CN114232892B - Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof - Google Patents

Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof Download PDF

Info

Publication number
CN114232892B
CN114232892B CN202210034987.3A CN202210034987A CN114232892B CN 114232892 B CN114232892 B CN 114232892B CN 202210034987 A CN202210034987 A CN 202210034987A CN 114232892 B CN114232892 B CN 114232892B
Authority
CN
China
Prior art keywords
concrete
steel
reserved
steel bars
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210034987.3A
Other languages
Chinese (zh)
Other versions
CN114232892A (en
Inventor
赵秋
胡坤煊
官润荣
陈萌佳
杨艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN202210034987.3A priority Critical patent/CN114232892B/en
Publication of CN114232892A publication Critical patent/CN114232892A/en
Application granted granted Critical
Publication of CN114232892B publication Critical patent/CN114232892B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/093Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Road Paving Structures (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention relates to an assembled concrete connection structure connected through segmented reinforcing steel bars, which comprises two concrete prefabricated parts with butt joint ends, wherein reserved pore canals are arranged in the connecting ends of the concrete prefabricated parts, the end heads of all main reinforcing steel bars in the concrete prefabricated parts are exposed out of the inner hole bottoms of the reserved pore canals, the end heads of the main reinforcing steel bars in the two inner hole bottoms are connected through a plurality of segmented connecting reinforcing steel bars positioned in the reserved pore canals, and cement paste filling layers are arranged in the reserved pore canals and used for filling gaps between the segmented connecting reinforcing steel bars and the reserved pore canals. The invention can be used for connecting prefabricated concrete structures, in particular to the prefabricated concrete structures which are required to be prefabricated to realize industrial production and directly assembled on site, has the advantages of less on-site construction wet operation, short construction period, guaranteed component quality, economy, environmental protection and the like, and has good engineering popularization prospect.

Description

通过分段钢筋连接的装配式混凝土连接构造及其施工方法Prefabricated concrete connection structure and construction method connected by segmental reinforcement

技术领域technical field

本发明涉及一种通过分段钢筋连接的装配式混凝土连接构造及其施工方法,涉及土木工程领域。The invention relates to a prefabricated concrete connection structure connected by section steel bars and a construction method thereof, and relates to the field of civil engineering.

背景技术Background technique

随着国家经济转型,产业结构的调整,我国正向工厂化、标准化的“制造”方式转变。目前,我国极大部分的结构都是采用现浇钢筋混凝土技术建造。随着装配式混凝土技术的推广应用,为了保证装配式混凝土结构在结构性能上不低于现浇混凝土结构,我国也制定相应的混凝土结构技术规程,包括从结构设计到构件预制和现场施工等方面,基本思路是将现浇混凝土结构经过合理的拆分、工厂预制构件、现场拼装等环节。其中拆分有利于工厂预制,也要有利于现场拼装,且拼装后的结构要满足结构的安全性和功能性要求。为此,出现了多种形式的拆分及拼装连接方式,其连接方式直接影响到施工速度及结构安全性,更受到广泛的关注。With the transformation of the national economy and the adjustment of the industrial structure, our country is changing to a factory-like and standardized "manufacturing" method. At present, most of the structures in our country are constructed by cast-in-place reinforced concrete technology. With the promotion and application of prefabricated concrete technology, in order to ensure that the structural performance of prefabricated concrete structures is not lower than that of cast-in-place concrete structures, my country has also formulated corresponding technical regulations for concrete structures, including from structural design to component prefabrication and on-site construction. , the basic idea is to rationally disassemble the cast-in-place concrete structure, prefabricate components in the factory, and assemble them on site. Among them, disassembly is beneficial to factory prefabrication and on-site assembly, and the assembled structure must meet the safety and functional requirements of the structure. For this reason, various forms of disassembly and assembly connection methods have appeared, and the connection methods directly affect the construction speed and structural safety, and have received more widespread attention.

与传统现浇混凝土结构相比,装配式混凝土结构中存在更多的接缝,这些接缝不仅直接决定结构的整体安全性,而且也影响着结构的耐久性及实用功能性。预制装配结构的连接方式需根据结构形式、抗震设防烈度、施工、运输、拼装等因素综合考虑。根据国内外的试验研究及应用调研,通过几种连接构造的对比,考虑到国外既有经验的可靠度及国内理念接受度,国内采用的连接构造多选用灌浆套筒连接构造。将螺纹钢筋插入金属套筒内部,再灌注高强灌浆料拌合物,利用灌浆料凝结固化后与螺纹钢筋之间形成的粘结锚固传递应力而实现钢筋对接连接的方式,简称为套筒灌浆连接,可分为全灌浆套筒连接和半灌浆套筒连接。Compared with traditional cast-in-place concrete structures, there are more joints in prefabricated concrete structures. These joints not only directly determine the overall safety of the structure, but also affect the durability and practical functionality of the structure. The connection method of the prefabricated assembly structure needs to be considered comprehensively according to the structural form, seismic fortification intensity, construction, transportation, assembly and other factors. According to domestic and foreign experimental research and application research, through the comparison of several connection structures, considering the reliability of foreign experience and the acceptance of domestic concepts, the connection structure used in China is mostly the grouting sleeve connection structure. The threaded steel bar is inserted into the metal sleeve, and then the high-strength grouting material mixture is poured, and the bonding and anchorage formed between the grouting material and the threaded steel bar is used to transfer stress to realize the butt connection of the steel bar, which is referred to as the sleeve grouting connection. , can be divided into full grout sleeve connection and half grout sleeve connection.

现有的钢筋与套筒之间的连接通常是由竖向插入完成,施工技术难,在实际过程中,会出现套筒和插筋各自的位置测量结果符合要求,但拼接时依然安装不上的问题,在实际工程中引发了大量的应用问题。The connection between the existing steel bar and the sleeve is usually completed by vertical insertion, which is difficult in construction technology. In the actual process, the measurement results of the respective positions of the sleeve and the inserted bar meet the requirements, but they still cannot be installed during splicing. The problem has caused a lot of application problems in actual engineering.

发明内容Contents of the invention

鉴于现有技术的不足,本发明所要解决的技术问题是提供一种通过分段钢筋连接的装配式混凝土连接构造及其施工方法。In view of the deficiencies in the prior art, the technical problem to be solved by the present invention is to provide a prefabricated concrete connection structure connected by segmented steel bars and a construction method thereof.

为了解决上述技术问题,本发明的技术方案是:一种通过分段钢筋连接的装配式混凝土连接构造,包括端部对接的两混凝土预制构件,所述混凝土预制构件的连接端内部均设置有预留孔道,所述混凝土预制构件内部的主钢筋均部分端头露出预留孔道的内孔底,两内孔底的主钢筋端头之间经位于预留孔道的多根分段连接钢筋连接,所述预留孔道内部均设置有水泥浆填充层,用以填充分段连接钢筋与预留孔道之间的空隙。In order to solve the above-mentioned technical problems, the technical solution of the present invention is: a prefabricated concrete connection structure connected by segmented steel bars, including two concrete prefabricated components whose ends are butted, and the connecting ends of the concrete prefabricated components are provided with prefabricated The holes are reserved, and the ends of the main steel bars inside the prefabricated concrete components partly expose the inner hole bottoms of the reserved holes, and the ends of the main steel bars at the bottom of the two inner holes are connected through a plurality of segmented connecting steel bars located in the reserved holes. A cement slurry filling layer is arranged inside the reserved channels to fill the gap between the segmented connecting steel bars and the reserved channels.

优选的,所述分段连接钢筋共分为三段:两段短钢筋,一段长钢筋;所述长钢筋长度应满足当全部放置于一侧混凝土预制构件的预留孔道内时,长钢筋不会伸出该预留孔道外;预留孔道由预埋的波纹管或钢制灌浆套筒成孔。Preferably, the section-connected steel bars are divided into three sections: two sections of short steel bars and one section of long steel bars; It will protrude out of the reserved channel; the reserved channel is formed by a pre-embedded bellows or a steel grouting sleeve.

优选的,所述长钢筋位于两预留孔道之间,两段短钢筋经钢筋套筒连接在长钢筋的两端,短钢筋的另一端再经钢筋套筒与同侧的主钢筋端头连接。Preferably, the long steel bar is located between the two reserved channels, two short steel bars are connected to both ends of the long steel bar through a steel bar sleeve, and the other end of the short steel bar is connected to the end of the main steel bar on the same side through a steel bar sleeve .

优选的,所述钢筋套筒的外径应小于波纹管或钢制灌浆套筒内径至少15mm;所述预留孔道内径比分段连接钢筋外径大至少20mm。Preferably, the outer diameter of the reinforcement sleeve should be at least 15mm smaller than the inner diameter of the bellows or the steel grouting sleeve; the inner diameter of the reserved channel is at least 20mm larger than the outer diameter of the segmented connecting reinforcement.

优选的,所述混凝土预制构件的侧面均开设有连通预留孔道的预留槽口,预留槽口位置与短钢筋相对应,预留槽口大小应满足短钢筋能够沿预留槽口放入预留孔道内。Preferably, the side surfaces of the prefabricated concrete components are provided with reserved notches connecting the reserved channels, the positions of the reserved notches correspond to the short steel bars, and the size of the reserved notches should meet the requirement that the short steel bars can be placed along the reserved notches. into the reserved hole.

优选的,所述预留槽口均位于混凝土预制构件的两个相对侧面上。Preferably, the reserved notches are located on two opposite sides of the prefabricated concrete component.

优选的,所述预留槽口均位于混凝土预制构件的两个相对侧面以及该两相对侧面之间的其中一个侧面上。Preferably, the reserved notches are located on two opposite sides of the precast concrete component and on one side between the two opposite sides.

一种通过分段钢筋连接的装配式混凝土连接构造的施工方法,按以下步骤进行:(1)施工预制构件台座,安装钢模板:制作钢筋混凝土台座或全钢结构台座,上铺钢板作为预制构件底模板,外侧模采用定形钢模板与台座配套设计,模板准确就位后,通过对拉螺栓对模板进行加固;(2)绑扎与安装钢筋笼:检查底模板和侧模板,并涂刷隔离剂,吊装钢筋笼放入预制的钢模板内,并固定保护层厚度;(3)安装端模板和预埋件:安装端模板,安装为分段连接钢筋所预埋的波纹管或钢制灌浆套筒,通过井字形定位钢筋网固定波纹管或钢制灌浆套筒的位置;由于需将分段连接钢筋中的短钢筋从混凝土预制构件的侧面置入,需在混凝土预制构件的侧面、波纹管或钢制灌浆套筒的侧面开长孔,波纹管或钢制灌浆套筒长孔需临时封堵,保证浇筑混凝土时不会渗入波纹管或钢制灌浆套筒的预留长孔;(4)在模板内浇筑混凝土:在钢筋及模板验收合格后进行混凝土的浇筑,采用附着式振动器并附振动棒进行振捣,一般混凝土不再下沉,无显著气泡上升,混凝土表面出现薄层水泥浆,并有均匀的外观和平面为止;(5)混凝土养护:当气温较高时,混凝土强度增长满足施工进度要求,采用自然养护;当外界气温不能满足工程进度要求时,则采用蒸汽养护;(6)吊装和安装混凝土预制构件:先将分段连接钢筋中的长钢筋放置在一侧混凝土预制构件的预留孔道内,依次吊运、拼装其相连接的混凝土预制构件;(7)安装连接钢筋并灌浆:将分段连接钢筋中的短钢筋经预留槽口放入预留孔道内,通过将长钢筋的一半通过预留孔道移到另一侧的混凝土预制构件的预留孔道内,长钢筋和短钢筋通过钢筋套筒连接;最后将灌浆料在注浆孔缓慢注浆,预留孔道、预留槽口混凝土填满,并进行养护;依此循环,将若干所述混凝土预制构件相互拼接。A construction method of a prefabricated concrete connection structure connected by segmental steel bars, which is carried out in the following steps: (1) constructing a prefabricated component pedestal and installing a steel formwork: making a reinforced concrete pedestal or an all-steel structure pedestal, and laying a steel plate on it as a prefabricated component The bottom formwork and the outer formwork are designed with shaped steel formwork and pedestal. After the formwork is in place, the formwork is reinforced by pull bolts; (2) Binding and installation of reinforcement cages: check the bottom formwork and side formwork, and apply release agent , the hoisting reinforcement cage is put into the prefabricated steel formwork, and the thickness of the protective layer is fixed; (3) Install the end formwork and embedded parts: install the end formwork, install the bellows or steel grouting sleeves that are pre-embedded for segmental connection of steel bars The position of the corrugated pipe or steel grouting sleeve is fixed by the well-shaped positioning steel mesh; since the short steel bars in the segmented connecting steel bars need to be inserted from the side of the concrete prefabricated component, it is necessary to place the corrugated tube on the side of the concrete prefabricated component and the bellows Or the side of the steel grouting sleeve has long holes, and the bellows or steel grouting sleeve long holes need to be temporarily blocked to ensure that the concrete will not penetrate into the reserved long holes of the bellows or steel grouting sleeve; (4 ) Pouring concrete in the formwork: After the steel bars and formwork are accepted, the concrete is poured, and the attached vibrator is used to vibrate with a vibrating rod. Generally, the concrete does not sink, there is no significant bubble rise, and a thin layer of cement appears on the surface of the concrete. (5) Concrete curing: When the temperature is high, the strength of the concrete increases to meet the construction progress requirements, and natural curing is adopted; when the external temperature cannot meet the project progress requirements, steam curing is used; (6) Hoisting and installation of prefabricated concrete components: first place the long steel bars in the section-connected steel bars in the reserved channels of the precast concrete components on one side, and then lift and assemble the prefabricated concrete components connected in turn; (7) Installation Connecting steel bars and grouting: Put the short steel bars in the segmented connecting steel bars into the reserved channels through the reserved slots, and move half of the long steel bars through the reserved channels to the reserved channels of the concrete prefabricated components on the other side , the long steel bar and the short steel bar are connected through the steel bar sleeve; finally, the grouting material is slowly grouted in the grouting hole, the reserved hole and the reserved notch are filled with concrete, and cured; according to this cycle, several concretes are prefabricated The components are joined together.

与现有技术相比,本发明具有以下有益效果:本发明可用于装配式混凝土预制结构连接,特别是对于需要预制实现工厂工业化生产、现场直接拼装的混凝土结构,具有现场施工湿作业少、施工周期短、构件质量有保证、经济环保等优点,有良好的工程推广前景。Compared with the prior art, the present invention has the following beneficial effects: the present invention can be used for the connection of prefabricated concrete structures, especially for concrete structures that require prefabrication to realize industrial production in factories and direct assembly on site, and has the advantages of less wet work in on-site construction and less construction cost. It has the advantages of short cycle, guaranteed component quality, economical and environmental protection, etc., and has a good prospect for project promotion.

下面结合附图和具体实施方式对本发明做进一步详细的说明。The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.

附图说明Description of drawings

图1为本发明实施例1的连接平面图。Fig. 1 is a connection plan view of Embodiment 1 of the present invention.

图2为本发明实施例1的连接状态立面图一。Fig. 2 is the elevation view 1 of the connection state of Embodiment 1 of the present invention.

图3为本发明实施例1的连接状态立面图二。Fig. 3 is the second elevation view of the connection state of Embodiment 1 of the present invention.

图4为本发明实施例1的连接状态立面图三。Fig. 4 is the third elevation view of the connection state of Embodiment 1 of the present invention.

图5为图2的I-I剖面图。Fig. 5 is a sectional view of I-I in Fig. 2 .

图6为图2的II-II断面图。FIG. 6 is a sectional view of II-II in FIG. 2 .

图7为本发明实施例2的连接立面图。Fig. 7 is a connection elevation view of Embodiment 2 of the present invention.

图8为本发明实施例2的连接平面图。Fig. 8 is a connection plan view of Embodiment 2 of the present invention.

图9为图7的Ⅲ-Ⅲ剖面图。Fig. 9 is a sectional view of III-III in Fig. 7 .

图中:1-预留孔道,2-钢筋套筒,3-预留槽口,4-水泥浆填充层,5-槽口后填混凝土,6-长钢筋,7-短钢筋,8-主钢筋,9-接缝,10-混凝土预制构件。In the figure: 1-reserved tunnel, 2-steel bar sleeve, 3-reserved notch, 4-cement slurry filling layer, 5-fill concrete after notch, 6-long steel bar, 7-short steel bar, 8-main Steel bars, 9-joints, 10-concrete precast elements.

具体实施方式Detailed ways

下面结合附图及实施例对本发明做进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

应该指出,以下详细说明都是示例性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed description is exemplary and is intended to provide further explanation to the present application. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used here is only for describing specific implementations, and is not intended to limit the exemplary implementations according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural, and it should also be understood that when the terms "comprising" and/or "comprising" are used in this specification, they mean There are features, steps, operations, means, components and/or combinations thereof.

如图1~9所示,本实施例提供了一种通过分段钢筋连接的装配式混凝土连接构造,包括端部对接的两混凝土预制构件,所述混凝土预制构件的连接端内部均设置有预留孔道,所述混凝土预制构件内部的主钢筋均部分端头露出预留孔道的内孔底,两内孔底的主钢筋端头之间经位于预留孔道的多根分段连接钢筋连接,所述预留孔道内部均设置有水泥浆填充层,水泥浆填充层为灌浆料或高强砂浆。用以填充分段连接钢筋与预留孔道之间的空隙,使两相连接的混凝土预制构件通过分段连接钢筋的连接形成一体共同受力。As shown in Figures 1 to 9, this embodiment provides a prefabricated concrete connection structure connected by segmented steel bars, including two concrete prefabricated components whose ends are butt-jointed. The holes are reserved, and the ends of the main steel bars inside the prefabricated concrete components partly expose the inner hole bottoms of the reserved holes, and the ends of the main steel bars at the bottom of the two inner holes are connected through a plurality of segmented connecting steel bars located in the reserved holes. A cement slurry filling layer is arranged inside the reserved channels, and the cement slurry filling layer is grouting material or high-strength mortar. It is used to fill the gap between the section-connected steel bars and the reserved channels, so that the two-phase connected concrete prefabricated components can form a whole and jointly bear the force through the connection of the section-connected steel bars.

在本发明实施例中,所述分段连接钢筋共分为三段:两段短钢筋,一段长钢筋;所述长钢筋长度应满足当全部放置于一侧混凝土预制构件的预留孔道内时,长钢筋不会伸出该预留孔道外,使得一侧的混凝土预制构件可以在安装前先将长钢筋放置于预留孔道内,方便实现分段连接钢筋的安装;预留孔道由预埋的波纹管或钢制灌浆套筒成孔实现,每根主钢筋在预制时套入合适长度的波纹管或钢制灌浆套筒。In the embodiment of the present invention, the segmented connecting steel bars are divided into three sections: two sections of short steel bars and one section of long steel bars; the length of the long steel bars should satisfy the , the long steel bars will not protrude out of the reserved channel, so that the prefabricated concrete components on one side can be placed in the reserved channel before installation, which is convenient for the installation of segmented connecting steel bars; the reserved channel is pre-embedded The corrugated pipe or steel grouting sleeve is formed into holes, and each main steel bar is inserted into a bellows or steel grouting sleeve of appropriate length during prefabrication.

在本发明实施例中,所述长钢筋位于两预留孔道之间,两段短钢筋经钢筋套筒连接在长钢筋的两端,短钢筋的另一端再经钢筋套筒与同侧的主钢筋端头连接。所述主钢筋也可以与预留孔道内的钢筋相搭接。In the embodiment of the present invention, the long steel bars are located between the two reserved channels, and the two short steel bars are connected to the two ends of the long steel bars through the steel bar sleeves, and the other end of the short steel bars is connected to the main steel bar on the same side through the steel bar sleeves. Rebar end connections. The main steel bar can also be overlapped with the steel bar in the reserved channel.

在本发明实施例中,所述钢筋套筒的外径应小于波纹管或钢制灌浆套筒内径至少15mm;所述预留孔道内径比分段连接钢筋外径大至少20mm。In the embodiment of the present invention, the outer diameter of the reinforcement sleeve should be at least 15mm smaller than the inner diameter of the bellows or the steel grouting sleeve; the inner diameter of the reserved channel is at least 20mm larger than the outer diameter of the segmented connecting reinforcement.

在本发明实施例中,所述混凝土预制构件的侧面均开设有连通预留孔道的预留槽口,预留槽口位置与短钢筋相对应,预留槽口大小应满足短钢筋能够沿预留槽口放入预留孔道内。对应所述预留孔道内的短钢筋安装的位置,在所述的波纹管或钢制灌浆套筒的侧面开槽,便于预留槽口连通预留孔道。In the embodiment of the present invention, the side surfaces of the prefabricated concrete components are provided with reserved notches connecting the reserved channels, the positions of the reserved notches correspond to the short steel bars, and the size of the reserved notches should meet the requirement that the short steel bars can Put the notch into the reserved hole. Corresponding to the installation position of the short steel bar in the reserved channel, grooves are made on the side of the bellows or the steel grouting sleeve to facilitate the connection of the reserved notch to the reserved channel.

在本发明实施例1中,所述预留槽口均位于混凝土预制构件的两个相对侧面上。预留槽口应用比混凝土预制构件的混凝土强度高一级混凝土或高强砂浆或灌浆料封堵,形成槽口后填混凝土。In Embodiment 1 of the present invention, the reserved notches are located on two opposite sides of the prefabricated concrete component. The reserved notch shall be sealed with concrete or high-strength mortar or grouting material higher than the concrete strength of the prefabricated concrete component, and the notch shall be filled with concrete after forming the notch.

在本发明实施例2中,所述预留槽口均位于混凝土预制构件的两个相对侧面以及该两相对侧面之间的其中一个侧面上。其与实施例1区别在于开挖预留槽口方向不同,实施例1中预留槽口为对向开挖,可用于大部分工程应用中,而实施例2中考虑边坡或放置于地基上进行连接的情况,由于操作面的限制,将其中一个面的预留槽口改为侧面对向各开挖一个预留槽口,以便施工安装。预留槽口应用比混凝土预制构件的混凝土强度高一级混凝土或高强砂浆或灌浆料封堵,形成槽口后填混凝土。In Embodiment 2 of the present invention, the reserved notches are located on two opposite sides of the precast concrete component and on one side between the two opposite sides. The difference between it and Embodiment 1 is that the direction of the reserved notch for excavation is different. In Embodiment 1, the reserved notch is opposite excavation, which can be used in most engineering applications, while in Embodiment 2, the side slope or placed on the foundation is considered In the case of connection on the upper side, due to the limitation of the operation surface, the reserved notch on one of the surfaces is changed to a reserved notch excavated on each side to facilitate construction and installation. The reserved notch shall be sealed with concrete or high-strength mortar or grouting material higher than the concrete strength of the prefabricated concrete component, and the notch shall be filled with concrete after forming the notch.

一种通过分段钢筋连接的装配式混凝土连接构造的施工方法,按以下步骤进行:A construction method of a prefabricated concrete connection structure connected by segmented steel bars is carried out in the following steps:

(1)施工预制构件台座,安装钢模板:制作钢筋混凝土台座或全钢结构台座,上铺钢板作为预制构件底模板,外侧模采用定形钢模板与台座配套设计,模板准确就位后,通过对拉螺栓对模板进行加固;(1) Construction of prefabricated component pedestals, installation of steel formwork: making reinforced concrete pedestals or all-steel structure pedestals, laying steel plates on top as the bottom formwork of prefabricated components, and the outer molds are designed with shaped steel formwork and pedestals. Pull bolts to reinforce the formwork;

(2)绑扎与安装钢筋笼:检查底模板和侧模板,并涂刷隔离剂,吊装钢筋笼放入预制的钢模板内,并固定保护层厚度;(2) Binding and installing reinforcement cages: check the bottom formwork and side formwork, and apply release agent, hoist the reinforcement cage into the prefabricated steel formwork, and fix the thickness of the protective layer;

(3)安装端模板和预埋件:安装端模板,安装为分段连接钢筋所预埋的波纹管或钢制灌浆套筒,通过井字形定位钢筋网固定波纹管或钢制灌浆套筒的位置;由于需将分段连接钢筋中的短钢筋从混凝土预制构件的侧面置入,需在混凝土预制构件的侧面、波纹管或钢制灌浆套筒的侧面开长孔,波纹管或钢制灌浆套筒长孔需临时封堵,保证浇筑混凝土时不会渗入波纹管或钢制灌浆套筒的预留长孔;预留孔道也可通过埋设波纹管形成,并螺旋筋套箍在波纹管外侧,其轴线与波纹管轴线一致;(3) Install the end formwork and embedded parts: install the end formwork, install the bellows or steel grouting sleeves that are pre-embedded for segmental connection reinforcement, and fix the bellows or steel grouting sleeves through the well-shaped positioning steel mesh position; since the short steel bars in the segmented connecting steel bars need to be inserted from the side of the concrete prefabricated component, long holes need to be opened on the side of the concrete prefabricated component, the side of the bellows or steel grouting sleeve, and the bellows or steel grouting The long hole of the sleeve needs to be temporarily blocked to ensure that it will not penetrate into the reserved long hole of the bellows or steel grouting sleeve when pouring concrete; the reserved hole can also be formed by embedding the bellows, and the spiral ribs are hooped outside the bellows , whose axis is consistent with the bellows axis;

(4)在模板内浇筑混凝土:在钢筋及模板验收合格后进行混凝土的浇筑,采用附着式振动器并附振动棒进行振捣,一般混凝土不再下沉,无显著气泡上升,混凝土表面出现薄层水泥浆,并有均匀的外观和平面为止;(4) Concrete pouring in the formwork: concrete is poured after the steel bars and formwork are accepted, and the attached vibrator and vibrating rod are used to vibrate. Generally, the concrete will not sink, there will be no significant air bubbles rising, and the concrete surface will appear thinner. layer of grout until it has a uniform appearance and plane;

(5)混凝土养护:当气温较高时,混凝土强度增长满足施工进度要求,采用自然养护;当外界气温不能满足工程进度要求时,则采用蒸汽养护;(5) Concrete curing: When the temperature is high, the strength of concrete increases to meet the construction progress requirements, and natural curing is adopted; when the external temperature cannot meet the project progress requirements, steam curing is used;

(6)吊装和安装混凝土预制构件:预制格构梁的场内移动吊装采用龙门吊,构件的堆放场地应宽敞,堆放场地应平整坚实、排水良好;预制构件采用轮胎式配套运梁车,在车厢板上面铺上减震和防止摩擦的橡胶垫,预制构件装车后应进行固定,并对固定情况进行检查,符合安全运输要求后方可发车。先将分段连接钢筋中的长钢筋放置在一侧混凝土预制构件的预留孔道内,依次吊运、拼装其相连接的混凝土预制构件,确保相邻格构梁(混凝土预制构件)在接缝严密对接;(6) Hoisting and installation of prefabricated concrete components: gantry cranes are used for mobile hoisting of prefabricated lattice beams in the field. Rubber pads for shock absorption and anti-friction are laid on the board, and the prefabricated components should be fixed after loading, and the fixing situation should be checked, and the vehicle can only start after meeting the requirements for safe transportation. First place the long steel bars in the section-connected steel bars in the reserved channel of the concrete prefabricated components on one side, and then lift and assemble the connected concrete precast components in sequence to ensure that the adjacent lattice beams (concrete prefabricated components) are at the joints. tight docking;

(7)安装连接钢筋并灌浆:将分段连接钢筋中的短钢筋经预留槽口放入预留孔道内,通过将长钢筋的一半通过预留孔道移到另一侧的混凝土预制构件的预留孔道内,使长钢筋两端均在对应预留槽口内露出一段预留长度,用于后续连接钢筋套筒,长钢筋和短钢筋通过钢筋套筒连接;最后将灌浆料在注浆孔缓慢注浆,预留孔道、预留槽口混凝土填满,并进行养护;依此循环,将若干所述混凝土预制构件相互拼接。(7) Install connecting steel bars and grout: put the short steel bars in the segmental connecting steel bars into the reserved channels through the reserved slots, and move half of the long steel bars to the concrete prefabricated components on the other side through the reserved channels In the reserved channel, make both ends of the long steel bar expose a reserved length in the corresponding reserved notch, which is used for subsequent connection of the steel bar sleeve. The long steel bar and the short steel bar are connected through the steel bar sleeve; Slowly grouting, reserved channels and slots are filled with concrete, and then cured; according to this cycle, several concrete prefabricated components are spliced together.

该结构不需要弯曲波纹管和钢筋,预制可以节省大量的人工,提高制作精度;现场施工时,分段钢筋连接也更易操作,可以降低劳动强度,加快施工速度,有着明显的经济效益。The structure does not require curved bellows and steel bars, and prefabrication can save a lot of labor and improve manufacturing accuracy; during on-site construction, segmental steel bar connections are also easier to operate, which can reduce labor intensity and speed up construction, which has obvious economic benefits.

以上所述,仅是本发明的较佳实施例而已,并非是对本发明作其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例。但是凡是未脱离本发明技术方案内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本发明技术方案的保护范围。The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention to other forms. Any skilled person who is familiar with this profession may use the technical content disclosed above to change or modify the equivalent of equivalent changes. Example. However, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still belong to the protection scope of the technical solution of the present invention.

Claims (1)

1.一种通过分段钢筋连接的装配式混凝土连接构造,其特征在于:包括端部对接的两混凝土预制构件,所述混凝土预制构件的连接端内部均设置有预留孔道,所述混凝土预制构件内部的主钢筋均部分端头露出预留孔道的内孔底,两内孔底的主钢筋端头之间经位于预留孔道的多根分段连接钢筋连接,所述预留孔道内部均设置有水泥浆填充层,用以填充分段连接钢筋与预留孔道之间的空隙;所述分段连接钢筋共分为三段:两段短钢筋,一段长钢筋;所述长钢筋长度应满足当全部放置于一侧混凝土预制构件的预留孔道内时,长钢筋不会伸出该预留孔道外;预留孔道由预埋的波纹管或钢制灌浆套筒成孔;所述长钢筋位于两预留孔道之间,两段短钢筋经钢筋套筒连接在长钢筋的两端,短钢筋的另一端再经钢筋套筒与同侧的主钢筋端头连接;所述钢筋套筒的外径应小于波纹管或钢制灌浆套筒内径至少15mm;所述预留孔道内径比分段连接钢筋外径大至少20mm;所述混凝土预制构件的侧面均开设有连通预留孔道的预留槽口,预留槽口位置与短钢筋相对应,预留槽口大小应满足短钢筋能够沿预留槽口放入预留孔道内;所述预留槽口均位于混凝土预制构件的两个相对侧面上;所述预留槽口均位于混凝土预制构件的两个相对侧面以及该两相对侧面之间的其中一个侧面上;该通过分段钢筋连接的装配式混凝土连接构造的施工方法按以下步骤进行:(1)施工预制构件台座,安装钢模板:制作钢筋混凝土台座或全钢结构台座,上铺钢板作为预制构件底模板,外侧模采用定形钢模板与台座配套设计,模板准确就位后,通过对拉螺栓对模板进行加固;(2)绑扎与安装钢筋笼:检查底模板和侧模板,并涂刷隔离剂,吊装钢筋笼放入预制的钢模板内,并固定保护层厚度;(3)安装端模板和预埋件:安装端模板,安装为分段连接钢筋所预埋的波纹管或钢制灌浆套筒,通过井字形定位钢筋网固定波纹管或钢制灌浆套筒的位置;由于需将分段连接钢筋中的短钢筋从混凝土预制构件的侧面置入,需在混凝土预制构件的侧面、波纹管或钢制灌浆套筒的侧面开长孔,波纹管或钢制灌浆套筒长孔需临时封堵,保证浇筑混凝土时不会渗入波纹管或钢制灌浆套筒的预留长孔;(4)在模板内浇筑混凝土:在钢筋及模板验收合格后进行混凝土的浇筑,采用附着式振动器并附振动棒进行振捣,一般混凝土不再下沉,无显著气泡上升,混凝土表面出现薄层水泥浆,并有均匀的外观和平面为止;(5)混凝土养护:当气温较高时,混凝土强度增长满足施工进度要求,采用自然养护;当外界气温不能满足工程进度要求时,则采用蒸汽养护;(6)吊装和安装混凝土预制构件:先将分段连接钢筋中的长钢筋放置在一侧混凝土预制构件的预留孔道内,依次吊运、拼装其相连接的混凝土预制构件;(7)安装连接钢筋并灌浆:将分段连接钢筋中的短钢筋经预留槽口放入预留孔道内,通过将长钢筋的一半通过预留孔道移到另一侧的混凝土预制构件的预留孔道内,长钢筋和短钢筋通过钢筋套筒连接;最后将灌浆料在注浆孔缓慢注浆,预留孔道、预留槽口混凝土填满,并进行养护;依此循环,将若干所述混凝土预制构件相互拼接。1. A prefabricated concrete connection structure connected by segmented steel bars, characterized in that: two concrete prefabricated components butt-jointed at the ends are included, the inside of the connection ends of the concrete prefabricated components are all provided with reserved channels, and the concrete prefabricated Part of the ends of the main steel bars inside the component are exposed at the bottom of the inner hole of the reserved hole, and the ends of the main steel bars at the bottom of the two inner holes are connected through a plurality of segmented connecting steel bars located in the reserved hole. A cement slurry filling layer is provided to fill the gap between the segmented connecting steel bar and the reserved channel; the segmented connecting steel bar is divided into three sections: two sections of short steel bar and one section of long steel bar; the length of the long steel bar should be Satisfied that when all are placed in the reserved channel of one side of the concrete prefabricated component, the long steel bars will not protrude from the reserved channel; the reserved channel is formed by a pre-embedded bellows or steel grouting sleeve; the long The steel bars are located between the two reserved channels, and the two short steel bars are connected to the two ends of the long steel bars through the steel bar sleeves, and the other end of the short steel bars is connected to the end of the main steel bars on the same side through the steel bar sleeves; the steel bar sleeves The outer diameter of the steel grouting sleeve should be at least 15mm smaller than the inner diameter of the bellows or the steel grouting sleeve; the inner diameter of the reserved channel is at least 20mm larger than the outer diameter of the segmented connecting steel bars; Reserve notches, the positions of the reserved notches correspond to the short steel bars, and the size of the reserved notches should be such that the short steel bars can be put into the reserved tunnel along the reserved notches; the reserved notches are located on both sides of the prefabricated concrete components on two opposite sides; the reserved notches are all located on two opposite sides of the prefabricated concrete component and on one of the sides between the two opposite sides; The following steps are carried out: (1) Construction of prefabricated component pedestal, installation of steel formwork: making reinforced concrete pedestal or all-steel structure pedestal, laying steel plates on it as the bottom formwork of prefabricated components, and the outer formwork adopts the matching design of shaped steel formwork and pedestal, and the formwork is accurately in place Finally, the formwork is reinforced by pulling bolts; (2) Binding and installation of reinforcement cages: check the bottom formwork and side formwork, and apply release agent, hoist the reinforcement cage into the prefabricated steel formwork, and fix the thickness of the protective layer; (3) Install the end formwork and embedded parts: install the end formwork, install the bellows or steel grouting sleeves that are pre-embedded for segmental connection reinforcement, and fix the bellows or steel grouting sleeves through the well-shaped positioning steel mesh position; since the short steel bars in the segmented connecting steel bars need to be inserted from the side of the concrete prefabricated component, long holes need to be opened on the side of the concrete prefabricated component, the side of the bellows or steel grouting sleeve, and the bellows or steel grouting The long hole of the sleeve needs to be temporarily blocked to ensure that it will not penetrate into the reserved long hole of the bellows or the steel grouting sleeve when pouring concrete; (4) Pouring concrete in the formwork: pouring concrete after the steel bars and formwork pass the acceptance , Vibrate with an attached vibrator and a vibrating rod. Generally, the concrete will no longer sink, there will be no significant air bubbles rising, and a thin layer of cement slurry will appear on the surface of the concrete, and it will have a uniform appearance and plane; (5) Concrete maintenance: when When the temperature is high, the strength of concrete increases to meet the requirements of the construction progress, and natural curing is adopted; when the external temperature cannot meet the requirements of the project progress, steam curing is used; The long steel bars are placed in the reserved channel of the concrete prefabricated components on one side, and the connected concrete precast components are lifted and assembled in sequence; (7) Connecting steel bars are installed and grouted: the short steel bars in the segmented connecting steel bars are passed through the reserved grooves Put the mouth into the reserved channel, and move half of the long steel bar through the reserved channel to the reserved channel of the concrete prefabricated component on the other side, and connect the long steel bar and the short steel bar through the steel bar sleeve; The grouting holes are slowly grouted, the reserved channels and notches are filled with concrete, and then cured; in this way, several prefabricated concrete components are spliced together.
CN202210034987.3A 2022-01-13 2022-01-13 Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof Active CN114232892B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210034987.3A CN114232892B (en) 2022-01-13 2022-01-13 Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210034987.3A CN114232892B (en) 2022-01-13 2022-01-13 Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof

Publications (2)

Publication Number Publication Date
CN114232892A CN114232892A (en) 2022-03-25
CN114232892B true CN114232892B (en) 2023-05-23

Family

ID=80746382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210034987.3A Active CN114232892B (en) 2022-01-13 2022-01-13 Fabricated concrete connection structure connected through segmented reinforcing steel bars and construction method thereof

Country Status (1)

Country Link
CN (1) CN114232892B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908886A (en) * 2022-06-02 2022-08-16 中国中材海外科技发展有限公司 Concrete prefabricated part connecting assembly and connecting method
CN115922905B (en) * 2022-12-31 2025-07-08 中建四局第一建设有限公司 Reserved steel bar surface template of prefabricated component

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006144337A (en) * 2004-11-18 2006-06-08 Taisei Corp Precast concrete member and beam construction method using the same
CN2797476Y (en) * 2005-04-22 2006-07-19 北京工业大学 Mixed jointing node of assembled concrete frame structure beam column
CN204225283U (en) * 2014-11-05 2015-03-25 沈阳建筑大学 The assembled syndeton of assembly concrete frame structure Shear-wall Connecting Beam Used
CN104775545B (en) * 2015-03-09 2016-09-07 沈阳建筑大学 Assembly concrete Frame-Shear Wall splits the method for attachment of component
CN104727441B (en) * 2015-03-31 2017-03-22 武汉理工大学 Prestress assembled concrete beam column joint structure and construction method thereof
CN105019558B (en) * 2015-08-02 2018-07-03 长安大学 The Bar Anchorage connection structure of prefabricated assembled concrete component and connection method
CN105937274B (en) * 2016-06-15 2018-12-04 华南理工大学建筑设计研究院 The prefabricated horizontal piece channel steel of shear wall is welded to connect device and connection method
CN110552423B (en) * 2018-05-30 2024-07-23 罗大威 Dry-method connecting joint for assembled building concrete beam, column and concrete node member
CN109339231A (en) * 2018-11-29 2019-02-15 徐志强 For the connecting node of assembled architecture, construction method and assembled architecture
CN110107023B (en) * 2019-05-10 2022-02-11 中国十七冶集团有限公司 Rigid connection prefabricated frame beam for assembly type building
CN110792166B (en) * 2019-12-03 2024-07-09 张延年 Reinforced assembled beam column joint
CN216893135U (en) * 2022-01-13 2022-07-05 福州大学 Assembled concrete connection structure through segmentation rebar connection

Also Published As

Publication number Publication date
CN114232892A (en) 2022-03-25

Similar Documents

Publication Publication Date Title
CN107165272B (en) Prestressed assembled concrete frame node connecting structure and construction method thereof
CN105804241A (en) Single-layer prefabricated assembly type reinforced concrete beam-column joint
CN111779160A (en) A kind of prestressed prefabricated concrete shear wall system and construction method thereof
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN104499568A (en) Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method
CN109025064A (en) Method for manufacturing and installing prefabricated concrete column and column assembly type connecting node
CN108560544A (en) A kind of sleeve connection assembled pile foundation and its construction method
CN111749365A (en) A prefabricated composite wall based on H-beam and its construction method
CN106013432A (en) Joint connecting structure in high-ductility assembled integrated frame and construction method
CN112853983A (en) Manufacturing and on-site assembling process of light segment prefabricated bridge pier
CN208251372U (en) A kind of assembled steel reinforced concrete shear force wall
CN109098278A (en) The connecting structure and construction method of prefabricated beam column
CN210152316U (en) A prefabricated reinforcement device for reinforced concrete beams
CN114232892A (en) Prefabricated concrete connection structure connected by segmented steel bars and its construction method
CN110924293B (en) Concrete pipe, bridge pier structure and manufacturing method thereof
CN216893135U (en) Assembled concrete connection structure through segmentation rebar connection
CN111827095A (en) Prefabricated and assembled hollow pier with built-in ribs and construction method
CN113833162B (en) Shear wall structure system with high prefabrication rate and low cost and construction method
CN207525960U (en) Easy connect band shear key reinforced concrete slab structure
CN212772979U (en) A prestressed assembled shear wall system
CN105951984A (en) High-ductility assembled integral type frame exterior joint connection structure and construction method thereof
CN216893134U (en) Prefabricated assembled reinforced concrete beam structure through hybrid connection of bolts and sleeves
CN216893133U (en) Prefabricated assembled reinforced concrete beam structure connected through sleeve
CN110820983B (en) A longitudinal connection method of prefabricated prefabricated wall panels
CN206554428U (en) A kind of precast stair connecting node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant