CN113789779A - Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method - Google Patents

Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method Download PDF

Info

Publication number
CN113789779A
CN113789779A CN202111088406.6A CN202111088406A CN113789779A CN 113789779 A CN113789779 A CN 113789779A CN 202111088406 A CN202111088406 A CN 202111088406A CN 113789779 A CN113789779 A CN 113789779A
Authority
CN
China
Prior art keywords
grouting
pile
foundation
pipe
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111088406.6A
Other languages
Chinese (zh)
Other versions
CN113789779B (en
Inventor
刘杰
汪岩松
沈汝康
张兴棚
李庚�
李轩宇
陈子悦
郭建祥
宋瑞
杨浩宇
杜卓兴
谢晓康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Heng'anxing Construction Engineering Co.,Ltd.
Original Assignee
China Three Gorges University CTGU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU filed Critical China Three Gorges University CTGU
Priority to CN202111088406.6A priority Critical patent/CN113789779B/en
Publication of CN113789779A publication Critical patent/CN113789779A/en
Application granted granted Critical
Publication of CN113789779B publication Critical patent/CN113789779B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length

Abstract

The invention provides a pile foundation structure applied to soft soil foundations and coral sand foundations and a construction method, wherein the pile foundation structure comprises a hollow prefabricated multiple cast-in-place pile, the hollow prefabricated multiple cast-in-place pile is prefabricated in a steel hollow mode, a prefabricated pile foundation framework surrounds the whole cement and hollow prefabricated pipes, the cross section of the pile is circular, the radius of the pile is R, a circular bottom pouring hole with the radius of R/10 is reserved in the center of the cross section, and a circular pipe and a side pouring hole with the diameter of R/20 are reserved at a position away from the edge of the cross section; also comprises a straight grouting pipe. This reducible expense cost of pile foundation, easy operation just is convenient for develop the implementation experiment, reduces the quantity of pile foundation, makes the weak soil durable fast, reaches the standard that can be under construction, can solve subsiding of pile foundation and building, is favorable to superstructure firm.

Description

Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method
Technical Field
The invention relates to a pile foundation structure applied to a soft soil foundation and a coral sand foundation and a construction method, and belongs to the technical field of pile foundation construction.
Background
In recent years, a great deal of civil engineering practice has promoted the development of the treatment technology of the soft soil foundation, and among various special soils in China, the soft soil is widely distributed in coastal plains, estuary delta, around lake basin lands and mountain valley lands in China. In the engineering construction of roads, bridges, buildings and the like, the pile foundation is widely applied, but the characteristics of the soft soil foundation cause that the load of the pile foundation cannot be well born, so that the soft soil foundation is firmer and the use of the pile foundation becomes a focus of attention of people. Therefore, how to form a pile foundation having a high strength on a soft soil foundation is a major problem in constructing buildings and road surfaces on a soft soil foundation. The existing problem that the settlement is easy to happen on the soft soil foundation and the coral sand foundation, so that the grouting and grouting are difficult and the cost is too high.
Disclosure of Invention
The invention aims to provide a device and a method for a pile foundation applied to a soft soil foundation and a coral sand foundation, wherein the pile foundation can reduce the cost, is simple to operate and convenient to develop and carry out experiments, reduces the number of the pile foundations, quickly leads the soft soil to be firm, reaches the construction standard, can solve the settlement of the pile foundation and a building, is beneficial to the stability of an upper building, can improve the stability of the pile foundation by combining the friction force of the pile foundation in all aspects, combines the advantages of a friction pile and an end bearing pile, reduces the settlement, has the advantages of reducing the cost, being beneficial to the smooth injection of slurry, achieving the purpose of quick construction, improving the efficiency of the engineering, being beneficial to the subsequent engineering, further improving the construction, increasing the bottom area, reducing the bottom pressure and reducing the settlement.
In order to achieve the technical features, the invention is realized as follows: a pile foundation structure applied to soft soil foundation and coral sand foundation comprises a hollow prefabricated multiple cast-in-place pile, wherein the hollow prefabricated multiple cast-in-place pile is prefabricated in a hollow way by steel, a prefabricated pile foundation framework surrounds the whole cement and hollow prefabricated pipe, the cross section of the pile is circular, the radius of the pile is R, a circular bottom cast-in-place hole with the radius of R/10 is reserved in the center of the cross section, and a circular pipe and a side cast-in-place hole with the diameter of R/20 are reserved at a position away from the edge of the cross section; also comprises a straight grouting pipe.
The side perfusion holes are formed by branch-shaped steel pipes, and the branch-shaped steel pipes are welded with the inclined steel pipes through the vertical steel pipes; the inclined steel pipe is directly communicated with the outside, and a plurality of fork structures are arranged on the inclined steel pipe, so that the integrity of the pile foundation is improved in the grouting process.
The bottom filling hole is composed of an R/10 vertical inner hollow round steel pipe, the bottom of the bottom filling hole is in a circular truncated cone shape and is directly communicated with the bottom of the bottom filling hole and is directly contacted with soft soil, the radius of a cylinder on the circular truncated cone is R/10, and the maximum radius of the bottom of the circular truncated cone is R/5.
The straight slip casting pipe comprises straight tube, two pivots and two iron sheets, thereby vertical circular slip casting straight tube combines the pivot to reach through the angle that manual regulation changed the iron sheet and changes the slip casting area, and the bottom pivot reduces the frictional force with the weak soil, forms a lot of slip casting pipe that can freely change the angle size.
The bottom filling hole is through changing the dynamics increase surface area slip casting many times, and the pipe is taken out the sanitization every time the slip casting is accomplished, and the soft mud compaction of the bottom of being convenient for makes the pile foundation effectively subside, and is constantly crowded densely, and the pipe is taken out every time the slip casting is accomplished, the going on of slip casting next time of being convenient for.
The grouting slurry is expanded cement slurry, surrounding soft soil is effectively squeezed, surrounding soil settlement is reduced, and finally all gaps are filled with expanded cement and are compacted.
A construction method of a pile foundation structure applied to a soft soil foundation and a coral sand foundation comprises the following steps:
aiming at the soft soil foundation:
step 1: the prepared material is as follows: the method comprises the following steps of prefabricating a multi-time cast-in-place pile in a hollow manner, wherein the pile comprises a branch-shaped steel pipe, a straight grouting pipe, three different steel circular pipes and two rotating shafts;
step 2: and (3) formwork support: a central pipeline and a side pipeline are reserved in the pipe, if the cross section of the pile is circular and the diameter of the pile is R, a circular bottom perfusion hole with the radius of R/10 is reserved in the center of the cross section, and a plastic circular pipe and a side perfusion pipe with the diameter of R/20 are reserved at the position 10cm away from the edge of the cross section;
step 3: pouring the pile body: firstly, using cement to pour and solidify the cement in step1, compacting the cement, covering the side grouting holes and the central grouting hole, reducing the injection of the cement into the pipeline, and waiting for the solidification of the pile foundation;
step 4: pile hole: drilling the soil by using a percussion drill, vertically driving the pile foundation into the soil by using a ramming machine, filling the gap of the pile foundation with the soil, and firmly filling the gap;
step 5: debris extraction: pumping out mud in the round hole by using a sand pump, checking whether the mud is pumped out completely and checking whether the mud is blocked, and compacting the bottom;
step 6: side surface symmetrical grouting: symmetrically grouting is carried out, equipment pressure is injected with expansion cement, the number of pipes can be adjusted according to the actual condition, the side pipelines are filled with the expansion cement at one time, and the expansion cement is compacted;
step 7: repeating step5, symmetrically grouting by the step two, performing the next grouting by the same method, completely filling the side grouting pipes, and compacting;
step 8: grouting at the bottom: the bottom grouting hole changes the opening angle of the iron sheet of the straight grouting pipe through the rotating shaft to achieve multiple times of grouting, the opening area of the bottom of the grouting pipe extending into the grouting hole is changed to perform grouting, the pipe is drawn out after each time of grouting, the next grouting is facilitated, and the pipeline is dredged by a pipeline dredging machine after each time of grouting;
step 9: repeating step7 for many times to carry out grouting, changing the opening area of the bottom of the grouting pipe of the grouting hole which stretches into each time, and adjusting the grouting times according to the actual situation;
step 10: backfilling: filling the remaining gaps and continuously compacting.
A construction method of a pile foundation structure applied to a soft soil foundation and a coral sand foundation comprises the following steps:
aiming at coral sand foundation:
step 1: the prepared material is as follows: the method comprises the following steps of (1) prefabricating a branch-shaped steel pipe, a straight grouting pipe, three different steel circular pipes, two rotating shafts, a multiple cast-in-place pile and iron sheets in a hollow manner;
step 1: and (3) formwork support: firstly, reserving a central pipeline and a side pipeline pile in the pipe, wherein the cross section of the pile is circular, the diameter of the pile is R, a circular bottom perfusion hole with the radius of R/10 is reserved in the center of the cross section, and a plastic circular pipe and a side perfusion pipe with the diameter of R/20 are reserved at a position 10cm away from the edge of the cross section;
step 2: pouring the pile body: firstly, using cement to pour and solidify the cement in step1, compacting the cement, covering the side grouting holes and the central grouting hole, reducing the injection of the cement into the pipeline, and waiting for the solidification of the pile foundation;
step 3: pile hole: drilling the soil by using a percussion drill, vertically driving the pile foundation into the soil by using a ramming machine, filling the gap of the pile foundation with the soil, and firmly filling the gap;
step 4: debris extraction: after the pile foundation is driven into, soil enters the pipeline, the soil in the pipeline is pumped out to prevent blockage, the sand in the round hole is pumped out by a sand pump, whether the soil is pumped out and blocked is checked, and the bottom is compacted
Step 5: side surface symmetrical grouting: filling the side pipelines with the expansion cement at one time and filling the side pipelines with the expansion cement at one time through symmetrical grouting and compacting the side pipelines
Step 6: grouting at the bottom: filling a part of the bottom by using a pipeline, then filling the rest base pictures at one time, and drawing out and filling the pipes after filling each time;
step 7: backfilling: filling the remaining gaps and continuously compacting.
The invention has the following beneficial effects:
1. the hollow pipeline formwork is manufactured, so that a hollow pile foundation is convenient to form, a grouting space is reserved for the pile foundation, subsequent grouting is convenient, and multiple times of grouting can be implemented.
2. The purpose of multiple times of grouting is achieved by adjusting the opening size of the iron sheet through the rotating shaft device, the surface area is increased, the pressure is reduced, the bottom soil is extruded and firmed for multiple times, the settlement is reduced, the bottom is firmer, and the building is easier to support.
3. The expansion cement mortar is injected for many times, so that the deformation of the soft soil is large, and the stability of the soft soil can not be ensured by one-time grouting, so that the soft soil can be stabilized again on the basis of one-time grouting by using the multiple-time grouting, and the effect of strengthening the hardness of the deep soft soil is achieved.
4. The soft soil is more compacted by grouting around the pile foundation, the gaps are reduced, the soft soil and the surrounding soil form a whole, the surrounding extrusion solidification increases the friction force, and the settlement is reduced
5. During grouting, the shape design in the side reserved pipe meets the gravity condition, so that the grouting operation is facilitated, the rapid grouting is facilitated, and the efficiency is improved.
6. Through changing different area at every turn and slip casting to the bottom many times, slip casting many times can make the bottom constantly extrude durable, makes the abundant earth with the bottom of inflation cement combine to form a whole, reduces and subsides.
7. And the lateral grouting pipes are symmetrically used for grouting, so that the stress of the pile foundation is balanced, the inclination of the pile foundation is reduced, and the subsequent implementation of grouting is facilitated.
8. The gap is filled, so that the toughness of the pile foundation is improved, the pile foundation can be used in various fields, unnecessary waste caused by settlement is reduced, and subsequent work of the foundation can be conveniently carried out
9. The design of side slip casting pipe can carry out the slip casting through different injected holes, need not consider whether it plugs up the slip casting pipeline.
10. The design of side slip casting hole is many forks structure, can improve the wholeness of whole pile foundation when making the slip casting.
11. The pile foundation does not need to be driven into the ground at one time, and sinks by utilizing the lifting of the self gravity after multiple times of grouting, and the bearing capacity and the friction force of the pile foundation are continuously improved by the method.
Drawings
The invention is further illustrated by the following figures and examples.
Fig. 1 is a hollow prefabricated multiple cast-in-place pile of the invention.
Fig. 2 shows the pile of the present invention after casting.
FIG. 3 is a dendritic steel pipe of the present invention.
Fig. 4 is a top view of the pile foundation of the present invention.
Fig. 5 is a front view of the straight grout pipe of the present invention.
Fig. 6 is a side view of a straight grout pipe of the present invention.
Detailed Description
Embodiments of the present invention will be further described with reference to the accompanying drawings.
Example 1:
referring to fig. 1-6, a pile foundation structure for soft soil foundation and coral sand foundation, its characterized in that: the pile comprises a hollow prefabricated multiple cast-in-place pile 5, wherein the hollow prefabricated multiple cast-in-place pile 5 is prefabricated in a hollow way by steel, a prefabricated pile foundation framework surrounds the whole cement and hollow prefabricated pipes, the cross section of the pile is circular, the radius of the pile is R, a circular bottom cast-in-place hole with the radius of R/10 is reserved in the center of the cross section, and a circular pipe 3 and a side cast-in-place hole with the diameter of R/20 are reserved at a position away from the edge of the cross section; a straight grouting pipe 2 is also included.
Further, the side perfusion holes are composed of dendritic steel pipes 1, and the dendritic steel pipes 1 are welded with the inclined steel pipes through vertical steel pipes; the inclined steel pipe is directly communicated with the outside, and a plurality of fork structures are arranged on the inclined steel pipe, so that the integrity of the pile foundation is improved in the grouting process.
Furthermore, the bottom filling hole is composed of an R/10 vertical inner hollow round steel pipe, the bottom of the bottom filling hole is in a circular truncated cone shape and is directly communicated with the bottom of the bottom filling hole and directly contacted with soft soil, the radius of a cylinder on the circular truncated cone is R/10, and the maximum radius of the bottom of the circular truncated cone is R/5.
Further, straight slip casting pipe 2 comprises straight tube, two pivots 4 and two iron sheets 6, thereby vertical circular slip casting straight tube combines the pivot to reach through the angle that manual regulation changed the iron sheet and changes the slip casting area, and the bottom pivot reduces the frictional force with the weak soil, forms a lot of slip casting pipe that can freely change the angle size.
Furthermore, the bottom filling hole is through changing the dynamics increase surface area slip casting many times, and the pipe is taken out the sanitization after the slip casting at every turn, and the soft mud of the bottom of being convenient for is crowded densely, makes the pile foundation effectively subside, and is constantly crowded densely, and the pipe is taken out after the slip casting at every turn, the going on of slip casting next time of being convenient for.
Furthermore, the grouting slurry is expanded cement slurry, surrounding soft soil is effectively squeezed, surrounding soil settlement is reduced, and finally all gaps are filled with the expanded cement and are compacted.
Example 2:
a construction method of a pile foundation structure applied to a soft soil foundation and a coral sand foundation comprises the following steps:
aiming at the soft soil foundation:
step 1: the prepared material is as follows: the method comprises the following steps that (1) a branch-shaped steel pipe, a straight grouting pipe 2, three different steel circular pipes, two rotating shafts and a hollow prefabricated multiple cast-in-place pile 5 are arranged;
step 2: and (3) formwork support: a central pipeline and a side pipeline are reserved in the pipe, if the cross section of the pile is circular and the diameter of the pile is R, a circular bottom perfusion hole with the radius of R/10 is reserved in the center of the cross section, and a plastic circular pipe and a side perfusion pipe with the diameter of R/20 are reserved at the position 10cm away from the edge of the cross section;
step 3: pouring the pile body: firstly, using cement to pour and solidify the cement in step1, compacting the cement, covering the side grouting holes and the central grouting hole, reducing the injection of the cement into the pipeline, and waiting for the solidification of the pile foundation;
step 4: pile hole: drilling the soil by using a percussion drill, vertically driving the pile foundation into the soil by using a ramming machine, filling the gap of the pile foundation with the soil, and firmly filling the gap;
step 5: debris extraction: pumping out mud in the round hole by using a sand pump, checking whether the mud is pumped out completely and checking whether the mud is blocked, and compacting the bottom;
step 6: side surface symmetrical grouting: symmetrically grouting is carried out, equipment pressure is injected with expansion cement, the number of pipes can be adjusted according to the actual condition, the side pipelines are filled with the expansion cement at one time, and the expansion cement is compacted;
step 7: repeating step5, symmetrically grouting by the step two, performing the next grouting by the same method, completely filling the side grouting pipes, and compacting;
step 8: grouting at the bottom: the bottom grouting hole changes the opening angle of the iron sheet of the straight grouting pipe through the rotating shaft to achieve multiple times of grouting, the opening area of the bottom of the grouting pipe extending into the grouting hole is changed to perform grouting, the pipe is drawn out after each time of grouting, the next grouting is facilitated, and the pipeline is dredged by a pipeline dredging machine after each time of grouting;
step 9: repeating step7 for many times to carry out grouting, changing the opening area of the bottom of the grouting pipe of the grouting hole which stretches into each time, and adjusting the grouting times according to the actual situation;
step 10: backfilling: filling the remaining gaps and continuously compacting.
Example 3:
a construction method of a pile foundation structure applied to a soft soil foundation and a coral sand foundation comprises the following steps:
aiming at coral sand foundation:
step 1: the prepared material is as follows: the method comprises the following steps of (1) prefabricating a branch-shaped steel pipe, a straight grouting pipe, three different steel circular pipes, two rotating shafts, a multiple cast-in-place pile and iron sheets in a hollow manner;
step 1: and (3) formwork support: firstly, reserving a central pipeline and a side pipeline pile in the pipe, wherein the cross section of the pile is circular, the diameter of the pile is R, a circular bottom perfusion hole with the radius of R/10 is reserved in the center of the cross section, and a plastic circular pipe and a side perfusion pipe with the diameter of R/20 are reserved at a position 10cm away from the edge of the cross section;
step 2: pouring the pile body: firstly, using cement to pour and solidify the cement in step1, compacting the cement, covering the side grouting holes and the central grouting hole, reducing the injection of the cement into the pipeline, and waiting for the solidification of the pile foundation;
step 3: pile hole: drilling the soil by using a percussion drill, vertically driving the pile foundation into the soil by using a ramming machine, filling the gap of the pile foundation with the soil, and firmly filling the gap;
step 4: debris extraction: after the pile foundation is driven into, soil enters the pipeline, the soil in the pipeline is pumped out to prevent blockage, the sand in the round hole is pumped out by a sand pump, whether the soil is pumped out and blocked is checked, and the bottom is compacted
Step 5: side surface symmetrical grouting: filling the side pipelines with the expansion cement at one time and filling the side pipelines with the expansion cement at one time through symmetrical grouting and compacting the side pipelines
Step 6: grouting at the bottom: filling a part of the bottom by using a pipeline, then filling the rest base pictures at one time, and drawing out and filling the pipes after filling each time;
step 7: backfilling: filling the remaining gaps and continuously compacting.

Claims (8)

1. The utility model provides a be applied to pile foundation structure of soft soil foundation and coral sand foundation which characterized in that: the prefabricated hollow multi-cast-in-place pile comprises a hollow prefabricated multi-cast-in-place pile (5), wherein the hollow prefabricated multi-cast-in-place pile (5) is prefabricated in a steel hollow mode, a prefabricated pile foundation framework surrounds the whole cement and hollow prefabricated pipes, the cross section of the pile is circular, the radius of the pile is R, a circular bottom cast-in-place hole with the radius of R/10 is reserved in the center of the cross section, and a circular pipe (3) and a side cast-in-place hole with the diameter of R/20 are reserved at a position away from the edge of the cross section; also comprises a straight grouting pipe (2).
2. The pile foundation structure applied to the soft soil foundation and the coral sand foundation of claim 1, wherein: the side perfusion holes are formed by branch-shaped steel pipes (1), and the branch-shaped steel pipes (1) are welded with the inclined steel pipes through vertical steel pipes; the inclined steel pipe is directly communicated with the outside, and a plurality of fork structures are arranged on the inclined steel pipe, so that the integrity of the pile foundation is improved in the grouting process.
3. The pile foundation structure applied to the soft soil foundation and the coral sand foundation of claim 1, wherein: the bottom filling hole is composed of an R/10 vertical inner hollow round steel pipe, the bottom of the bottom filling hole is in a circular truncated cone shape and is directly communicated with the bottom of the bottom filling hole and is directly contacted with soft soil, the radius of a cylinder on the circular truncated cone is R/10, and the maximum radius of the bottom of the circular truncated cone is R/5.
4. The pile foundation structure applied to the soft soil foundation and the coral sand foundation of claim 1, wherein: the straight grouting pipe (2) is composed of a straight pipe, two rotating shafts (4) and two iron sheets (6), the vertical round grouting straight pipe is combined with the rotating shaft, the angle of the iron sheets can be changed through manual adjustment, so that the grouting area can be changed, the rotating shaft at the bottom reduces the friction force with soft soil, and a plurality of grouting pipes capable of freely changing the angle are formed.
5. The pile foundation structure applied to the soft soil foundation and the coral sand foundation of claim 1, wherein: the bottom filling hole is through changing the dynamics increase surface area slip casting many times, and the pipe is taken out the sanitization every time the slip casting is accomplished, and the soft mud compaction of the bottom of being convenient for makes the pile foundation effectively subside, and is constantly crowded densely, and the pipe is taken out every time the slip casting is accomplished, the going on of slip casting next time of being convenient for.
6. The pile foundation structure applied to the soft soil foundation and the coral sand foundation of claim 1, wherein: the grouting slurry is expanded cement slurry, surrounding soft soil is effectively squeezed, surrounding soil settlement is reduced, and finally all gaps are filled with expanded cement and are compacted.
7. The method for constructing a pile foundation structure for a soft soil foundation and a coral sand foundation as claimed in any one of claims 1 to 6, comprising the steps of:
aiming at the soft soil foundation:
step 1: the prepared material is as follows: the system comprises a branch-shaped steel pipe (1), a straight grouting pipe (2), three different steel circular pipes, two rotating shafts and a hollow prefabricated multiple cast-in-place pile (5);
step 2: and (3) formwork support: a central pipeline and a side pipeline are reserved in the pipe, if the cross section of the pile is circular and the diameter of the pile is R, a circular bottom perfusion hole with the radius of R/10 is reserved in the center of the cross section, and a plastic circular pipe and a side perfusion pipe with the diameter of R/20 are reserved at the position 10cm away from the edge of the cross section;
step 3: pouring the pile body: firstly, using cement to pour and solidify the cement in step1, compacting the cement, covering the side grouting holes and the central grouting hole, reducing the injection of the cement into the pipeline, and waiting for the solidification of the pile foundation;
step 4: pile hole: drilling the soil by using a percussion drill, vertically driving the pile foundation into the soil by using a ramming machine, filling the gap of the pile foundation with the soil, and firmly filling the gap;
step 5: debris extraction: pumping out mud in the round hole by using a sand pump, checking whether the mud is pumped out completely and checking whether the mud is blocked, and compacting the bottom;
step 6: side surface symmetrical grouting: symmetrically grouting is carried out, equipment pressure is injected with expansion cement, the number of pipes can be adjusted according to the actual condition, the side pipelines are filled with the expansion cement at one time, and the expansion cement is compacted;
step 7: repeating step5, symmetrically grouting by the step two, performing the next grouting by the same method, completely filling the side grouting pipes, and compacting;
step 8: grouting at the bottom: the bottom grouting hole changes the opening angle of the iron sheet of the straight grouting pipe through the rotating shaft to achieve multiple times of grouting, the opening area of the bottom of the grouting pipe extending into the grouting hole is changed to perform grouting, the pipe is drawn out after each time of grouting, the next grouting is facilitated, and the pipeline is dredged by a pipeline dredging machine after each time of grouting;
step 9: repeating step7 for many times to carry out grouting, changing the opening area of the bottom of the grouting pipe of the grouting hole which stretches into each time, and adjusting the grouting times according to the actual situation;
step 10: backfilling: filling the remaining gaps and continuously compacting.
8. The method for constructing a pile foundation structure for a soft soil foundation and a coral sand foundation as claimed in any one of claims 1 to 6, comprising the steps of:
aiming at coral sand foundation:
step 1: the prepared material is as follows: the method comprises the following steps of (1) prefabricating a branch-shaped steel pipe, a straight grouting pipe, three different steel circular pipes, two rotating shafts, a multiple cast-in-place pile and iron sheets in a hollow manner;
step 1: and (3) formwork support: firstly, reserving a central pipeline and a side pipeline pile in the pipe, wherein the cross section of the pile is circular, the diameter of the pile is R, a circular bottom perfusion hole with the radius of R/10 is reserved in the center of the cross section, and a plastic circular pipe and a side perfusion pipe with the diameter of R/20 are reserved at a position 10cm away from the edge of the cross section;
step 2: pouring the pile body: firstly, using cement to pour and solidify the cement in step1, compacting the cement, covering the side grouting holes and the central grouting hole, reducing the injection of the cement into the pipeline, and waiting for the solidification of the pile foundation;
step 3: pile hole: drilling the soil by using a percussion drill, vertically driving the pile foundation into the soil by using a ramming machine, filling the gap of the pile foundation with the soil, and firmly filling the gap;
step 4: debris extraction: after the pile foundation is driven into, soil enters the pipeline, the soil in the pipeline is pumped out to prevent blockage, the sand in the round hole is pumped out by a sand pump, whether the soil is pumped out and blocked is checked, and the bottom is compacted
Step 5: side surface symmetrical grouting: filling the side pipelines with the expansion cement at one time and filling the side pipelines with the expansion cement at one time through symmetrical grouting and compacting the side pipelines
Step 6: grouting at the bottom: filling a part of the bottom by using a pipeline, then filling the rest base pictures at one time, and drawing out and filling the pipes after filling each time;
step 7: backfilling: filling the remaining gaps and continuously compacting.
CN202111088406.6A 2021-09-16 2021-09-16 Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method Active CN113789779B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111088406.6A CN113789779B (en) 2021-09-16 2021-09-16 Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111088406.6A CN113789779B (en) 2021-09-16 2021-09-16 Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method

Publications (2)

Publication Number Publication Date
CN113789779A true CN113789779A (en) 2021-12-14
CN113789779B CN113789779B (en) 2022-08-30

Family

ID=78878747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111088406.6A Active CN113789779B (en) 2021-09-16 2021-09-16 Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method

Country Status (1)

Country Link
CN (1) CN113789779B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457833A (en) * 2022-02-21 2022-05-10 三峡大学 Pile foundation structure capable of being strengthened on coral sand and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB669661A (en) * 1949-08-12 1952-04-09 Harold Franklin Rosevear Improvements relating to concrete piles
CN107338804A (en) * 2017-06-13 2017-11-10 安徽建工集团有限公司 A kind of hollow independent composite pile foundation of super-large diameter and its method of construction
CN110318390A (en) * 2019-08-05 2019-10-11 沈阳建筑大学 Prefabricated grouting behind shaft or drift lining bamboo joint pile and its construction method
CN211640425U (en) * 2019-12-09 2020-10-09 中煤建工集团有限公司 Thixotropic slurry grouting structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB669661A (en) * 1949-08-12 1952-04-09 Harold Franklin Rosevear Improvements relating to concrete piles
CN107338804A (en) * 2017-06-13 2017-11-10 安徽建工集团有限公司 A kind of hollow independent composite pile foundation of super-large diameter and its method of construction
CN110318390A (en) * 2019-08-05 2019-10-11 沈阳建筑大学 Prefabricated grouting behind shaft or drift lining bamboo joint pile and its construction method
CN211640425U (en) * 2019-12-09 2020-10-09 中煤建工集团有限公司 Thixotropic slurry grouting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457833A (en) * 2022-02-21 2022-05-10 三峡大学 Pile foundation structure capable of being strengthened on coral sand and method
CN114457833B (en) * 2022-02-21 2024-03-12 三峡大学 Pile foundation structure capable of being reinforced on coral sand and method

Also Published As

Publication number Publication date
CN113789779B (en) 2022-08-30

Similar Documents

Publication Publication Date Title
CN103184734B (en) A kind of construction method implanting slip casting compound pile
CN102493437B (en) Grouting-type micro steel pipe pile and grouting reinforcement method
CN104131555B (en) A kind of outsourcing water penetration concrete reinforced pipe crushed stone grouting pile and construction method thereof
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN103510510B (en) A kind of enhancement mode long auger cast-with-pressure concrete pile and construction method
CN101812976B (en) Adjustable multiple coil extruding and expanding drilling tool
CN103556628B (en) Spiral conical soil compaction pile construction method
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN203213101U (en) Embedding grouting combined pile
CN113789779B (en) Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method
CN1206419C (en) Combined rock-embedding pile and its construction method
CN1341795A (en) Variable supporting-plate club-footed embedded pile and its forming method
CN107700480B (en) Concrete pile suitable for foundation treatment
CN101793027B (en) Core-grouted static pressure anchor rod pile
CN111254909B (en) Construction process of composite pile foundation of soft soil area foundation
CN1182301C (en) Technology for boring and prefabricating cast piles for foundation of building
CN103334428B (en) Disc type cast-in-place concrete pile and construction process for same
CN105672329B (en) The large size prefabricated building enclosure of deep basal pit and construction method
CN103741682B (en) The construction method of a kind of carbon fiber cloth bag cast-in-place antiarch surface composition shaped pile
CN113863294B (en) PHC pipe pile internally provided with pile end grouting device and construction process thereof
CN106149709B (en) The pile making method of pre-poured stake
CN210086328U (en) Root pile for underpinning and reinforcing existing building foundation
CN202124857U (en) Splitting pile
CN205276261U (en) Zero friction stake becomes pilework
CN104727305A (en) Drilling and high-pressure grouting construction method for uplift pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230807

Address after: Room 307, 1-3/F, Building B15-1, Block B, Huading Printing and Packaging Industrial Park, Industrial Avenue, Shamao Street Economic Development Zone, Hannan District, Wuhan City, Hubei Province, 430090

Patentee after: Hubei Heng'anxing Construction Engineering Co.,Ltd.

Address before: 443002 No. 8, University Road, Xiling District, Yichang, Hubei

Patentee before: CHINA THREE GORGES University

TR01 Transfer of patent right