CN114293591A CN202210076742.7A CN202210076742A CN114293591A CN 114293591 A CN114293591 A CN 114293591A CN 202210076742 A CN202210076742 A CN 202210076742A CN 114293591 A CN114293591 A CN 114293591A
Authority
CN
China
Prior art keywords
hpvc
flexible pipe
concrete
inspection well
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210076742.7A
Other languages
Chinese (zh)
Inventor
齐小伟
陈甜阁
许德帅
赵保勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering No14 Construction Co ltd
Original Assignee
China National Chemical Engineering No14 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering No14 Construction Co ltd filed Critical China National Chemical Engineering No14 Construction Co ltd
Priority to CN202210076742.7A priority Critical patent/CN114293591A/en
Publication of CN114293591A publication Critical patent/CN114293591A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a combination device of an HPVC-U flexible pipe and a concrete inspection well, which comprises the inspection well and an HPVC-U flexible pipe arranged in the side wall of the inspection well in a penetrating way, wherein a concrete envelope is sleeved outside the end part of the HPVC-U flexible pipe, and the concrete envelope is arranged on the outer side wall of the inspection well. The invention has simple structure, saves cost, accelerates the project progress, solves the problem of new material HPVC-U pipe and the leakage node of the inspection well, and is beneficial to the popularization and application of new technology, new process and new material.

Description

Combination device of HPVC-U flexible pipe and concrete inspection well
Technical Field
The invention relates to the technical field of municipal engineering, in particular to a device for combining an HPVC-U flexible pipe and a concrete inspection well.
Background
In order to avoid the water seepage phenomenon at the joint of the concrete pipe, the design of the HPVC-U pipe is adopted, and the rubber ring is adopted at the joint of the pipes, so that the water seepage phenomenon at the joint between the pipes is avoided, but the water leakage between the HPVC-U pipe and the template well is difficult to block in the construction process, particularly, the large-area water seepage phenomenon exists at the joint of the HPVC-U pipe and the sewage inspection well, although the polyurethane waterproof coating is coated at the joint, the water leakage phenomenon is temporarily solved, and when the water level reaches the test water level, the water leakage phenomenon exists at part of the joint.
Disclosure of Invention
In order to solve the problems, the invention discloses a combination device of an HPVC-U flexible pipe and a concrete inspection well.
The specific scheme is as follows:
the device for combining the HPVC-U flexible pipe with the concrete inspection well is characterized by comprising the inspection well and an HPVC-U flexible pipe penetrating through the side wall of the inspection well, wherein a concrete envelope is sleeved outside the end part of the HPVC-U flexible pipe, and the concrete envelope is arranged on the outer side wall of the inspection well.
As a further improvement of the invention, the concrete envelope is of a cuboid structure and comprises a cushion layer horizontally arranged below the HPVC-U flexible pipe, two brick moulding beds are arranged on the cushion layer and symmetrically arranged on two sides of the HPVC-U flexible pipe, the brick moulding beds are connected with the outer side wall of the inspection well, concrete is filled between the two brick moulding beds, and the concrete is tightly coated outside the HPVC-U flexible pipe.
As a further improvement of the invention, a preformed hole for inserting the end part of the HPVC-U flexible pipe is formed in the side wall of the inspection well, a beam frame matched with the preformed hole is arranged in the preformed hole in a matched mode, and the beam frame is sleeved outside the end part of the HPVC-U flexible pipe.
As a further improvement of the invention, the concrete encapsulated by the concrete is filled in a gap between the beam frame and the HPVC-U flexible pipe, and a polyurethane waterproof coating layer is further coated in the inspection well.
As a further improvement of the invention, the concrete is C20 fine-stone concrete. The minimum thickness between the concrete envelope and the HPVC-U flexible pipe is more than 200 mm. The width of the brick moulding bed is 120 mm. The cushion layer is a C15 cushion layer with the thickness of 100 mm.
The construction method of the combination device is characterized by comprising the following steps:
s1: carefully checking whether the HPVC-U flexible pipe is damaged or not in the processes of loading, unloading, transporting and stacking, and if defects such as breakage, crack, deformation and the like are found, removing the defect;
s2: the connection between the HPVC-U flexible pipe and the inspection well is constructed according to a design drawing;
s3: the HPVC-U flexible pipe is connected with a brick-built or concrete-cast inspection well, and an intermediate layer method can be adopted, namely, a polyvinyl chloride adhesive and coarse sand are used in advance to form an intermediate layer on the outer surface of the joint part of the HPVC-U flexible pipe and the well wall, and then cement mortar is used for building the well wall of the inspection well;
s4: when the HPVC-U flexible pipe is flexibly connected with the inspection well, a precast concrete lantern ring and a rubber sealing joint can be used;
s5, the reserved aperture of the connection between the inspection well and the HPVC-U flexible pipe is larger than the outer diameter of the pipe or the pipe fitting by 0.2m, and the circumferential surface of the reserved aperture is roughened before installation;
s6: and the bottom sand stone cushion layer of the inspection shaft bottom plate base is gently connected with the pipeline base layer.
The invention has the beneficial effects that: the structure is simple, the cost is saved, the engineering progress is accelerated, the problem of the new material HPVC-U pipe and the water leakage joint of the inspection well is solved, and the popularization and the application of the new technology, the new process and the new material are facilitated.
Drawings
FIG. 1 is a cross-sectional view of a concrete envelope of the present invention.
FIG. 2 is a schematic view of a prepared hole of the inspection well according to the present invention.
List of reference numerals:
1-inspection well, 2-HPVC-U flexible pipe, 3-cushion layer, 4-brick bed film, 5-concrete and 6-beam frame.
Detailed Description
The present invention will be further illustrated with reference to the accompanying drawings and specific embodiments, which are to be understood as merely illustrative of the invention and not as limiting the scope of the invention.
As shown in the figure, the device for combining the HPVC-U flexible pipe with the concrete inspection well comprises the inspection well 1 and the HPVC-U flexible pipe 2 penetrating through the side wall of the inspection well, wherein a concrete envelope is sleeved outside the end part of the HPVC-U flexible pipe 2, and the concrete envelope is arranged on the outer side wall of the inspection well 1.
In the embodiment, the concrete envelope is of a cuboid structure and comprises a cushion layer 3 horizontally arranged below the HPVC-U flexible pipe 2, two brick moulding beds 4 are arranged on the cushion layer 3, the two brick moulding beds 4 are symmetrically arranged on two sides of the HPVC-U flexible pipe 2, the brick moulding beds 4 are connected with the outer side wall of the inspection well 1, concrete 5 is filled between the two brick moulding beds 4, and the concrete 5 is tightly wrapped outside the HPVC-U flexible pipe.
In the embodiment, a preformed hole for inserting the end part of the HPVC-U flexible pipe 1 is formed in the side wall of the inspection well 1, a beam frame 6 matched with the preformed hole is installed in the preformed hole in a matched mode, and the beam frame 6 is sleeved outside the end part of the HPVC-U flexible pipe 2.
In the embodiment, the concrete 5 encapsulated by the concrete is filled into the gap between the beam frame 6 and the HPVC-U flexible pipe 2, and a polyurethane waterproof coating layer is further coated in the inspection well 1.
In the present embodiment, the concrete 5 is C20 fine-grained concrete. The minimum thickness between the concrete envelope and the flexible tube of HPVC-U is greater than 200 mm. The width of the brick moulding bed 4 is 120 mm. The pad 3 was a 100mm thick pad of C15.
The invention also provides a construction method of the combination device of the HPVC-U flexible pipe and the concrete inspection well, which comprises the following steps:
s1: carefully checking whether the HPVC-U flexible pipe 2 is damaged or not in the processes of loading, unloading, transporting and stacking, and if defects such as breakage, crack, deformation and the like are found, removing the defects;
s2: the connection between the HPVC-U flexible pipe 2 and the inspection well 1 is constructed according to a design drawing;
s3: the HPVC-U flexible pipe 2 is connected with a brick-built or concrete-cast inspection well 1, and an intermediate layer method can be adopted, namely, a polyvinyl chloride adhesive and coarse sand are used in advance to form an intermediate layer on the outer surface of the joint part of the HPVC-U flexible pipe 2 and the well wall, and then cement mortar is used for building the well wall of the inspection well 1;
s4: when the HPVC-U flexible pipe 2 is flexibly connected with the inspection well 1, a precast concrete lantern ring and a rubber sealing joint can be used;
s5, the reserved aperture of the connection between the inspection well 1 and the HPVC-U flexible pipe 2 is larger than the outer diameter of the pipe or the pipe fitting by 0.2m, and the circumferential surface of the reserved aperture is roughened before installation;
s6: the sand cushion layer 3 on the bottom plate base of the inspection well 1 is gently connected with the pipeline foundation layer.
In addition, the invention is characterized in that:
1. the HPVC-U construction section pipes are covered in time, because chemical pipes are easy to expand with heat and contract with cold, particularly in summer, because the chemical pipes are hot in weather, and crack phenomena are easy to occur at joints after concrete pouring, the chemical pipes are covered in time, the pipes are really simple, the pipes are covered by medium coarse sand about 10cm according to design requirements in time, the pipes can be protected, the maintenance effect is achieved, when the weather is hot, water can be sprayed for maintenance, but the water quantity cannot be too large, so that the pipe ditch foundation is not damaged, and the bearing capacity of the foundation is not damaged;
2. the concrete encapsulation of the joint of the HPV-U and the concrete module well is also the key point of the technology, the encapsulated concrete adopts fine aggregate concrete, the construction mix proportion is strictly controlled, the excessive hydration heat of the concrete is avoided, the cement adopts common silicate concrete, the template adopts a brick moulding bed and adopts 360-degree encapsulation, the original design adopts 180-degree encapsulation, the water leakage problem can be solved by adopting 50cm in length, the concrete material is saved compared with the original design, but the water leakage problem is solved, after the concrete pouring is finished, the concrete should be covered with water for maintenance in time, and the phenomena of cracking and water leakage can also occur when the concrete is not maintained in time;
3. the polyurethane waterproof coating is a mature construction process and is widely applied to room water leakage repair, roof water leakage repair and outer wall water seepage phenomena, and is also widely applied to sewer well maintenance.
The technical means disclosed in the invention scheme are not limited to the technical means disclosed in the above embodiments, but also include the technical scheme formed by any combination of the above technical features. It should be noted that those skilled in the art can make various improvements and modifications without departing from the principle of the present invention, and such improvements and modifications are also considered to be within the scope of the present invention.

Claims (9)

  1. The device for combining the HPVC-U flexible pipe with the concrete inspection well is characterized by comprising the inspection well (1) and an HPVC-U flexible pipe (2) penetrating through the side wall of the inspection well, wherein a concrete envelope is sleeved outside the end part of the HPVC-U flexible pipe (2), and the concrete envelope is arranged on the outer side wall of the inspection well (1).
  2. 2. The device for combining the HPVC-U flexible pipe with the concrete inspection well is characterized in that the concrete is packaged into a cuboid structure and comprises a cushion layer (3) horizontally arranged below an HPVC-U flexible pipe (2), two brick bed moulds (4) are arranged on the cushion layer (3), the two brick bed moulds (4) are symmetrically arranged at two sides of the HPVC-U flexible pipe (2), the brick bed moulds (4) are connected with the outer side wall of the inspection well (1), concrete (5) is filled between the two brick bed moulds (4), and the concrete (5) is tightly wrapped outside the HPVC-U flexible pipe.
  3. 3. The device for combining the HPVC-U flexible pipe with the concrete inspection well as recited in claim 2, wherein a preformed hole for inserting the end of the HPVC-U flexible pipe (1) is formed in the side wall of the inspection well (1), a beam frame (6) matched with the preformed hole is installed in the preformed hole in a matching manner, and the beam frame (6) is sleeved outside the end of the HPVC-U flexible pipe (2).
  4. 4. The device for combining the HPVC-U flexible pipe and the concrete inspection well is characterized in that the concrete (5) encapsulated by the concrete is filled into a gap between a beam frame (6) and the HPVC-U flexible pipe (2), and a polyurethane waterproof coating layer is further painted in the inspection well (1).
  5. 5. Device for joining an HPVC-U flexible pipe to a concrete manhole according to claim 2, characterised in that said concrete (5) is C20 fine stone concrete.
  6. 6. The HPVC-U flexible tubing and concrete manhole combination according to claim 2, wherein the minimum thickness between the concrete envelope and the HPVC-U flexible pipe is greater than 200 mm.
  7. 7. Device for joining an HPVC-U flexible pipe material to a concrete manhole according to claim 2, wherein the width of the membrane (4) is 120 mm.
  8. 8. Device according to claim 2, characterized in that said bedding (3) is a C15 bedding of 100mm thickness.
  9. 9. The construction method of the combination device according to any one of claims 1 to 8, characterized by comprising the following steps:
    s1: carefully checking whether the HPVC-U flexible pipe (2) is damaged or not in the processes of loading, unloading, transporting and stacking, and if defects such as breakage, crack, deformation and the like are found, removing the defects;
    s2: the connection between the HPVC-U flexible pipe (2) and the inspection well (1) is constructed according to a design drawing;
    s3: the HPVC-U flexible pipe (2) is connected with a brick-laid or concrete-cast inspection well (1), and an intermediate layer manufacturing method can be adopted, namely, a polyvinyl chloride adhesive and coarse sand are used in advance for manufacturing an intermediate layer on the outer surface of the joint part of the HPVC-U flexible pipe (2) and the well wall, and then cement mortar is used for building the well wall of the inspection well (1);
    s4: when the HPVC-U flexible pipe (2) is flexibly connected with the inspection well (1), a precast concrete lantern ring and a rubber sealing joint can be used;
    s5, the reserved aperture of the connection between the inspection well (1) and the HPVC-U flexible pipe (2) is larger than the outer diameter of the pipe or the pipe fitting by 0.2m, and the circumferential surface of the reserved aperture is roughened before installation;
    s6: the sand-rock cushion layer (3) of the bottom plate base of the inspection well (1) is gently connected with the pipeline foundation layer.
CN202210076742.7A 2022-01-24 2022-01-24 Combination device of HPVC-U flexible pipe and concrete inspection well Pending CN114293591A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210076742.7A CN114293591A (en) 2022-01-24 2022-01-24 Combination device of HPVC-U flexible pipe and concrete inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210076742.7A CN114293591A (en) 2022-01-24 2022-01-24 Combination device of HPVC-U flexible pipe and concrete inspection well

Publications (1)

Publication Number Publication Date
CN114293591A true CN114293591A (en) 2022-04-08

Family

ID=80977410

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210076742.7A Pending CN114293591A (en) 2022-01-24 2022-01-24 Combination device of HPVC-U flexible pipe and concrete inspection well

Country Status (1)

Country Link
CN (1) CN114293591A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2546500Y (en) * 2002-04-17 2003-04-23 北京市市政工程研究院 Precast assembling concrete manhole
JP2009114771A (en) * 2007-11-08 2009-05-28 Sanritsu:Kk Earthquakeproof flexible joint
CN211312769U (en) * 2019-09-12 2020-08-21 中国水利水电第十四工程局有限公司 Connecting member of plastic pipe and concrete prefabricated inspection well
CN113293802A (en) * 2021-06-29 2021-08-24 中建三局集团有限公司 Construction method of inspection well

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2546500Y (en) * 2002-04-17 2003-04-23 北京市市政工程研究院 Precast assembling concrete manhole
JP2009114771A (en) * 2007-11-08 2009-05-28 Sanritsu:Kk Earthquakeproof flexible joint
CN211312769U (en) * 2019-09-12 2020-08-21 中国水利水电第十四工程局有限公司 Connecting member of plastic pipe and concrete prefabricated inspection well
CN113293802A (en) * 2021-06-29 2021-08-24 中建三局集团有限公司 Construction method of inspection well

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
丁绍兰,马飞编著: "《革制品材料学》", 中国轻工业出版社 *
王水华等: "一种随路基沉降式检查井井盖及支座安装方法介绍", 《特种结构》 *

Similar Documents

Publication Publication Date Title
US5002438A (en) Method of rehabilitating manholes by custom lining/relining
CN201232197Y (en) Combined inspection well
CN109440951B (en) Waterproof structure for joint of new and old concrete structures and construction process
CN101761096B (en) Anti-crack and anti-leak construction method of arranging tower crane foundation below waterproof baseplate
CN109026079B (en) Tunnel joint waterproof structure and waterproof construction method
CN112832279B (en) Waterproof structure and method for dewatering well of underground foundation pit
CN111764428A (en) Trapezoidal socket structure of underground municipal comprehensive pipe gallery and construction method thereof
CN106013471A (en) Anti-seepage construction method for expansion joint
CN202131613U (en) Lined prefabricated reinforced concrete inspection well
CN113513048A (en) Station house underground passage leakage-proof structure and construction process
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
CN213541549U (en) Waterproof plugging structure of floor pipeline sleeve pipe
CN114293591A (en) Combination device of HPVC-U flexible pipe and concrete inspection well
CN211312769U (en) Connecting member of plastic pipe and concrete prefabricated inspection well
CN216787229U (en) Basement outer wall post-cast strip assembled shutoff steel sheet structure
CN214363658U (en) Seamless waterproof structure of prestressed anchor rod reverse construction method
CN112482446A (en) Construction method for spraying outer water-proof film on bottom plate of comprehensive pipe gallery
CN219653866U (en) Inspection shaft and HDPE winding reinforcing pipe connection structure
CN111365030A (en) Tunnel concrete lining structure gap water leakage treatment device and treatment method
CN218719380U (en) Roof penetrating waterproof sleeve based on main structure embedding
CN217502850U (en) Waterproof construction suitable for vertical pipeline water repellent
CN211371504U (en) Toilet downpipe wall-penetrating pipe table structure
CN219588298U (en) Waterproof shutoff structure of basement outer wall steam pipeline
CN217603531U (en) Pipeline wall body junction antiseep device
CN214699575U (en) Steel cylinder concrete pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220408