CN114004631A - Engineering cost control method and system based on BIM technology and computer equipment - Google Patents

Engineering cost control method and system based on BIM technology and computer equipment Download PDF

Info

Publication number
CN114004631A
CN114004631A CN202111219564.0A CN202111219564A CN114004631A CN 114004631 A CN114004631 A CN 114004631A CN 202111219564 A CN202111219564 A CN 202111219564A CN 114004631 A CN114004631 A CN 114004631A
Authority
CN
China
Prior art keywords
construction
subentry
model
cost
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111219564.0A
Other languages
Chinese (zh)
Inventor
胡湘
李帝文
张晓峰
张毓敏
陈甲云
肖秀杰
邹锦辉
胡罕才
陈文深
王兴宽
郑奖妹
彭雄杰
张乐
方家富
王荣江
陈惠宁
陈文锴
宁正兴
邓民强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jianhan Engineering Management Co ltd
Original Assignee
Guangdong Jianhan Engineering Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jianhan Engineering Management Co ltd filed Critical Guangdong Jianhan Engineering Management Co ltd
Priority to CN202111219564.0A priority Critical patent/CN114004631A/en
Publication of CN114004631A publication Critical patent/CN114004631A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0201Market modelling; Market analysis; Collecting market data
    • G06Q30/0206Price or cost determination based on market factors
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/16Real estate
    • G06Q50/165Land development

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Accounting & Taxation (AREA)
  • Geometry (AREA)
  • Finance (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Economics (AREA)
  • Computer Hardware Design (AREA)
  • Civil Engineering (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Pure & Applied Mathematics (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses a project cost control method, a system and computer equipment based on BIM technology, which belongs to the field of building engineering management, and the project cost control method comprises the following steps: generating a three-dimensional model of a target project according to a construction drawing, and dividing the three-dimensional model into a plurality of subentry models according to a construction plan; acquiring the engineering quantity of the components in the subentry model, and calculating the preset cost of the subentry model according to the unit price of the components; acquiring construction information, and marking a corresponding subentry model according to the construction information; acquiring construction member information and comprehensive unit price of a project list, and calculating the construction cost of the subentry model; and if the variance between the construction cost and the preset cost is greater than a first threshold value, sending early warning information to the client. This application can realize monitoring engineering cost, has also improved the efficiency of managing simultaneously.

Description

Engineering cost control method and system based on BIM technology and computer equipment
Technical Field
The application relates to the field of building engineering management, in particular to a project cost control method, a project cost control system and computer equipment based on a BIM technology.
Background
The construction cost refers to the construction price of the project, and refers to the total sum of all the expenses expected or actually required for completing the construction of one project. The project cost is defined from the perspective of an owner, and refers to the construction cost of a project, namely the investment cost of all fixed assets expected to be paid or actually paid for constructing a project.
The BIM technology (Building Information Modeling) is generally translated into a Building Information model. As a new technology in the engineering construction industry, the BIM technology emphasizes the application of coordinated and consistent information in each stage of the whole life cycle of an engineering project, and the most intuitive expression form of the BIM technology is a three-dimensional building model with project information.
The construction cost is in an uncertain state in the construction stage, so that the control of the construction cost has the characteristic of dynamic management, and the control of the construction cost by engineering management personnel brings difficulty in the aspect of the construction cost in the construction stage.
Disclosure of Invention
In order to monitor the construction cost in the construction process, the application provides a construction cost control method, a system and computer equipment based on the BIM technology.
In a first aspect, the present application provides a project cost control method based on the BIM technology, which adopts the following technical scheme:
a project cost control method based on BIM technology comprises the following steps:
generating a three-dimensional model of a target project according to a construction drawing, and dividing the three-dimensional model into a plurality of subentry models according to a construction plan;
acquiring the engineering quantity of the components in the subentry model, and calculating the preset cost of the subentry model according to the unit price of the components;
acquiring construction information, and marking a corresponding subentry model according to the construction information;
acquiring construction member information and comprehensive unit price of a project list, and calculating the construction cost of the subentry model;
and if the variance between the construction cost and the preset cost is greater than a first threshold value, sending early warning information to the client.
By adopting the technical scheme, the construction information of the site is acquired, the corresponding subentry model is marked according to the construction information, the constructed subentry model and the constructed subentry model are distinguished, the current construction progress can be visually known on the three-dimensional model, and the construction progress is conveniently controlled. Meanwhile, the preset cost of the subentry model is calculated, the actual construction cost is calculated through the comprehensive unit price of the component information, the construction cost is compared with the preset cost, and when the construction cost exceeds the preset cost and the exceeding range is larger than a first threshold value, early warning information is sent to the client side, so that the exceeding situation can be known in time, and the engineering cost can be regulated and controlled subsequently.
Optionally, after acquiring the information of the constructed components and the comprehensive unit price of the project list and calculating the construction cost of the subentry model, the method further includes:
acquiring the type, material and size of the component;
obtaining a weight set of the component in a table look-up mode according to the type, the material and the size of the component;
and acquiring the actual weight of the component, calculating the deviation between the actual weight and the weight set, and if the deviation is greater than a second threshold value, sending alarm information to the client.
By adopting the technical scheme, the range of the estimated weight of the member is obtained according to the type, the material and the size of the member, then the actual weight of the member is obtained, the actual weight is compared with the estimated weight in the weight set, and whether the member belongs to the condition of material reduction by the work stealing or not is judged, so that the condition of material reduction by the work stealing can be reduced.
Optionally, the calculating the deviation between the actual weight and the weight set includes:
the variance between the actual weight and each value in the weight set is calculated and the variance is averaged to obtain the deviation.
By adopting the technical scheme, the average of the variances is calculated. The accuracy of the deviation can be improved, and errors can be reduced.
Optionally, if the deviation is greater than the second threshold, after sending the warning information to the client, the method further includes:
if the deviation is less than the second threshold and the actual weight is different from the values in the weight set, the actual weight is added to the weight set until the number of values in the weight set is greater than the predetermined number.
By adopting the technical scheme, the deviation is smaller than the second threshold value, the weight is the normal weight of the workpiece, if the weight does not appear in the weight set, the weight is added into the weight set, the base number of the weight set can be enlarged, and the accuracy is improved.
Optionally, the obtaining the engineering quantity of the component in the subentry model, and calculating the preset cost of the subentry model according to the unit price of the component, includes:
monitoring contract change information of a target project, and obtaining the variation of a component according to the contract change information;
and acquiring the construction cost information of the component, and updating the preset cost of the subentry model according to the variable quantity.
By adopting the technical scheme, contract change information appears, and the preset cost is enabled to correspond to the cost of the construction plan by recalculating the variable quantity of the member.
Optionally, after the obtaining of the construction information and marking the corresponding itemized model according to the construction information, the method further includes:
analyzing the marked subentry model to obtain the current construction progress;
and comparing the current construction progress with the predicted progress, and if the current construction progress is smaller than the predicted progress, sending an overdue signal to the client.
By adopting the technical scheme, the construction progress is monitored, and the overdue signal is timely sent to the client when the current construction progress is behind, so that the overdue condition can be conveniently and timely known.
In a second aspect, the present application provides a project cost control system based on the BIM technology, which adopts the following technical scheme:
a construction cost control system based on BIM technology comprises:
the generation and division module is used for generating a three-dimensional model of the target project according to the construction drawing and dividing the three-dimensional model into a plurality of subentry models according to the construction plan;
the first calculation module is used for acquiring the engineering quantity of the component in the subentry model and calculating the preset cost of the subentry model according to the unit price of the component;
the acquisition marking module is used for acquiring construction information and marking the corresponding subentry model according to the construction information;
the second calculation module is used for acquiring the construction member information and the comprehensive unit price of the project list and calculating the construction cost of the subentry model;
a comparison sending module: and sending early warning information to the client if the variance between the construction cost and the preset cost is greater than a first threshold.
By adopting the technical scheme, the construction information of the site is acquired, the corresponding subentry model is marked according to the construction information, the constructed subentry model and the constructed subentry model are distinguished, the current construction progress can be visually known on the three-dimensional model, and the construction progress is conveniently controlled. Meanwhile, the preset cost of the subentry model is calculated, the actual construction cost is calculated through the comprehensive unit price of the component information, the construction cost is compared with the preset cost, and when the construction cost exceeds the preset cost and the exceeding range is larger than a first threshold value, early warning information is sent to the client side, so that the exceeding situation can be known in time, and the engineering cost can be regulated and controlled subsequently.
In a third aspect, the present application provides a computer device, which adopts the following technical solution:
a computer device comprising a memory and a processor, the memory having stored thereon a computer program that can be loaded by the processor and executed to perform any of the methods described above.
In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solutions:
a computer readable storage medium storing a computer program that can be loaded by a processor and executed to perform any of the methods described above.
In summary, the present application includes at least one of the following beneficial technical effects:
1. marking the corresponding subentry model according to the construction information, and distinguishing the constructed subentry model from the non-constructed subentry model, so that the current construction progress can be visually known on the three-dimensional model, and the construction progress can be conveniently controlled; 2. calculating the actual construction cost through the comprehensive unit price of the component information, comparing the construction cost with the preset cost, and sending early warning information to the client when the construction cost exceeds the preset cost and the exceeding range is greater than a first threshold value, so that the exceeding condition can be known in time, and the construction cost can be regulated and controlled subsequently;
3. and comparing the actual weight of the member with the predicted weight in the weight set, and further judging whether the member belongs to work stealing and material reducing, so that the situation of work stealing and material reducing can be reduced.
Drawings
FIG. 1 is a flow chart of a construction cost control method based on BIM technology in an embodiment of the present application;
FIG. 2 is a flow chart of a construction cost control method based on BIM technology in another embodiment of the present application;
fig. 3 is a block diagram of a construction cost control system based on the BIM technology in the embodiment of the present application.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application is further described in detail below with reference to fig. 1-3 and the embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application.
The project cost control method based on the BIM technology can be executed by a project cost control system based on the BIM technology, and the project cost control system based on the BIM technology comprises a memory and a processor. The memory stores program of BIM software, which may be but not limited to Revit software, and also stores computer program executable by the processor for implementing project cost control method based on BIM technology.
The embodiment of the application discloses a project cost control method based on BIM technology, and with reference to figure 1, the project cost control method comprises the following steps:
s1: and generating a three-dimensional model of the target project according to the construction drawing, and dividing the three-dimensional model into a plurality of subentry models according to the construction plan.
Specifically, for example, during building construction, a three-dimensional model of a target project is generated in the BIM software according to the overall construction information of the column, the wall, the door and window position, and the outer vertical surface in the construction drawing, and the corresponding information such as the elevation, the floor height, and the dimensions of the members. When a bridge is constructed, a three-dimensional model of a target project is generated in BIM software according to information such as bridge piers, bridge abutments and bearing platforms in a construction drawing, corresponding elevations, bridge heights and sizes of components.
For example, in building a house, the construction plan is to build a bedroom first, then a bathroom and a balcony, and then, in the three-dimensional model of the house, the three-dimensional model is divided into a bedroom itemized model, a bathroom itemized model and a balcony itemized model.
S2: and acquiring the engineering quantity of the component in the subentry model, and calculating the preset cost of the subentry model according to the unit price of the component.
Specifically, the preset cost of the subentry model can be calculated by counting the number of materials used in the subentry model and the unit price of the materials used. For example, when a living room is built, the number of the required wallboards is 10, the price of each wallboard is 900 yuan, and the preset cost of the living room is 9000 yuan.
S3: and acquiring construction information, and marking the corresponding itemized model according to the construction information.
Specifically, the construction information is the construction progress, the construction photo of the construction site is obtained, then the construction photo is processed through a relatively mature image processing technology in the prior art, so that the corresponding target building in the construction photo is extracted, the proportion of the target building is adjusted to be consistent with that of the model, the target building is compared with the three-dimensional model, and the overall construction progress is further obtained.
By comparing the target building with the three-dimensional model, which itemized models are already constructed, which itemized models are under construction and which itemized models are not under construction can be obtained, and the constructed and under-construction itemized models are marked. For example, when a bridge is constructed, the three-dimensional model of the bridge comprises a bridge pier subentry model, a bridge abutment subentry model and a cushion cap subentry model; the integral color of the original three-dimensional model is gray, wherein a bearing platform can be obtained through a construction picture on site to complete construction, a bridge pier is under construction, the color of the bearing platform is green, the color of the bridge pier is yellow, the color of the bridge platform is still gray in the three-dimensional model, and the color is displayed in a distinguishing mode through different colors, so that a worker can conveniently know the actual construction progress from the three-dimensional model.
S4: and acquiring the construction member information and the comprehensive unit price of the project list, and calculating the construction cost of the subentry model.
Specifically, the component information includes the type, material and size of the component, and the item list includes the list code, the item name, the component amount, the measurement unit and the component feature description. For example, types of members in building construction include wall panel members for the construction of bedrooms, balcony members for the construction of balconies, and toilet members for the construction of toilets.
S5: and if the variance between the construction cost and the preset cost is greater than a first threshold value, sending early warning information to the client.
Specifically, the client may be a mobile phone, a tablet computer, a laptop computer, or a desktop computer. For example, when the client is a mobile phone, the mobile phone is started to the mobile phone of the responsible person in a short message manner to remind the responsible person.
The first threshold may be set according to actual conditions, and in this embodiment, the first threshold is equal to the preset cost × 8%. For example, if the preset cost is 10000 yuan, the first threshold value is 10000 × 8% — 800, if the actual cost is 10070 yuan, the variance between the construction cost and the preset cost is 10070-; if the actual cost is 9800, the variance between the construction cost and the preset cost is 9800 and 10000 is-200, and-200 <800, the early warning information is not sent; if the actual cost is 12000, the variance between the construction cost and the preset cost is 12000 and 10000 is-2000, and 2000 is more than 800, the early warning information of the excessive advance is sent to the mobile phone of the responsible person.
Referring to fig. 2, after step S4, that is, after acquiring the information of the constructed components and the comprehensive unit price of the project list and calculating the construction cost of the itemized model, the method further includes the following steps:
s6: the type, material and dimensions of the component are obtained.
Specifically, by selling the information of the document and inputting the corresponding information of the member into the server, for example, the material of the wall plate member is concrete, and the size is 3 meters by 4 meters.
S7: and obtaining a weight set to which the component belongs by a table look-up mode according to the type, the material and the size of the component.
Specifically, the weight set is a set of numerical values of the weight of a certain member, and the normal weight of the member is actually measured and stored in the form of a number set. For example, if the dimensions of a 3 m x 4 m wallboard element, the material of which is concrete, are 1560kg, 1553kg, 1565kg, respectively, the normal weight of the wallboard element is (1553, 1560, 1565); a wall panel element of 5 x 6 m size, the material of the wall panel element being concrete, the normal weight of the wall panel element being 3130kg, 3139kg, 3125kg, respectively, the weight aggregate of the wall panel elements being (3125, 3130, 3139); balcony members of dimensions 2 m x 3 m, the material of which is concrete, the normal weight of which is 1360kg, 1352kg, 1365kg, respectively, the weight of the wall panel members then being (1352, 1360, 1365) in total.
S8: and acquiring the actual weight of the component, calculating the deviation between the actual weight and the weight set, and if the deviation is greater than a second threshold value, sending alarm information to the client.
Specifically, during on-site construction, the hoisting equipment is used for hoisting the component, the component is weighed through the weighing device on the hoisting equipment so as to obtain the actual weight of the component, and the actual weight is sent to the server. The construction position of the component is obtained by obtaining a construction photo of a construction site, and the type, material and size of the component at the construction position can be obtained according to a construction drawing.
Optionally, in step S8, the calculating the deviation between the actual weight and the weight set includes the following sub-steps:
s81: in particular, the variance is a positive integer, the second threshold is set to 500, e.g., the set of weights for wallboard component A is (1553, 1560, 1565), the actual weight for wallboard component A is 1550kg, and the variance for wallboard component A is [ (1550-2+(1550-1560)2+(1550-1565)2]111, wherein 111<500, no alarm information is sent. If the actual weight of the wallboard member B is 1510kg, the variance of the wallboard member B is [ (1510-2+(1510-1560)2+(1510-1565)2]And 3, 5357 and 5357 is more than 500, sending alarm information that the weight of the component is abnormal to the client.
Optionally, in step S8, after sending the warning message to the client if the deviation is greater than the second threshold, the method further includes the following steps:
s82: if the deviation is less than the second threshold and the actual weight is different from the values in the weight set, the actual weight is added to the weight set until the number of values in the weight set is greater than the predetermined number.
Specifically, for example, the second threshold is set to 500, for example, the weight set of the wall plate members is (1553, 1560, 1565), the actual weight of the wall plate member a is 1550kg, and the variance of the wall plate member a is [ (1550-2+(1550-1560)2+(1550-1565)2]111, wherein 111<500 and 1550 is different from 1553, 1560, 1565, then take 1550 into the weight set of wallboard component a, update the weight set of wallboard component a to (1550, 1553, 1560, 1565); the actual weight of the wallboard member B is 1550kg, and the variance of the wallboard member B is 1550-2+(1550-1553)2+(1550-1560)2+(1550-1565)2]83, wherein 83<500, but 1550 is already in the weight set, so 1550 is no longer added to the weight set of the wallboard member.
For example, if the predetermined number is 3, the weight set of wallboard members is (1550, 1553, 1560, 1565), the weight set already has 4 values, and no value is subsequently added to the weight set.
Optionally, in step S2, acquiring the engineering quantity of the component in the polynomial model, and calculating the preset cost of the polynomial model according to the unit price of the component, includes:
s21: and monitoring contract change information of the target project, and obtaining the variation of the component according to the contract change information.
S22: and acquiring the construction cost information of the component, and updating the preset cost of the subentry model according to the variable quantity.
Specifically, when the contract is changed, the changed contract is scanned or manually entered into the server, and the server stores the changed contract and records the storage date of the contract. And identifying contract information in real time to determine that the three-dimensional model of the current version is matched with the current latest contract, identifying the cost information and the variable quantity of the updated component if the three-dimensional model of the current version is not matched with the current latest contract, and updating the preset cost of the item model.
Optionally, after step S3, and after acquiring the construction information, and marking the corresponding itemized model according to the construction information, the method further includes:
s31: and analyzing the marked subentry model to obtain the current construction progress.
S32: and comparing the current construction progress with the predicted progress, and if the current construction progress is smaller than the predicted progress, sending an overdue signal to the client.
Specifically, construction photos of a construction site are obtained periodically, then the construction photos are processed through a relatively mature image processing technology in the prior art to extract a corresponding target building in the construction photos, the proportion of the target building is adjusted to be consistent with that of the model, the target building is compared with the three-dimensional model, the overall construction progress is carried out, and the hierarchical model is marked. After marking, the current construction progress can be obtained through the marked subentry model, and a construction photo does not need to be obtained in real time. And comparing the current construction progress with the predicted progress, and if the construction progress is smaller than the predicted progress, sending an overdue signal to the client.
Referring to fig. 3, an embodiment of the present application further discloses a project cost control system based on the BIM technology, including: and the generation and division module is used for generating a three-dimensional model of the target project according to the construction drawing and dividing the three-dimensional model into a plurality of subentry models according to the construction plan.
The first calculation module is used for acquiring the engineering quantity of the component in the subentry model and calculating the preset cost of the subentry model according to the unit price of the component.
And the acquisition marking module is used for acquiring the construction information and marking the corresponding subentry model according to the construction information.
And the second calculation module is used for acquiring the construction member information and the comprehensive unit price of the project list and calculating the construction cost of the subentry model.
A comparison sending module: and the early warning device is used for sending early warning information to the client if the difference value between the construction cost and the preset cost is greater than a first threshold value.
The specific limitations of the construction cost control system based on the BIM technology can be referred to the limitations of the construction cost control method based on the BIM technology, and will not be described herein again. All or part of each module in the BIM technology-based project cost control system can be realized by software, hardware and a combination thereof. The modules can be embedded in a hardware form or independent from a processor in the computer device, and can also be stored in a memory in the computer device in a software form, so that the processor can call and execute operations corresponding to the modules.
The embodiment of the application also discloses computer equipment which comprises a memory and a processor, wherein the memory is stored with a computer program which can be loaded by the processor and can execute the project cost control method based on the BIM technology.
The embodiment of the application also discloses a computer readable storage medium, which stores a computer program capable of being loaded by a processor and executing the project cost control method based on the BIM technology.
It will be apparent to those skilled in the art that, for convenience and brevity of description, only the above-mentioned division of the functional units and modules is illustrated, and in practical applications, the above-mentioned function distribution may be performed by different functional units and modules according to needs, that is, the internal structure of the apparatus is divided into different functional units or modules to perform all or part of the above-mentioned functions.
The above-mentioned embodiments are only used for illustrating the technical solutions of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; such modifications and substitutions do not substantially depart from the spirit and scope of the embodiments of the present application and are intended to be included within the scope of the present application.

Claims (9)

1. A project cost control method based on BIM technology is characterized by comprising the following steps:
generating a three-dimensional model of a target project according to a construction drawing, and dividing the three-dimensional model into a plurality of subentry models according to a construction plan;
acquiring the engineering quantity of the components in the subentry model, and calculating the preset cost of the subentry model according to the unit price of the components;
acquiring construction information, and marking a corresponding subentry model according to the construction information;
acquiring construction member information and comprehensive unit price of a project list, and calculating the construction cost of the subentry model;
and if the variance between the construction cost and the preset cost is greater than a first threshold value, sending early warning information to the client.
2. The BIM technology-based construction cost control method according to claim 1, wherein after acquiring construction component information and a comprehensive unit price of a project list and calculating construction costs of the itemized models, the method further comprises:
acquiring the type, material and size of the component;
obtaining a weight set of the component in a table look-up mode according to the type, the material and the size of the component;
and acquiring the actual weight of the component, calculating the deviation between the actual weight and the weight set, and if the deviation is greater than a second threshold value, sending alarm information to the client.
3. The BIM technology-based construction cost control method according to claim 2, wherein the summing calculating the deviation between the actual weight and the set of weights comprises:
the variance between the actual weight and each value in the weight set is calculated and the variance is averaged to obtain the deviation.
4. The BIM technology-based construction cost control method according to claim 2, wherein after sending the warning message to the client if the deviation is greater than the second threshold, the method further comprises:
if the deviation is less than the second threshold and the actual weight is different from the values in the weight set, the actual weight is added to the weight set until the number of values in the weight set is greater than the predetermined number.
5. The BIM technology-based construction cost control method according to claim 1, wherein the obtaining of the construction amount of the component in the subentry model and the calculating of the preset cost of the subentry model according to the unit price of the component comprise:
monitoring contract change information of a target project, and obtaining the variation of a component according to the contract change information;
and acquiring the construction cost information of the component, and updating the preset cost of the subentry model according to the variable quantity.
6. The BIM technology-based construction cost control method according to claim 1, wherein the step of obtaining the construction information and marking the corresponding subentry model according to the construction information further comprises:
analyzing the marked subentry model to obtain the current construction progress;
and comparing the current construction progress with the predicted progress, and if the current construction progress is smaller than the predicted progress, sending an overdue signal to the client.
7. A project cost control system based on BIM technology, comprising:
the generation and division module is used for generating a three-dimensional model of the target project according to the construction drawing and dividing the three-dimensional model into a plurality of subentry models according to the construction plan;
the first calculation module is used for acquiring the engineering quantity of the component in the subentry model and calculating the preset cost of the subentry model according to the unit price of the component;
the acquisition marking module is used for acquiring construction information and marking the corresponding subentry model according to the construction information;
the second calculation module is used for acquiring the construction member information and the comprehensive unit price of the project list and calculating the construction cost of the subentry model;
a comparison sending module: and sending early warning information to the client if the variance between the construction cost and the preset cost is greater than a first threshold.
8. A computer device comprising a memory and a processor, the memory having stored thereon a computer program that can be loaded by the processor and that executes the method according to any one of claims 1 to 6.
9. A computer-readable storage medium, in which a computer program is stored which can be loaded by a processor and which executes the method of any one of claims 1 to 6.
CN202111219564.0A 2021-10-20 2021-10-20 Engineering cost control method and system based on BIM technology and computer equipment Pending CN114004631A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111219564.0A CN114004631A (en) 2021-10-20 2021-10-20 Engineering cost control method and system based on BIM technology and computer equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111219564.0A CN114004631A (en) 2021-10-20 2021-10-20 Engineering cost control method and system based on BIM technology and computer equipment

Publications (1)

Publication Number Publication Date
CN114004631A true CN114004631A (en) 2022-02-01

Family

ID=79923471

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111219564.0A Pending CN114004631A (en) 2021-10-20 2021-10-20 Engineering cost control method and system based on BIM technology and computer equipment

Country Status (1)

Country Link
CN (1) CN114004631A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114580974A (en) * 2022-04-28 2022-06-03 江苏南通冠仟新材料科技有限公司 BIM project cost control method and system based on computer aided design
CN115329448A (en) * 2022-10-14 2022-11-11 中国电建集团山东电力建设第一工程有限公司 BIM-based fabricated building construction cost control method and system
CN116862545A (en) * 2023-04-25 2023-10-10 广东源恒软件科技有限公司 Dynamic analysis method and system for engineering cost
CN116934369A (en) * 2023-07-17 2023-10-24 佛山市盈科工程造价咨询事务所有限公司 Engineering cost real-time analysis management method, system, terminal and storage medium
CN117011081A (en) * 2023-08-07 2023-11-07 深圳叮当科技技术有限公司 Whole process engineering calculation amount management method and system based on BIM technology
CN117474487A (en) * 2023-11-06 2024-01-30 青矩技术股份有限公司 Engineering material inspection method, device, equipment and storage medium

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114580974A (en) * 2022-04-28 2022-06-03 江苏南通冠仟新材料科技有限公司 BIM project cost control method and system based on computer aided design
CN115329448A (en) * 2022-10-14 2022-11-11 中国电建集团山东电力建设第一工程有限公司 BIM-based fabricated building construction cost control method and system
CN116862545A (en) * 2023-04-25 2023-10-10 广东源恒软件科技有限公司 Dynamic analysis method and system for engineering cost
CN116934369A (en) * 2023-07-17 2023-10-24 佛山市盈科工程造价咨询事务所有限公司 Engineering cost real-time analysis management method, system, terminal and storage medium
CN117011081A (en) * 2023-08-07 2023-11-07 深圳叮当科技技术有限公司 Whole process engineering calculation amount management method and system based on BIM technology
CN117474487A (en) * 2023-11-06 2024-01-30 青矩技术股份有限公司 Engineering material inspection method, device, equipment and storage medium

Similar Documents

Publication Publication Date Title
CN114004631A (en) Engineering cost control method and system based on BIM technology and computer equipment
CN113744395B (en) Monitoring and early warning method and system for building foundation settlement
Zhang et al. BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies
CN108385691A (en) Pit retaining monitoring, early warning and the construction management D-BIM platforms of integrated Big Dipper high-accuracy position system
CN107122910A (en) A kind of river course wisdom management platform based on BIM+GIS
CN112948950B (en) BIM technology-based integrated information intelligent management system and management method
CN108428196B (en) Loading sequence determination method and device based on BIM assembly type building components
CN111457854A (en) Deformation monitoring method and device based on building
Navon et al. Algorithms for automated monitoring and control of fall hazards
CN114372311B (en) BIM-based design detection method and device, electronic equipment and storage medium
CN115456398A (en) Consumable missing detection method, device, storage medium and system
CN114660528A (en) Power distribution station electric energy meter abnormity determining method, device and system
CN110750885A (en) On-site fire safety monitoring method and system
Wang et al. Integrating building information modelling and firefly algorithm to optimize tower crane layout
Biel Concept of using the BIM technology to support the defect management process
CN116977124A (en) BIM quality detection-based informationized management method, system, equipment and medium
CN111199495A (en) Health state visual analysis method and system for historical protection building
CN113720283B (en) Building construction height identification method, device, electronic equipment and system
CN114065440A (en) Method for evaluating service life of tower crane, controller and server
CN116311770A (en) House safety early warning system, method and terminal based on Internet of things edge computing gateway
Pan et al. Research on Dynamic Monitoring and Early Warning of the High‐Rise Building Machine during the Climbing Stage
Yuan et al. Real-time Cyber-Physical Systems (CPS)-based monitoring of temporary structures: A scaffolding system example
CN112116278A (en) Assembly type building construction safety monitoring method and system and cloud platform
CN116977122B (en) Remote automatic monitoring method for dangerous rooms based on digital twin technology
CN115994070B (en) System availability detection method and device, electronic equipment and readable storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination