CN101545267A - Method for closed construction of large-area factory building equipment foundations - Google Patents
Method for closed construction of large-area factory building equipment foundations Download PDFInfo
- Publication number
- CN101545267A CN101545267A CN200810035279A CN200810035279A CN101545267A CN 101545267 A CN101545267 A CN 101545267A CN 200810035279 A CN200810035279 A CN 200810035279A CN 200810035279 A CN200810035279 A CN 200810035279A CN 101545267 A CN101545267 A CN 101545267A
- Authority
- CN
- China
- Prior art keywords
- construction
- equipment foundations
- factory building
- foundations
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention relates to construction of factory building equipment foundations, in particular to a method for the construction of large-area factory building equipment foundations. The method for closed construction of large-area factory building equipment foundations comprises the following: a step of supporting column foundations or existing structures; a step of mounting steel structures; a step of mounting and precontrolling rails; a step of precipitation for blocks of the equipment foundations; a step of excavating earthwork for the equipment foundations by a closed bunker-jump method; a step of structural closed construction for the equipment foundations by a bunker-jump method; a step of precontrolling and adjusting the thin part of a steel structure; and a step of mounting equipment and protecting finished products. The method for closed construction greatly saves the construction investment, facilitates the construction, and well ensures the safety and the normal production of the existing structures and the equipment.
Description
Technical field
The present invention relates to the factory building equipment foundations construction, relate in particular to a kind of large-area factory building equipment foundations job practices.
Background technology
Along with making full use of of economic development and land resources, the industrial construction of many production lines is more and more, usually there are civil engineering and steel work interchange operation, in order to save cost, accelerating construction progress, the control operation dangerous matter sources, reduce the graded crossing construction, the situation that need carry out foundation construction in newly-built or existing multispan factory building has appearred at work progress, promptly so-called " remaining silent " construction, the large-area Equipment Foundations of soft foundation construction of remaining silent is the difficult point that engineers and technicians capture always, handles and constantly usually to cause the irregular displacement of patten, the distortion of factory building crane girder, driving and equipment can't normal mounting and runnings.
Usually adopt the mode of steel sheet pile supporting for small-sized foundation ditch, the Chinese patent ZL03116821.3 ordinary concrete piecemeal that adopts the applicant to have simultaneously is provided by the method for building method for controlling crack and provide in the storehouse can finish the Equipment Foundations construction smoothly.But for the large-area factory building equipment foundations construction of remaining silent, there is not the technical experience of system to use for reference at present, have no alternative but to adopt opening construction, that is: carrying out plant and equipment again after the Equipment Foundations construction installs, construction period prolongs greatly like this, need to drop into a large amount of main equipments simultaneously and install, engineering cost is big, the work high above the ground risk is many.
Summary of the invention
The present invention is intended to solve the problems referred to above in the large-area factory building equipment foundations construction, and a kind of method for closed construction of large-area factory building equipment foundations is provided.Method of remaining silent construction of the present invention is saved construction investment, convenient construction greatly, has also well guaranteed the safety and the ordinary production of existing structure and equipment.
The present invention is achieved in that a kind of method for closed construction of large-area factory building equipment foundations, and its feature is that it comprises the following steps:
Patten or existing structure supporting step;
The Steel Structure Installation step;
Track is installed the pre-control step;
Equipment Foundations piecemeal step of precipitation;
Equipment Foundations are remained silent and are jumped storehouse method soil excavation step;
Equipment Foundations are jumped the storehouse method structure construction sequence of remaining silent;
The thin portion of steel work pre-control set-up procedure;
Equipment is installed and the finished product protection step.
Described a kind of method for closed construction of large-area factory building equipment foundations, described patten or existing structure supporting step comprise cement mixing pile block of wood supporting step, diaphragm wall and draw anchor supporting step or one or several step of steel sheet pile supporting step.
Described a kind of method for closed construction of large-area factory building equipment foundations, described Equipment Foundations are remained silent and jumped storehouse method soil excavation step and be: soil excavation unloading and symmetrical excavation and filling measure are taked in the earthwork of the factory building columns and the scope of remaining silent, one of soil excavation, one of structure construction, the mode that block-by-block advances..
Described a kind of method for closed construction of large-area factory building equipment foundations, described Equipment Foundations are jumped the storehouse method structure construction sequence of remaining silent: according to soil excavation sequential partition piecemeal dewatering construction, divide the block length should be at 30m~60m, with the structure construction continuous productive process.
Described a kind of method for closed construction of large-area factory building equipment foundations; described equipment is installed and the finished product protection step is: remain silent and constructed the Equipment Foundations base plate after 7 days; carry out suspension column once, back-grouting; it is back more than 3 days to be in the milk; adjust the track of crane girder, installation of driving a vehicle again and equipment are installed.
Described a kind of method for closed construction of large-area factory building equipment foundations, described method for closed construction also comprises: the set-up procedure of taking pre-control means in each steps such as described supporting, precipitation, the earthwork, structures according to monitored data, when observation point was provided with: building horizontal movement spacing 15m was provided with a bit, draw the anchor place to select to represent each mask of counting to be no less than 6 points, should monitor axial force of the supports and water level monitoring by standard when support or deep-well precipitation are arranged.
Described a kind of method for closed construction of large-area factory building equipment foundations, described building comprises vertical direction factory building crane girder or track.
The present invention has embodied the underground space and aboveground space integrated construction technology, has guaranteed the operating environment of newly-built or alteration work, for the transformation of old construction of structures provides technical guarantee.Method for closed construction of large-area factory building equipment foundations of the present invention meets domestic design commonly used at present, construction technology and execution conditions, not only saves construction investment, convenient construction greatly, has also well guaranteed the safety and the ordinary production of existing structure and equipment.For large-area factory building equipment foundations engineering or public welfare construction work, remaining silent construction provides method, the measure of practicable environmental protection and pre-control from theory into action, and economic benefit, social benefit are huge.
The specific embodiment
The present invention jumps under the polytechnic situations such as storehouse piece construction, information-based monitoring in protection, workshop steel structure installation pre-control, piecemeal well-points dewatering, cubic metre of earth piecemeal symmetry excavation, the Equipment Foundations structure of pre-control protection, existing device basis and the equipment of patten; successfully solved the weak soil large-area factory building equipment foundations remain silent construction difficult problem (as: certain engineering cold bed Equipment Foundations buried depth for-4.2m~-8.6m, part-10.0m.Foundation ditch is long to be 219.5m, and width the widest part is the construction of remaining silent of 145.8m; As certain old factory rehabilitation engineering 57m * 32.65m, the construction of remaining silent of the furnace apparatus basis of dark-9.5m).Comprise the following steps: that mainly patten or existing structure supporting (supporting of cement mixing pile block of wood, diaphragm wall and draw anchor) → Steel Structure Installation → track installs pre-control → Equipment Foundations piecemeal precipitation → Equipment Foundations and remain silent and jump storehouse method soil excavation → Equipment Foundations and jump the storehouse method structure symmetrical installation → finished product protection of the thin portion of construction → steel work pre-control adjustment → equipment of remaining silent.Particularly, necessary:
1, at first, according to cutting depth the supporting pre-control is carried out with excavation of foundation pit displacement trend direction in factory building insulated column basis:
1) for the pre-control means of cement mixing pile block of wood supporting, reinforcement depth is 3~5m under Equipment Foundations excavation face, and is wide than the wide 0.5~2m in insulated column basis, remains silent to construct for Equipment Foundations and creates good excavation condition.
2) RC Continuous wall and anchor pole have been adopted in factory building insulated column basis, and combined the construction of remaining silent of forming factory building equipment foundations under the composite support structure with the used equipment basis.
2, soil excavation unloading and symmetrical excavation and filling measure, one of soil excavation, one of structure construction, the mode that block-by-block advances are taked in the earthwork of the factory building columns and the scope of remaining silent.
3, according to soil excavation sequential partition piecemeal dewatering construction, the branch block length should be at 30m~60m, with the structure construction continuous productive process; Structure construction is taked the technology measure of " jumping the storehouse method ".
4, rationally determine steel work suspension column grouting time, construct behind the Equipment Foundations base plate remaining silent, carry out suspension column once, back-grouting, be in the milk reach design strength after, adjust track, the installation of driving a vehicle again and the equipment installation of crane girder.
5, strengthen information-aided construction, take the adjustment of pre-control means in each links such as supporting, precipitation, the earthwork, structures according to monitored data.
6, " large-area factory building equipment foundations remain silent construction technology " is the ground that is applied in the underground construction in the structure of ground of " tau-effect " principle, underground organic unity, this comprehensive technology is saved construction investment, convenient construction greatly, has economic benefit, social benefit widely.
Claims (7)
1. method for closed construction of large-area factory building equipment foundations, its feature is that it comprises the following steps:
Patten or existing structure supporting step;
The Steel Structure Installation step;
Track is installed the pre-control step;
Equipment Foundations piecemeal step of precipitation;
Equipment Foundations are remained silent and are jumped storehouse method soil excavation step;
Equipment Foundations are jumped the storehouse method structure construction sequence of remaining silent;
The thin portion of steel work pre-control set-up procedure;
Equipment is installed and the finished product protection step.
2. a kind of method for closed construction of large-area factory building equipment foundations according to claim 1, it is characterized in that described patten or existing structure supporting step comprise cement mixing pile block of wood supporting step, diaphragm wall and draw anchor supporting step or one or several step of steel sheet pile supporting step.
3. a kind of method for closed construction of large-area factory building equipment foundations according to claim 1, it is characterized in that, described Equipment Foundations are remained silent and jumped storehouse method soil excavation step and be: soil excavation unloading and symmetrical excavation and filling measure are taked in the earthwork of the factory building columns and the scope of remaining silent, one of soil excavation, one of structure construction, the mode that block-by-block advances.
4. a kind of method for closed construction of large-area factory building equipment foundations according to claim 1, it is characterized in that, described Equipment Foundations are jumped the storehouse method structure construction sequence of remaining silent: according to soil excavation sequential partition piecemeal dewatering construction, divide the block length should be at 30m~60m, with the structure construction continuous productive process.
5. a kind of method for closed construction of large-area factory building equipment foundations according to claim 1; it is characterized in that; described equipment is installed and the finished product protection step is: remain silent and constructed the Equipment Foundations base plate after 7 days; carry out suspension column once, back-grouting; it is back more than 3 days to be in the milk; adjust the track of crane girder, installation of driving a vehicle again and equipment are installed.
6. according to claim 1,2,3,4 or 5 described a kind of method for closed construction of large-area factory building equipment foundations, it is characterized in that, described method for closed construction also comprises: the set-up procedure of taking pre-control means in each steps such as described supporting, precipitation, the earthwork, structures according to monitored data, when observation point was provided with: building horizontal movement spacing 15m was provided with a bit, draw the anchor place to select to represent each mask of counting to be no less than 6 points, should monitor axial force of the supports and water level monitoring by standard when support or deep-well precipitation are arranged.
7. a kind of method for closed construction of large-area factory building equipment foundations according to claim 6 is characterized in that described building comprises vertical direction factory building crane girder or track.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100352791A CN101545267B (en) | 2008-03-27 | 2008-03-27 | Method for closed construction of large-area factory building equipment foundations |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100352791A CN101545267B (en) | 2008-03-27 | 2008-03-27 | Method for closed construction of large-area factory building equipment foundations |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101545267A true CN101545267A (en) | 2009-09-30 |
CN101545267B CN101545267B (en) | 2011-02-16 |
Family
ID=41192625
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008100352791A Active CN101545267B (en) | 2008-03-27 | 2008-03-27 | Method for closed construction of large-area factory building equipment foundations |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101545267B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102121253A (en) * | 2010-12-21 | 2011-07-13 | 上海市第一建筑有限公司 | Stepped backfill construction method for overlarge underground structure |
CN102535471A (en) * | 2012-01-10 | 2012-07-04 | 江苏建筑职业技术学院 | Secondary grouting method applied to space between bottom plate and foundation in installation work of mechanical equipment |
CN106499226A (en) * | 2016-11-14 | 2017-03-15 | 中国能源建设集团江苏省电力建设第三工程有限公司 | A kind of method of main building construction in layer |
CN111663779A (en) * | 2020-06-29 | 2020-09-15 | 中国二十冶集团有限公司 | Closed construction method for metallurgical industry factory building |
CN114635430A (en) * | 2022-03-28 | 2022-06-17 | 广州一建建设集团有限公司 | Construction process for large-depth semi-reverse excavation and steel pipe column inner support structure |
-
2008
- 2008-03-27 CN CN2008100352791A patent/CN101545267B/en active Active
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102121253A (en) * | 2010-12-21 | 2011-07-13 | 上海市第一建筑有限公司 | Stepped backfill construction method for overlarge underground structure |
CN102535471A (en) * | 2012-01-10 | 2012-07-04 | 江苏建筑职业技术学院 | Secondary grouting method applied to space between bottom plate and foundation in installation work of mechanical equipment |
CN102535471B (en) * | 2012-01-10 | 2014-09-17 | 江苏建筑职业技术学院 | Secondary grouting method applied to space between bottom plate and foundation in installation work of mechanical equipment |
CN106499226A (en) * | 2016-11-14 | 2017-03-15 | 中国能源建设集团江苏省电力建设第三工程有限公司 | A kind of method of main building construction in layer |
CN106499226B (en) * | 2016-11-14 | 2019-04-09 | 中国能源建设集团江苏省电力建设第三工程有限公司 | A kind of method of main building construction in layer |
CN111663779A (en) * | 2020-06-29 | 2020-09-15 | 中国二十冶集团有限公司 | Closed construction method for metallurgical industry factory building |
CN114635430A (en) * | 2022-03-28 | 2022-06-17 | 广州一建建设集团有限公司 | Construction process for large-depth semi-reverse excavation and steel pipe column inner support structure |
CN114635430B (en) * | 2022-03-28 | 2023-12-26 | 广州一建建设集团有限公司 | Construction process for large-depth half-reverse excavation |
Also Published As
Publication number | Publication date |
---|---|
CN101545267B (en) | 2011-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103556579B (en) | A kind of comprehensive grouting pressurize adds the box culvert pushing construction method of pipe curtain supporting | |
CN204000901U (en) | The vertical high slope prestressing anchor support of a kind of massif device | |
CN101748758B (en) | Timbering method of foundation ditches for reforming on-line equipment foundations in factory buildings | |
CN101725357B (en) | Construction method for lower section of underground tunnel | |
CN108487252A (en) | A kind of deep foundation pit open cutting is suitable to make construction method | |
CN204418187U (en) | Subway protection region soil nail wall is in conjunction with double-row pile deep foundation ditch composite supporting construction | |
CN101545267B (en) | Method for closed construction of large-area factory building equipment foundations | |
CN106522241A (en) | Deep foundation pit supporting method of ultrahigh floor height type basement structure | |
CN102031784A (en) | Slope protection pile pouring and cable bolting construction method for deep foundation pit | |
CN102562074A (en) | Construction method for composite stratum with hard top and soft bottom of large-section tunnel | |
CN103469798B (en) | A kind of foundation pit supporting construction and construction method thereof | |
CN105089670B (en) | Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel | |
CN103938634A (en) | Deep foundation pit supporting structure and construction method | |
CN103114595A (en) | Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch | |
CN204590048U (en) | A kind of high slope rockmass structure | |
CN111236241A (en) | Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method | |
CN102926408B (en) | A kind of base isolation structure and underpin processing method | |
CN105649091A (en) | High slope support method and structure | |
CN1279319A (en) | Full-reverse construction technology for basement | |
CN201991009U (en) | Deep foundation pit shoring system using poured slope-supporting piles and anchor ropes | |
CN204282399U (en) | A kind of subway space enclosing structure | |
CN103132465A (en) | Underground box culvert constructing method closely attached to pile foundation bearing platform | |
CN103850257A (en) | Digging slope body structure used for rock side slope and digging construction method of digging slope body structure | |
CN203821399U (en) | Deep foundation pit supporting structure | |
CN109930610A (en) | Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |