter takes a while from sampling, analyzing, signaling to the engine control system, it is required that the natural gas flow time from the heat meter sampling port to the engine be as closely matched as possible to the real time signal transmission time of the heat meter. And by increasing the pipeline volume, reducing the natural gas flow rate will help the two to match in time.
2) Scheme II: compression buffer tank scheme
To meet the minimum buffer volume requirement, this can also be achieved by adding a compressed buffer tank arrangement as shown in fig. 2. When the unit normally operates, the front and rear isolation valves of the compressor are opened, the compressor works to compress and boost natural gas from the natural gas main pipe to a set pressure, the isolation valves are closed, and the compressor stops operating. When the unit booster is required to be switched, the isolation valve behind the compression buffer tank is opened, the natural gas is decompressed to the set pressure through the decompression valve, and the natural gas is continuously supplied to the gas turbine until the unit booster completes the switching process. The capacity of the compressed buffer tank of about 45m3 is calculated according to the formula (2) and can meet the requirements, and the investment estimation of the device is shown in the following table:
TABLE 5 Natural gas compression buffer tank installation investment evaluation Table
But this solution has the following drawbacks:
(1) The equipment such as a natural gas compressor unit, a buffer tank, a regulating valve group and the like is added, the design pressure of the equipment needs to be increased to the highest working pressure after the compressor unit, and the investment of the equipment, pipelines and civil engineering foundations is increased to more than 160 ten thousand yuan;
(2) The compressor unit, the roundabout buffer tank and the like are required to be added with larger installation sites (about 350m < 2 >), the total planar arrangement of practical projects is often tension, and the sites are difficult to leave;
(3) The whole natural gas system is provided with a large supercharger and a small compressor for compressing the buffer tank, so that the complexity of the system is increased, and the control difficulty is increased;
(4) The workload of overhauling and maintaining is increased.
The recommended scheme is as follows:
because the first scheme adopts pipeline volume buffering to meet the requirement of minimum buffering volume, a compression buffer tank system is canceled, engineering investment is saved, system reliability is improved, and the undisturbed switching problem of the booster unit is effectively solved. Therefore, the use of scheme one "tube buffer scheme" is preferred when the general layout is conditional. When the minimum buffer volume is calculated to be too large, the pipe capacity buffer scheme which is only realized by the scheme one is difficult to realize, and the supercharging unit arrangement site is provided with a space for installing facilities such as a compression buffer tank, a matched compressor and the like, the scheme two compression buffer tank scheme can be considered to be adopted.
Other considerations for undisturbed switching of the supercharger:
(1) The starting step of the normal booster is that the auxiliary oil pump is started and started for about 1-2 minutes, purged for about 1 minute, started and lubricated for 1 minute, started for 0.5 minute, and the loading time is about 4-5 minutes after the oil temperature reaches the loading condition, and the total time is about 10 minutes, during the starting loading process, the fuel engine jumps due to the insufficient natural gas stored in the pipeline, so as to ensure that the standby booster is not disturbed to be switched to a full-load running state, the standby booster must be in a warm standby state rather than a cold state before being switched, and the booster can be quickly started in the warm standby state without performing the starting of the auxiliary system and a series of checking procedures like the cold state starting, so that the starting time is saved to the greatest extent:
the compressed air supply and the nitrogen supply required by the supercharger are good;
the dry gas seal of the supercharger, the housing ventilation fan and the shaft seal work well;
the supercharger lubricating oil system is normally operated;
the cooling water system of the supercharger normally operates;
(2) It is suggested that the "time required for starting the supercharger from warm standby to full load" be written as performance assurance data and important bid evaluation factors into the bid file during the supercharger bid stage to promote the supercharger suppliers to perform sufficient optimization work, reduce the time required for supercharger switching, and enable the power plant to more easily achieve a non-disturbing supercharger switching.
(3) The different gas suppliers will differ with respect to the "minimum allowable pressure" (in the case of a switched state of the supercharger) required before the gas fuel module, and should negotiate as much as possible with the gas suppliers to reduce this pressure as much as possible, for example by taking the alarm pressure or the trip pressure as the minimum allowable pressure in the case of a switched state of the supercharger, and the final duct volume is guaranteed to be larger than the minimum buffer volume calculated in this way, leaving a certain amount of desire.
(4) When the working supercharger needs to be switched to the standby supercharger, the working supercharger recommends to delay for proper time to be shut down again so as to ensure the reliable completion of undisturbed switching.
(5) Because the supercharger is one of the most important auxiliary machines of the gas turbine power station, the switching process is complex, the function requirement of ' undisturbed switching ' is higher, the realization difficulty of a supercharger supplier is still higher at present, in order to avoid the risk of unnecessary check fines, the EPC bidder and a homeowner are suggested to fully negotiate in the foreign project EPC contract negotiation stage, the requirement of ' the supercharger has the undisturbed switching under the premise of maintaining the full load of the gas turbine ' is reduced to be ' the supercharger has reliable switching function ', the gas turbine is ensured not to be started to jump (the gas turbine is allowed to run in a short time in the switching process of the supercharger) ', the calculation value of the minimum buffering capacity is greatly reduced, and the supercharger supplier is easier to meet.
Conclusion: according to the invention, through calculation and optimization of the minimum buffer volume, a scheme of pipe capacity buffer or compression buffer tank buffer is adopted, so that undisturbed switching between the working booster and the standby booster of the 9H-cascade combined cycle unit is realized, and the safety and reliability of unit operation are improved. The main conclusion is as follows: (1) When the time required for starting the supercharger from the warm standby state to the full load is 30 seconds, when the natural gas pipe volume between the supercharger and the fuel module of the combustion engine is about 118m3 or more, the undisturbed switching between the supercharger sets can be realized without affecting the load of the combustion engine. (2) By adopting the scheme of pipeline volume buffering, the compression buffer tank system can be canceled, the engineering investment can be saved, the system reliability can be improved, and the undisturbed switching problem of the booster unit can be effectively solved. Therefore, the use of a "tube buffer solution" is preferred when the overall layout is conditional.
The specific embodiments described herein are merely illustrative of the principles and functions of the present invention, and are not meant to limit the invention. Modifications and variations may be made to the above-described embodiments by those skilled in the art without departing from the spirit and scope of the invention. It is therefore intended that all equivalent modifications and changes made by those skilled in the art without departing from the spirit and technical spirit of the present invention shall be covered by the appended claims.

Claims (3)

1. A method for undisturbed switching between 9H-cascade combined circulating unit booster units is characterized in that: the method comprises the following steps:
1) The method comprises the steps of determining the pressure requirement of a gas engine inlet on natural gas and the technical parameters of a supercharger; the natural gas pressure range of the inlet of the 9H-level gas turbine fuel module is 3.64 MPa.a-4.05 MPa.a, and the supercharger comprises a working supercharger and a standby supercharger;
2) Calculating a minimum buffer volume; the natural gas operating pressure in the pipeline is continuously reduced until the minimum pressure allowed by the natural gas at the inlet of the combustion engine is reduced in the process of stopping the working booster and starting the standby booster, and the standby booster is started to reach full load and put into use at the moment; under a certain gas storage volume of the pipeline, the pressure reduction process can enable the pipeline to release natural gas, and enable the gas turbine to maintain full-load operation in the switching time, and the minimum gas storage volume is the minimum buffer volume;
the minimum buffer volume calculation formula is as follows:
wherein: v (V) min M3, the minimum buffer volume; q is natural gas mass flow: kg/s; t is the time required for switching the supercharger, s; ρ 1 The density of the natural gas is kg/m3 under normal working pressure; ρ 0 Kg/m3 to allow natural gas density at minimum pressure;
3) At or below the lowest value of the range of natural gas pressures at the inlet of the fuel module of the combustion engine, back-pushing the lowest allowable pressure at the outlet of the supercharger and calculating the minimum buffer volume under the corresponding conditions;
4) Further optimizing and reducing the calculated minimum buffer volume;
5) Setting a realization scheme of the buffer volume according to the buffer volume obtained after optimization;
6) The potential influencing factors of the undisturbed switching of the supercharger are considered and optimized or adjusted.
2. The undisturbed switching method between the 9H-cascade combined cycle units and the booster units according to claim 1, wherein the method comprises the following steps: in step 5), the implementation scheme of the buffer volume includes a tube-volume buffer scheme and a compression buffer tank scheme, wherein the Guan Rong buffer scheme is as follows: on the premise of reasonable total plane arrangement, the distance between the supercharger and the combustion engine room is properly increased, and the pipe diameter is properly increased, so that the volume of a pipeline between the supercharger and the fuel module of the combustion engine meets the optimized minimum buffer volume requirement; the compression buffer tank scheme meets the optimized minimum buffer volume requirement by additionally installing a compression buffer tank device.
3. The undisturbed switching method between the 9H-cascade combined cycle units and the booster units according to claim 2, wherein the method comprises the following steps: the compression buffer tank scheme comprises the following contents:
a) When the unit normally operates, the front and rear isolation valves of the compressor are opened, the compressor works to compress and boost natural gas from the natural gas main pipe to a set pressure, the isolation valves are closed, and the compressor stops operating;
b) When the unit booster is required to be switched, the isolation valve behind the compression buffer tank is opened, the natural gas is decompressed to the set pressure through the decompression valve, and the natural gas is continuously supplied to the gas turbine until the unit booster completes the switching process;
since the temperature of the natural gas will rise after passing through the compressor, the minimum buffer volume calculation formula is adjusted as follows:
wherein T is 1 K is the temperature of natural gas in the compression buffer tank; t (T) 0 Temperature of 273K at standard state; the minimum buffer volume, i.e. the compressed buffer tank volume, which meets the requirements, can be calculated by equation (2).
CN202210042619.3A 2022-01-14 2022-01-14 Undisturbed switching method between 9H-cascade combined circulating unit booster units Active CN114320493B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210042619.3A CN114320493B (en) 2022-01-14 2022-01-14 Undisturbed switching method between 9H-cascade combined circulating unit booster units

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210042619.3A CN114320493B (en) 2022-01-14 2022-01-14 Undisturbed switching method between 9H-cascade combined circulating unit booster units

Publications (2)

Publication Number Publication Date
CN114320493A CN114320493A (en) 2022-04-12
CN114320493B true CN114320493B (en) 2023-11-03

Family

ID=81027329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210042619.3A Active CN114320493B (en) 2022-01-14 2022-01-14 Undisturbed switching method between 9H-cascade combined circulating unit booster units

Country Status (1)

Country Link
CN (1) CN114320493B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005240608A (en) * 2004-02-25 2005-09-08 Mitsubishi Heavy Ind Ltd Gas turbine control device
CN102514701A (en) * 2011-12-07 2012-06-27 中国舰船研究设计中心 System and method for guaranteeing oxygen supply on ship
WO2012176256A1 (en) * 2011-06-20 2012-12-27 熱技術開発株式会社 Closed-cycle gas turbine and method for operating same
CN105443978A (en) * 2015-12-28 2016-03-30 重庆耐德节能装备有限公司 Hydraulic pressurized natural gas filling substation system
CN111902622A (en) * 2018-03-05 2020-11-06 Mtu 腓特烈港有限责任公司 Method for model-based control and regulation of an internal combustion engine
CN112145248A (en) * 2020-09-08 2020-12-29 北京科技大学 External compression air separation process flow with energy storage, power generation and material recovery functions
CN113738510A (en) * 2021-09-27 2021-12-03 上海电气燃气轮机有限公司 Double-pressure reheating-free combined cycle power plant and performance optimization method thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5221443B2 (en) * 2009-05-08 2013-06-26 株式会社東芝 Method for starting single-shaft combined cycle power plant and single-shaft combined cycle power plant
EP2458181A1 (en) * 2010-11-30 2012-05-30 Siemens Aktiengesellschaft Method for operating a gas turbine during load control, device for regulating the operation of a gas turbine and power plant

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005240608A (en) * 2004-02-25 2005-09-08 Mitsubishi Heavy Ind Ltd Gas turbine control device
WO2012176256A1 (en) * 2011-06-20 2012-12-27 熱技術開発株式会社 Closed-cycle gas turbine and method for operating same
CN102514701A (en) * 2011-12-07 2012-06-27 中国舰船研究设计中心 System and method for guaranteeing oxygen supply on ship
CN105443978A (en) * 2015-12-28 2016-03-30 重庆耐德节能装备有限公司 Hydraulic pressurized natural gas filling substation system
CN111902622A (en) * 2018-03-05 2020-11-06 Mtu 腓特烈港有限责任公司 Method for model-based control and regulation of an internal combustion engine
CN112145248A (en) * 2020-09-08 2020-12-29 北京科技大学 External compression air separation process flow with energy storage, power generation and material recovery functions
CN113738510A (en) * 2021-09-27 2021-12-03 上海电气燃气轮机有限公司 Double-pressure reheating-free combined cycle power plant and performance optimization method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
提高V94.3A型燃气轮机燃料供应系统中增压机运行稳定性的探讨;吴明浩;闫乃欣;刘旭生;李伟;;自动化博览(第11期);全文 *
燃气-蒸汽联合循环燃料切换缓冲系统设计计算方法;许红;;山东工业技术(第02期);全文 *

Also Published As

Publication number Publication date
CN114320493A (en) 2022-04-12

Similar Documents

Publication Publication Date Title
CN110748494B (en) Self-stabilizing steam pressurizing system and working method thereof
CN112653189B (en) Combustion engine black start method based on small combustion engine as black start power supply
CN110671162B (en) Steam pressure matcher and control method thereof
CN210949190U (en) Self-stabilizing steam pressurization system
CN110953571A (en) Heat supply steam residual pressure cascade utilization system applied to coal-fired heat supply unit
Arakelyan et al. Increased reliability, manoeuvrabity and durability of steam turbines through the implementation of the generator driving mode
CN115263476A (en) Control method of supercritical carbon dioxide series double-turbine power generation system
CN114320493B (en) Undisturbed switching method between 9H-cascade combined circulating unit booster units
CN114562362A (en) Engine turbocharging method and engine turbocharging system
CN104500218A (en) System capable of simultaneously improving low-speed working condition performance, high-speed working condition fuel efficiency, NOx emission and transient performance of internal combustion engine
CN109882422A (en) A kind of double flow moves feed pump turbine recirculation pipe road device and its control method
CN210164663U (en) Double-pneumatic feed water pump steam turbine recirculation water pipeline device
CN115788612A (en) Pipeline system and start-stop mode of differential pressure turboexpander set
CN214836591U (en) Gas-steam combined cycle unit with multiple sampling points at outlet of high-pressure water feed pump
CN214944469U (en) High-pressure gas-phase fluid pressure energy recovery system of dry gas recovery device
CN112902023A (en) Steam pipeline pressurization system and full-automatic control method thereof
CN210087487U (en) Device for solving problems of pulsation of air flow at outlet of supercharger and cold state leakage in distributed energy system
CN210533715U (en) High-temperature high-pressure test system for gas turbine combustor
CN110714804B (en) Bypass control system suitable for CAES system expansion unit
CN114810231A (en) Gas-steam combined cycle unit gas supercharger frequency conversion control method
CN205578384U (en) Second grade supercharged diesel engine hydraulic means based on waste gas utilization
CN213810038U (en) Natural gas pressure regulating station system with fault switching function
CN213361874U (en) Waste natural gas recovery system of gas turbine
CN215804733U (en) Gas turbine cooling system
CN214887268U (en) Gas-steam combined cycle unit capable of preventing natural gas leakage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant