CN113936442A - Progress monitoring and early warning system for slope engineering - Google Patents

Progress monitoring and early warning system for slope engineering Download PDF

Info

Publication number
CN113936442A
CN113936442A CN202111366668.4A CN202111366668A CN113936442A CN 113936442 A CN113936442 A CN 113936442A CN 202111366668 A CN202111366668 A CN 202111366668A CN 113936442 A CN113936442 A CN 113936442A
Authority
CN
China
Prior art keywords
elevation
support
early warning
slope engineering
shallow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111366668.4A
Other languages
Chinese (zh)
Other versions
CN113936442B (en
Inventor
刘小强
张敬
张冲
潘燕芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN202111366668.4A priority Critical patent/CN113936442B/en
Publication of CN113936442A publication Critical patent/CN113936442A/en
Application granted granted Critical
Publication of CN113936442B publication Critical patent/CN113936442B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/18Status alarms
    • G08B21/182Level alarms, e.g. alarms responsive to variables exceeding a threshold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention relates to a progress monitoring and early warning system of slope engineering, which relates to the technical field of slope engineering, divides the slope engineering into a plurality of stages according to the elevation, calculates the lowest elevation of the finished processes in each stage of elevation, the maximum elevation difference of shallow support and the maximum elevation difference of deep support by an operation module on the basis of each stage of elevation, reflects the compatibility of excavation and support by the maximum elevation difference of shallow support and the maximum elevation difference of deep support, sends out early warning when the maximum elevation difference of shallow support exceeds a first threshold value and sends out early warning when the maximum elevation difference of deep support exceeds a second threshold value by the early warning module, and a slope engineering manager can judge whether the excavation and support are inconsistent according to the early warning, thereby solving the problem that the slope engineering manager is difficult to count the compatibility of excavation and support in the slope engineering construction process, the method is suitable for slope engineering management.

Description

Progress monitoring and early warning system for slope engineering
Technical Field
The invention relates to the technical field of slope engineering, in particular to a progress monitoring and early warning system for slope engineering.
Background
In the water and electricity engineering high slope engineering from high to low work progress, the process is more, including excavation, shallow layer support and deep support, the process of shallow layer support includes stock, shotcrete, string net and wash port etc. deep support is like the anchor rope, the process of anchor rope includes drilling, reeving, grout, waters anchor pier and stretch-draw, and in the implementation, according to construction specification and technical requirement to excavation, shallow layer support and the timeliness of deep support put forward concrete requirement, nevertheless often can appear strutting the disjointing on the progress, and the support progress lags behind the excavation promptly, if the lag range is too big, the time overlength, probably takes place the slope deformation, even takes place to collapse.
In order to control the coordination of excavation and support, the construction progress of each procedure of excavation, shallow layer support and deep layer support is mainly counted and updated every week and reflected in the construction period, if the current situation of excavation and support of a side slope is described by using a pile number, the construction period content of the side slope engineering is various, so that a side slope engineering manager is difficult to count the coordination of excavation and support in the construction process of the side slope engineering, and can not intuitively obtain a lagging support procedure, thereby having difficulty in the control of the construction progress of the side slope engineering.
Disclosure of Invention
The technical problems solved by the invention are as follows: the progress monitoring and early warning system for the slope engineering solves the problem that a slope engineering manager is difficult to count the coordination of excavation and support in the slope engineering construction process.
The invention adopts the technical scheme for solving the technical problems that: the progress monitoring and early warning system of the slope engineering comprises a data input module, an operation module and a monitoring and early warning module;
the data input module is used for inputting all levels of elevations of the side slope, the excavation time of each level of elevation, the excavation completion time of each level of elevation, the completion time of each procedure of shallow layer support in the excavated elevation and the completion time of each procedure of deep layer support in the excavated elevation;
the operation module is used for calculating the highest elevation of an unfinished process, the maximum elevation difference of a shallow support and the maximum elevation difference of a deep support in each level of elevation at a certain time point, the maximum elevation difference of the shallow support is the difference between the highest elevation of the last unfinished process of the shallow support at the time point and the lowest elevation excavated at the time point, and the maximum elevation difference of the deep support is the difference between the highest elevation of the last unfinished process of the deep support at the time point and the lowest elevation excavated at the time point;
the monitoring and early warning module is used for comparing the size relation between the maximum height difference of the shallow support and a first threshold value, and sending out early warning when the maximum height difference of the shallow support is larger than the first threshold value; and the device is also used for comparing the size relation between the maximum height difference of the deep support and a second threshold value, and giving out an early warning when the maximum height difference of the deep support is greater than the second threshold value.
Further, each process of the excavated shallow layer support in the elevation comprises anchor rods, concrete spraying, net hanging and drainage holes.
Furthermore, each process of the excavated deep-medium support of the elevation comprises drilling, rope penetrating, grouting, anchor pier pouring and tensioning.
Further, the data input module is further used for inputting the starting time of each process of the excavated middle-shallow layer support in the height and the starting time of each process of the excavated middle-deep layer support in the height, and the early warning module is further used for comparing the time spent in the same process with the set maximum finishing time limit of the process and sending out early warning when the maximum finishing time of the process reaches the previous period.
Furthermore, the operation module is further configured to calculate a lowest elevation of a completed procedure in each level of elevations at a certain time point.
Furthermore, the monitoring and early warning module is further used for displaying a slope engineering progress chart, and the slope engineering progress chart displays each finished procedure and the excavated lowest elevation in each level of elevation by taking the week as a time unit.
The invention has the beneficial effects that: the progress monitoring and early warning system for the slope engineering divides the slope engineering into multiple levels according to the elevation, calculates the lowest elevation of finished processes in each level of elevation, the maximum height difference of shallow support and the maximum height difference of deep support by using an operation module on the basis of each level of elevation, reflects the compatibility of excavation and support by using the maximum height difference of shallow support and the maximum height difference of deep support, sends out early warning when the maximum height difference of shallow support exceeds a first threshold value by using an early warning module, and sends out early warning when the maximum height difference of deep support exceeds a second threshold value, and a slope engineering manager can judge whether the slope engineering has the problem of incompatibility of excavation and support according to the early warning, thereby solving the problem that the slope engineering manager is difficult to count the compatibility of excavation and support in the slope engineering construction process.
Drawings
Fig. 1 is a frame structure diagram of the slope engineering progress monitoring and early warning system of the invention.
Detailed Description
The progress monitoring and early warning system of slope engineering, as shown in figure 1, comprises a data input module, an operation module and a monitoring and early warning module;
the data input module is used for inputting all levels of elevations of the side slope, the excavation time of each level of elevation, the excavation completion time of each level of elevation, the completion time of each procedure of shallow layer support in the excavated elevation and the completion time of each procedure of deep layer support in the excavated elevation;
specifically, the slope engineering is classified according to elevation, for example, one grade is provided at intervals of 30 meters, and each grade of elevation comprises excavation, shallow layer support and deep layer support; each procedure of shallow layer support comprises anchor rods, concrete spraying, net hanging and water drainage holes; each procedure of deep support comprises drilling, rope penetrating, grouting, anchor pier pouring and tensioning; the time is in units of days.
The operation module is used for calculating the highest elevation of an unfinished process, the maximum elevation difference of a shallow support and the maximum elevation difference of a deep support in each level of elevation at a certain time point, the maximum elevation difference of the shallow support is the difference between the highest elevation of the last unfinished process of the shallow support at the time point and the lowest elevation excavated at the time point, and the maximum elevation difference of the deep support is the difference between the highest elevation of the last unfinished process of the deep support at the time point and the lowest elevation excavated at the time point;
specifically, the highest elevation of unfinished procedures in each level of elevation, the maximum height difference of a shallow support and the maximum height difference of a deep support are calculated from the data input module, and an engineering manager obtains the compatibility of excavation and support through the maximum height difference of the shallow support and the maximum height difference of the deep support; in addition, the operation module is also used for calculating the lowest elevation of the finished processes in all levels of elevations at a certain time point, and a project manager can obtain the process with the fastest construction progress aiming at different processes.
The monitoring and early warning module is used for comparing the size relation between the maximum height difference of the shallow support and a first threshold value, and sending out early warning when the maximum height difference of the shallow support is larger than the first threshold value; and the device is also used for comparing the size relation between the maximum height difference of the deep support and a second threshold value, and giving out an early warning when the maximum height difference of the deep support is greater than the second threshold value.
Specifically, an engineering manager judges whether the excavation and the support of the slope engineering are inconsistent through early warning.
On the basis of the invention, the data input module is also used for inputting the starting time of each process of the excavated middle-shallow layer support in the height and the starting time of each process of the excavated middle-deep layer support in the height, the early warning module is also used for comparing the time consumption of the same process with the set maximum finishing time limit of the process, and sending out early warning when the maximum finishing time of the process reaches the previous period, so that an engineering manager can intuitively obtain a lagging support process through the early warning, and the engineering manager can conveniently and further manage the lagging support process.
In addition, the monitoring and early warning module is further used for displaying a slope engineering progress chart, the slope engineering progress chart displays each finished process and the excavated lowest elevation in each level of elevation by taking the week as a time unit, and an engineering manager can obtain each finished process and the excavated lowest elevation in each level of elevation at the adjusted time point from the slope engineering progress chart by adjusting the time, so that the engineering manager can conveniently control the progress of the slope engineering.

Claims (6)

1. The progress monitoring and early warning system for the slope engineering is characterized by comprising a data input module, an operation module and a monitoring and early warning module;
the data input module is used for inputting all levels of elevations of the side slope, the excavation time of each level of elevation, the excavation completion time of each level of elevation, the completion time of each procedure of shallow layer support in the excavated elevation and the completion time of each procedure of deep layer support in the excavated elevation;
the operation module is used for calculating the highest elevation of an unfinished process, the maximum elevation difference of a shallow support and the maximum elevation difference of a deep support in each level of elevation at a certain time point, the maximum elevation difference of the shallow support is the difference between the highest elevation of the last unfinished process of the shallow support at the time point and the lowest elevation excavated at the time point, and the maximum elevation difference of the deep support is the difference between the highest elevation of the last unfinished process of the deep support at the time point and the lowest elevation excavated at the time point;
the monitoring and early warning module is used for comparing the size relation between the maximum height difference of the shallow support and a first threshold value, and sending out early warning when the maximum height difference of the shallow support is larger than the first threshold value; and the device is also used for comparing the size relation between the maximum height difference of the deep support and a second threshold value, and giving out an early warning when the maximum height difference of the deep support is greater than the second threshold value.
2. The slope engineering progress monitoring and early warning system according to claim 1, wherein the excavated shallow support in the elevation comprises anchor rods, concrete spraying, net hanging and drainage holes.
3. The slope engineering progress monitoring and early warning system according to claim 1, wherein the excavated elevation middle and deep layer support comprises drilling, rope penetrating, grouting, anchor pier pouring and tensioning.
4. The slope engineering progress monitoring and early warning system according to any one of claims 1 to 3, wherein the data input module is further configured to input start times of steps of excavated middle and shallow layer support and steps of excavated middle and deep layer support, and the early warning module is further configured to compare the time spent in the same step with a set maximum completion time limit of the step, and issue an early warning a period of time before the maximum completion time of the step reaches.
5. The slope engineering progress monitoring and early warning system according to any one of claims 1 to 3, wherein the computing module is further configured to calculate a lowest elevation of completed processes at each elevation at a certain time point.
6. The slope engineering progress monitoring and early warning system according to any one of claims 1 to 3, wherein the monitoring and early warning module is further used for displaying a slope engineering progress chart, and the slope engineering progress chart displays each finished process and the excavated lowest elevation in each level of elevation in a week unit of time.
CN202111366668.4A 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering Active CN113936442B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111366668.4A CN113936442B (en) 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111366668.4A CN113936442B (en) 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering

Publications (2)

Publication Number Publication Date
CN113936442A true CN113936442A (en) 2022-01-14
CN113936442B CN113936442B (en) 2023-05-16

Family

ID=79286990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111366668.4A Active CN113936442B (en) 2021-11-18 2021-11-18 Progress monitoring and early warning system for slope engineering

Country Status (1)

Country Link
CN (1) CN113936442B (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321258A (en) * 1992-05-19 1993-12-07 Tokyu Constr Co Ltd Method for timbering of underground continuous wall
US20100257794A1 (en) * 2009-04-10 2010-10-14 Stark N Daniel W Lateral support device
CN102797503A (en) * 2012-08-31 2012-11-28 中铁二十一局集团有限公司 Remote three-dimensional digital alarm method and system of deformation stability of primary tunnel supporting body
CN103850257A (en) * 2014-03-21 2014-06-11 中国水电顾问集团成都勘测设计研究院有限公司 Digging slope body structure used for rock side slope and digging construction method of digging slope body structure
CN104454010A (en) * 2014-12-10 2015-03-25 西安科技大学 Integrated monitoring and early warning system and early warning method for dynamic condition of deep well drivage construction
CN107575234A (en) * 2017-09-07 2018-01-12 长沙有色冶金设计研究院有限公司 A kind of deep-well support design method
CN107761742A (en) * 2017-10-23 2018-03-06 上海市城市建设设计研究总院(集团)有限公司 Along depth direction is multi-form, variable cross-section supporting construction and its construction method
US20180272434A1 (en) * 2017-03-22 2018-09-27 Kennametal Inc. Cutting tool, in particular a boring bar, and method for machining a number of holes
CN109440787A (en) * 2018-11-12 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The structure and method of engineering slope and underground chamber excavation and support simultaneously in a kind of Toppling Deformation rock mass
CN110439617A (en) * 2019-08-09 2019-11-12 精英数智科技股份有限公司 The supporting of fully-mechanized mining working advance support is apart from monitoring and pre-alarming method, apparatus and system
CN112854235A (en) * 2020-12-31 2021-05-28 中铁建设集团基础设施建设有限公司 Deep foundation pit supporting structure and stability monitoring and early warning system thereof
CN112878333A (en) * 2021-01-04 2021-06-01 中冶南方武汉建筑设计有限公司 Intelligent support system and method integrating monitoring and early warning
CN112990866A (en) * 2021-03-10 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Method for controlling construction progress of slope engineering of water conservancy and hydropower engineering
CN113267157A (en) * 2021-05-18 2021-08-17 中铁北京工程局集团有限公司 Tunnel preliminary bracing large deformation monitoring system

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321258A (en) * 1992-05-19 1993-12-07 Tokyu Constr Co Ltd Method for timbering of underground continuous wall
US20100257794A1 (en) * 2009-04-10 2010-10-14 Stark N Daniel W Lateral support device
CN102797503A (en) * 2012-08-31 2012-11-28 中铁二十一局集团有限公司 Remote three-dimensional digital alarm method and system of deformation stability of primary tunnel supporting body
CN103850257A (en) * 2014-03-21 2014-06-11 中国水电顾问集团成都勘测设计研究院有限公司 Digging slope body structure used for rock side slope and digging construction method of digging slope body structure
CN104454010A (en) * 2014-12-10 2015-03-25 西安科技大学 Integrated monitoring and early warning system and early warning method for dynamic condition of deep well drivage construction
US20180272434A1 (en) * 2017-03-22 2018-09-27 Kennametal Inc. Cutting tool, in particular a boring bar, and method for machining a number of holes
CN107575234A (en) * 2017-09-07 2018-01-12 长沙有色冶金设计研究院有限公司 A kind of deep-well support design method
CN107761742A (en) * 2017-10-23 2018-03-06 上海市城市建设设计研究总院(集团)有限公司 Along depth direction is multi-form, variable cross-section supporting construction and its construction method
CN109440787A (en) * 2018-11-12 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The structure and method of engineering slope and underground chamber excavation and support simultaneously in a kind of Toppling Deformation rock mass
CN110439617A (en) * 2019-08-09 2019-11-12 精英数智科技股份有限公司 The supporting of fully-mechanized mining working advance support is apart from monitoring and pre-alarming method, apparatus and system
CN112854235A (en) * 2020-12-31 2021-05-28 中铁建设集团基础设施建设有限公司 Deep foundation pit supporting structure and stability monitoring and early warning system thereof
CN112878333A (en) * 2021-01-04 2021-06-01 中冶南方武汉建筑设计有限公司 Intelligent support system and method integrating monitoring and early warning
CN112990866A (en) * 2021-03-10 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Method for controlling construction progress of slope engineering of water conservancy and hydropower engineering
CN113267157A (en) * 2021-05-18 2021-08-17 中铁北京工程局集团有限公司 Tunnel preliminary bracing large deformation monitoring system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
易 丹: "破碎围岩条件下高边坡开挖施工技术", 《四川水利发电》 *

Also Published As

Publication number Publication date
CN113936442B (en) 2023-05-16

Similar Documents

Publication Publication Date Title
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN103352455B (en) Monitoring method of bottom soil heave of excavation foundation pit
CN204000901U (en) The vertical high slope prestressing anchor support of a kind of massif device
CN111456666B (en) Automatic control method and system for intelligent scratching of soft pump pressure
CN115167212A (en) Foundation pit dynamic construction control system and method based on monitoring platform
CN104929133B (en) The construction method of sloping timbering at the bottom of a kind of deep basal pit Larsen steel sheet pile stake
CN108222950A (en) Diversion water-conveyance tunnel penetrates through method for correcting error under a kind of weak broken wall rock geological conditions
CN108661073A (en) A kind of barrier wall structure and its construction method
CN111778996A (en) BIM technology-based method for quickly constructing foundation pit pile-anchor supporting structure
CN108755698A (en) A kind of big inclined rock base foundation construction method of abrupt slope incompact-deposit bodies
CN110984132B (en) Construction method for grooving underground diaphragm wall under complex geological condition
CN113936442A (en) Progress monitoring and early warning system for slope engineering
CN102979102B (en) Open-excavation sequential-operation deformation-control design method for deep and large circular foundation ditch in soft soil areas
CN114370071A (en) Device, system and method for monitoring controllable grouting reinforcement of existing building in real time
CN103850257B (en) For excavation slope body structure and the excavation construction method thereof of rock side slope
CN105970966B (en) A kind of excavation construction method of extra-high arch dam foundation weakness disturbed belt
CN102704937B (en) Method for identifying settlement pattern during shield tunnel construction
CN100554882C (en) Architectural engineering pit quick line-putting method
CN102995649B (en) Method for levelling inclination of open caisson in grading and layer-by-layer manner
CN113236222B (en) Automatic drilling control method and system for rotary drilling rig based on self-learning
CN108510202A (en) The monitoring information management method and managing device of building are worn under hydraulic tunnel
CN111963053B (en) Positioning system-based hole forming control method and system for cast-in-place pile machine
CN106812148A (en) A kind of open caisson construction technique
CN112051794A (en) Intelligent double-wheel milling pulping and grouting monitoring system and method
CN107817830B (en) Method for automatically matching stirring times and lifting speed of deep cement soil at sea

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant