CN113910440B - Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof - Google Patents

Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof Download PDF

Info

Publication number
CN113910440B
CN113910440B CN202111326518.0A CN202111326518A CN113910440B CN 113910440 B CN113910440 B CN 113910440B CN 202111326518 A CN202111326518 A CN 202111326518A CN 113910440 B CN113910440 B CN 113910440B
Authority
CN
China
Prior art keywords
concrete
wall
rod
die
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111326518.0A
Other languages
Chinese (zh)
Other versions
CN113910440A (en
Inventor
潘培亮
张国宁
李宜南
张前进
金浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rizhao Highway Development Center
Original Assignee
Rizhao Highway Development Center
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rizhao Highway Development Center filed Critical Rizhao Highway Development Center
Priority to CN202111326518.0A priority Critical patent/CN113910440B/en
Publication of CN113910440A publication Critical patent/CN113910440A/en
Application granted granted Critical
Publication of CN113910440B publication Critical patent/CN113910440B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/02Methods or machines specially adapted for the production of tubular articles by casting into moulds
    • B28B21/10Methods or machines specially adapted for the production of tubular articles by casting into moulds using compacting means
    • B28B21/12Methods or machines specially adapted for the production of tubular articles by casting into moulds using compacting means tamping or ramming the material or the mould elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/56Methods or machines specially adapted for the production of tubular articles incorporating reinforcements or inserts
    • B28B21/60Methods or machines specially adapted for the production of tubular articles incorporating reinforcements or inserts prestressed reinforcements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/76Moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A concrete diversion and solidification device for a highway bridge precast pile and an implementation method thereof belong to the technical field of bridge construction, and aim to solve the problem that concrete is guided into a mould by a chute, so that concrete aggregate and fluid are easily separated and even separated to influence the forming processing of a pile body; the problem that the forming and curing time period of the existing precast pile is longer when the existing precast pile is naturally solidified and formed in a mould; the invention forms a segmented casting space by intermittently moving the flow guide assembly in the bottom die forming groove, utilizes the matching of the annular flow guide pipe, the concrete spray pipe and the concrete conveying pipe to spray concrete, avoids aggregate separation and even segregation, simultaneously moves a forward and reverse rotation driving motor and a lead screw carrying an additive feeder, vibrates the concrete from a feeding channel at the top of the top die cover plate and uniformly mixes an accelerator to accelerate the solidification forming of a pile body; the invention effectively avoids the problem of aggregate separation and segregation when the chute is used for guiding concrete into the mould, accelerates the stable forming of the pile body and is convenient to use.

Description

Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof
Technical Field
The invention relates to the technical field of bridge construction, in particular to a concrete diversion and solidification device for a highway bridge precast pile and an implementation method thereof.
Background
The precast reinforced concrete pile is prefabricated in a prefabricated part processing factory, maintained to reach the design strength, transported to a construction site, driven into the soil by a pile driver, and then a bearing platform beam (plate) foundation is poured on the top of the pile. The grade of concrete adopted by the reinforced concrete precast pile should not be lower than 300#. The diameter of the stressed steel bar of the pile is not less than 12 mm, and 4-8 main bars are generally configured. In order to resist hammering and penetrate through soil, hooping should be densely arranged on the pile top and the pile tip, and the main reinforcement at the pile tip is bent and welded on a core rod. The prefabricated reinforced concrete pile has the advantages of simple manufacture, high strength, high rigidity and capability of being manufactured into various cross-sectional shapes, and is a widely adopted pile type.
The precast concrete pile is widely applied to bridge construction, and can be transported to the site for construction after being processed in a factory, so that the construction period of the bridge is greatly shortened, and the construction is more convenient. When precast piles are produced in factories, concrete is poured into a pile body mould for solidification and forming, generally, concrete is guided into the mould by using a chute, but aggregate and fluid are easy to separate when the chute is used for guiding the concrete, the quality of the pile body is influenced after the concrete with uneven components is formed, and the pile body can be separated after entering the mould when the separation is serious, so that the concrete cannot be used, and the production and processing of the pile body are influenced; in addition, the existing precast pile is generally formed by natural solidification in a mould, and the forming and maintenance time period is long and troublesome.
Therefore, the concrete diversion and solidification device for the highway bridge precast pile and the implementation method thereof are provided.
Disclosure of Invention
The invention aims to provide a concrete diversion and solidification device for a highway bridge precast pile and an implementation method thereof, and aims to solve the problems that in the background technology, concrete is introduced into a mould by using a chute, concrete aggregate and fluid are easily separated and even separated, and the forming and processing of a pile body are influenced, and the conventional precast pile is generally naturally solidified and formed in the mould, and the forming and maintenance time period is long.
In order to achieve the purpose, the invention provides the following technical scheme: a road bridge precast pile concrete diversion solidification device comprises a bottom die and raised plates, wherein the bottom die is provided with a forming groove, the raised plates are arranged at the bottoms of the side walls at the two ends of the bottom die, positioning columns are arranged at the two sides of the upper end of each raised plate, the positioning columns are sleeved in sleeve holes of side die plates, a diversion assembly is arranged in the forming groove of the bottom die and is attached to the inner wall of the forming groove of the bottom die, a top die cover plate is covered on the top of the bottom die in a sealing manner, a feeding channel is arranged at the top of the top die cover plate, fixing plates are symmetrically and fixedly arranged on the outer walls of the two ends of the top die cover plate at the two sides of the feeding channel, guide rods are fixedly connected between the two fixing plates at the same side of the feeding channel, two additive feeders are respectively connected with the two guide rods in a sliding manner, a lead screw is arranged between the two fixing plates at the same side of the feeding channel and is positioned below the guide rods and parallel to the guide rods, one end of the lead screw is rotatably connected with one fixing plate, a driving motor is fixedly connected to the outer side of the other fixing plate, and the other end of the lead screw is fixedly connected with the output end of the driving motor;
the water conservancy diversion subassembly includes mounting panel and the powerful magnet of gomphosis on the mounting panel outer wall, the mounting panel is fixed in on the side template inner wall of die block one end through powerful magnet absorption, powerful magnet's one side fixedly connected with electric telescopic handle is kept away from to the mounting panel, electric telescopic handle's terminal fixed connection is on the outer wall of annular slab, the inner chamber fixedly connected with annular honeycomb duct of annular slab, the annular honeycomb duct has hollow cavity, electric telescopic handle's one end fixedly connected with rather than the communicating concrete spray tube of hollow cavity is kept away from to the annular honeycomb duct, the one end fixedly connected with that the annular honeycomb duct is close to electric telescopic handle is rather than the communicating concrete conveying pipe of hollow cavity, the concrete conveying pipe runs through the outside that extends to the side template, and install the connecting rod on the lateral wall at annular honeycomb duct both ends, the ball has been cup jointed in the end activity of connecting rod, ball laminating die block shaping inslot wall.
Further, T-shaped positioning rods are evenly installed at the upper ends of the outer walls of the two sides of the bottom die, the T-shaped positioning rods are movably sleeved in sleeve holes in bottom plates on the two sides of the top die cover plate, limiting parts are fixedly connected to the upper ends of the bottom plates on the two sides of the top die cover plate, and the limiting parts are matched with the T-shaped positioning rods to fix the top die cover plate and the bottom die.
Further, the locating part includes fixed connection in the casing of top mould apron both sides bottom plate upper end, and casing one side upper end is rotated and is connected with the regulation swing arm, adjusts the swing arm lower extreme and runs through and extend to casing inside and fixedly connected with take-up reel, and the take-up reel rotates to be connected in casing bottom plate upper end, and the inside rolling of take-up reel has the stay cord, the terminal fixedly connected with spacing couple of stay cord, the terminal of spacing couple runs through the casing lateral wall and extends to the outside of casing.
Furthermore, a reset spring is sleeved on the outer wall of a straight rod of the limiting hook in the shell, when the limiting hook is hung on the T-shaped positioning rod, the reset spring is in a stretching state, a limiting rod is fixedly connected to one side of the bottom of the winding roll, a blocking rod penetrates through the top of the shell corresponding to the tail end of the limiting rod, the lower end of the blocking rod extends into the shell, and the tail end of the blocking rod is suspended on one side of the limiting rod.
Furthermore, the two side walls of the bottom die are of a hollow structure, air blowers are mounted on the outer walls of the two sides of the bottom die, the air blowers are electrically connected with controllers on the side walls of the bottom die, air outlet cylinders of the air blowers are communicated with the side walls of the bottom die, paraffin layers are laid on the inner walls of the bottom die forming grooves, air holes are uniformly formed in the inner walls of the two sides of the bottom die forming grooves, and the air holes are communicated with the hollow cavities of the bottom die.
Further, the side form laminating die block both ends shaping notch outer wall sets up, is fixed with the fixed block on the lateral wall at side form both ends, is fixed with L type take-up lever on the outer wall that the fixed block is close to die block one side, rotates on the die block outer wall of the terminal adjacent department of L type take-up lever and is connected with the carousel, fixedly connected with dog on the one side outer wall that the carousel is close to L type take-up lever, dog and the terminal baffle contact surface parallel arrangement that inclines each other of L type take-up lever.
Further, glassware is including sliding sleeve and the hydraulic lifting rod of fixed connection at the sliding sleeve top that the slip cup joints on the guide bar outer wall under the additive, the riser screw thread of sliding sleeve lower extreme cup joints on the outer wall of lead screw, and hydraulic lifting rod top fixedly connected with connecting strip, the terminal fixed connection of connecting strip is on the both sides outer wall of liquid storage pot, the accelerator has been stored in the liquid storage pot, and the liquid storage pot bottom installs the force pump, force pump input end and liquid storage pot are linked together, force pump bottom output is connected with the catheter, the catheter runs through feedstock channel.
Furthermore, the outer wall of the catheter is fixedly connected with a fixed sleeve, the outer walls of the two sides of the fixed sleeve are fixedly connected with machine heads, the output end of the bottom of the machine head is fixedly connected with vibrating rods, and the vibrating rods are suspended on the two sides of the catheter in parallel.
Further, the spout has been seted up to the symmetry on the relative inside wall of catheter bottom port top, sliding connection has L type jib in the spout, L type jib bottom fixedly connected with shutoff head, the shutoff head is pegged graft inside the catheter, and L type jib diaphragm lower extreme is provided with compression spring, compression spring lower extreme fixed connection is on the bottom lateral wall of spout, and evenly seted up out the liquid hole on the catheter lateral wall of spout lower extreme, when compression spring normally relaxes, the shutoff of shutoff head goes out the liquid hole.
The invention also provides another technical scheme: an implementation method of a concrete diversion and solidification device for a highway bridge precast pile comprises the following steps:
s1: sleeving the side template on the outer wall of the positioning column to enable the side template to be attached to and plug the end face of the forming groove in the bottom die, fixing the rotary turntable by clamping the L-shaped lap rod through the stop block, clamping and sleeving the reinforcement cage in the sleeve on the inner wall of the side template far away from the flow guide assembly, suspending the reinforcement cage in the forming groove of the bottom die through the sleeve, and sealing and covering the upper end of the bottom die with a top die cover plate;
s2: sleeving the side template on the outer wall of the positioning column to enable the side template to be attached and plugged on the end face of the forming groove in the bottom die, fixing the rotary turntable by clamping the L-shaped lap bar through the stop block, clamping and sleeving one end of the reinforcement cage in the sleeve on the inner wall of the side template away from one side of the flow guide assembly, penetrating the other end of the reinforcement cage through the annular flow guide pipe, suspending the reinforcement cage in the bottom die forming groove through the sleeve, and sealing and covering the top die cover plate at the upper end of the bottom die;
s3: starting an electric telescopic rod, pushing an annular plate to be attached to the inner wall of a bottom die forming groove by the electric telescopic rod to move to a side template close to the other end of the bottom die, so that a section of casting space is formed between the annular plate and the side template, pumping concrete to a cavity of an annular flow guide pipe by using a concrete conveying pipe at the moment, spraying the concrete from a concrete spraying pipe on the annular flow guide pipe, controlling the electric telescopic rod to pull the annular plate to move back after the height of the concrete reaches the lower edge of a port of the annular flow guide pipe, spraying and filling the concrete in the next section of casting space, and filling the concrete in sections;
s4: after the annular plate moves back to the position outside the convex column of the annular flow guide pipe clamped and sleeved on the inner wall of the mounting plate, continuously spraying filling concrete to the bottom port of the feeding channel, after the annular plate is filled with the concrete, starting a driving motor to match with a screw rod and a sliding sleeve to transfer the liquid storage tank to one side of the feeding channel, which is close to the fixed end of the reinforcement cage, and descending a hydraulic lifting rod to enable the liquid guide pipe and the vibrating rod to be inserted into the concrete;
s5: the quick-setting admixture pump sending to the catheter with the storage tank internal accelerating agent pump is started to the pressure pump, the accelerating agent promotes the shutoff head to overcome the elasticity of compression spring and move downwards to remove the shutoff to going out the liquid hole, the accelerating agent is mixed in the concrete from going out the liquid hole blowout on the catheter lateral wall, start the aircraft nose when spraying the accelerating agent, the aircraft nose drives the vibrating rod and vibrates concrete and accelerating agent, make both misce benes, control driving motor counter-rotation after that and remove the storage tank and carry out the accelerating agent interpolation to subsequent concrete, form removal is maintained after the pile body shaping.
Compared with the prior art, the invention has the following beneficial effects:
1. the invention provides a road bridge precast pile concrete diversion and solidification device and an implementation method thereof, wherein a mounting plate is fixed on the inner wall of a side template at one end of a bottom die through strong magnets in an adsorption manner, an electric telescopic rod is arranged on the outer wall of the side of the mounting plate far away from the strong magnets, the tail end of the electric telescopic rod is fixedly connected to the outer wall of an annular plate, an annular guide pipe is arranged in an inner cavity of the annular plate, concrete spray pipes are uniformly arranged on the outer wall of the side of the annular guide pipe far away from the electric telescopic rod, a concrete conveying pipe is arranged on the outer wall of the side of the annular guide pipe close to the electric telescopic rod, the concrete conveying pipe penetrates and extends to the outside of the side template, a connecting rod is arranged on the side wall at two ends of the annular guide pipe, balls are movably sleeved on the tail end of the connecting rod and are attached to the inner wall of a bottom die forming groove, a reinforcement cage is clamped and sleeved in a sleeve on the inner wall of the side template far away from a diversion assembly, the suspension reinforcement cage is suspended in the bottom die forming groove by utilizing the sleeve, starting an electric telescopic rod, pushing an annular plate to be attached to the inner wall of a bottom die forming groove by the electric telescopic rod to move to a side template close to the other end of the bottom die to form a section of casting space between the annular plate and the side template, pumping concrete to a cavity of an annular flow guide pipe by using a concrete conveying pipe at the moment, spraying the concrete out of a concrete spray pipe on the annular flow guide pipe, controlling the electric telescopic rod to pull the annular plate to move back after the height of the concrete reaches the lower edge of a port of the annular flow guide pipe, spraying and filling the concrete in the next section of casting space, filling the concrete in the section, continuously spraying and filling the concrete to the bottom port of a feeding channel after the annular plate moves back to the outside of a convex column sleeved on the inner wall of the side template by an annular flow guide pipe clamp, and continuously and sequentially spraying the flow guide concrete in a small range of a moving interval mode of the annular plate after the annular plate is filled with the concrete, the problems of aggregate separation and segregation when chute diversion concrete is used for entering a mold are avoided.
2. The invention provides a concrete diversion solidification device for a highway bridge precast pile and an implementation method thereof, wherein a sliding sleeve is arranged on the outer wall of a guide rod and is provided with a hydraulic lifting rod, a vertical plate at the lower end of the sliding sleeve is sleeved on the outer wall of a screw rod in a threaded manner, the top of the hydraulic lifting rod is fixedly connected with a connecting strip, the tail end of the connecting strip is fixedly connected to the outer walls of two sides of a liquid storage tank, an accelerating agent is stored in the liquid storage tank, the bottom of the liquid storage tank is provided with a pressure pump, the input end of the pressure pump is communicated with the liquid storage tank, the output end of the bottom of the pressure pump is connected with a liquid guide pipe, the liquid guide pipe passes through the upper part of a feed channel port, the outer wall of the liquid guide pipe is provided with a fixed sleeve, the outer walls of two sides of the fixed sleeve are fixedly connected with a machine head, the output end of the bottom of the machine head is fixedly connected with a vibrating rod, the vibrating rod is suspended on two sides of the liquid guide pipe in parallel, the hydraulic lifting rod is lowered to enable the liquid guide pipe and the vibrating rod to be inserted into concrete, the pressure pump is started to pump the accelerating agent in the liquid storage tank to the liquid guide pipe, the accelerating agent impacts the sealing head to compress the compression spring and expose the liquid outlet hole, the accelerating agent is sprayed out of the liquid outlet hole in the side wall of the liquid guide pipe and mixed in the concrete, the machine head is started when the accelerating agent is sprayed, the machine head drives the vibrating rod to vibrate the concrete and the accelerating agent, the concrete and the accelerating agent are mixed uniformly, then the driving motor is controlled to rotate reversely to move the liquid storage tank to add the accelerating agent to the subsequent concrete, the mixing accelerating agent is added while the concrete in the mold is vibrated uniformly to shorten the forming time of the pile body, the accelerating agent is utilized to improve the performance of the pile body, and the production forming of the pile body is accelerated.
3. The invention provides a concrete diversion and solidification device for a highway bridge precast pile and an implementation method thereof, wherein a shell is arranged at the upper ends of bottom plates at two sides of a top die cover plate, an adjusting rotary rod is arranged at the upper end of one side of the shell, the lower end of the adjusting rotary rod penetrates and extends into the shell, the tail end of the adjusting rotary rod is fixedly connected with a wire winding disc, the wire winding disc is rotatably connected with the upper end of the bottom plate of the shell, a pull rope is wound on the outer wall of the wire winding disc, the tail end of the pull rope is fixedly connected with a limiting hook, the tail end of the limiting hook penetrates through the side wall of the shell and extends to the outside of the shell, a reset spring is wound on the outer wall of a straight rod of the limiting hook in the shell, a limiting rod is arranged at one side of the bottom of the wire winding disc, a stop rod penetrates and is arranged at the top of the shell at the position adjacent to the tail end of the limiting rod, the lower end of the limiting rod extends into the shell, and the tail end of the stop rod is suspended at one side of the stop rod, cup joint the trepanning on the bottom plate of top mould apron both sides on T type locating lever outer wall after, top mould apron closing cap is on die block shaping groove top port outer wall, extract the shelves pole at casing top, the rotatory rolling stay cord of rotatory regulation rotating-rod drive take-up reel, when stay cord pulling spacing couple removes and tensile reset spring, make spacing couple end card cover on the outer wall of T type locating lever, accomplish the fixing of die block and top mould apron, insert back shelves pole and make it stop to the gag lever post on the take-up reel lateral wall after that, prevent that reset spring from returning back and returning and driving take-up reel gyration release stay cord, it only needs to extract the shelves pole at casing top once more to pull down the top mould apron, reset spring returns and contracts and drives the take-up reel gyration, spacing couple is automatic to break away from T type locating lever, can take off the top mould apron, and is convenient and fast.
Drawings
FIG. 1 is a schematic view of the whole structure of the concrete diversion and solidification device for the highway bridge precast pile of the present invention;
FIG. 2 is a schematic view of a flow guide assembly mounting structure of the concrete flow guide and solidification device for the highway bridge precast pile of the invention;
FIG. 3 is a schematic view of a partial cut-away structure of a flow guide assembly of the concrete flow guide and solidification device for the highway bridge precast pile of the invention;
FIG. 4 is an enlarged schematic structural view of the position A in the concrete diversion and solidification device 1 of the highway bridge precast pile of the invention;
FIG. 5 is a schematic structural view of an additive feeder of the concrete diversion and solidification device for the highway bridge precast pile of the present invention;
FIG. 6 is an enlarged schematic structural view of a concrete diversion and solidification device of a highway bridge precast pile in the position B in FIG. 5;
FIG. 7 is a cross-sectional view of a liquid guiding pipe of the concrete guiding and solidifying device for the precast pile of the highway bridge of the present invention;
fig. 8 is a schematic structural view of a limiting part of the concrete diversion and solidification device for the highway bridge precast pile.
In the figure: 1. bottom die; 2. a raised plate; 3. a positioning column; 4. a sideform; 5. a flow guide assembly; 51. mounting a plate; 52. a strong magnet; 53. an electric telescopic rod; 54. an annular plate; 55. an annular flow guide pipe; 56. a concrete nozzle; 57. a concrete delivery pipe; 58. a connecting rod; 59. a ball bearing; 6. a top mold cover plate; 7. a feed channel; 8. a fixing plate; 9. a guide rod; 10. an additive feeder; 101. a sliding sleeve; 102. a hydraulic lifting rod; 103. a connecting strip; 104. a liquid storage tank; 105. a pressure pump; 106. a catheter; 1061. a chute; 1062. an L-shaped boom; 1063. plugging a plug; 1064. a compression spring; 1065. a liquid outlet hole; 107. fixing a sleeve; 108. a machine head; 109. vibrating a tamper; 11. a lead screw; 12. a drive motor; 13. a T-shaped positioning rod; 14. a limiting member; 141. a housing; 142. adjusting the rotary rod; 143. a take-up reel; 144. pulling a rope; 145. a limiting hook; 146. a return spring; 147. a limiting rod; 148. a gear lever; 15. a blower; 16. air holes; 17. a fixed block; 18. an L-shaped lapping rod; 19. a turntable; 20. and a stop block.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The concrete is introduced into the mould by using the chute, which easily causes the problem that the separation of concrete aggregate and fluid and even segregation affect the forming processing of the pile body, please refer to fig. 1-3, and the following preferred technical scheme is provided:
the utility model provides a highway bridge precast pile concrete water conservancy diversion solidification equipment, including the die block 1 of seting up the shaping groove with set up in the kickboard 2 of die block 1 both ends lateral wall bottom department, 2 upper end both sides of kickboard are provided with reference column 3, reference column 3 cup joints in the cover hole of side form 4, die block 1 shaping inslot is provided with water conservancy diversion subassembly 5, the setting of the 1 shaping inslot wall of die block of water conservancy diversion subassembly 5 laminating, and the top closing cap of die block 1 has top die cover board 6, top die cover board 6 top department is provided with feedstock channel 7, symmetry fixed mounting has fixed plate 8 on the 6 both ends outer walls of top die cover board of feedstock channel 7 both sides, be located fixedly connected with guide bar 9 between two fixed plates 8 of feedstock channel 7 homonymy, be provided with the both ends respectively with under the additive of two guide bar 9 sliding connection glassware 10, be located between two fixed plates 8 of feedstock channel 7 homonymy still be located guide bar 9 below and with the lead screw 11 that the guide bar 9 is parallel, the one end of lead screw 11 rotates with one of them and is connected, the outside fixedly connected with the output of another fixed plate 8, driving motor 12 is just reversing motor.
The flow guide assembly 5 comprises a mounting plate 51 and a strong magnet 52 embedded on the outer wall of the mounting plate 51, the mounting plate 51 is fixed on the inner wall of the side template 4 at one end of the bottom die 1 through the strong magnet 52 in an adsorption manner, a sleeve is arranged on the inner wall of the side template 4 at the other end of the bottom die 1 and used for fixedly sleeving a reinforcement cage, one side of the mounting plate 51 away from the strong magnet 52 is fixedly connected with an electric telescopic rod 53, the tail end of the electric telescopic rod 53 is fixedly connected on the outer wall of a ring-shaped plate 54, an inner cavity of the ring-shaped plate 54 is fixedly connected with an annular flow guide pipe 55, the annular flow guide pipe 55 is provided with a hollow cavity, a convex column is arranged on the side wall of the mounting plate 51 corresponding to the annular flow guide pipe 55, one end of the annular flow guide pipe 55 away from the electric telescopic rod 53 is fixedly connected with a concrete spray pipe 56 communicated with the hollow cavity, one end of the annular flow guide pipe 55 close to the electric telescopic rod 53 is fixedly connected with a concrete delivery pipe 57 communicated with the hollow cavity, the concrete delivery pipe 57 penetrating through the side template 4, a connecting rod 58 is arranged on the side wall at two ends of the annular flow guide pipe 55, a ball 59 is movably sleeved on the inner wall of the bottom die 1.
1 both sides wall of die block is hollow structure, installs air-blower 15 on the outer wall of 1 both sides of die block, and air-blower 15 is connected with the controller electricity on the 1 lateral wall of die block, and air-blower 15 goes out 1 lateral wall of dryer intercommunication die block, and the inner wall upper berth in 1 shaping groove of die block is equipped with the paraffin layer, and evenly is provided with gas pocket 16 on the 1 shaping groove of die block both sides inner wall, and the well cavity of gas pocket 16 intercommunication die block 1 is provided with the cross opening pad in the port of gas pocket 16, and gas pocket 16 is used for the supplementary drawing of patterns of jet-propelled.
The side die plate 4 is attached to the outer walls of forming notches at two ends of the bottom die 1, the fixing blocks 17 are fixed on the side walls at two ends of the side die plate 4, the L-shaped lapping rods 18 are fixed on the outer wall of the fixing block 17 close to one side of the bottom die 1, the outer wall of the bottom die 1 at the adjacent position of the tail ends of the L-shaped lapping rods 18 is rotatably connected with a rotary table 19, a stop block 20 is fixedly connected to the outer wall of one side of the rotary table 19 close to the L-shaped lapping rods 18, and the contact surfaces of the stop block 20 and the tail end baffle of the L-shaped lapping rods 18 are mutually inclined and arranged in parallel.
Specifically, the steel reinforcement cage is clamped and sleeved in a sleeve on the inner wall of a side template 4 far away from one side of a diversion assembly 5, the steel reinforcement cage is suspended in a bottom template 1 forming groove by the sleeve, an electric telescopic rod 53 is started, the electric telescopic rod 53 pushes an annular plate 54 to be attached to the inner wall of the bottom template 1 forming groove to move to a side template 4 close to the other end of the bottom template 1, so that a section of casting space is formed between the annular plate 54 and the side template 4, concrete is pumped to a cavity of an annular diversion pipe 55 by a concrete conveying pipe 57 at the moment, the concrete is sprayed out from a concrete spraying pipe 56 on the annular diversion pipe 55, after the height of the concrete reaches the lower edge of the port of the annular diversion pipe 55, the electric telescopic rod 53 is controlled to pull the annular plate 54 to move back to perform concrete spraying and filling in the next section of casting space, so that the concrete is filled in sections, after the annular plate 54 moves back to the outer part of a convex column, the annular diversion pipe 55 is clamped and sleeved on the inner wall of the side template 4, the concrete is continuously sprayed and filled to the bottom of a feeding channel 7, and the concrete is separated from aggregates when the chute.
In order to solve the problem that the conventional precast pile is generally formed by natural solidification in a mold and has a long forming and curing time period, please refer to fig. 1 and 5-7, and the following preferred technical scheme is provided:
additive unloading ware 10 is including sliding sleeve 101 and the hydraulic lifting rod 102 of fixed connection in sliding sleeve 101 top on guide bar 9 outer wall, the riser screw thread of sliding sleeve 101 lower extreme cup joints on the outer wall of lead screw 11, and hydraulic lifting rod 102 top fixedly connected with connecting strip 103, the terminal fixed connection of connecting strip 103 is on the both sides outer wall of liquid storage pot 104, the accelerator has been stored in liquid storage pot 104, and liquid storage pot 104 bottom installs force pump 105, force pump 105 input is linked together with liquid storage pot 104, force pump 105 bottom output is connected with catheter 106, catheter 106 runs through feedstock channel 7.
The outer wall of the catheter 106 is fixedly connected with a fixing sleeve 107, the outer walls of two sides of the fixing sleeve 107 are fixedly connected with machine heads 108, the output end of the bottom of the machine head 108 is fixedly connected with vibrating rods 109, and the vibrating rods 109 are suspended on two sides of the catheter 106 in parallel.
The liquid guiding device comprises a liquid guiding pipe 106, sliding grooves 1061 are symmetrically formed in the opposite inner side walls above the bottom port of the liquid guiding pipe 106, an L-shaped hanging rod 1062 is connected in the sliding grooves 1061 in a sliding mode, a blocking head 1063 is fixedly connected to the bottom of the L-shaped hanging rod 1062, the blocking head 1063 is inserted into the liquid guiding pipe 106 in a plugging mode, a compression spring 1064 is arranged at the lower end of a transverse plate of the L-shaped hanging rod 1062, the lower end of the compression spring 1064 is fixedly connected to the side wall of the bottom of the sliding grooves 1061, liquid outlet holes 1065 are uniformly formed in the side wall of the liquid guiding pipe 106 at the lower end of the sliding grooves 1061, and when the compression spring 1064 normally expands, the blocking head 1063 blocks the liquid outlet holes 1065.
Specifically, a driving motor 12 is started to cooperate with a screw rod 11 and a sliding sleeve 101 to transfer a liquid storage tank 104 to one side of a feeding channel 7 close to the fixed end of a reinforcement cage, a hydraulic lifting rod 102 is lowered to enable a liquid guide pipe 106 and a vibrating rod 109 to be inserted into concrete, a pressure pump 105 is started to pump an accelerator in the liquid storage tank 104 to the liquid guide pipe 106, the accelerator impacts a plug 1063 to compress a compression spring 1064 to expose a liquid hole 1065, the accelerator is sprayed out of the liquid hole 1065 in the side wall of the liquid guide pipe 106 and mixed in the concrete, a machine head 108 is started when the accelerator is sprayed, the machine head 108 drives the vibrating rod 109 to vibrate the concrete and the accelerator, the concrete and the accelerator are uniformly mixed, then the driving motor 12 is controlled to rotate reversely to move the liquid storage tank 104 to add the accelerator to the subsequent concrete, the forming time of the pile body is shortened by adding the accelerator while uniformly vibrating the concrete in the mold, meanwhile, the performance of the pile body is improved by the accelerator, and the production forming of the pile body is accelerated.
In order to realize the quick installation and fixation of the bottom die 1 and the top die cover plate 6, as shown in fig. 1, 2 and 8, the following preferred technical solutions are provided:
t-shaped positioning rods 13 are uniformly arranged at the upper ends of the outer walls of the two sides of the bottom die 1, the T-shaped positioning rods 13 are movably sleeved in sleeve holes in bottom plates on the two sides of the top die cover plate 6, limiting parts 14 are fixedly connected to the upper ends of the bottom plates on the two sides of the top die cover plate 6, and the limiting parts 14 are matched with the T-shaped positioning rods 13 to fix the top die cover plate 6 and the bottom die 1.
The limiting member 14 includes a casing 141 fixedly connected to the upper ends of the bottom plates on both sides of the top mold cover plate 6, the upper end of one side of the casing 141 is rotatably connected with an adjusting rotating rod 142, the lower end of the adjusting rotating rod 142 penetrates through the inside of the casing 141 and is fixedly connected with a winding roll 143, the winding roll 143 is rotatably connected to the upper end of the bottom plate of the casing 141, a pulling rope 144 is wound inside the winding roll 143, the tail end of the pulling rope 144 is fixedly connected with a limiting hook 145, and the tail end of the limiting hook 145 penetrates through the side wall of the casing 141 and extends to the outside of the casing 141.
The outer wall of a straight rod of the limiting hook 145 in the shell 141 is sleeved with a return spring 146, when the limiting hook 145 is hung on the T-shaped positioning rod 13, the return spring 146 is in a stretching state, one side of the bottom of the winding roll 143 is fixedly connected with a limiting rod 147, a blocking rod 148 penetrates through the top of the shell 141 corresponding to the tail end of the limiting rod 147, the lower end of the blocking rod 148 extends into the shell 141, and the tail end of the blocking rod 148 is hung on one side of the limiting rod 147.
Specifically, after sleeve holes on bottom plates on two sides of the top die cover plate 6 are sleeved on the outer wall of the T-shaped positioning rod 13, the top die cover plate 6 is covered on the outer wall of a top port of a forming groove of the bottom die 1 in a sealing manner, a blocking rod 148 at the top of the shell 141 is pulled out, the rotation adjusting rotary rod 142 drives the winding roll 143 to rotate and wind the pulling rope 144, the pulling rope 144 pulls the limiting hook 145 to move and stretch the reset spring 146, the tail end of the limiting hook 145 is clamped on the outer wall of the T-shaped positioning rod 13, the bottom die 1 and the top die cover plate 6 are fixed, then the blocking rod 148 is inserted back to block a limiting rod 147 on the side wall of the winding roll 143, the reset spring 146 is prevented from retracting to drive the winding roll 143 to rotate and release the pulling rope 144, the top die cover plate 6 needs to be detached, only the blocking rod 148 at the top of the shell 141 needs to be pulled out again, the reset spring 146 retracts to drive the winding roll 143 to rotate, the limiting hook 145 is automatically separated from the T-shaped positioning rod 13, and the top die cover plate 6 can be detached conveniently and quickly.
In order to better show the concrete diversion and solidification device for the precast pile of the highway bridge, the embodiment also provides an implementation method of the concrete diversion and solidification device for the precast pile of the highway bridge, which comprises the following steps:
the method comprises the following steps: sleeving the side template 4 on the outer wall of the positioning column 3, enabling the side template 4 to be attached and plugged on the end face of a forming groove in the bottom die 1, clamping and fixing the rotary turntable 19 by utilizing the stop block 20 to clamp the L-shaped lap bar 18, clamping and sleeving one end of the reinforcement cage in a sleeve on the inner wall of the side template 4 far away from one side of the flow guide assembly 5, enabling the other end of the reinforcement cage to penetrate through the annular flow guide pipe 55, suspending the reinforcement cage in the forming groove of the bottom die 1 by utilizing the sleeve, and sealing and capping the upper end of the bottom die 1 with the top die cover plate 6;
step two: the stop lever 148 at the top of the shell 141 is pulled out, the adjusting rotary rod 142 is rotated to drive the winding roll 143 to rotate and wind the pull rope 144, the pull rope 144 pulls the limiting hook 145 to move and stretches the reset spring 146, and meanwhile, the tail end of the limiting hook 145 is clamped and sleeved on the outer wall of the T-shaped positioning rod 13, so that the bottom die 1 and the top die cover plate 6 are fixed;
step three: starting the electric telescopic rod 53, wherein the electric telescopic rod 53 pushes the annular plate 54 to be attached to the inner wall of the forming groove of the bottom die 1 and move to the side die plate 4 close to the other end of the bottom die 1, so that a section of casting space is formed between the annular plate 54 and the side die plate 4, at the moment, concrete is pumped to the cavity of the annular guide pipe 55 by using the concrete conveying pipe 57, the concrete is sprayed out from the concrete spray pipe 56 on the annular guide pipe 55, after the height of the concrete reaches the lower edge of the port of the annular guide pipe 55, the electric telescopic rod 53 is controlled to pull the annular plate 54 to move back, then the concrete in the next section of casting space is sprayed and filled, and the concrete is filled in the section;
step four: after the annular plate 54 moves back to the outside of the convex column of the annular guide pipe 55 clamped on the inner wall of the mounting plate 51, continuously injecting the filling concrete to the bottom port of the feeding channel 7, after the filling concrete, starting the driving motor 12 to match the screw rod 11 and the sliding sleeve 101 to transfer the liquid storage tank 104 to one side of the feeding channel 7 close to the fixed end of the reinforcement cage, and lowering the hydraulic lifting rod 102 to enable the liquid guide pipe 106 and the vibrating rod 109 to be inserted into the concrete;
step five: the pressure pump 105 is started to pump the accelerating agent in the liquid storage tank 104 to the liquid guide pipe 106, the accelerating agent pushes the plugging head 1063 to move downwards to overcome the elasticity of the compression spring 1064, so that the plugging of the liquid outlet 1065 is removed, the accelerating agent is sprayed out from the liquid outlet 1065 on the side wall of the liquid guide pipe 106 and mixed in concrete, the machine head 108 is started when the accelerating agent is sprayed, the machine head 108 drives the vibrating rod 109 to vibrate the concrete and the accelerating agent to uniformly mix the concrete and the accelerating agent, then the driving motor 12 is controlled to rotate reversely to move the liquid storage tank 104 to add the accelerating agent to the subsequent concrete, and the mold is removed for maintenance after the pile body is formed.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides a highway bridge precast pile concrete water conservancy diversion solidification equipment, is including die block (1) of seting up the shaping groove and set up in protruding board (2) of die block (1) both ends lateral wall bottom department, protruding board (2) upper end both sides are provided with reference column (3), reference column (3) cup joint in the trepanning of side form board (4), be provided with water conservancy diversion subassembly (5), its characterized in that in die block (1) shaping groove: the guide assembly (5) is attached to the inner wall of a forming groove in the bottom die (1), a top die cover plate (6) is sealed on the top of the bottom die (1), a feeding channel (7) is arranged at the top of the top die cover plate (6), fixing plates (8) are symmetrically and fixedly mounted on the outer walls of two ends of the top die cover plate (6) on two sides of the feeding channel (7), guide rods (9) are fixedly connected between the two fixing plates (8) on the same side of the feeding channel (7), an additive feeder (10) with two ends respectively connected with the two guide rods (9) in a sliding mode is arranged above the top die cover plate (6), a lead screw (11) which is arranged below the guide rods (9) and parallel to the guide rods (9) is further arranged between the two fixing plates (8) on the same side of the feeding channel (7), one end of the lead screw (11) is rotatably connected with one fixing plate (8), a driving motor (12) is fixedly connected to the outer side of the other fixing plate (8), and the other end of the lead screw (11) is fixedly connected with the output end of the driving motor (12);
flow guide assembly (5) are including mounting panel (51) and powerful magnet (52) of gomphosis on mounting panel (51) outer wall, mounting panel (51) are fixed in on side form board (4) inner wall of die block (1) one end through powerful magnet (52) absorption, one side fixedly connected with electric telescopic handle (53) of powerful magnet (52) are kept away from in mounting panel (51), the terminal fixed connection of electric telescopic handle (53) is on the outer wall of annular board (54), the inner chamber fixedly connected with annular honeycomb duct (55) of annular board (54), annular honeycomb duct (55) have hollow cavity, the one end fixedly connected with that electric telescopic handle (53) were kept away from in annular honeycomb duct (55) has rather than the communicating concrete spray tube (56) of hollow cavity, the one end fixedly connected with that annular honeycomb duct (55) are close to electric telescopic handle (53) has rather than the communicating concrete conveying pipe (57) of hollow cavity, concrete conveying pipe (57) run through and extend to the outside of side form board (4), and install connecting rod (58) on the lateral wall at annular honeycomb duct (55) both ends, ball (59) end activity cup joints ball (59), die block (1) laminating shaping groove.
2. The road bridge precast pile concrete diversion and solidification device of claim 1, characterized in that: t type locating lever (13) are evenly installed to die block (1) both sides outer wall upper end, and T type locating lever (13) activity cup joints in the cover hole on top die cover board (6) both sides bottom plate, and the equal fixedly connected with locating part (14) in top die cover board (6) both sides bottom plate upper end, and locating part (14) and T type locating lever (13) cooperation are fixed top die cover board (6) and die block (1).
3. The concrete diversion and solidification device for the highway bridge precast pile according to claim 2, wherein: the limiting part (14) comprises a shell (141) fixedly connected to the upper ends of bottom plates on two sides of the top die cover plate (6), the upper end of one side of the shell (141) is rotatably connected with an adjusting rotary rod (142), the lower end of the adjusting rotary rod (142) penetrates through and extends to the inside of the shell (141) and is fixedly connected with a winding roll (143), the winding roll (143) is rotatably connected to the upper end of the bottom plate of the shell (141), a pull rope (144) is wound in the inside of the winding roll (143), the tail end of the pull rope (144) is fixedly connected with a limiting hook (145), and the tail end of the limiting hook (145) penetrates through the side wall of the shell (141) and extends to the outside of the shell (141).
4. The concrete diversion and solidification device for the highway bridge precast pile according to claim 3, wherein: the outer wall of a straight rod of the limiting hook (145) in the shell (141) is sleeved with a return spring (146), when the limiting hook (145) is hung on the T-shaped positioning rod (13), the return spring (146) is in a stretching state, one side of the bottom of the winding roll (143) is fixedly connected with a limiting rod (147), the top of the shell (141) corresponding to the tail end of the limiting rod (147) is provided with a blocking rod (148) in a penetrating mode, the lower end of the blocking rod (148) extends into the shell (141), and the tail end of the blocking rod (148) is suspended on one side of the limiting rod (147).
5. The concrete diversion and solidification device for the highway bridge precast pile according to claim 1, wherein: die block (1) both sides wall is hollow structure, installs air-blower (15) on die block (1) both sides outer wall, and air-blower (15) are connected with the controller electricity on die block (1) lateral wall, and air-blower (15) play dryer intercommunication die block (1) lateral wall, and die block (1) shaping groove's inner wall upper berth is equipped with the paraffin layer, and evenly is provided with gas pocket (16) on die block (1) shaping groove both sides inner wall, and gas pocket (16) communicate the well cavity of die block (1).
6. The concrete diversion and solidification device for the highway bridge precast pile according to claim 5, wherein: side form (4) laminating die block (1) both ends shaping notch outer wall sets up, be fixed with fixed block (17) on the lateral wall at side form (4) both ends, fixed block (17) are close to and are fixed with L type take pole (18) on the outer wall of die block (1) one side, it is connected with carousel (19) to rotate on die block (1) outer wall of the terminal adjacent department of L type take pole (18), fixedly connected with dog (20) on one side outer wall that carousel (19) are close to L type take pole (18), dog (20) and L type take pole (18) end baffle contact surface parallel arrangement that inclines each other.
7. The road bridge precast pile concrete diversion and solidification device of claim 1, characterized in that: additive unloading ware (10) including sliding sleeve joint sliding sleeve (101) and the hydraulic lifting rod (102) of fixed connection in sliding sleeve (101) top on guide bar (9) outer wall, the riser screw thread of sliding sleeve (101) lower extreme cup joints on the outer wall of lead screw (11), and hydraulic lifting rod (102) top fixedly connected with connecting strip (103), the terminal fixed connection of connecting strip (103) is on the both sides outer wall of liquid storage pot (104), the accelerator has been stored in liquid storage pot (104), and install force pump (105) bottom liquid storage pot (104), force pump (105) input is linked together with liquid storage pot (104), force pump (105) bottom output is connected with catheter (106), catheter (106) run through feedstock channel (7).
8. The road bridge precast pile concrete diversion and solidification device of claim 7, wherein: the outer wall of the liquid guide pipe (106) is fixedly connected with a fixing sleeve (107), the outer walls of the two sides of the fixing sleeve (107) are fixedly connected with machine heads (108), the output end of the bottom of the machine head (108) is fixedly connected with vibrating rods (109), and the vibrating rods (109) are suspended on the two sides of the liquid guide pipe (106) in parallel.
9. The concrete diversion and solidification device for the highway bridge precast pile according to claim 8, wherein: the liquid guide tube is characterized in that sliding grooves (1061) are symmetrically formed in the inner side wall, opposite to the upper side of a port at the bottom of the liquid guide tube (106), an L-shaped hanging rod (1062) is connected in the sliding grooves (1061) in a sliding mode, a blocking head (1063) is fixedly connected to the bottom of the L-shaped hanging rod (1062), the blocking head (1063) is inserted into the liquid guide tube (106), a compression spring (1064) is arranged at the lower end of a transverse plate of the L-shaped hanging rod (1062), the lower end of the compression spring (1064) is fixedly connected to the side wall of the bottom of the sliding groove (1061), liquid outlet holes (1065) are uniformly formed in the side wall of the liquid guide tube (106) at the lower end of the sliding groove (1061), and when the compression spring (1064) normally relaxes, the blocking head (1063) blocks the liquid outlet holes (1065).
10. A method for implementing the road bridge precast pile concrete diversion and solidification device as claimed in any one of claims 1 to 9, wherein: the method comprises the following steps:
s1: sleeving the side templates (4) on the outer wall of the positioning column (3) to enable the side templates (4) to be attached to and plug the end face of a forming groove in the bottom die (1), clamping and fixing a rotary table (19) by using a stop block (20) to clamp an L-shaped lap bar (18), clamping and sleeving one end of a reinforcement cage in a sleeve on the inner wall of the side template (4) on one side far away from the flow guide assembly (5), penetrating the other end of the reinforcement cage through an annular flow guide pipe (55), suspending the reinforcement cage in the forming groove of the bottom die (1) by using the sleeve, and sealing and covering a top die cover plate (6) at the upper end of the bottom die (1);
s2: pulling out a blocking rod (148) at the top of the shell (141), rotating the adjusting rotary rod (142) to drive the winding roll (143) to rotate and wind the pull rope (144), pulling the limiting hook (145) by the pull rope (144) to move and stretch the reset spring (146), and simultaneously clamping the tail end of the limiting hook (145) on the outer wall of the T-shaped positioning rod (13) to finish the fixation of the bottom die (1) and the top die cover plate (6);
s3: starting an electric telescopic rod (53), wherein the electric telescopic rod (53) pushes an annular plate (54) to be attached to the inner wall of a forming groove of a bottom die (1) to move to a side die plate (4) close to the other end of the bottom die (1) so as to form a section of casting space between the annular plate (54) and the side die plate (4), at the moment, concrete is pumped to a cavity of an annular guide pipe (55) by using a concrete conveying pipe (57), the concrete is sprayed out from a concrete spray pipe (56) on the annular guide pipe (55), after the height of the concrete reaches the lower edge of a port of the annular guide pipe (55), the electric telescopic rod (53) is controlled to pull the annular plate (54) to move back, then concrete spraying and filling are carried out in the next section of casting space, and the concrete is filled in sections in such a way;
s4: after the annular plate (54) moves back to the convex column outside of the annular guide pipe (55) clamped and sleeved on the inner wall of the mounting plate (51), continuously injecting filling concrete to the bottom port of the feeding channel (7), after the filling concrete is filled, starting the driving motor (12) to match the screw rod (11) and the sliding sleeve (101) to transfer the liquid storage tank (104) to the side, close to the fixed end of the reinforcement cage, of the feeding channel (7), and lowering the hydraulic lifting rod (102) to enable the liquid guide pipe (106) and the vibrating rod (109) to be inserted into the concrete;
s5: the method comprises the steps of starting a pressure pump (105) to pump an accelerator in a liquid storage tank (104) to a liquid guide pipe (106), pushing a plugging head (1063) to move downwards by the accelerator to overcome the elasticity of a compression spring (1064), so that plugging of a liquid outlet hole (1065) is removed, ejecting the accelerator from the liquid outlet hole (1065) on the side wall of the liquid guide pipe (106) and mixing the accelerator in concrete, starting a machine head (108) when the accelerator is ejected, driving a vibrating rod (109) by the machine head 108 to vibrate the concrete and the accelerator to enable the concrete and the accelerator to be uniformly mixed, controlling a driving motor (12) to rotate reversely to move the liquid storage tank (104) to add the accelerator to subsequent concrete, and removing a mold for maintenance after a pile body is formed.
CN202111326518.0A 2021-11-10 2021-11-10 Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof Active CN113910440B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111326518.0A CN113910440B (en) 2021-11-10 2021-11-10 Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111326518.0A CN113910440B (en) 2021-11-10 2021-11-10 Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof

Publications (2)

Publication Number Publication Date
CN113910440A CN113910440A (en) 2022-01-11
CN113910440B true CN113910440B (en) 2022-10-04

Family

ID=79246052

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111326518.0A Active CN113910440B (en) 2021-11-10 2021-11-10 Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof

Country Status (1)

Country Link
CN (1) CN113910440B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080030373A (en) * 2006-09-30 2008-04-04 방용섭 Apparatus for manufacture of pretensioned spun high strength concrete piles and method for manufacture by using the same
CN108894232A (en) * 2018-07-28 2018-11-27 江苏地基工程有限公司 A kind of concrete precast pile post-grouting device and its forming method and grouting process
CN109624042A (en) * 2018-11-20 2019-04-16 嘉兴市康立德构件有限公司 A kind of pile for prestressed pipe production system
CN111730735A (en) * 2020-07-17 2020-10-02 曹银花 Method for manufacturing prestressed high-strength concrete pipe pile
CN111745777A (en) * 2019-03-28 2020-10-09 周兆弟 Concrete precast pile mould, mould set and manufacturing method
CN111873169A (en) * 2020-08-03 2020-11-03 钱昌杰 Pouring forming process for prestressed precast concrete pipe pile
WO2020256141A1 (en) * 2019-06-20 2020-12-24 株式会社技研製作所 Method and device for producing concrete pile
CN112606197A (en) * 2020-12-31 2021-04-06 陆彬燕 Concrete pipe pile preparation facilities
CN112706279A (en) * 2021-01-29 2021-04-27 李龙洋 Concrete pipe pile pouring device
CN213999932U (en) * 2020-10-26 2021-08-20 周兆弟 Solid prefabricated component production device and prefabricated component quantitative production equipment
CN113414872A (en) * 2021-08-24 2021-09-21 启东霓辉新材料科技有限公司 Mould for producing prestressed concrete corrugated sheet pile

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080030373A (en) * 2006-09-30 2008-04-04 방용섭 Apparatus for manufacture of pretensioned spun high strength concrete piles and method for manufacture by using the same
CN108894232A (en) * 2018-07-28 2018-11-27 江苏地基工程有限公司 A kind of concrete precast pile post-grouting device and its forming method and grouting process
CN109624042A (en) * 2018-11-20 2019-04-16 嘉兴市康立德构件有限公司 A kind of pile for prestressed pipe production system
CN111745777A (en) * 2019-03-28 2020-10-09 周兆弟 Concrete precast pile mould, mould set and manufacturing method
WO2020256141A1 (en) * 2019-06-20 2020-12-24 株式会社技研製作所 Method and device for producing concrete pile
CN111730735A (en) * 2020-07-17 2020-10-02 曹银花 Method for manufacturing prestressed high-strength concrete pipe pile
CN111873169A (en) * 2020-08-03 2020-11-03 钱昌杰 Pouring forming process for prestressed precast concrete pipe pile
CN213999932U (en) * 2020-10-26 2021-08-20 周兆弟 Solid prefabricated component production device and prefabricated component quantitative production equipment
CN112606197A (en) * 2020-12-31 2021-04-06 陆彬燕 Concrete pipe pile preparation facilities
CN112706279A (en) * 2021-01-29 2021-04-27 李龙洋 Concrete pipe pile pouring device
CN113414872A (en) * 2021-08-24 2021-09-21 启东霓辉新材料科技有限公司 Mould for producing prestressed concrete corrugated sheet pile

Also Published As

Publication number Publication date
CN113910440A (en) 2022-01-11

Similar Documents

Publication Publication Date Title
CN104260185B (en) Multifunctional concrete prefabricated components battery mould production equipment and production line
CN103774561B (en) The job execution of speedway prefabricated small box girder frock method streamlined
CN209633297U (en) A kind of mold of precast concrete wall panel
CN110385774B (en) Production device and construction method of bidirectional core-pulling prefabricated hollow anti-seismic wallboard
CN209384639U (en) A kind of impression-taking apparatus applied to house sliding formwork molding machine
CN1850470A (en) Gypsum block continuous production apparatus capable of adjusting thickness
CN106593468B (en) Tunnel inverted arch concrete lining sliding formwork and construction method
CN115319909B (en) Pretensioned prestressing precast pile manufacturing equipment and method
CN200945680Y (en) Steam-press air-entrainment concrete block shock ultrasonic exhausting apparatus
CN113910440B (en) Concrete diversion and solidification device for highway bridge precast pile and implementation method thereof
CN207954201U (en) A kind of pouring molding device of concrete segment
CN113216614B (en) Template structure for pouring constructional column
JP2001514101A (en) Building material panel and method and apparatus for forming building material panel
CN209669811U (en) Dam body seepage wall trolley and its walling mechanism
CN211923547U (en) Concrete placement device for construction
CN109763458A (en) Dam body seepage wall trolley, walling mechanism, dam body seepage wall construction method
CN202592504U (en) Automatic gypsum plate manufacturing device
CN205976531U (en) Novel convenient machine of pouring of constructional column concrete
CN210850767U (en) High-strength cement floor heating board production is with throwing material device
CN212375695U (en) Template system suitable for hollow high pier
CN211054062U (en) Whole wall one shot forming frock of insulating brick that falls is filled out to soil matrix cementation
CN111688000A (en) Forming and cutting method and device for perforated building blocks
CN209533695U (en) A kind of prefabricated hollow square pile system of processing
CN216658377U (en) Precast concrete square pile mould group
CN206706768U (en) City integrated piping lane 3D printer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant