CN114277834B - Wind power single pile foundation and construction method - Google Patents
Wind power single pile foundation and construction method Download PDFInfo
- Publication number
- CN114277834B CN114277834B CN202210011630.3A CN202210011630A CN114277834B CN 114277834 B CN114277834 B CN 114277834B CN 202210011630 A CN202210011630 A CN 202210011630A CN 114277834 B CN114277834 B CN 114277834B
- Authority
- CN
- China
- Prior art keywords
- steel
- single pile
- steel pipe
- pile
- baffle plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 153
- 239000010959 steel Substances 0.000 claims abstract description 153
- 239000002689 soil Substances 0.000 claims abstract description 28
- 230000035515 penetration Effects 0.000 claims description 8
- 238000002347 injection Methods 0.000 claims description 4
- 239000007924 injection Substances 0.000 claims description 4
- 238000003466 welding Methods 0.000 claims description 4
- 239000004568 cement Substances 0.000 claims description 3
- 238000009826 distribution Methods 0.000 claims description 2
- 230000006978 adaptation Effects 0.000 claims 2
- 230000007423 decrease Effects 0.000 claims 2
- 230000005611 electricity Effects 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 10
- 230000000694 effects Effects 0.000 abstract description 5
- 238000004519 manufacturing process Methods 0.000 abstract description 4
- 230000002708 enhancing effect Effects 0.000 abstract 1
- 238000009933 burial Methods 0.000 description 3
- 230000001681 protective effect Effects 0.000 description 3
- 239000013535 sea water Substances 0.000 description 3
- 238000007789 sealing Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 239000002002 slurry Substances 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
- E02D27/525—Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/40—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2200/00—Geometrical or physical properties
- E02D2200/16—Shapes
- E02D2200/1685—Shapes cylindrical
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0061—Production methods for working underwater
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2240/00—Components
- F05B2240/90—Mounting on supporting structures or systems
- F05B2240/95—Mounting on supporting structures or systems offshore
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/727—Offshore wind turbines
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Paleontology (AREA)
- Mining & Mineral Resources (AREA)
- Sustainable Energy (AREA)
- Mechanical Engineering (AREA)
- Combustion & Propulsion (AREA)
- Chemical & Material Sciences (AREA)
- Sustainable Development (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a wind power single pile foundation and a construction method, which comprises a single pile, wherein a prefabricated member group is arranged in the single pile, the prefabricated member group comprises a truss, a steel shaft, a pile casing and a baffle plate component, the truss and the baffle plate component are respectively fixed at the upper side and the lower side in the single pile, the steel shaft penetrates through the center of the truss and the baffle plate component to be fixed, the pile casing is sleeved at the upper section of the steel shaft, a jack is fixed at the lower end of the pile casing, a plurality of steel pipes are arranged between the steel shaft and the pile casing at intervals along the circumferential direction, the middle section of each steel pipe is connected with a top plate of the jack, the baffle plate component is used for enhancing the soil plug effect in the piling process, after piling is finished, the jack drives the steel pipe to move and drives the lower section of the steel pipe to slide along the chute of the baffle plate component and pass through the constructional hole to enter the soil body around the single pile, and the soil body around the pile is grouted and reinforced through the seamless steel pipe, so that the vertical, horizontal and anti-torsion bearing capacity of the single-pile foundation is comprehensively improved. The invention greatly improves the pulling resistance, overturning resistance and torsion resistance bearing capacity of the single pile for manufacturing the wind generating set.
Description
Technical Field
The invention relates to a wind power generation device and a construction method, in particular to a wind power single-pile foundation and a construction method.
Background
Currently, the clean and sustainable development of energy is a common concern in all countries of the world, and the gradual replacement of traditional fossil energy by clean green energy is a necessary trend. Therefore, offshore wind power construction has good resource potential and application prospect in China.
In the process of constructing an offshore wind farm, the wind power foundation is a key factor for ensuring reasonable budget and normal operation of a fan, whether in cost control or stability and reliability. According to statistics of BOEM company, in general offshore wind power project cost, a fan accounts for the largest proportion, and accounts for about 33% of the total cost; secondly, the wind power basis is 19 percent. Therefore, reasonable basic model selection and design are important links in saving cost and shortening construction period of offshore wind power. The wind power projects built and under construction are mostly concentrated in shallow sea areas, wherein a large-diameter single-pile foundation becomes the dominant foundation form.
The design idea of the large-diameter single-pile foundation of the offshore wind power at the present stage is very conservative, and the large-diameter single-pile foundation has the problems of high construction difficulty, complex environment and the like. On the basis of not increasing the construction difficulty and the construction period, the uplift resistance, the overturning resistance and the torsion resistance bearing capacity of a single pile for manufacturing the wind generating set are greatly improved, the pile length is shortened, the construction cost is obviously reduced, and the method is a difficult problem which is urgently needed to be solved in the industry at present.
Disclosure of Invention
The purpose of the invention is as follows: the invention aims to provide a wind power single-pile foundation, which solves the problems that the existing single-pile foundation can not greatly improve the uplift resistance, the overturn resistance and the torsion resistance bearing capacity of a single pile for manufacturing a wind generating set on the basis of not increasing the construction difficulty and the construction period, shorten the pile length, enlarge the effective pile diameter and reinforce the soil mass around the pile.
The invention also aims to provide a construction method of the wind power single pile foundation.
The technical scheme is as follows: the wind power single pile foundation comprises a single pile, wherein a prefabricated component group is arranged in the single pile, the prefabricated member group comprises a truss, a steel shaft, a pile casing and a baffle plate component, the truss and the baffle plate component are respectively fixed on the upper side and the lower side in the single pile, the steel shaft penetrates through the truss and is fixed with the center of the baffle plate component, the protecting cylinder is sleeved on the upper section of the steel shaft, the lower end of the protecting cylinder is fixed with a jack, a plurality of steel pipes are arranged between the steel shaft and the protective cylinder at intervals along the circumferential direction, each steel pipe comprises an upper steel pipe section, a middle steel pipe section and a lower steel pipe section which are connected through flexible interfaces, the middle section of the steel pipe is connected with the top plate of the jack, the lower section of the steel pipe extends along the surface of the baffle plate component and can slide along the baffle plate component, and the single pile is provided with a structural hole for the steel pipe to pass through, and the jack drives the steel pipe to act to drive the lower section of the steel pipe to slide along the baffle plate assembly sliding groove to pass through the structural hole and enter soil around the single pile.
The protective cylinder is convenient to fix, and the cylinder wall at the upper end of the protective cylinder is welded and fixed with the steel truss.
The baffle assembly comprises an upper baffle and a lower baffle, the centers of the upper baffle and the lower baffle are provided with through holes matched with the steel shaft, the surface of the upper baffle is provided with a sliding groove matched with the lower section of the steel pipe, and the upper baffle and the lower baffle are circumferentially distributed with sector blanks and sector steel plates in a staggered manner.
In order to ensure that a gap is reserved in the vertical direction after the upper baffle and the lower baffle are closed, and the seawater is convenient to discharge, the included angle between the normal of the surface of the upper baffle fan-shaped steel plate and the axis of the steel shaft is larger than the included angle between the normal of the surface of the lower baffle fan-shaped steel plate and the axis of the steel shaft.
The soil plug is formed in the piling process and the structural damage of the baffle is avoided, the plate thickness of the upper baffle is linearly reduced from the center to the edge, and the wall thickness of the lower baffle is linearly reduced from the edge to the center.
In order to ensure uniform grouting, the surface of the lower section of the steel pipe is provided with a hole, and one end extending to a soil body is of a tip structure.
And (5) avoiding local damage of the structure, and welding stiffening ribs around the construction hole.
The flexible interface is a flexible sealing pipeline.
The construction method of the wind power single pile foundation comprises the following steps:
(1) welding the prefabricated member group at the specified position of the single pile;
(2) before piling, the upper baffle plate is overlapped with the lower baffle plate, and the fan-shaped blank spaces of the upper baffle plate are aligned with the fan-shaped blank spaces of the lower baffle plate;
(3) when the number of single pile injection hammering is obviously increased and the injection depth exceeds the depth of the lower baffle, stopping piling, and rotating the steel shaft anticlockwise to enable the fan-shaped steel plate of the upper baffle to cover the fan-shaped blank of the lower baffle, wherein the tip structures of the lower sections of the steel pipes correspond to the structure holes one by one, and the steel shaft is welded and fixed with the steel truss;
(4) stopping piling when the penetration depth of the single pile reaches the designed burial depth, starting the jack, and driving the lower section of the steel pipe to be completely pressed into the soil body by the jack;
(5) starting grouting equipment to perform grouting on the steel pipe, and pouring cement paste into a soil body through the steel pipe;
(6) and after grouting is stopped, pouring one end of the seamless steel pipe, which is far away from the soil body, and the bearing platform into a whole.
Has the advantages that: according to the single-pile foundation, the baffle plate assembly is adopted at the designed depth position inside the steel pipe to enhance the soil plug effect, the steel pipe extends out of the baffle plate position to the pile wall, and the soil body around the pile is reinforced through the steel pipe by adopting a mud jacking method, so that the vertical, horizontal and anti-torsion bearing capacity of the offshore wind power large-diameter single-pile foundation is comprehensively improved. The invention can greatly improve the uplift resistance, overturn resistance and torsion resistance bearing capacity of the single pile for manufacturing the wind generating set, shorten the pile length, enlarge the effective pile diameter, reinforce the soil body around the pile and effectively reduce the construction cost.
Drawings
FIG. 1 is an overall schematic view of the novel mono-pile foundation of the present invention;
FIG. 2 is a sectional view of the construction of the pre-pile driving member set of the present invention;
FIG. 3 is a top plan view of the steel truss arrangement of the present invention;
FIG. 4 is a top view of the arrangement of the steel casing, the seamless steel pipe and the steel shaft according to the present invention;
FIG. 5 is a schematic view of the seamless steel pipe joint of the present invention;
FIG. 6 is a top view of the upper baffle of the present invention;
FIG. 7 is a top view of a lower baffle of the present invention;
FIG. 8 is a schematic view of a steel pipe pile with structural holes and reinforcing ribs according to the present invention;
FIG. 9 is a cross-sectional view of a pre-grouting component set in accordance with the invention;
FIG. 10 is a top view of the upper shield before grouting after rotation;
FIG. 11 is a schematic view of the construction of the lower section of a seamless steel pipe;
FIG. 12 is a schematic representation of the slurry distribution after grouting.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
As shown in fig. 1-2, the wind power single pile foundation disclosed by the invention comprises a single pile 2, a wind power generator set and a bearing platform 1 are fixedly connected to the upper end of the single pile 2, a prefabricated member set 3 is arranged in the single pile 2, the prefabricated member set comprises a steel truss 31, a steel casing 32, a plurality of seamless steel pipes 33, a jack 34, a steel shaft 35, an upper baffle plate 36 and a lower baffle plate 37, and the number of the seamless steel pipes in the embodiment is 8. The total length of the member group 3 can be adjusted according to the soil plug effect and the lifting requirement of the vertical bearing capacity, the length adopted in the embodiment is slightly smaller than 1/3 of the soil penetration depth of the single pile 2, and the distance between the opening of the single pile 2 and the steel truss 31 is 2 m.
As shown in fig. 3-5, the cylinder wall of the upper end of the steel casing 32 is welded and fixed to the upper surface of the steel truss 31, the steel casing 32 and the steel shaft 35 are coaxially sleeved and penetrate through the center of the steel truss 31, 8 seamless steel pipe upper sections 331 are axially distributed at intervals along the axis between the steel casing 32 and the steel shaft 35, the seamless steel pipe upper sections 331 and the middle section 332 are connected by flexible connectors 335, the top plate of the jack 34 is connected with the flexible connectors 335 of the seamless steel pipe upper sections 331 and the middle section 332, the flexible connectors 335 can be made of flexible sealed pipelines such as annular grouting pipes, and the flexible connectors provide a hinged form, only transmit force and do not transmit deformation and moment. One end of the flexible interface 335 close to the upper section of the seamless steel tube is welded and fixed at the lifting end of the jack 34, the fixed chassis of the jack 34 is welded and fixed with the lower end of the steel casing 32, and the hollow part of the jack 34 coaxially penetrates through the steel shaft 35 and the seamless steel tube 33. One end of the seamless steel tube upper section 331 and one end of the steel shaft 35 extend out of the steel casing 32, in order to ensure the stability of the seamless steel tube upper section 331 in the construction process, the steel wire can be wound to be temporarily fixed on the steel shaft 35, the steel truss 31 and the steel casing 32 provide counter force for the jack, the jack 34 is provided with a hole penetrating through the center, and the hole can meet the requirement that all seamless steel tubes and the steel shaft penetrate and can provide vertical downward thrust. The jack 34 may be a one-way or two-way hollow jack.
As shown in fig. 6-7, the baffle plate assembly comprises an upper baffle plate 36 and a lower baffle plate 37, in order to facilitate seawater discharge and ensure smooth driving process, a hole is reserved in the center of the upper baffle plate 36 and the lower baffle plate 37, 8 fan-shaped blank spaces and fan-shaped steel plates are distributed in an equidistant and staggered mode along the circumferential direction of the center, the thickness of the upper baffle plate 36 is linearly reduced from the center to the edge, the thickness of the center plate is twice that of the edge, the thickness of the edge is equal to that of the wall of the single pile 2, the thickness of the wall of the lower baffle plate 37 is linearly reduced from the edge to the center, the thickness of the edge is twice that of the center, and the thickness of the center plate is equal to that of the wall of the single pile 2. The center of the upper baffle plate 36 is coaxially welded and fixed with the steel shaft, the other end is free, and the diameter of the upper baffle plate is slightly smaller than that of the lower baffle plate 37; the outer edge of the lower baffle plate 37 is welded and fixed with the single pile 2, and the other end is coaxially sleeved at the tail end of the steel shaft 35. In the initial stage of piling. In order to discharge seawater and ensure that the piling process is carried out smoothly, the upper baffle plate 36 is right opposite to the lower baffle plate 37, and the bottom end of the component group forms a form of 8 sector-shaped blank spaces which are symmetrically distributed at equal intervals in a staggered manner along the center. The included angle between the normal of the plane of each fan-shaped steel plate of the upper baffle plate 36 and the axis of the steel shaft is required to be larger than the included angle corresponding to the lower baffle plate. In this embodiment, the included angles between the normal of the plane where the 8 steel plates of the upper baffle 36 are located and the axis of the steel shaft are all 10 °, and the included angles between the normal of the plane where the 8 steel plates of the lower baffle are located and the axis of the steel shaft are all 5 °. The 8 steel sheet surfaces of overhead gage all open chisel have with seamless steel pipe assorted spout 361, 8 seamless steel pipe middle sections and hypomere adopt flexible interface sealing connection in spout department, for guaranteeing that the mud jacking is even, seamless steel pipe hypomere 334 surface gathers the aperture, the one end that extends to the soil body is most advanced structure, seamless steel pipe hypomere 334 can be followed the spout and slided, for guaranteeing seamless steel pipe upper segment, the middle section, the hypomere links to each other and forms complete mud jacking passageway, the junction is flexible interface connection, flexible interface material can adopt flexible sealing pipeline materials such as annular mud jacking pipe, its length is approximately equal to the diameter (D) of twice seamless steel pipe, flexible interface is the transmission power only of articulated form, do not transmit deformation and moment.
As shown in fig. 8, the base of the jack 34 is welded and fixed with the lower end of the steel casing 32, the middle section of the seamless steel pipe is pushed downwards by the other end, the lower sections of the 8 seamless steel pipes are linked to slide along the corresponding sliding grooves, penetrate through the structural holes and are jacked into the soil around the single pile 2, when the lower section 333 of the seamless steel pipe completely enters the soil, the included angle between the middle section of the seamless steel pipe and the axis of the steel shaft is 30 degrees, the length of the lower section 333 of the seamless steel pipe is equal to the radius of the single pile 2, the single pile 2 is provided with structural holes matched with the lower section of the seamless steel pipe near the upper baffle, and the stiffening ribs 21 are welded around the structural holes to prevent the local structure of the single pile from being damaged.
As shown in fig. 9-10, when the number of single pile penetration hammering is significantly increased and the penetration depth exceeds 2/3 of the designed burial depth, the steel shaft is rotated counterclockwise by 22.5 degrees, so that the upper baffle 36 covers the blank space on the lower baffle 37, the lower segments and the middle segments of 8 seamless steel pipes are rotated along with the upper baffle, the tip structures of the lower segments of 8 seamless steel pipes are in one-to-one correspondence with the structural holes, and the slight rotation of the middle segments of 8 seamless steel pipes does not affect the linkage effect of a jack on the middle segments and the lower segments. The upper baffle 36 covers the lower baffle 37, so that the soil mass in the single pile is prevented from upwelling in the piling process, the soil plug effect is enhanced, and the bearing capacity of the single pile is improved. Because the inclined angles of the surfaces of the upper baffle plate 36 and the lower baffle plate 37 are different, a certain gap is reserved between the two plates in the vertical direction, so that the water pressure of the soil body in the pile in the piling process is dissipated, and the smooth construction is ensured. In the embodiment, the diameter of the steel pile casing is 1/6-1/4 of the diameter of the single pile, and the wall thickness of the single pile are 1/8-1/6 of the wall thickness of the single pile, and the steel pile casing can be adjusted according to the actual size of the single pile.
During construction, the invention comprises the following steps:
(1) welding the member group at the designated position of the single pile, and transporting the member group to a designated place for construction after the member group is assembled with the single pile;
(2) before piling, the upper baffle plate is overlapped with the lower baffle plate, and at the moment, 8 blank spaces of the upper baffle plate are aligned with 8 blank spaces of the lower baffle plate;
(3) when the number of the single pile penetration hammering is obviously increased and the penetration depth exceeds 2/3 of the designed burial depth, stopping piling, and rotating the steel shaft anticlockwise to enable 8 steel plates of the upper baffle plate to cover 8 blank spaces of the lower baffle plate, wherein the tip structures of the lower sections of the 8 seamless steel pipes correspond to the structure holes one by one, and the steel shaft and the steel truss are welded firmly;
(4) stopping piling until the penetration depth of the single pile reaches the designed buried depth, starting a jack, and completely pressing the lower sections of the 8 seamless steel pipes into the soil body;
(5) starting grouting equipment, grouting 8 seamless steel pipes, and pouring cement slurry into a soil body;
(6) and after grouting is stopped, pouring one end of each of the 8 seamless steel pipes close to the fan and a bearing platform into a whole.
Claims (9)
1. The wind power single pile foundation comprises a single pile (2) and is characterized in that a prefabricated member group (3) is arranged in the single pile (2) and comprises a steel truss (31), a steel shaft (35), a pile casing (32) and a baffle assembly, the steel truss (31) and the baffle assembly are respectively fixed on the upper side and the lower side of the single pile (2), the steel shaft (35) penetrates through the steel truss (31) and the center of the baffle assembly to be fixed, the pile casing (32) is sleeved on the upper section of the steel shaft (35), a jack (34) is fixed at the lower end of the pile casing (32), a plurality of steel pipes (33) are arranged between the steel shaft (35) and the pile casing (32) at intervals along the circumferential direction, each steel pipe comprises a steel pipe upper section (331), a steel pipe middle section (332) and a steel pipe lower section (333) which are connected through a flexible interface, the steel pipe middle section (332) is connected with a top plate of the jack (34), the steel pipe lower section (333) extends along the surface of the baffle assembly and can slide along the baffle assembly, a structural hole (22) for the steel pipe (33) to pass through is formed in the single pile (2), and the jack (34) drives the steel pipe lower section (333) to slide along the baffle assembly sliding groove to pass through the structural hole and enter soil around the single pile (2).
2. The wind power single pile foundation according to claim 1, characterized in that the wall of the upper end of the casing (32) is welded and fixed with the steel truss (31).
3. The wind-powered electricity generation single pile basis of claim 1, characterized in that, the baffle subassembly includes overhead gage (36) and lower baffle (37), overhead gage (36) and lower baffle (37) center are provided with the through-hole with steel axle (35) adaptation, the spout (361) with steel pipe lower segment adaptation is seted up on overhead gage (36) surface, overhead gage (36) and lower baffle (37) are along central circumference crisscross distribution fan-shaped blank and fan-shaped steel sheet.
4. A wind power single pile foundation according to claim 3, wherein the included angle between the normal of the sector-shaped steel plate surface of the upper baffle (36) and the axis of the steel shaft is larger than the included angle between the normal of the sector-shaped steel plate surface of the lower baffle (37) and the axis of the steel shaft.
5. The wind power single pile foundation according to claim 1, characterized in that the plate thickness of the upper baffle (36) decreases linearly from the center to the edge, and the plate thickness of the lower baffle (7) decreases linearly from the edge to the center.
6. The wind power single pile foundation according to claim 1, characterized in that the surface of the lower section (333) of the steel pipe is provided with holes, and one end extending to the soil body is of a tip structure.
7. Wind power single pile foundation according to claim 1, characterised in that stiffening ribs (21) are welded around the structural holes (22).
8. The wind-powered single pile foundation of claim 1, wherein the flexible interface is a flexible sealed conduit.
9. The construction method of the wind power single pile foundation according to claim 1, characterized by comprising the steps of:
(1) welding the prefabricated member group at the specified position of the single pile;
(2) before piling, the upper baffle plate is overlapped with the lower baffle plate, and the fan-shaped blank spaces of the upper baffle plate are aligned with the fan-shaped blank spaces of the lower baffle plate;
(3) when the number of the single pile injection hammering is obviously increased and the injection depth exceeds the depth of the lower baffle plate, the pile driving is suspended, the steel shaft is rotated anticlockwise, the fan-shaped steel plate of the upper baffle plate covers the fan-shaped blank of the lower baffle plate, the tip structures of the lower sections of the steel pipes correspond to the structural holes one by one, and the steel shaft and the steel truss are welded and fixed;
(4) stopping piling when the penetration depth of the single pile reaches the designed buried depth, starting a jack, and driving the lower section of the steel pipe to be completely pressed into the soil body by the jack;
(5) starting grouting equipment to carry out grouting on the steel pipe, and pouring cement paste into a soil body through the steel pipe to reinforce;
(6) and after grouting is stopped, pouring one end of the seamless steel pipe, which is far away from the soil body, and the bearing platform into a whole.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210011630.3A CN114277834B (en) | 2022-01-06 | 2022-01-06 | Wind power single pile foundation and construction method |
PCT/CN2022/114373 WO2023130739A1 (en) | 2022-01-06 | 2022-08-24 | Single pile foundation for wind generating set and construction method |
KR1020227044858A KR20230107748A (en) | 2022-01-06 | 2022-08-24 | Wind power generation single pile foundation and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210011630.3A CN114277834B (en) | 2022-01-06 | 2022-01-06 | Wind power single pile foundation and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114277834A CN114277834A (en) | 2022-04-05 |
CN114277834B true CN114277834B (en) | 2022-09-23 |
Family
ID=80880575
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210011630.3A Active CN114277834B (en) | 2022-01-06 | 2022-01-06 | Wind power single pile foundation and construction method |
Country Status (3)
Country | Link |
---|---|
KR (1) | KR20230107748A (en) |
CN (1) | CN114277834B (en) |
WO (1) | WO2023130739A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114277834B (en) * | 2022-01-06 | 2022-09-23 | 江苏科技大学 | Wind power single pile foundation and construction method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2662495A1 (en) * | 2012-05-09 | 2013-11-13 | Alstom Wind, S.L.U. | Wind turbine foundation |
CN104727315A (en) * | 2015-03-26 | 2015-06-24 | 上海市房屋建筑设计院有限公司 | Post-grouting prestressed concrete hollow pile and manufacturing method thereof |
CN105862905A (en) * | 2016-05-27 | 2016-08-17 | 福建省新能海上风电研发中心有限公司 | Rock-socketed single pile foundation through offshore wind power and construction method of rock-socketed single pile foundation |
CN106088087A (en) * | 2016-08-15 | 2016-11-09 | 中国电建集团华东勘测设计研究院有限公司 | A kind of embedding rock single pile bitubular construction auxiliary device and construction method thereof |
CN106906840A (en) * | 2017-03-31 | 2017-06-30 | 华电重工股份有限公司 | The method of offshore wind farm rock-socketed steel pipe piles and the outer grouting construction of stake |
CN209429159U (en) * | 2018-11-22 | 2019-09-24 | 中国电建集团成都勘测设计研究院有限公司 | Offshore wind farm single-pile foundation |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN206289651U (en) * | 2016-08-10 | 2017-06-30 | 福建省新能海上风电研发中心有限公司 | A kind of offshore wind power foundation structure of single pile anchoring |
DE102019102464A1 (en) * | 2019-01-31 | 2020-08-06 | Innogy Se | Monopile foundation and monopile foundation installation for an offshore structure and method for establishing a monopile foundation installation |
CN213329092U (en) * | 2020-08-18 | 2021-06-01 | 中国长江三峡集团有限公司 | Offshore wind power ultra-large diameter single pile composite foundation |
CN113718831A (en) * | 2021-09-16 | 2021-11-30 | 中国华能集团清洁能源技术研究院有限公司 | Offshore wind power reinforcing device and method |
CN114277834B (en) * | 2022-01-06 | 2022-09-23 | 江苏科技大学 | Wind power single pile foundation and construction method |
-
2022
- 2022-01-06 CN CN202210011630.3A patent/CN114277834B/en active Active
- 2022-08-24 WO PCT/CN2022/114373 patent/WO2023130739A1/en unknown
- 2022-08-24 KR KR1020227044858A patent/KR20230107748A/en unknown
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2662495A1 (en) * | 2012-05-09 | 2013-11-13 | Alstom Wind, S.L.U. | Wind turbine foundation |
CN104727315A (en) * | 2015-03-26 | 2015-06-24 | 上海市房屋建筑设计院有限公司 | Post-grouting prestressed concrete hollow pile and manufacturing method thereof |
CN105862905A (en) * | 2016-05-27 | 2016-08-17 | 福建省新能海上风电研发中心有限公司 | Rock-socketed single pile foundation through offshore wind power and construction method of rock-socketed single pile foundation |
CN106088087A (en) * | 2016-08-15 | 2016-11-09 | 中国电建集团华东勘测设计研究院有限公司 | A kind of embedding rock single pile bitubular construction auxiliary device and construction method thereof |
CN106906840A (en) * | 2017-03-31 | 2017-06-30 | 华电重工股份有限公司 | The method of offshore wind farm rock-socketed steel pipe piles and the outer grouting construction of stake |
CN209429159U (en) * | 2018-11-22 | 2019-09-24 | 中国电建集团成都勘测设计研究院有限公司 | Offshore wind farm single-pile foundation |
Also Published As
Publication number | Publication date |
---|---|
CN114277834A (en) | 2022-04-05 |
KR20230107748A (en) | 2023-07-18 |
WO2023130739A1 (en) | 2023-07-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114277834B (en) | Wind power single pile foundation and construction method | |
CN109267567B (en) | Steel pipe pile with pile end and pile side capable of being subjected to grouting in converted mode and pouring process of steel pipe pile | |
WO2021184746A1 (en) | Wind turbine base having composite cylindrical structure | |
CN209636843U (en) | Offshore wind turbine suction bucket jacket large-diameter pile composite foundation | |
CN113279425A (en) | Offshore wind power single-pile composite novel cylindrical foundation with wings and construction method thereof | |
CN204608782U (en) | Pile-sinking device is dug in static pressure | |
CN112252989B (en) | Ultra-large-diameter rotary drilling bit | |
CN210827547U (en) | Spiral pile composite cylindrical foundation for offshore wind turbine | |
CN115305943B (en) | Offshore steel tube concrete high-pile cap fan foundation and construction method thereof | |
CN112411528A (en) | Novel spiral steel pipe pile and construction process thereof | |
CN206800379U (en) | Grouting behind shaft or drift lining pre-stress hollow square pile | |
CN110593298A (en) | Composite foundation for improving bearing performance of cylindrical foundation by using auxiliary piles and construction method thereof | |
CN113513039B (en) | Marine wind power variable-diameter spiral pile composite cylindrical foundation and construction mode thereof | |
CN101936011B (en) | Bayonet binding-type connection method of steel sleeve box blocks and construction method using same | |
CN105155573A (en) | Offshore wind turbine barrel-in-barrel foundation | |
CN210827544U (en) | Composite foundation for improving bearing performance of cylindrical foundation by using auxiliary piles | |
CN111412112B (en) | Construction method of floating jacket pile foundation structure | |
CN211547794U (en) | Multi-cylinder jacket foundation connected by grouting | |
CN204125957U (en) | Flange transition interconnection system single-pile foundation structure | |
CN209973377U (en) | Direct-buried trash can with remote control electric cover opening function | |
CN202672139U (en) | Prefabricated reinforced concrete square pile | |
CN210827538U (en) | Compound circular basis with screw pile | |
CN219118220U (en) | Marine fan single pile foundation with cylindrical friction supporting structure | |
CN219080396U (en) | Deep water offshore wind power truss single pile combined foundation | |
LU505248B1 (en) | Blade screw pile and screw pile driving system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |