CN114301003A - A load transfer method for flexible cables between adjacent tension towers - Google Patents

A load transfer method for flexible cables between adjacent tension towers Download PDF

Info

Publication number
CN114301003A
CN114301003A CN202111405303.8A CN202111405303A CN114301003A CN 114301003 A CN114301003 A CN 114301003A CN 202111405303 A CN202111405303 A CN 202111405303A CN 114301003 A CN114301003 A CN 114301003A
Authority
CN
China
Prior art keywords
flexible cable
cable
load transfer
tension
flexible
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111405303.8A
Other languages
Chinese (zh)
Inventor
郑新龙
孙璐
林晓波
陈国志
张引贤
胡凯
陶诗洁
雷之楮
李渊
阮天余
沈琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhoushan Institute Of Oceanic Electric Power Transmission Co ltd
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Zhejiang Zhoushan Institute Of Oceanic Electric Power Transmission Co ltd
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zhoushan Institute Of Oceanic Electric Power Transmission Co ltd, Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Zhejiang Zhoushan Institute Of Oceanic Electric Power Transmission Co ltd
Priority to CN202111405303.8A priority Critical patent/CN114301003A/en
Publication of CN114301003A publication Critical patent/CN114301003A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种相邻耐张杆塔间软电缆的负荷转接方法。本发明公开了一种基于可重复应用的软电缆的负荷转接方法,涉及电力线路施工方法领域。在新建线路搭接过程中会对已有架空线产生跨接,目前常采用硬电缆进行负荷转接,但硬电缆弯曲半径要求严格,不可任意卷曲收放,多为单次使用,可重复利用率低。本发明过程为:选取可重复应用的软电缆;制作电缆终端;架设软电缆;短时停电,拆除第一耐张杆塔的引流线,与软电缆相连;拆开第二耐张杆塔引流线,与软电缆另一端相连;新建线路搭接结束,拆除软电缆,挂上引流线软电缆用电缆盘回收,可供后续继续使用。本方法通过采用软电缆进行临时负荷转接,可有效实现临时负荷转接电缆的多次重复回收利用连接及架线操作更加简单方便。

Figure 202111405303

A load transfer method for flexible cables between adjacent tension towers. The invention discloses a load transfer method based on a reusable flexible cable, and relates to the field of power line construction methods. The existing overhead lines will be bridged in the process of new line overlapping. At present, hard cables are often used for load transfer. However, the bending radius of hard cables is strict, and cannot be curled and retracted arbitrarily. Most of them are single-use and reusable. rate is low. The process of the invention is as follows: selecting a reusable flexible cable; making a cable terminal; erecting a flexible cable; short-term power failure, removing the drainage line of the first tension tower, and connecting it with the flexible cable; disassembling the drainage line of the second tension tower, Connect to the other end of the flexible cable; after the new line is lapped, remove the flexible cable, hang up the drainage wire and use the cable reel to recover the flexible cable, which can be used for subsequent use. By using the flexible cable for temporary load transfer, the method can effectively realize the repeated recycling and connection of the temporary load transfer cable and the wiring operation is simpler and more convenient.

Figure 202111405303

Description

一种相邻耐张杆塔间软电缆的负荷转接方法A load transfer method for flexible cables between adjacent tension towers

技术领域technical field

本发明涉及电力线路施工方法领域,尤其涉及一种基于可重复应用的软电缆的负荷转接方法。The invention relates to the field of power line construction methods, in particular to a load transfer method based on a reusable flexible cable.

背景技术Background technique

新建线路交叉跨越已建线路的情况日益增加,在新建线路搭接过程中会对已有架空线产生跨接,为保证安全距离和可靠供电,常采用交联聚乙烯电缆进行负荷转接,但交联聚乙烯电缆弯曲半径要求严格,不可任意卷曲收放,多为单次使用,可重复利用率低。The situation that the new line crosses the existing line is increasing day by day, and the existing overhead line will be crossed during the overlapping process of the new line. In order to ensure a safe distance and reliable power supply, cross-linked polyethylene cable is often used for load transfer, but XLPE cables have strict requirements on the bending radius and cannot be curled and retracted arbitrarily. Most of them are single-use and have low reusability.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题和提出的技术任务是对现有技术方案进行完善与改进,提供一种基于可重复应用的软电缆的负荷转接方法,以实现多次重复使用为目的。为此,本发明采取以下技术方案。The technical problem to be solved and the technical task proposed by the present invention are to perfect and improve the existing technical solutions, and to provide a load switching method based on a reusable flexible cable for the purpose of realizing multiple reuse. Therefore, the present invention adopts the following technical solutions.

一种相邻耐张杆塔间软电缆的负荷转接方法,包括以下步骤:A load transfer method for flexible cables between adjacent tension towers, comprising the following steps:

1)选取可重复应用的软电缆,其长度大于耐张段长度与两耐张杆塔高度之和;1) Select a reusable flexible cable whose length is greater than the sum of the length of the tension section and the height of the two tension towers;

2)制作电缆终端,压接铜鼻子,铜鼻子与耐张线夹尺寸相匹配;2) Make the cable terminal, crimp the copper nose, and the copper nose matches the size of the tension clamp;

3)装设软电缆支撑架,将软电缆由地面引至横担附近,并保持安全距离;3) Install a flexible cable support frame, lead the flexible cable from the ground to the vicinity of the cross arm, and maintain a safe distance;

4)短时停电,拆除第一耐张杆塔的引流线,与软电缆一端接头相连;4) In case of short-term power failure, remove the drainage line of the first tension tower and connect it with one end of the flexible cable;

5)拆开第二耐张杆塔的引流线,与软电缆另一端相连,实现由软电缆继续供电;5) Disassemble the drainage line of the second tension tower and connect it with the other end of the flexible cable, so that the flexible cable can continue to supply power;

6)新建线路搭接结束,拆除软电缆,挂上引流线,负荷继续由原架空线路供电,软电缆用电缆盘回收,可供后续继续使用。6) After the new line is overlapped, the flexible cable is removed, and the drainage line is hung up. The load continues to be powered by the original overhead line, and the flexible cable is recovered with a cable reel for subsequent use.

通过采用软电缆进行临时负荷转接,可有效实现临时负荷转接电缆的多次重复回收利用,并且软电缆的特性,连接及架线操作更加简单方便,有效提升电缆的利用率,降低成本,避免了传统负荷转接电缆由于不能任意弯曲,操作不方便,且不能再次回收使用的问题。By using flexible cables for temporary load transfer, the repeated recycling of temporary load transfer cables can be effectively achieved, and the characteristics of flexible cables, connection and wiring operations are more simple and convenient, effectively improving the utilization rate of cables and reducing costs. It avoids the problems that the traditional load transfer cable cannot be bent arbitrarily, is inconvenient to operate, and cannot be recycled again.

作为优选技术手段:所述的软电缆应符合下列要求:外观检查,应无明显伤痕;绝缘电阻测量,与前次测量应无明显变化;介质损耗角正切,应不大于0.005;局部放电试验:施加1.73U0额定电压,主线芯绝缘放电量不大于10pC。通过这些条件,可有效保证软电缆的质量要求,使之符合临时负荷转接的要求。As the preferred technical means: the flexible cable should meet the following requirements: appearance inspection, there should be no obvious scars; insulation resistance measurement, there should be no obvious change from the previous measurement; dielectric loss tangent, should not be greater than 0.005; partial discharge test: The rated voltage of 1.73U0 is applied, and the insulation discharge of the main wire core is not more than 10pC. Through these conditions, the quality requirements of the flexible cable can be effectively guaranteed to meet the requirements of temporary load transfer.

有益效果:通过采用软电缆进行临时负荷转接,可有效实现临时负荷转接电缆的多次重复回收利用,并且软电缆的特性,连接及架线操作更加简单方便,有效提升电缆的利用率,有效节约资源,降低成本,避免了传统负荷转接电缆由于不能任意弯曲,操作不方便,且不能再次回收使用的问题。Beneficial effects: By using flexible cables for temporary load transfer, the repeated recycling of temporary load transfer cables can be effectively realized, and the characteristics of flexible cables, connection and wiring operations are simpler and more convenient, and the utilization rate of cables can be effectively improved. It effectively saves resources, reduces costs, and avoids the problems that traditional load transfer cables cannot be bent arbitrarily, are inconvenient to operate, and cannot be recycled again.

附图说明Description of drawings

图1是本发明流程示意图。Fig. 1 is a schematic flow chart of the present invention.

图2是本发明软电缆架线施工示意图。FIG. 2 is a schematic diagram of the construction of the flexible cable wiring of the present invention.

图中:1、软电缆;2、第一耐张杆塔;3、第二耐张杆塔;4、引流线;5、新建线路。In the figure: 1. Flexible cable; 2. The first tensile tower; 3. The second tensile tower; 4. Drainage line; 5. New line.

具体实施方式Detailed ways

以下结合说明书附图对本发明的技术方案做进一步的详细说明。The technical solutions of the present invention will be further described in detail below with reference to the accompanying drawings.

如图1-2所示,一种相邻耐张杆塔间软电缆的负荷转接方法,其过程包括以下步骤:As shown in Figure 1-2, a load transfer method for flexible cables between adjacent tension towers, the process includes the following steps:

S1.选取可重复应用的软电缆1,其长度大于耐张段长度与两耐张杆塔高度之和;S1. Select a reusable flexible cable 1 whose length is greater than the sum of the length of the tension section and the height of the two tension towers;

S2.制作电缆终端,压接铜鼻子,铜鼻子与耐张线夹尺寸相匹配;S2. Make the cable terminal, crimp the copper nose, and the copper nose matches the size of the tension clamp;

S3.装设软电缆1支撑架,将软电缆1由地面引至横担附近,并保持安全距离;S3. Install the flexible cable 1 support frame, lead the flexible cable 1 from the ground to the vicinity of the cross arm, and maintain a safe distance;

S4.短时停电,拆除第一耐张杆塔2的引流线4,与软电缆1一端接头相连;S4. Short-term power failure, remove the drainage wire 4 of the first tension tower 2, and connect it with one end of the flexible cable 1;

S5.拆开第二耐张杆塔3的引流线4,与软电缆1另一端相连,实现由软电缆1继续供电;S5. Disassemble the drain wire 4 of the second tension tower 3 and connect it with the other end of the flexible cable 1, so that the flexible cable 1 can continue to supply power;

S6.新建线路5搭接结束,拆除软电缆1,挂上引流线4,负荷继续由原架空线路供电,软电缆1用电缆盘回收,可供后续继续使用。S6. After the new line 5 is lapped, the flexible cable 1 is removed, and the drain line 4 is hung up. The load continues to be powered by the original overhead line, and the flexible cable 1 is recovered with a cable reel for subsequent use.

为了保证软电缆1的质量要求,软电缆1应符合下列要求:外观检查,应无明显伤痕;绝缘电阻测量,与前次测量应无明显变化;介质损耗角正切,应不大于0.005;局部放电试验:施加1.73U0额定电压,主线芯绝缘放电量不大于10pC。通过这些条件,可有效保证软电缆1的质量要求,使之符合临时负荷转接的要求。In order to ensure the quality requirements of flexible cable 1, flexible cable 1 should meet the following requirements: visual inspection, there should be no obvious scars; insulation resistance measurement should have no obvious change from the previous measurement; dielectric loss tangent should not be greater than 0.005; partial discharge Test: The rated voltage of 1.73U0 is applied, and the insulation discharge of the main core is not more than 10pC. Through these conditions, the quality requirements of the flexible cable 1 can be effectively guaranteed to meet the requirements of temporary load transfer.

通过采用软电缆1进行临时负荷转接,可有效实现临时负荷转接电缆的多次重复回收利用,并且软电缆1的特性,连接及架线操作更加简单方便,有效提升电缆的利用率,降低成本,避免了传统负荷转接电缆由于不能任意弯曲,操作不方便,且不能再次回收使用的问题。By using the flexible cable 1 for temporary load transfer, the repeated recycling of the temporary load transfer cable can be effectively realized, and the characteristics of the flexible cable 1, the connection and wiring operations are more simple and convenient, effectively improve the utilization rate of the cable, reduce cost, and avoids the problems that the traditional load transfer cable cannot be bent arbitrarily, is inconvenient to operate, and cannot be recycled again.

以上图1-2所示的一种相邻耐张杆塔间软电缆的负荷转接方法是本发明的具体实施例,已经体现出本发明突出的实质性特点和显著进步,可根据实际的使用需要,在本发明的启示下,对其进行形状、结构等方面的等同修改,均在本方案的保护范围之列。The load transfer method of a flexible cable between adjacent tension towers shown in the above Figures 1-2 is a specific embodiment of the present invention, which has embodied the outstanding substantive features and significant progress of the present invention, and can be used according to actual applications. If necessary, under the inspiration of the present invention, equivalent modifications in terms of shape and structure are included in the protection scope of this solution.

Claims (2)

1.一种相邻耐张杆塔间软电缆的负荷转接方法,其特征在于包括以下步骤:1. the load transfer method of the flexible cable between adjacent tension towers, is characterized in that comprising the following steps: 1)选取可重复应用的软电缆(1),其长度大于耐张段长度与两耐张杆塔高度之和;1) Select a reusable flexible cable (1) whose length is greater than the sum of the length of the tension section and the height of the two tension towers; 2)制作电缆终端,压接铜鼻子,铜鼻子与耐张线夹尺寸相匹配;2) Make the cable terminal, crimp the copper nose, and the copper nose matches the size of the tension clamp; 3)装设软电缆(1)支撑架,将软电缆(1)由地面引至横担附近,并保持安全距离;3) Install the flexible cable (1) support frame, lead the flexible cable (1) from the ground to the vicinity of the cross arm, and keep a safe distance; 4)短时停电,拆除第一耐张杆塔(2)的引流线(4),与软电缆(1)一端接头相连;4) In the event of a short-term power failure, remove the drain wire (4) of the first tension tower (2) and connect it to one end of the flexible cable (1); 5)拆开第二耐张杆塔(3)的引流线(4),与软电缆(1)另一端相连,实现由软电缆(1)继续供电;5) Disassemble the drain line (4) of the second tension tower (3), and connect it with the other end of the flexible cable (1), so as to continue to supply power from the flexible cable (1); 6)新建线路(5)搭接结束,拆除软电缆(1),挂上引流线(4),负荷继续由原架空线路供电,软电缆(1)用电缆盘回收,可供后续继续使用。6) After the new line (5) is lapped, the flexible cable (1) is removed, the drain line (4) is hung up, the load continues to be powered by the original overhead line, and the flexible cable (1) is recovered with a cable reel for subsequent use. 2.根据权利要求1所述的一种相邻耐张杆塔间软电缆的负荷转接方法,其特征在于:所述的软电缆(1)应符合下列要求:外观检查,应无明显伤痕;绝缘电阻测量,与前次测量应无明显变化;介质损耗角正切,应不大于0.005;局部放电试验:施加1.73U0额定电压,主线芯绝缘放电量不大于10pC。2. The load transfer method of a flexible cable between adjacent tensile towers according to claim 1, characterized in that: the flexible cable (1) should meet the following requirements: appearance inspection, there should be no obvious scars; Insulation resistance measurement, there should be no significant change from the previous measurement; dielectric loss tangent should not be greater than 0.005; partial discharge test: apply a rated voltage of 1.73U0, and the insulation discharge of the main core core should not be greater than 10pC.
CN202111405303.8A 2021-11-24 2021-11-24 A load transfer method for flexible cables between adjacent tension towers Pending CN114301003A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111405303.8A CN114301003A (en) 2021-11-24 2021-11-24 A load transfer method for flexible cables between adjacent tension towers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111405303.8A CN114301003A (en) 2021-11-24 2021-11-24 A load transfer method for flexible cables between adjacent tension towers

Publications (1)

Publication Number Publication Date
CN114301003A true CN114301003A (en) 2022-04-08

Family

ID=80966321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111405303.8A Pending CN114301003A (en) 2021-11-24 2021-11-24 A load transfer method for flexible cables between adjacent tension towers

Country Status (1)

Country Link
CN (1) CN114301003A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040074749A (en) * 2003-02-18 2004-08-26 우창전력(주) Uninterruptable distributing method of single-phase wire using temporary line
CN201789232U (en) * 2010-08-30 2011-04-06 河南省电力公司郑州供电公司 Device for handling failure of overhead line without power cut
CN203734209U (en) * 2014-02-17 2014-07-23 广东电网公司佛山供电局 Live working device for cable bypass
CN106451220A (en) * 2016-12-01 2017-02-22 华北电力科学研究院有限责任公司 Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower
CN108963875A (en) * 2018-07-19 2018-12-07 吉林师范大学 The method of on-load migration 10KV overhead transmission line

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040074749A (en) * 2003-02-18 2004-08-26 우창전력(주) Uninterruptable distributing method of single-phase wire using temporary line
CN201789232U (en) * 2010-08-30 2011-04-06 河南省电力公司郑州供电公司 Device for handling failure of overhead line without power cut
CN203734209U (en) * 2014-02-17 2014-07-23 广东电网公司佛山供电局 Live working device for cable bypass
CN106451220A (en) * 2016-12-01 2017-02-22 华北电力科学研究院有限责任公司 Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower
CN108963875A (en) * 2018-07-19 2018-12-07 吉林师范大学 The method of on-load migration 10KV overhead transmission line

Similar Documents

Publication Publication Date Title
CN103972825B (en) Manufacture method around packet mode transition joint
CN114301003A (en) A load transfer method for flexible cables between adjacent tension towers
US11587698B2 (en) Electric submersible pump (ESP) power cable splice containment filler
CN110429522A (en) A kind of preformed armor rods T binding clip
CN105490130A (en) Hydraulic crimping technology forstrain clamp for steel-cored aluminum stranded wire
CN209786624U (en) A wire end insulation protection device
CN103630806B (en) 10kV cable intermediate joint stress cone dislocation partial discharge model manufacture method
CN206412500U (en) A kind of emergent fast splicing device of cable
CN206276841U (en) The small line stretcher of Portable secondary
CN207339089U (en) Line fixing device more than bypass cable
CN105680262A (en) Connection structure for aerial optical fiber composite phase line and conventional wire and circuit connection method
CN206412738U (en) A cable ground shell
CN204905757U (en) Tightly, take out stitches and use coaster
CN104600533A (en) Internal wire margin control method of electric connector
CN114709765A (en) High-voltage cable transfer connection construction method
CN205621981U (en) Connection structure of built on stilts optical phase conductor and conventional wire
CN206302126U (en) A kind of new parcel Transition wire clip
CN207098092U (en) A kind of wire jumper crosses thermal shunt connecting line folder
CN215527292U (en) Stretch-proofing electronic wire harness
CN104752847B (en) Three-core crosslinked cable prefabricated traction wire clamp technology
RU2825433C1 (en) Method of making water-cooled cable and water-cooled cable made according to this method
CN204615346U (en) Cable intermediate head
CN204760902U (en) Wire anchor installation specialized tool
CN109038438A (en) A kind of Combined insulating sub-conductor clamp device
CN218569256U (en) Anpu wire clamp type ground connection link

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination