CN113936442B - Progress monitoring and early warning system for slope engineering - Google Patents

Progress monitoring and early warning system for slope engineering Download PDF

Info

Publication number
CN113936442B
CN113936442B CN202111366668.4A CN202111366668A CN113936442B CN 113936442 B CN113936442 B CN 113936442B CN 202111366668 A CN202111366668 A CN 202111366668A CN 113936442 B CN113936442 B CN 113936442B
Authority
CN
China
Prior art keywords
elevation
early warning
layer support
support
slope engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111366668.4A
Other languages
Chinese (zh)
Other versions
CN113936442A (en
Inventor
刘小强
张敬
张冲
潘燕芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN202111366668.4A priority Critical patent/CN113936442B/en
Publication of CN113936442A publication Critical patent/CN113936442A/en
Application granted granted Critical
Publication of CN113936442B publication Critical patent/CN113936442B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/18Status alarms
    • G08B21/182Level alarms, e.g. alarms responsive to variables exceeding a threshold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a progress monitoring and early warning system of slope engineering, which relates to the technical field of slope engineering, and is characterized in that the slope engineering is divided into multiple stages according to the elevation, the lowest elevation, the highest elevation difference of shallow layer support and the highest elevation difference of deep layer support of the working procedures completed in each stage are calculated through an operation module, the coordination of excavation and support is embodied through the highest elevation difference of shallow layer support and the highest elevation difference of deep layer support, and an early warning is sent out when the highest elevation difference of shallow layer support exceeds a first threshold value through an early warning module, and an early warning is sent out when the highest elevation difference of deep layer support exceeds a second threshold value, so that a slope engineering manager can judge whether the excavation and support are inconsistent according to the early warning, and the problem that the excavation and support coordination in the slope engineering construction process is difficult to be counted by a slope engineering manager is solved.

Description

Progress monitoring and early warning system for slope engineering
Technical Field
The invention relates to the technical field of slope engineering, in particular to a progress monitoring and early warning system for slope engineering.
Background
In the construction process of the high side slope engineering of the hydropower engineering from high to low, the working procedures are more, the working procedures comprise excavation, shallow layer support and deep layer support, the working procedures of the shallow layer support comprise anchor rods, concrete spraying, net hanging, drainage holes and the like, the working procedures of the deep layer support comprise anchor cables, the working procedures of the anchor cables comprise drilling, rope penetrating, grouting, anchor pier pouring and tensioning, in the implementation process, specific requirements are provided for timeliness of the excavation, the shallow layer support and the deep layer support according to construction specifications and technical requirements, but support disjointing on progress frequently occurs, namely the support progress is delayed behind the excavation, and if the delay range is too large and the time is too long, side slope deformation and even collapse can occur.
In order to control the coordination of excavation and support, the construction progress of each working procedure of excavation, shallow support and deep support is counted and updated periodically and reflected in construction report at present, for example, pile number is adopted to describe the current situation of excavation and support of a side slope.
Disclosure of Invention
The technical problems solved by the invention are as follows: the progress monitoring and early warning system for the slope engineering solves the problem that a slope engineering manager is difficult to count the coordination of excavation and support in the slope engineering construction process.
The invention solves the technical problems by adopting the technical scheme that: the progress monitoring and early warning system for the slope engineering comprises a data input module, an operation module and a monitoring and early warning module;
the data input module is used for inputting each level of elevation of the side slope, the excavation time of each level of elevation, the excavation completion time of each level of elevation, the completion time of each procedure of shallow layer support in the excavated elevation and the completion time of each procedure of deep layer support in the excavated elevation;
the operation module is used for calculating the highest elevation, the shallow layer support maximum elevation difference and the deep layer support maximum elevation difference of unfinished working procedures in each elevation at a certain time point, wherein the shallow layer support maximum elevation difference is the difference between the highest elevation of the last working procedure of the unfinished shallow layer support at the time point and the lowest elevation of the excavated working procedure at the time point, and the deep layer support maximum elevation difference is the difference between the highest elevation of the last working procedure of the unfinished deep layer support at the time point and the lowest elevation of the excavated working procedure at the time point;
the monitoring and early warning module is used for comparing the magnitude relation between the maximum elevation difference of the shallow support and the first threshold value, and sending out early warning when the maximum elevation difference of the shallow support is larger than the first threshold value; and the method is also used for comparing the magnitude relation between the maximum elevation difference of the deep support and the second threshold value, and sending out early warning when the maximum elevation difference of the deep support is larger than the second threshold value.
Further, each working procedure of shallow layer support in the excavated elevation comprises an anchor rod, concrete spraying, net hanging and water draining holes.
Further, each working procedure of deep layer support in the excavated elevation comprises drilling, rope penetrating, grouting, anchor pier pouring and tensioning.
Furthermore, the data input module is further used for inputting the starting time of each working procedure of the shallow layer support in the excavated elevation and the starting time of each working procedure of the deep layer support in the excavated elevation, and the early warning module is further used for comparing the time consumption of the same working procedure with the set longest finishing time limit of the working procedure and sending early warning after the longest finishing time of the working procedure reaches a period of time before the longest finishing time of the working procedure reaches.
Furthermore, the operation module is also used for calculating the lowest elevation of the finished working procedures in each level elevation at a certain time point.
Furthermore, the monitoring and early warning module is also used for displaying a slope engineering progress chart, and the slope engineering progress chart displays each finished process and the excavated lowest elevation in each elevation in a unit of time.
The invention has the beneficial effects that: the progress monitoring and early warning system for the slope engineering divides the slope engineering into a plurality of stages according to the elevation, takes each stage of elevation as a basis, calculates the lowest elevation, the largest elevation difference of the shallow layer support and the largest elevation difference of the deep layer support of the finished working procedures in each stage of elevation through the operation module, reflects the coordination of excavation and support through the largest elevation difference of the shallow layer support and the largest elevation difference of the deep layer support, sends out early warning when the largest elevation difference of the shallow layer support exceeds a first threshold value through the early warning module, and sends out early warning when the largest elevation difference of the deep layer support exceeds a second threshold value, and a slope engineering manager can judge whether the slope engineering is uncoordinated with the support according to the early warning, so that the problem that the coordination of excavation and support in the construction process of the slope engineering is difficult to be counted by a slope engineering manager is solved.
Drawings
FIG. 1 is a frame construction diagram of the progress monitoring and early warning system of the slope engineering of the invention.
Detailed Description
The progress monitoring and early warning system for slope engineering, as shown in figure 1, comprises a data input module, an operation module and a monitoring and early warning module;
the data input module is used for inputting each level of elevation of the side slope, the excavation time of each level of elevation, the excavation completion time of each level of elevation, the completion time of each procedure of shallow layer support in the excavated elevation and the completion time of each procedure of deep layer support in the excavated elevation;
specifically, the slope engineering is classified according to the elevations, for example, each interval is 30 meters as one level, and each level comprises excavation, shallow layer support and deep layer support; each working procedure of shallow layer support comprises anchor rods, concrete spraying, net hanging and drainage holes; the deep layer support comprises the working procedures of drilling, rope threading, grouting, anchor pier pouring and tensioning; the time is in days.
The operation module is used for calculating the highest elevation, the shallow layer support maximum elevation difference and the deep layer support maximum elevation difference of unfinished working procedures in each elevation at a certain time point, wherein the shallow layer support maximum elevation difference is the difference between the highest elevation of the last working procedure of the unfinished shallow layer support at the time point and the lowest elevation of the excavated working procedure at the time point, and the deep layer support maximum elevation difference is the difference between the highest elevation of the last working procedure of the unfinished deep layer support at the time point and the lowest elevation of the excavated working procedure at the time point;
specifically, calculating the highest elevation, the largest shallow layer support elevation difference and the largest deep layer support elevation difference of unfinished procedures in each elevation from a data input module, and obtaining coordination of excavation and support by an engineering manager through the largest shallow layer support elevation difference and the largest deep layer support elevation difference; in addition, the operation module is also used for calculating the lowest elevation of the completed working procedures in each level elevation at a certain time point, so that engineering managers can obtain working procedures with the fastest construction progress aiming at different working procedures.
The monitoring and early warning module is used for comparing the magnitude relation between the maximum elevation difference of the shallow support and the first threshold value, and sending out early warning when the maximum elevation difference of the shallow support is larger than the first threshold value; and the method is also used for comparing the magnitude relation between the maximum elevation difference of the deep support and the second threshold value, and sending out early warning when the maximum elevation difference of the deep support is larger than the second threshold value.
Specifically, the engineering manager judges whether the side slope engineering has uncoordinated excavation and support through early warning.
On the basis of the invention, the data input module is also used for inputting the starting time of each working procedure of shallow layer support in the excavated elevation and the starting time of each working procedure of deep layer support in the excavated elevation, the early warning module is also used for comparing the time consumption of the same working procedure with the set longest finishing time limit of the working procedure, and sending out early warning after the longest finishing time of the working procedure reaches a period of time, and an engineering manager can intuitively obtain a lagged support working procedure through the early warning, so that the engineering manager can further manage the lagged support working procedure conveniently.
In addition, the monitoring and early warning module is also used for displaying a slope engineering progress chart, the slope engineering progress chart displays all the finished procedures and the minimum excavated elevation in each level of elevation in a unit of time, and an engineering manager can acquire all the finished procedures and the minimum excavated elevation in each level of elevation on the adjusted time point from the slope engineering progress chart through adjusting the time, so that the engineering manager can conveniently control the slope engineering progress.

Claims (6)

1. The progress monitoring and early warning system for the slope engineering is characterized by comprising a data input module, an operation module and a monitoring and early warning module;
the data input module is used for inputting each level of elevation of the side slope, the excavation time of each level of elevation, the excavation completion time of each level of elevation, the completion time of each procedure of shallow layer support in the excavated elevation and the completion time of each procedure of deep layer support in the excavated elevation;
the operation module is used for calculating the highest elevation, the shallow layer support maximum elevation difference and the deep layer support maximum elevation difference of unfinished working procedures in each elevation at a certain time point, wherein the shallow layer support maximum elevation difference is the difference between the highest elevation of the last working procedure of the unfinished shallow layer support at the time point and the lowest elevation of the excavated working procedure at the time point, and the deep layer support maximum elevation difference is the difference between the highest elevation of the last working procedure of the unfinished deep layer support at the time point and the lowest elevation of the excavated working procedure at the time point;
the monitoring and early warning module is used for comparing the magnitude relation between the maximum elevation difference of the shallow support and the first threshold value, and sending out early warning when the maximum elevation difference of the shallow support is larger than the first threshold value; and the method is also used for comparing the magnitude relation between the maximum elevation difference of the deep support and the second threshold value, and sending out early warning when the maximum elevation difference of the deep support is larger than the second threshold value.
2. The progress monitoring and early warning system of slope engineering according to claim 1, wherein each procedure of shallow layer support in the excavated elevation comprises anchor rods, concrete spraying, net hanging and drainage holes.
3. The progress monitoring and early warning system of slope engineering according to claim 1, wherein each process of deep layer support in the excavated elevation comprises drilling, rope threading, grouting, anchor pier casting and tensioning.
4. A progress monitoring and early warning system for slope engineering according to any one of claims 1 to 3, wherein the data input module is further configured to input a start time of each process of shallow layer support in an excavated elevation and a start time of each process of deep layer support in an excavated elevation, and the early warning module is further configured to compare a time of the same process with a set maximum completion time limit of the process, and send an early warning for a period of time before the maximum completion time of the process is reached.
5. The progress monitoring and early warning system of slope engineering according to any one of claims 1 to 3, wherein the operation module is further configured to calculate a lowest elevation of a completed process in each elevation at a certain point in time.
6. A slope engineering progress monitoring and early warning system according to any one of claims 1 to 3, wherein the monitoring and early warning module is further configured to display a slope engineering progress chart, and the slope engineering progress chart displays each completed process and the excavated lowest elevation in each level in units of time.
CN202111366668.4A 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering Active CN113936442B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111366668.4A CN113936442B (en) 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111366668.4A CN113936442B (en) 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering

Publications (2)

Publication Number Publication Date
CN113936442A CN113936442A (en) 2022-01-14
CN113936442B true CN113936442B (en) 2023-05-16

Family

ID=79286990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111366668.4A Active CN113936442B (en) 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering

Country Status (1)

Country Link
CN (1) CN113936442B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321258A (en) * 1992-05-19 1993-12-07 Tokyu Constr Co Ltd Method for timbering of underground continuous wall
CN102797503A (en) * 2012-08-31 2012-11-28 中铁二十一局集团有限公司 Remote three-dimensional digital alarm method and system of deformation stability of primary tunnel supporting body
CN104454010A (en) * 2014-12-10 2015-03-25 西安科技大学 Integrated monitoring and early warning system and early warning method for dynamic condition of deep well drivage construction
CN107575234A (en) * 2017-09-07 2018-01-12 长沙有色冶金设计研究院有限公司 A kind of deep-well support design method
CN110439617A (en) * 2019-08-09 2019-11-12 精英数智科技股份有限公司 The supporting of fully-mechanized mining working advance support is apart from monitoring and pre-alarming method, apparatus and system
CN112854235A (en) * 2020-12-31 2021-05-28 中铁建设集团基础设施建设有限公司 Deep foundation pit supporting structure and stability monitoring and early warning system thereof
CN113267157A (en) * 2021-05-18 2021-08-17 中铁北京工程局集团有限公司 Tunnel preliminary bracing large deformation monitoring system

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100257794A1 (en) * 2009-04-10 2010-10-14 Stark N Daniel W Lateral support device
CN103850257B (en) * 2014-03-21 2015-12-30 中国电建集团成都勘测设计研究院有限公司 For excavation slope body structure and the excavation construction method thereof of rock side slope
DE102017204858A1 (en) * 2017-03-22 2018-09-27 Kennametal Inc. Cutting tool, in particular boring bar, and method for machining a number of holes
CN107761742A (en) * 2017-10-23 2018-03-06 上海市城市建设设计研究总院(集团)有限公司 Along depth direction is multi-form, variable cross-section supporting construction and its construction method
CN109440787A (en) * 2018-11-12 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The structure and method of engineering slope and underground chamber excavation and support simultaneously in a kind of Toppling Deformation rock mass
CN112878333A (en) * 2021-01-04 2021-06-01 中冶南方武汉建筑设计有限公司 Intelligent support system and method integrating monitoring and early warning
CN112990866A (en) * 2021-03-10 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Method for controlling construction progress of slope engineering of water conservancy and hydropower engineering

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321258A (en) * 1992-05-19 1993-12-07 Tokyu Constr Co Ltd Method for timbering of underground continuous wall
CN102797503A (en) * 2012-08-31 2012-11-28 中铁二十一局集团有限公司 Remote three-dimensional digital alarm method and system of deformation stability of primary tunnel supporting body
CN104454010A (en) * 2014-12-10 2015-03-25 西安科技大学 Integrated monitoring and early warning system and early warning method for dynamic condition of deep well drivage construction
CN107575234A (en) * 2017-09-07 2018-01-12 长沙有色冶金设计研究院有限公司 A kind of deep-well support design method
CN110439617A (en) * 2019-08-09 2019-11-12 精英数智科技股份有限公司 The supporting of fully-mechanized mining working advance support is apart from monitoring and pre-alarming method, apparatus and system
CN112854235A (en) * 2020-12-31 2021-05-28 中铁建设集团基础设施建设有限公司 Deep foundation pit supporting structure and stability monitoring and early warning system thereof
CN113267157A (en) * 2021-05-18 2021-08-17 中铁北京工程局集团有限公司 Tunnel preliminary bracing large deformation monitoring system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
破碎围岩条件下高边坡开挖施工技术;易 丹;《四川水利发电》;第40卷(第3期);全文 *

Also Published As

Publication number Publication date
CN113936442A (en) 2022-01-14

Similar Documents

Publication Publication Date Title
Zhong et al. Real-time compaction quality monitoring of high core rockfill dam
CN103352455B (en) Monitoring method of bottom soil heave of excavation foundation pit
CN105043445B (en) A kind of strong rammer quality remote monitoring system and its method of work
CN104008272A (en) Concrete vibration visual monitoring method based on computer graphic technology
CN109583852B (en) Material and progress informatization management system for bridge cantilever pouring construction
CN105003828A (en) Online drainage monitoring and early warning method and system based on mobile platform
CN104568410A (en) Continuous-casting secondary cooling nozzle working state online judgment method
CN113936442B (en) Progress monitoring and early warning system for slope engineering
CN105178280B (en) A kind of dynamic compaction machinery parameter of synthetic job acquisition system and its method of work
CN111767003A (en) Mining equipment sensor data self-adaptive acquisition method based on different working conditions
CN114370071A (en) Device, system and method for monitoring controllable grouting reinforcement of existing building in real time
CN203716164U (en) Automatic numerical control foundation pit dewatering system
CN103850257B (en) For excavation slope body structure and the excavation construction method thereof of rock side slope
CN113419461A (en) Construction site machinery supervision method and system
CN207567834U (en) The superfilled automatic alarm set of concrete pipe base
CN101545267A (en) Method for closed construction of large-area factory building equipment foundations
CN108803512B (en) Monitoring method for grouting of distorted concrete jack of roller compacted concrete dam
CN112926027B (en) Foundation pit risk monitoring system based on machine learning
CN108510202A (en) The monitoring information management method and managing device of building are worn under hydraulic tunnel
CN107642121B (en) Energy-saving prompt control method and system for excavator
CN114086926A (en) Control method and device of oil field mechanical recovery system and oil field mechanical recovery system
CN110096757B (en) Method for dynamically controlling anti-floating of basement construction process based on BIM technology
CN114928555B (en) Fully-mechanized coal mining face display method, device and medium
CN110532703A (en) A kind of sea bed security management method and system for sea area section seabed tunnel
CN113885592B (en) Intelligent operation and maintenance method, system and device for sewage deep tunneling and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant