CN113944262A - Construction method for foundation-pillar-free deep foundation pit and outer wall integrated structure - Google Patents

Construction method for foundation-pillar-free deep foundation pit and outer wall integrated structure Download PDF

Info

Publication number
CN113944262A
CN113944262A CN202111225770.2A CN202111225770A CN113944262A CN 113944262 A CN113944262 A CN 113944262A CN 202111225770 A CN202111225770 A CN 202111225770A CN 113944262 A CN113944262 A CN 113944262A
Authority
CN
China
Prior art keywords
wall
retaining wall
foundation pit
membrane retaining
outer side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111225770.2A
Other languages
Chinese (zh)
Other versions
CN113944262B (en
Inventor
奚邦凤
熊金鹏
刘志远
杨宏正
陶志红
桂高斌
贺梅芳
冯友雄
王波
张博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Co Ltd
Original Assignee
Wuhan Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Co Ltd filed Critical Wuhan Construction Engineering Co Ltd
Priority to CN202111225770.2A priority Critical patent/CN113944262B/en
Publication of CN113944262A publication Critical patent/CN113944262A/en
Application granted granted Critical
Publication of CN113944262B publication Critical patent/CN113944262B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2/8611Walls made by casting, pouring, or tamping in situ made in permanent forms with spacers being embedded in at least one form leaf
    • E04B2/8617Walls made by casting, pouring, or tamping in situ made in permanent forms with spacers being embedded in at least one form leaf with spacers being embedded in both form leaves

Abstract

The invention provides a construction method of a foundation-pillar-free deep foundation pit and outer wall integrated structure, wherein a template supporting wall is arranged in a foundation pit, a foundation pit supporting side wall and the template supporting wall are fixedly connected through connecting ribs, a template of an outer wall is built by means of the template supporting wall, so that the outer wall is poured, the template supporting wall comprises a membrane retaining wall and ring beams which are sequentially arranged from bottom to top at intervals, each layer of membrane retaining wall is embedded and installed in an upper groove and a lower groove in each layer of ring beam, and the foundation pit supporting side wall and the ring beams on the membrane retaining wall are fixedly connected through the connecting ribs. The membrane retaining wall consists of an outer side membrane retaining wall and an inner side membrane retaining wall, a waterproof coiled material is paved between the two walls, and the waterproof coiled material extends from the membrane retaining wall to cover the lower part of the underground indoor structure bottom plate. The whole supporting system is designed to be close to the outer wall of the basement, so that the period for building the outer wall formwork of the basement is shortened, constructional columns are omitted, and the earthwork construction amount and the outer wall backfill amount are reduced.

Description

Construction method for foundation-pillar-free deep foundation pit and outer wall integrated structure
Technical Field
The invention relates to the field of construction of outer walls of building deep foundation pits, in particular to a construction method of an integrated structure of the outer walls of a foundation-pillar-free deep foundation pit.
Background
In the traditional construction process, as shown in figure 3, a template support is erected, a waterproof coiled material is laid on a cushion layer, a basement structure bottom plate 12 is poured on the waterproof coiled material, an outer wall side line is bounced on the cushion layer, a constructional column 30 is erected on the inner boundary and the outer boundary of the outer wall, then a template wall for pouring an outer wall 15 is fixed based on the constructional column 30, a template enclosing wall is removed, finally, the outer side 31 of the basement outer wall continues to extend upwards along the wall surface to cover a waterproof roll layer, and the constructional column between the basement outer wall and the foundation pit supporting side wall is removed, and backfilling earthwork.
Therefore, in the existing construction of the basement exterior wall of the deep foundation pit shown in fig. 3, the exterior wall template and the inner side constructional column close to the center of the foundation pit cannot be backfilled between the exterior wall template and the foundation pit supporting side wall, so that the waterproof layer cannot be paved, and the basement exterior wall is subjected to water seepage.
Therefore, in the support design stage, a certain operation space, namely 1.2m-1.5m, is ensured, the design width can be convenient for installing formwork enclosing walls on the inner side and the outer side of the outer wall sideline in a wide place, the distance between the inner side formwork enclosing wall and the outer side formwork enclosing wall is controlled by using the opposite-pulling screw rods, and the wide place is also convenient for the evacuation of constructors. If the deviation appears when receiving place restriction or lateral wall fender pile construction, the operation space will reduce, and the actual construction also can often have the operation face of actual reservation and reduce a lot than the operation face of design reservation, so construction condition is very unfavorable to above-mentioned outer wall construction method construction this moment, finally causes very negative effect to engineering quality and construction safety.
On the other hand, in the existing outer wall construction process, firstly, the reserved space between the supporting pile and the outer wall of the basement is too large, so that the earthwork excavation and the backfill amount are directly increased, and the construction cost is increased; secondly, the working procedures are more, the lapping of the front working procedure and the rear working procedure is limited and is influenced by narrow space, so that the working efficiency is not high, and the adverse effect is generated on the construction of a basement; thirdly, the backfill construction of the outer wall is difficult, and the backfill cost is high.
Disclosure of Invention
Based on the actual problems, the technical scheme provided by the invention can provide the wall body for supporting the waterproof coiled material, the wall body can form an enclosing wall for pouring the basement outer wall by pulling the formwork, and can resist extrusion of backfill materials to the wall body when the wall body is backfilled between the basement outer wall and the foundation pit supporting side wall, so that the displacement of the waterproof coiled material layer is avoided, the space between the wall body and the foundation pit supporting side wall can be backfilled before the basement outer wall is poured, and the working procedure of constructing the supporting columns on the side, facing the foundation pit supporting side, of the wall body and the working procedure of recovering the supporting columns are omitted. Therefore, dependence on the outer space in basement exterior wall construction is reduced, namely the outer space can be controlled within 0.5m, meanwhile, construction period and cost are saved, the foundation pit is designed into an integrated structure of the outer wall more flexibly and more economically, the efficiency of deep foundation pit basement exterior wall construction is improved, the whole construction progress is accelerated, and the construction cost of the foundation pit is reduced.
According to the technical scheme, the construction method of the foundation-pillar-free type deep foundation pit outer wall integrated structure can improve the construction efficiency of the deep foundation pit basement outer wall, greatly quickens the overall construction progress compared with the traditional basement outer wall construction, and can reduce the construction cost of the foundation pit.
In order to solve the technical problems, the invention adopts the following technical scheme:
a construction method for an integrated structure of an external wall of a foundation-pillar-free deep foundation pit comprises the following steps:
step 1, pouring a cushion layer on the ground of a foundation pit, reserving an annular groove on the cushion layer along the side wall of the foundation pit support, enabling the annular groove to surround one circle of the side wall of the foundation pit support and be parallel to the side wall of the foundation pit support, uniformly arranging reinforcement embedding holes on the surface of the side wall of the foundation pit support, inserting tie bars into the reinforcement embedding holes, then pouring reinforcement embedding glue, building an outer side membrane retaining wall by taking one side, adjacent to the side wall of the foundation pit support, in the annular groove as a boundary, placing a layer of I-steel on a wall edge when the outer side membrane retaining wall is built at a certain height, enabling the wall edge to be embedded into a notch of the I-steel, horizontally pushing each I-steel in the direction far away from the side wall of the foundation pit support, enabling a plurality of I-steels to be connected into a circle along the wall edge of the outer side membrane retaining wall to form a ring beam, enabling the flange of each layer of I-steel far away from the side wall of the foundation pit support and one side of the outer side membrane retaining wall facing the center of the foundation pit to form a groove, enabling the I-steel in each ring beam to be equal in height, each layer of ring beam is welded and connected with the tie bars through the connecting bars, and one end of each tie bar, which is far away from the side wall of the foundation pit support, does not contact the outer side fetal membrane retaining wall;
step 2, continuously building the outer side tire membrane retaining wall above each layer of ring beam according to the method in the step 1 until the elevation is reached, laying waterproof coiled materials along one side, facing the inside of the foundation pit, of the cushion layer, the annular groove, the outer side tire membrane retaining wall and the ring beam, and enabling every two adjacent waterproof coiled materials to be staggered;
step 3, building an inner side tire membrane retaining wall along the annular groove and adjacent to the outer side tire membrane retaining wall, immediately filling high-strength mortar in a gap of the annular groove, so that the annular groove, the outer side tire membrane retaining wall and the inner side tire membrane retaining wall are tightly fastened, meanwhile, the inner side tire membrane retaining wall is built into the groove between the ring beam and the outer side tire membrane retaining wall, and the width of the notch of the I-steel is equal to the sum of the wall thicknesses of the outer side tire membrane retaining wall and the inner side tire membrane retaining wall;
step 4, pouring a concrete layer of the backfilled plain concrete on the outer side between the side wall of the foundation pit support and the outer side fetal membrane retaining wall, so that the backfilled plain concrete is tightly connected with the side wall of the foundation pit support;
step 5, pouring a structural bottom plate on the waterproof coiled material on the cushion layer on the inner periphery of the inner side tire membrane retaining wall, uniformly anchoring a plurality of draw hooks into one side of the inner side tire membrane retaining wall, which is opposite to the side wall of the foundation pit support, to form an array in an annular mode, bouncing a boundary line of an outer wall on the basement structural bottom plate, building a fence along the boundary line by using a template, hooking one end of a counter-pull screw on a draw hook ring on the inner side tire membrane retaining wall in the building process, screwing the other end of the counter-pull screw through a through hole in the fence by using a butterfly buckle, adjusting the counter-pull screw at the same time, and reinforcing the completed fence;
and 6, pouring an outer wall between the enclosing wall and the inner side tire membrane retaining wall.
Preferably, in the method, the step (2) is replaced by laying waterproof rolls along the cushion layer, the annular groove, the outer side membrane retaining wall and one side of the ring beam facing the inside of the foundation pit, wherein each adjacent waterproof roll is staggered;
a step is added between the step (4) and the step (5): and (4) continuously building the outer side tire membrane retaining wall and the inner side tire membrane retaining wall above each layer of ring beam according to the methods in the steps (1) to (4), laying waterproof coiled materials, filling high-strength mortar, and backfilling plain concrete until the elevation is reached.
The invention has the beneficial effects that:
1. the requirement on the outer construction operation surface is small, the earth excavation amount is reduced, and the construction is flexible; the whole supporting system is designed to be close to the outer wall of the basement, so that the period for building the outer wall formwork of the basement is shortened, constructional columns are omitted, and the earthwork construction amount and the outer wall backfill amount are reduced.
2. The tie bar installed on the foundation pit supporting side wall fastens and connects each layer of ring beam with the foundation pit supporting side wall through the connecting bar, the ring beam fixes the outer side fetal membrane retaining wall and the inner side fetal membrane retaining wall, and prevents the falling of the outer side fetal membrane retaining wall and the inner side fetal membrane retaining wall when plain concrete is backfilled, thereby avoiding the displacement of the waterproof coiled material laid between the outer side fetal membrane retaining wall and the inner side fetal membrane retaining wall, and the inner side fetal membrane retaining wall is pulled and tied with the template through the pulling and hooking ring and the pulling and tying screw rod, thereby ensuring the flatness of the outer wall poured between the inner side fetal membrane retaining wall and the template, on the other hand, directly backfilling the plain concrete between the outer side fetal membrane retaining wall and the foundation pit supporting side wall, and omitting the construction quantity of the supporting structure of the outer side fetal membrane retaining wall, thereby shortening the construction period of the basement outer wall.
In general, realize deep basal pit basement outer wall integral type construction, not only can practice thrift construction period greatly, can let the foundation ditch design more nimble more practice thrift moreover.
Drawings
FIG. 1 is a schematic structural view of a vertical section node of the present invention;
FIG. 2 is a schematic diagram of a structure of a tie node at a backfill layer according to the present invention;
FIG. 3 is a schematic diagram of conventional construction of an outer wall of a deep foundation pit;
wherein, 1-layer line; 2-oppositely pulling the screw rod; 3-ring beam; 4-inner side fetal membrane retaining wall; 5-outer side fetal membrane retaining wall; 6-plain concrete; 7-an annular groove; 8-tie bars; 9-pulling the shackle; 10-i-beam; 11-supporting the side wall of the foundation pit; 12-a structural backing plate; 17-a template; 14-a cushion layer; 15-outer wall; 16-a cross keel; 17-main keel; 18-tendon-planting holes; 19-planting bar glue; 20-connecting ribs.
Detailed Description
The following detailed description of embodiments of the invention refers to the accompanying drawings. It should be understood that the detailed description and specific examples, while indicating the present invention, are given by way of illustration and explanation only, not limitation.
Referring to fig. 1 to 2, an installation process of a construction method for an integrated structure of an outer wall of a deep foundation pit includes the steps of:
(1) pouring a cushion layer 14 on the ground of the foundation pit, reserving an annular groove 7 on the cushion layer 14 along a foundation pit supporting side wall 11, enabling the annular groove 7 to surround the foundation pit supporting side wall 11 for one circle and be parallel to the foundation pit supporting side wall 11, uniformly arranging reinforcing bar holes 18 on the surface of the foundation pit supporting side wall 11 at intervals of 0.5-0.8 m along the length direction and the height direction, inserting tie bars 8 into the reinforcing bar holes 18, pouring reinforcing bar glue 19, building an outer side membrane retaining wall 5 by taking one side, adjacent to the foundation pit supporting side wall 11, in the annular groove 7 as a boundary, placing a layer of I-shaped steel 10 on a wall edge (namely the upper side of the wall) at each building height of the outer side membrane retaining wall 5, enabling the wall edge to be embedded into a notch of the I-shaped steel (namely a groove between flanges at two sides of the I-shaped steel), horizontally pushing each I-shaped steel 10 away from the foundation pit supporting side wall 11, enabling the I-shaped steels 10 to be connected into a circle along the wall supporting edge of the outer side membrane retaining wall 5 to form a ring beam 3, a groove is formed between the flange of each layer of I-steel 10 far away from the foundation pit supporting side wall 11 and one surface of the outer side fetal membrane retaining wall 5 facing the center of the foundation pit, so that the inner side fetal membrane retaining wall 4 can be laid in, the I-steel in each layer of ring beam 3 is equal in height, each layer of ring beam 3 is welded and connected with the tie bars 8 through the connecting bars 20, and one end of each tie bar 8 far away from the foundation pit supporting side wall 11 does not contact with the outer side fetal membrane retaining wall 5;
(2) building the outer side film retaining wall 5 above each layer of ring beam 3 continuously according to the method in the step 1 until the elevation is reached, laying waterproof coiled materials along the cushion layer 14, the annular groove 7, the outer side film retaining wall 5 and one side of the ring beam 3 facing the inside of the foundation pit, and mutually staggering each adjacent waterproof coiled material;
(3) building an inner side tire membrane retaining wall 4 along the annular groove 7 and by attaching a waterproof coiled material adjacent to the surface of the outer side tire membrane retaining wall 5, immediately filling high-strength mortar in a gap of the annular groove 7, so that the annular groove 7, the outer side tire membrane retaining wall 5 and the inner side tire membrane retaining wall 4 are tightly fastened, meanwhile, building the inner side tire membrane retaining wall 4 upwards into the groove between the ring beam 3 and the outer side tire membrane retaining wall 5, and the width of the notch of the I-steel 10 is equal to the sum of the wall thicknesses of the outer side tire membrane retaining wall 5 and the inner side tire membrane retaining wall 4;
the outer side film retaining wall 5 is a prefabricated hollow concrete slab with the thickness of 8cm and the thickness of 0.6m by 3 m; the inboard fetal membrane barricade 4 is 10 ~ 12cm thick 0.6m 3m precast concrete board, and all fetal membrane barricades downside all reserve 1.5cm deeply, and 3 ~ 4 centimeters wide connection tongue-and-groove, all fetal membrane barricade upper flank all reserve 1.5cm deeply, and 3 ~ 4 centimeters wide connection protrusion strip.
(4) Then, a concrete layer of the outer side backfilling plain concrete 6 is poured between the foundation pit supporting side wall 11 and the outer side fetal membrane retaining wall 5, so that the backfilling plain concrete is tightly connected with the foundation pit supporting side wall, and the outer side fetal membrane retaining wall 5 is supported;
(5) pouring a structural bottom plate 12 on a waterproof coiled material on a cushion layer 14 on the inner periphery of an inner side membrane retaining wall 4, anchoring 1 pulling hook ring 9 at intervals of 0.5m along the height direction and the length direction at one side of the inner side membrane retaining wall 4, which is opposite to a foundation pit supporting side wall 11, so as to form an array, bouncing a boundary line of an outer wall 15 on the basement structural bottom plate 12, building a fence by using a template 17 along the boundary line, hooking one end of a counter-pulling screw rod 2 on the pulling hook ring 9 on the inner side membrane retaining wall 4 in the building process, screwing the other end of the counter-pulling screw rod 2 by using a butterfly buckle after penetrating through a through hole on the fence, adjusting the counter-pulling screw rod 2 at the same time, and finishing the reinforcement of the fence;
(6) and pouring an outer wall 15 between the enclosing wall and the inner side membrane retaining wall 4.
The steps can be changed into the following steps:
(1) pouring a cushion layer 14 on the ground of the foundation pit, reserving an annular groove 7 on the cushion layer 14 along a foundation pit supporting side wall 11, enabling the annular groove 7 to surround the foundation pit supporting side wall 11 for one circle and be parallel to the foundation pit supporting side wall 11, uniformly arranging reinforcing bar holes 18 on the surface of the foundation pit supporting side wall 11 at intervals of 0.5-0.8 m along the length direction and the height direction, inserting tie bars 8 into the reinforcing bar holes 18, pouring reinforcing bar glue 19, building an outer side tire membrane retaining wall 5 by taking one side, adjacent to the foundation pit supporting side wall 11, in the annular groove 7 as a boundary, placing a layer of I-shaped steel 10 on a wall edge (namely the upper side of the wall) by building the outer side tire membrane retaining wall 5 for 2m height, enabling the wall edge to be embedded into a notch of the I-shaped steel (namely a groove between flanges at two sides of the I-shaped steel), and horizontally pushing each I-shaped steel 10 away from the foundation pit supporting side wall 11 to enable the I-shaped steels 10 to be connected into a circle to form a ring beam 3 along the wall edge of the outer side tire retaining wall 5, a groove is formed between the flange of each layer of I-steel 10 far away from the foundation pit supporting side wall 11 and one surface of the outer side fetal membrane retaining wall 5 facing the center of the foundation pit, so that the inner side fetal membrane retaining wall 4 can be laid in, the I-steel in each layer of ring beam 3 is equal in height, each layer of ring beam 3 is welded and connected with the tie bars 8 through the connecting bars 20, and one end of each tie bar 8 far away from the foundation pit supporting side wall 11 does not contact with the outer side fetal membrane retaining wall 5;
(2) waterproof coiled materials are laid along the cushion layer 14, the annular groove 7, the outer side membrane retaining wall 5 and one side of the ring beam 3 facing the inside of the foundation pit, and every two adjacent waterproof coiled materials are staggered;
(3) building an inner side tire membrane retaining wall 4 along the annular groove 7 and by attaching a waterproof coiled material adjacent to the surface of the outer side tire membrane retaining wall 5, immediately filling high-strength mortar in a gap of the annular groove 7, so that the annular groove 7, the outer side tire membrane retaining wall 5 and the inner side tire membrane retaining wall 4 are tightly fastened, meanwhile, building the inner side tire membrane retaining wall 4 upwards into the groove between the ring beam 3 and the outer side tire membrane retaining wall 5, and the width of the notch of the I-steel 10 is equal to the sum of the wall thicknesses of the outer side tire membrane retaining wall 5 and the inner side tire membrane retaining wall 4;
the outer side film retaining wall 5 is a prefabricated hollow concrete slab with the thickness of 8cm and the thickness of 0.6m by 3 m; the inner side fetal membrane retaining wall 4 is a precast concrete slab with the thickness of 10-12 cm and the thickness of 0.6m by 3m, the lower side surfaces of all the precast hollow concrete slabs are reserved with 1.5cm depth, the connecting mortises with the width of 3-4 cm are reserved with 1.5cm depth and the connecting protruding strips with the width of 3-4 cm are reserved on the upper side surfaces of all the precast hollow concrete slabs.
(4) Then, a concrete layer of the outer side backfilling plain concrete 6 is poured between the foundation pit supporting side wall 11 and the outer side fetal membrane retaining wall 5, so that the backfilling plain concrete is tightly connected with the foundation pit supporting side wall, and the outer side fetal membrane retaining wall 5 is supported;
(5) building an outer side tire membrane retaining wall 5 and an inner side tire membrane retaining wall 4 above each layer of ring beam 3 according to the methods in the steps (1) to (4), laying waterproof coiled materials, filling high-strength mortar, and backfilling plain concrete 6 until the elevation is reached;
(6) pouring a structural bottom plate 12 on a waterproof coiled material on a cushion layer 14 on the inner periphery of an inner side membrane retaining wall 4, anchoring 1 pulling hook ring 9 at intervals of 0.5m along the height direction and the length direction at one side of the inner side membrane retaining wall 4, which is opposite to a foundation pit supporting side wall 11, so as to form an array, bouncing a boundary line of an outer wall 15 on the basement structural bottom plate 12, building a fence by using a template 17 along the boundary line, hooking one end of a counter-pulling screw rod 2 on the pulling hook ring 9 on the inner side membrane retaining wall 4 in the building process, screwing the other end of the counter-pulling screw rod 2 by using a butterfly buckle after penetrating through a through hole on the fence, adjusting the counter-pulling screw rod 2 at the same time, and finishing the reinforcement of the fence;
(7) and pouring an outer wall 15 between the enclosing wall and the inner side membrane retaining wall 4.
The utility model provides a construction method that is used for deep basal pit outer wall integral type and construction method thereof, creatively adopts a nimble I-steel connected node structure and basement outer wall integrated structure's construction method, not only can strengthen the stability at basement fetal membrane barricade, but also can accomplish all outer wall processes construction such as outer wall waterproofing, protective layer, backfill layer before basement outer wall concrete placement, later stage only need demolish outer wall inboard reinforcement support can, the construction is quick high-efficient, construction cost is cheap. The construction scheme can greatly save cost and resources, and increase the speed and efficiency particularly in the construction process of the outer wall of the deep foundation pit, thereby greatly accelerating the whole process of the basement outer wall construction.
The above-described embodiments of the present invention for the integrated structure of the external wall of the deep foundation pit and the construction method thereof do not limit the scope of the present invention, and any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the scope of the claims of the present invention.

Claims (2)

1. A construction method for an integrated structure of an external wall of a foundation-pillar-free deep foundation pit is characterized by comprising the following steps:
step 1, pouring a cushion layer (14) on the ground of a foundation pit, reserving an annular groove (7) on the cushion layer (14) along a foundation pit supporting side wall (11), enabling the annular groove (7) to surround the foundation pit supporting side wall (11) for a circle and be parallel to the foundation pit supporting side wall (11), uniformly arranging reinforcement embedding holes (18) on the surface of the foundation pit supporting side wall (11), inserting tie bars (8) into the reinforcement embedding holes (18), then pouring reinforcement embedding glue (19), building an outer side membrane retaining wall (5) by taking one side, adjacent to the foundation pit supporting side wall (11), in the annular groove (7) as a boundary, placing a layer of I-shaped steel (10) on the wall edge at each building height of the outer side membrane retaining wall (5), enabling the wall edge to be embedded into a notch of the I-shaped steel (10), horizontally pushing each I-shaped steel (10) in the direction far away from the foundation pit supporting side wall (11), and enabling the I-shaped steel (10) to be connected into a circle along the wall edge of the outer side membrane retaining wall (5) to form a ring beam (3), a flange of each layer of I-shaped steel (10) far away from the foundation pit supporting side wall (11) and one surface of the outer side fetal membrane retaining wall (5) facing the center of the foundation pit form a groove, the I-shaped steel in each layer of ring beam (3) is equal in height, each layer of ring beam (3) is welded and connected with a tie bar (8) through a connecting bar (20), and one end of each tie bar (8) far away from the foundation pit supporting side wall (11) does not touch the outer side fetal membrane retaining wall (5);
step 2, continuously building the outer side film retaining wall (5) above each layer of ring beam (3) according to the method in the step 1 until the elevation is reached, paving waterproof coiled materials on one side, facing the foundation pit, of the cushion layer (14), the annular groove (7), the outer side film retaining wall (5) and the ring beam (3), and enabling every two adjacent waterproof coiled materials to be staggered;
step 3, building an inner side tire membrane retaining wall (4) along the annular groove (7) and adjacent to the outer side tire membrane retaining wall (5), immediately filling high-strength mortar in a gap of the annular groove (7), so that the annular groove (7), the outer side tire membrane retaining wall (5) and the inner side tire membrane retaining wall (4) are tightly fastened, meanwhile, the inner side tire membrane retaining wall (4) is built into the groove between the ring beam (3) and the outer side tire membrane retaining wall (5), and the width of a notch of the I-shaped steel (10) is equal to the sum of the wall thicknesses of the outer side tire membrane retaining wall (5) and the inner side tire membrane retaining wall (4);
step 4, a concrete layer of the outer side backfill plain concrete (6) is poured between the foundation pit supporting side wall (11) and the outer side membrane retaining wall (5) so that the backfill plain concrete is tightly connected with the foundation pit supporting side wall;
step 5, pouring a structural bottom plate (12) on a waterproof coiled material on a cushion layer (14) on the inner periphery of the inner side membrane retaining wall (4), uniformly anchoring a plurality of pulling hook rings (9) into one side, back to a foundation pit supporting side wall (11), of the inner side membrane retaining wall (4) to form an array, bouncing a boundary line of an outer wall (15) on the basement structural bottom plate (12), building a fence by using a template (17) along the boundary line, hooking one end of a counter-pulling screw rod (2) on the pulling hook ring (9) on the inner side membrane retaining wall (4) in the building process, screwing the other end of the counter-pulling screw rod (2) by using a butterfly buckle after penetrating through a through hole on the fence, adjusting the counter-pulling screw rod (2) at the same time, and reinforcing the completed fence;
and 6, pouring an outer wall (15) between the enclosing wall and the inner side membrane retaining wall (4).
2. The construction method of the foundation-pillar-free deep foundation pit and outer wall integrated structure according to claim 1, wherein the step (2) is replaced by laying waterproof coiled materials along the cushion layer (14), the annular groove (7), the outer side membrane retaining wall (5) and one side of the ring beam (3) facing the inside of the foundation pit, and every two adjacent waterproof coiled materials are staggered with each other;
a step is added between the step (4) and the step (5): and (3) continuously building an outer side tire membrane retaining wall (5) and an inner side tire membrane retaining wall (4) above each layer of ring beam (3) according to the methods in the steps (1) to (4), paving waterproof coiled materials, filling high-strength mortar, and backfilling plain concrete (6) until the elevation is reached.
CN202111225770.2A 2021-10-21 2021-10-21 Construction method for foundation-column-free type deep foundation pit and outer wall integrated structure Active CN113944262B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111225770.2A CN113944262B (en) 2021-10-21 2021-10-21 Construction method for foundation-column-free type deep foundation pit and outer wall integrated structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111225770.2A CN113944262B (en) 2021-10-21 2021-10-21 Construction method for foundation-column-free type deep foundation pit and outer wall integrated structure

Publications (2)

Publication Number Publication Date
CN113944262A true CN113944262A (en) 2022-01-18
CN113944262B CN113944262B (en) 2023-04-14

Family

ID=79331982

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111225770.2A Active CN113944262B (en) 2021-10-21 2021-10-21 Construction method for foundation-column-free type deep foundation pit and outer wall integrated structure

Country Status (1)

Country Link
CN (1) CN113944262B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1591595A2 (en) * 2004-04-26 2005-11-02 Glatthaar Fertigkeller GmbH Watertight cellar
US20080104909A1 (en) * 2003-04-17 2008-05-08 Wallin Arne B Modoular Wall System with Footing Form
CN105604099A (en) * 2016-03-11 2016-05-25 中建三局集团有限公司 Waterproof coiled-material base layer
CN107119695A (en) * 2017-06-27 2017-09-01 中国建筑第二工程局有限公司 A kind of operation support body and construction method for cancelling outer wall of basement backfill
CN107435335A (en) * 2017-09-15 2017-12-05 上海建工建集团有限公司 Brick retaining wall steel bar girder hardened system and method on foundation pit enclosure top beam
CN206722391U (en) * 2017-05-22 2017-12-08 中冶建工集团有限公司 Basement barricade moulding wall formwork erecting structure based on brick fetal membrane
CN206752667U (en) * 2017-05-22 2017-12-15 中冶建工集团有限公司 A kind of basement barrier wall structure
CN109024700A (en) * 2017-02-27 2018-12-18 中冶建工集团有限公司 A kind of water-proof concrete configuration device and its building basement external wall waterproof construction method
CN212249179U (en) * 2020-03-16 2020-12-29 中国建筑第四工程局有限公司 Basement outer wall single face formwork support system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080104909A1 (en) * 2003-04-17 2008-05-08 Wallin Arne B Modoular Wall System with Footing Form
EP1591595A2 (en) * 2004-04-26 2005-11-02 Glatthaar Fertigkeller GmbH Watertight cellar
CN105604099A (en) * 2016-03-11 2016-05-25 中建三局集团有限公司 Waterproof coiled-material base layer
CN109024700A (en) * 2017-02-27 2018-12-18 中冶建工集团有限公司 A kind of water-proof concrete configuration device and its building basement external wall waterproof construction method
CN206722391U (en) * 2017-05-22 2017-12-08 中冶建工集团有限公司 Basement barricade moulding wall formwork erecting structure based on brick fetal membrane
CN206752667U (en) * 2017-05-22 2017-12-15 中冶建工集团有限公司 A kind of basement barrier wall structure
CN107119695A (en) * 2017-06-27 2017-09-01 中国建筑第二工程局有限公司 A kind of operation support body and construction method for cancelling outer wall of basement backfill
CN107435335A (en) * 2017-09-15 2017-12-05 上海建工建集团有限公司 Brick retaining wall steel bar girder hardened system and method on foundation pit enclosure top beam
CN212249179U (en) * 2020-03-16 2020-12-29 中国建筑第四工程局有限公司 Basement outer wall single face formwork support system

Also Published As

Publication number Publication date
CN113944262B (en) 2023-04-14

Similar Documents

Publication Publication Date Title
CN107447613B (en) Deep and ultra-soft soil embankment and construction method
CN112554198B (en) Construction method of deep foundation pit protection structure adjacent to high-rise building
CN111236260A (en) Variable-rigidity combined type prefabricated double-row pile supporting structure and construction method thereof
CN110820762A (en) Construction method of stiff-core curtain pile and retaining wall pile anchor combined supporting structure
CN111236258A (en) Prefabricated pile wall supporting structure with stiffening rib wall and unloading platform and construction method thereof
CN110777806B (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
CN108385693B (en) Equal-generation anchor bolt supporting method and system for staged basement supporting
CN210263073U (en) Supporting construction that adjacent foundation ditch synchronous excavation was asynchronously backfilled
CN111236259A (en) Combined lattice-shaped prefabricated pile wall supporting structure and construction method thereof
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
CN113944262B (en) Construction method for foundation-column-free type deep foundation pit and outer wall integrated structure
CN113802721B (en) Deep foundation pit and outer wall integrated structure and construction method
CN115198806A (en) Underground wall post-cast strip template reinforcing and installing construction method
CN215211151U (en) Overhead supporting structure based on soil retaining structure
CN213448506U (en) Plugging structure arranged between foundation pit fender posts
CN211395698U (en) Stiff core curtain pile and dado stake anchor combined supporting construction
CN216616424U (en) Foundation-column-free deep foundation pit and outer wall integrated structure
CN210104806U (en) Basement outer wall post-cast strip closed in advance
CN208328940U (en) A kind of support system
CN111042214A (en) Anti-floating structure of shallow-soil-covered underground structure and construction method thereof
CN112609706B (en) Construction method of opposite-bracing angle brace concrete horizontal supporting structure of foundation pit in sea reclamation area
CN211498975U (en) Anti structure of floating of shallow earthing underground structure
CN218990240U (en) Side mold system at deep pit of foundation slab
CN216839459U (en) Vertical variable cross-section structure adjacent to deep and shallow foundation pit in foundation pit
CN220847623U (en) Integrated foundation pit supporting structure for building engineering construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant