CN114091939A - Project progress monitoring system and method based on block chain - Google Patents

Project progress monitoring system and method based on block chain Download PDF

Info

Publication number
CN114091939A
CN114091939A CN202111417755.8A CN202111417755A CN114091939A CN 114091939 A CN114091939 A CN 114091939A CN 202111417755 A CN202111417755 A CN 202111417755A CN 114091939 A CN114091939 A CN 114091939A
Authority
CN
China
Prior art keywords
engineering material
progress
actual
material quantity
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111417755.8A
Other languages
Chinese (zh)
Inventor
王丰
毛华
罗喜群
孔冠荀
李拥福
马骏
韩国龙
蒋程
张树民
何玉龙
杨洲
马鑫
孙滨
秦永保
汤强
孙泽
文艺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202111417755.8A priority Critical patent/CN114091939A/en
Publication of CN114091939A publication Critical patent/CN114091939A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an engineering progress supervision system and method based on a block chain, relating to the technical field of engineering progress supervision and comprising the following steps: acquiring the actual engineering material quantity, the just-needed engineering material quantity and the pre-estimated engineering material quantity from the data center; checking and verifying the actual engineering material quantity and the estimated engineering material quantity, and judging whether data deviation exists or not; comparing the actual engineering material quantity with the newly-needed engineering material quantity, and judging whether the material quantity is sufficient or not; calculating the time spent on the whole progress, determining the actual project progress, comparing and adjusting the actual project progress with the expected project progress, and acquiring the adjusted work content; and judging whether the construction can be normally carried out or whether the construction progress adjustment is correct or not, and sending the final work content to each receiving device of the engineering personnel. The invention avoids the condition of insufficient material or unqualified material in the subsequent construction period and ensures the stability of the construction period.

Description

Project progress monitoring system and method based on block chain
Technical Field
The invention relates to the technical field of project progress supervision, in particular to a block chain-based project progress supervision system and a block chain-based project progress supervision method.
Background
Along with the development of the construction industry in China, the proportion of the production value of the construction industry to the total production value in China is increased year by year, and due to the continuous improvement of the construction scientific and technical level, the scale and the structural complexity of the project are increased, and the owners put forward higher requirements on the construction progress. The construction progress management is an important content in the field of engineering project management, the normal operation of an engineering project is directly influenced, and the economic benefit and the social benefit of the project are related.
Disclosure of Invention
In view of the above, the present invention provides a block chain-based project progress monitoring system and a method thereof, so as to solve the technical problem of unstable construction period caused by insufficient material or unqualified material in the subsequent construction period in the prior art.
In order to achieve the above object, the present invention is implemented by the following technical solutions, and a system and a method for project progress supervision based on a block chain specifically include the following steps:
step 1: acquiring actual engineering material quantity, just needed engineering material quantity and pre-estimated engineering material quantity;
step 2: checking and verifying the actual engineering material quantity data and the estimated engineering material quantity data based on the obtained actual engineering material quantity and the estimated engineering material quantity, and judging whether data deviation exists or not;
if so, adjusting the actual engineering material quantity to eliminate an error;
if not, the operation is continued.
And step 3: comparing the actual engineering material quantity with the just-needed engineering material quantity based on the obtained actual engineering material quantity and the just-needed engineering material quantity, judging whether the material is sufficient,
if yes, calculating the time spent on the whole progress;
if not, acquiring the actual supplement amount of the engineering material;
and 4, step 4: acquiring the current progress amount based on the time spent on the acquired overall progress, determining the actual project progress, comparing and adjusting the actual project progress with the expected project progress, and acquiring the adjusted work content;
and 5: based on the adjusted work content, judging whether the construction can be normally carried out or whether the construction progress is adjusted correctly according to the current demand information and the current construction progress,
and if the construction can be normally carried out or the construction progress is correctly adjusted, the final data content is sent to each engineering personnel receiving device.
Preferably, the obtaining module is configured to obtain data of the actual engineering material amount, the engineering material amount just needed, and the estimated engineering material amount from the data center.
Preferably, the actual engineering material amount data and the estimated engineering material amount data are verified based on the obtained actual engineering material amount and the estimated engineering material amount, and whether a data deviation exists is judged to generate a verification module, wherein the verification module is used for verifying the actual engineering material amount data and the estimated engineering material amount data and judging whether the data deviation exists.
Preferably, the actual engineering material amount and the engineering material amount just needed are compared based on the obtained actual engineering material amount and the engineering material amount just needed to generate a comparison calculation module, and the comparison calculation module is used for comparing the actual engineering material amount and the engineering material amount just needed and judging whether the materials are sufficient or not and calculating the time taken by the overall progress.
Preferably, the existing progress amount is obtained based on the obtained time spent on the overall progress, the actual project progress is determined and is compared and adjusted with the expected project progress, and the adjusted work content is obtained to generate a progress adjustment module, and the progress adjustment module is used for obtaining the existing progress amount and comparing and adjusting the existing progress amount with the expected progress amount.
Preferably, based on the adjusted work content, whether construction can be normally performed or whether the construction progress adjustment is correct is judged according to the current demand information and the current construction progress to generate a judgment execution module, and the judgment execution module is used for reading whether the adjusted work content can be normally performed or whether the construction progress adjustment is correct, and sending the final work content to each receiving device of engineering personnel.
In another aspect, a system for project progress supervision based on a blockchain includes,
a material quantity acquisition module: the data information is used for acquiring the actual engineering material quantity, the just-needed engineering material quantity and the predicted engineering material quantity from the data center;
a determination module: the method is used for judging whether the material is sufficient or not based on the obtained actual engineering material quantity, the just-needed engineering material quantity and the estimated engineering material quantity;
actual progress acquisition module: the method comprises the steps of obtaining the existing progress amount based on the obtained time spent on the whole progress, and determining the actual project progress;
the actual progress adjusting module: the system is used for comparing and adjusting the actual project progress with the expected project progress based on the obtained actual project progress to obtain the adjusted work content;
a redistribution module: the system is used for classifying the work contents based on the obtained adjusted work contents, and after the work contents are reordered according to the difficulty and the priority, the contents needing to be preferentially processed can be preferentially processed, so that the subsequent work contents can be more stable;
a feedback update module: for judging whether the construction can be normally carried out or whether the construction progress is correctly adjusted according to the current demand information and the current construction progress based on the redistributed work content,
and if the construction can be normally carried out or the construction progress is correctly adjusted, the final work content is sent to each engineering personnel receiving device.
Compared with the prior art, the invention has the following beneficial effects:
the invention discloses a block chain-based engineering progress monitoring system and a method thereof, wherein the system comprises the following steps: acquiring the actual engineering material quantity, the just-needed engineering material quantity and the pre-estimated engineering material quantity from the data center; checking and verifying the actual engineering material quantity and the estimated engineering material quantity, and judging whether data deviation exists or not; comparing the actual engineering material quantity with the newly-needed engineering material quantity, and judging whether the material quantity is sufficient or not; calculating the time spent on the whole progress, determining the actual project progress, comparing and adjusting the actual project progress with the expected project progress, and acquiring the adjusted work content; and judging whether the construction can be normally carried out or whether the construction progress adjustment is correct or not, and sending the final work content to each receiving device of the engineering personnel. According to the construction method, the acquisition module is used for acquiring the data of the engineering material quantity, and after the data is confirmed by the comparison and verification module, the system is used for calculating to ensure that the materials are sufficient during construction, so that the condition that the materials are insufficient or unqualified during the subsequent construction period is avoided, and the stability of the construction period is ensured.
Drawings
Fig. 1 is a structural diagram of a block chain-based project progress monitoring system according to an embodiment of the present invention.
Detailed Description
To make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings, and it is apparent that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a block chain-based project progress monitoring system and a method thereof, which specifically comprise the following steps:
step 1: acquiring actual engineering material quantity, just needed engineering material quantity and pre-estimated engineering material quantity;
step 2: checking and verifying the actual engineering material quantity data and the estimated engineering material quantity data based on the obtained actual engineering material quantity and the estimated engineering material quantity, and judging whether data deviation exists or not;
if so, adjusting the actual engineering material quantity to eliminate an error;
if not, the operation is continued.
And step 3: comparing the actual engineering material quantity with the just-needed engineering material quantity based on the obtained actual engineering material quantity and the just-needed engineering material quantity, judging whether the material is sufficient,
if yes, calculating the time spent on the whole progress;
if not, acquiring the actual supplement amount of the engineering material;
and 4, step 4: acquiring the current progress amount based on the time spent on the acquired overall progress, determining the actual project progress, comparing and adjusting the actual project progress with the expected project progress, and acquiring the adjusted work content;
and 5: based on the adjusted work content, judging whether the construction can be normally carried out or whether the construction progress is adjusted correctly according to the current demand information and the current construction progress,
and if the construction can be normally carried out or the construction progress is correctly adjusted, the final data content is sent to each engineering personnel receiving device.
Preferably, the obtaining module is configured to obtain data of the actual engineering material amount, the engineering material amount just needed, and the estimated engineering material amount from the data center.
Preferably, the actual engineering material amount data and the estimated engineering material amount data are verified based on the obtained actual engineering material amount and the estimated engineering material amount, and whether a data deviation exists is judged to generate a verification module, wherein the verification module is used for verifying the actual engineering material amount data and the estimated engineering material amount data and judging whether the data deviation exists.
Preferably, the actual engineering material amount and the engineering material amount just needed are compared based on the obtained actual engineering material amount and the engineering material amount just needed to generate a comparison calculation module, and the comparison calculation module is used for comparing the actual engineering material amount and the engineering material amount just needed and judging whether the materials are sufficient or not and calculating the time taken by the overall progress.
Preferably, the existing progress amount is obtained based on the obtained time spent on the overall progress, the actual project progress is determined and is compared and adjusted with the expected project progress, and the adjusted work content is obtained to generate a progress adjustment module, and the progress adjustment module is used for obtaining the existing progress amount and comparing and adjusting the existing progress amount with the expected progress amount.
Preferably, based on the adjusted work content, whether construction can be normally performed or whether the construction progress adjustment is correct is judged according to the current demand information and the current construction progress to generate a judgment execution module, and the judgment execution module is used for reading whether the adjusted work content can be normally performed or whether the construction progress adjustment is correct, and sending the final work content to each receiving device of engineering personnel.
In another aspect, a system for project progress supervision based on a blockchain includes,
a material quantity acquisition module: the data information is used for acquiring the actual engineering material quantity, the just-needed engineering material quantity and the predicted engineering material quantity from the data center;
a determination module: the method is used for judging whether the material is sufficient or not based on the obtained actual engineering material quantity, the just-needed engineering material quantity and the estimated engineering material quantity;
if yes, calculating the time spent on the whole progress;
if not, acquiring the actual supplement amount of the engineering material;
actual progress acquisition module: the method comprises the steps of obtaining the existing progress amount based on the obtained time spent on the whole progress, and determining the actual project progress;
the actual progress adjusting module: the system is used for comparing and adjusting the actual project progress with the expected project progress based on the obtained actual project progress to obtain the adjusted work content;
a redistribution module: the system is used for classifying the work contents based on the obtained adjusted work contents, and after the work contents are reordered according to the difficulty and the priority, the contents needing to be preferentially processed can be preferentially processed, so that the subsequent work contents can be more stable;
a feedback update module: for judging whether the construction can be normally carried out or whether the construction progress is correctly adjusted according to the current demand information and the current construction progress based on the redistributed work content,
and if the construction can be normally carried out or the construction progress is correctly adjusted, the final work content is sent to each engineering personnel receiving device.
It should be noted that, in this document, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. A project progress supervision method based on a block chain is characterized by comprising the following steps:
step 1: acquiring actual engineering material quantity, just needed engineering material quantity and pre-estimated engineering material quantity;
step 2: checking and verifying the actual engineering material quantity and the estimated engineering material quantity based on the obtained actual engineering material quantity and the estimated engineering material quantity, and judging whether data deviation exists or not;
if so, adjusting the actual engineering material quantity to eliminate an error;
if not, continuing working;
and step 3: comparing the actual engineering material quantity with the just-needed engineering material quantity based on the obtained actual engineering material quantity and the just-needed engineering material quantity, judging whether the material quantity is sufficient,
if yes, calculating the time spent on the whole progress;
if not, acquiring the actual supplement amount of the engineering material;
and 4, step 4: acquiring the current progress amount based on the time spent on the acquired overall progress, determining the actual project progress, comparing and adjusting the actual project progress with the expected project progress, and acquiring the adjusted work content;
and 5: based on the adjusted work content, judging whether the construction can be normally carried out or whether the construction progress is adjusted correctly according to the current demand information and the current construction progress;
and if the construction can be normally carried out or the construction progress is correctly adjusted, the final data content is sent to each engineering personnel receiving device.
2. The method of claim 1, wherein the obtaining of the actual engineering material amount, the just-needed engineering material amount, and the pre-estimated engineering material amount to generate the obtaining module,
the acquisition module is used for acquiring data of actual engineering material quantity, just-needed engineering material quantity and pre-estimated engineering material quantity from the data center.
3. The method as claimed in claim 1, wherein the actual quantity of engineering material and the estimated quantity of engineering material are verified based on the obtained actual quantity of engineering material and the estimated quantity of engineering material, and whether data deviation exists is judged to generate a verification module,
the checking and verifying module is used for checking and verifying the actual engineering material quantity data and the estimated engineering material quantity data, judging whether data deviation exists or not, and if the data deviation exists, adjusting the actual engineering material quantity.
4. The method of claim 1, comparing the actual quantity of engineering material with the quantity of engineering material just needed to generate a comparison calculation module based on the obtained actual quantity of engineering material and quantity of engineering material just needed,
the comparison calculation module is used for comparing the actual engineering material quantity with the just-needed engineering material quantity and judging whether the materials are sufficient or not and calculating the time spent on the whole progress.
5. The method of claim 1, wherein the obtaining of the amount of progress is based on the time taken for the overall progress obtained, determining the actual project progress, and adjusting in comparison with the expected project progress to obtain the adjusted work content to generate a progress adjustment module,
the progress adjusting module is used for acquiring the existing progress amount and comparing and adjusting the existing progress amount with the expected progress amount.
6. The method according to claim 1, wherein the judging whether the construction can be normally performed or whether the construction progress adjustment is correct is performed based on the adjusted work content according to the current demand information and the current construction progress to generate a judgment execution module,
and the judgment execution module is used for reading whether the adjusted work content can be normally constructed or whether the construction progress adjustment is correct or not and sending the final work content to each receiving device of engineering personnel.
7. A project progress monitoring system based on a block chain is characterized by comprising,
a material quantity acquisition module: the data information is used for acquiring the actual engineering material quantity, the just-needed engineering material quantity and the predicted engineering material quantity from the data center;
a determination module: the method is used for judging whether the material quantity is sufficient or not based on the obtained actual engineering material quantity, the just-needed engineering material quantity and the estimated engineering material quantity;
actual progress acquisition module: the method comprises the steps of obtaining the existing progress amount based on the obtained time spent on the whole progress, and determining the actual project progress;
the actual progress adjusting module: the system is used for comparing and adjusting the actual project progress with the expected project progress based on the obtained actual project progress to obtain the adjusted work content;
a redistribution module: the system is used for classifying the work contents based on the obtained adjusted work contents and reordering the work contents according to the difficulty and the priority, so that the contents needing to be preferentially processed can be preferentially processed, and the subsequent work contents can be more stable;
a feedback update module: for judging whether the construction can be normally carried out or whether the construction progress is correctly adjusted according to the current demand information and the current construction progress based on the redistributed work content,
and if the construction can be normally carried out or the construction progress is correctly adjusted, the final work content is sent to each engineering personnel receiving device.
CN202111417755.8A 2021-11-26 2021-11-26 Project progress monitoring system and method based on block chain Pending CN114091939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111417755.8A CN114091939A (en) 2021-11-26 2021-11-26 Project progress monitoring system and method based on block chain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111417755.8A CN114091939A (en) 2021-11-26 2021-11-26 Project progress monitoring system and method based on block chain

Publications (1)

Publication Number Publication Date
CN114091939A true CN114091939A (en) 2022-02-25

Family

ID=80304755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111417755.8A Pending CN114091939A (en) 2021-11-26 2021-11-26 Project progress monitoring system and method based on block chain

Country Status (1)

Country Link
CN (1) CN114091939A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115760009A (en) * 2022-11-30 2023-03-07 中诚智信工程咨询集团股份有限公司 Project progress management method, device, equipment and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170013422A (en) * 2015-07-14 2017-02-07 서울시립대학교 산학협력단 Labor-based Progress Measurement for Cost and Schedule Control System in Construction Programs
CN108647847A (en) * 2018-03-26 2018-10-12 崔战宾 Material management system in work progress and method
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN112633717A (en) * 2020-12-28 2021-04-09 青岛亿联建设集团股份有限公司 BIM-based management system for building construction
CN112819261A (en) * 2021-04-19 2021-05-18 中数通信息有限公司 Wisdom engineering cooperative management system
CN113065776A (en) * 2021-04-07 2021-07-02 苏州索芙特威尔软件科技有限公司 Raw material management method and system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170013422A (en) * 2015-07-14 2017-02-07 서울시립대학교 산학협력단 Labor-based Progress Measurement for Cost and Schedule Control System in Construction Programs
CN108647847A (en) * 2018-03-26 2018-10-12 崔战宾 Material management system in work progress and method
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN112633717A (en) * 2020-12-28 2021-04-09 青岛亿联建设集团股份有限公司 BIM-based management system for building construction
CN113065776A (en) * 2021-04-07 2021-07-02 苏州索芙特威尔软件科技有限公司 Raw material management method and system
CN112819261A (en) * 2021-04-19 2021-05-18 中数通信息有限公司 Wisdom engineering cooperative management system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115760009A (en) * 2022-11-30 2023-03-07 中诚智信工程咨询集团股份有限公司 Project progress management method, device, equipment and storage medium
CN115760009B (en) * 2022-11-30 2023-12-08 中诚智信工程咨询集团股份有限公司 Engineering progress management method, device, equipment and storage medium

Similar Documents

Publication Publication Date Title
CN108121306A (en) Scheduling system and method
CN114091939A (en) Project progress monitoring system and method based on block chain
CN108804708B (en) Method and device for archiving and correcting business data table, computer equipment and storage medium
CN109740760B (en) Text quality inspection automatic training method, electronic device and computer equipment
CN111694652B (en) Task dynamic scheduling method, device, computer equipment and storage medium
CN113283846A (en) Material processing method and device, terminal equipment and storage medium
CN111833594A (en) Traffic flow prediction method, traffic flow prediction device, electronic device, and storage medium
CN114328095A (en) Task abnormity warning method and device
CN113807821A (en) Discrete scene based work order synchronization method, system, equipment and storage medium
CN111522303A (en) Planned scheduling method and equipment
CN112308636B (en) Market demand value calculation method and device based on market demand change
CN112686433A (en) Express quantity prediction method, device, equipment and storage medium
CN113469612A (en) Logistics timeliness prompting method, device, equipment and storage medium
CN117235062A (en) Service system data modeling method based on data center
CN117273980A (en) Intelligent factory management method, system and storage medium based on data analysis
CN110310098B (en) Automatic construction method and device for distribution network planning problem library
CN111767179A (en) Computer hardware dimension system based on cloud platform
CN110659818A (en) Information processing method and system
CN113190997B (en) Big data terminal data restoration method and system
CN113865681A (en) Intelligent material weighing method and system
CN109502276B (en) Material supplementing method and device and intelligent terminal
CN114742391B (en) Artificial intelligence based exception handling method and device, computer equipment and medium
CN112712308A (en) Inventory monitoring management method and device and storage medium
CN108205740A (en) The manufacturing management device and manufacture system for checking information and tracking information are used
CN113961868B (en) Logistics transport adjusting method and system based on block chain and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination