CN113756396A - Self-induction pressurization pumping pipe conveying system - Google Patents

Self-induction pressurization pumping pipe conveying system Download PDF

Info

Publication number
CN113756396A
CN113756396A CN202111129668.2A CN202111129668A CN113756396A CN 113756396 A CN113756396 A CN 113756396A CN 202111129668 A CN202111129668 A CN 202111129668A CN 113756396 A CN113756396 A CN 113756396A
Authority
CN
China
Prior art keywords
water
pressure
information
time
water consumption
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111129668.2A
Other languages
Chinese (zh)
Other versions
CN113756396B (en
Inventor
朱贝贝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202111129668.2A priority Critical patent/CN113756396B/en
Publication of CN113756396A publication Critical patent/CN113756396A/en
Application granted granted Critical
Publication of CN113756396B publication Critical patent/CN113756396B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons or valves, in the pipe systems
    • E03B7/075Arrangement of devices for control of pressure or flow rate
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons or valves, in the pipe systems
    • E03B7/072Arrangement of flowmeters
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons or valves, in the pipe systems
    • E03B7/078Combined units with different devices; Arrangement of different devices with respect to each other

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Control Of Positive-Displacement Pumps (AREA)

Abstract

The invention relates to a self-induction pressurization pumping pipe conveying system. Carry out correlation analysis with water consumption information and precipitation information, temperature information, real-time power consumption information, carry out the pressurization regulation of force (forcing) pump according to the result of analysis to realize the accurate regulation and the control of supplying water, both can prevent to lead to because the water pressure that supplies water when adjusting untimely excessively or too high, can avoid the delivery pipe pressure that long-time high pressure water supply leads to too big again, the life-span of the delivery pipe of extension. The two-stage booster pump is arranged, the water pressure of each building can be independently adjusted by combining the actual water consumption under the condition that the water supply pressure is roughly adjusted according to the climate information, and the safety and accurate adjustment of water use are guaranteed.

Description

Self-induction pressurization pumping pipe conveying system
Technical Field
The invention relates to the field of water supply regulation, in particular to a self-induction pressurization pumping pipe system.
Background
In the resident's water, what influence the water consumption the biggest is clean water, is used for the water of aspects such as bathing, laundry promptly, and when concurrent a large amount of water, water pressure can reduce, if not in time carry out the pressure boost to water this moment can lead to water pressure to reduce very greatly, influence the user and use. The existing method generally directly increases water to a larger water pressure, but the disadvantage of this is that on one hand, the safety risk of the pipeline is increased due to the excessive water pressure, and on the other hand, energy waste is caused. There are also systems that detect the current water pressure in real time and then adjust the pumping power based on the water pressure, but because there is a distance between the user and the pumping location, there is some hysteresis in the pumping mode, i.e. the user will still feel the water pressure is unstable.
Research shows that the amount of clean water is actually related to the current precipitation and temperature, so that some adjustment can be performed on the water pressure by acquiring some climate information; in addition, because the current cleaning can not be carried out without the electric appliance, the power consumption is also related to the water consumption, so that a correlation can be carried out with the power consumption so as to adjust the water pressure;
based on the invention, a water pressure regulating system related to weather conditions, power consumption conditions and real-time water consumption is established.
Disclosure of Invention
In view of the above, to solve the above problems, a self-induction pressurization pump pipe system is provided, which includes a main control module, a model calculation module, an information acquisition module, a flow detection module, a pressure detection module, and a pressurization pump module;
the model calculation module, the information acquisition module, the flow detection module, the pressure detection module and the pressure pump module are all connected to the main control module;
the pressurizing pump module is arranged on the water supply pipeline, is used for controlling the pressure of the water supply pipeline and pressurizing the water supply pipeline and comprises a primary pressurizing pump and a secondary pressurizing pump, wherein the primary pressurizing pump is arranged on the water supply main pipeline, and the secondary pressurizing pump is arranged on a water supply branch corresponding to each building;
the pressure detection module is used for detecting the water pressure in front of the primary booster pump and the secondary booster pump and sending the detected water pressure in front of the pump to the main control module;
the flow detection module is used for detecting the real-time water consumption and sending the real-time water consumption to the main control module;
the information acquisition module is used for acquiring information influencing water consumption, including precipitation information, temperature information and real-time power utilization information, and sending the collected precipitation information, temperature information and real-time power utilization information to the main control module;
the main control module sends precipitation information, temperature information, real-time electricity information, water pressure before pumping and water consumption in time to the model calculation module, the water pressure calculation model is arranged in the model calculation module, and the precipitation information, the temperature information, the real-time electricity information, the water pressure before pumping and the water consumption in time are used for obtaining the pressurizing power of the first-stage pressurizing pump and the pressurizing power of the second-stage pressurizing pump.
The flow detection module comprises a flow detection controller, a wireless communication module, an abnormity alarm module and a detection terminal;
the detection terminal is arranged on a water supply pipeline of each user and used for collecting the real-time water consumption of each user and sending data to the detection controller;
each terminal corresponds to a unique code in the flow detection controller;
the wireless communication module is used for sending the collected real-time water consumption to the main control module;
the abnormity alarm module is used for sending out a leakage alarm when the continuous water consumption of a certain terminal obviously exceeds a threshold value.
The primary pressure pump is used for providing integral pressurization for the main pipeline, and the secondary pressure pump is used for providing fine pressurization for water supply of each building;
the water pressure before the pump of the primary booster pump is P1, and the water pressure after the pump is P2; the water pressure before the pump of the secondary booster pump is P3, and the water pressure after the pump is P4;
the total real-time water consumption detected by the flow detection module is V1, and the total real-time water consumption of all users corresponding to a single building is V2;
the rainfall probability corresponding to the rainfall information is k, the temperature corresponding to the temperature information is T, and the power consumption corresponding to the real-time power consumption information is C;
therefore, P1 corresponds to the initial water pressure of the water supply, P2 corresponds to the pressure to which the primary pressure pump needs to be increased, and the pressure power needed by the primary pressure pump can be calculated through P1 and P2; p3 corresponds to the initial water pressure of a single building, P4 corresponds to the pressure to which the secondary booster pump needs to be increased, and the required boosting power of the secondary booster pump can be calculated through P3 and P4;
a correlation coefficient model is prestored in the model calculation module and is respectively a precipitation correlation coefficient model, an air temperature correlation coefficient model, an electricity consumption correlation coefficient model and a time correlation coefficient model;
the model of the precipitation correlation coefficient is a corresponding change curve of the daily water consumption under the condition of different precipitation probabilities k, namely the daily water consumption can be obtained by inputting the precipitation probabilities k;
the temperature correlation coefficient model is a change curve of the water consumption of the corresponding day under the condition of different temperatures T, namely the water consumption of the day can be obtained by inputting the temperatures T;
the power consumption correlation coefficient model is a corresponding real-time water consumption change curve under the condition of different power consumption C, namely the real-time water consumption can be obtained by inputting the power consumption C;
the time correlation coefficient model is a change curve of the corresponding real-time water consumption at different moments, namely the real-time water consumption can be obtained by inputting the time t;
the calculation method of P2 is P2= P1 · (f (k)/f (k0)) · (g (T)/g (T0)) · (V1/V0);
wherein f (k)/f (k0) represents the water pressure proportion required to be adjusted when the precipitation probability is changed from k0 to k, g (T)/g (T0) represents the water pressure proportion required to be adjusted when the air temperature is changed from T0 to T, f (k0) represents the precipitation probability corresponding to P1, and g (T0) represents the air temperature corresponding to P1; specific expressions of f () and g () are obtained by an empirical model, V0 represents the allowable water consumption without pressurization when the initial water pressure is P1, and the allowable water consumption does not influence the water consumption used by a user;
the calculation method of P4 is P4= P3 (h (C)/h (C0)) (s (t)/s (t0)) (V2/V3);
wherein h (C)/h (C0) represents the proportion of the water pressure required to be regulated when the electricity consumption is changed from C0 to C, s (t)/s (t0) represents the proportion of the water pressure required to be regulated when the time is changed from t0 to t, C0 represents the electricity consumption corresponding to P3, and t0 represents the time corresponding to P3; the concrete expressions of h () and s () are obtained by an empirical model, and V3 represents the allowable water consumption when the building water pressure is P3 without pressurization, and the allowable water consumption does not influence the water consumption used by a user.
Before the model is set in the model calculation module, all water consumption information, precipitation information, temperature information and real-time electricity utilization information for at least 3 months need to be counted; then, carrying out correlation analysis on the water consumption information, the rainfall information, the temperature information and the real-time power utilization information, averaging all water consumption corresponding to the same rainfall probability, and then drawing a relation curve between the rainfall probability and the water consumption; averaging all water consumption corresponding to the same air temperature, and then drawing a relation curve of the air temperature and the water consumption; averaging all water consumption corresponding to the same power consumption in any one hour every day, and then drawing a relation curve of the power consumption and the water consumption; and then segmenting the time of each day according to 5 minutes, calculating the average value of the water consumption in each time period, and drawing a relation curve of the time and the water consumption to obtain the required models.
The invention has the beneficial effects that:
according to the invention, correlation analysis is carried out on the water consumption information, the precipitation information, the air temperature information and the real-time power utilization information, and the pressurization adjustment of the pressurization pump is carried out according to the analysis result, so that the accurate adjustment and control of water supply are realized, the too low or too high water pressure caused by untimely water supply adjustment can be prevented, the too high pressure of a water supply pipe caused by long-time high-pressure water supply can be avoided, and the service life of the water supply pipe is prolonged.
The two-stage booster pump is arranged, the water pressure of each building can be independently adjusted by combining the actual water consumption under the condition that the water supply pressure is roughly adjusted according to the climate information, and the safety and accurate adjustment of water use are guaranteed.
Drawings
The accompanying drawings, which are included to provide a further understanding of the disclosed subject matter, are incorporated in and constitute a part of this specification. The drawings illustrate the implementations of the disclosed subject matter and, together with the detailed description, serve to explain the principles of implementations of the disclosed subject matter. No attempt is made to show structural details of the disclosed subject matter in more detail than is necessary for a fundamental understanding of the disclosed subject matter and various modes of practicing the same.
FIG. 1 is a schematic diagram of the overall architecture of the present invention;
FIG. 2 is a schematic diagram of the water consumption detecting module according to the present invention.
Detailed Description
The advantages, features and methods of accomplishing the same will become apparent from the drawings and the detailed description that follows.
Example (b): a self-induction pressure pumping pipe conveying system comprises a main control module, a model calculation module, an information acquisition module, a flow detection module, a pressure detection module and a pressure pump module;
the model calculation module, the information acquisition module, the flow detection module, the pressure detection module and the pressure pump module are all connected to the main control module;
the pressurizing pump module is arranged on the water supply pipeline, is used for controlling the pressure of the water supply pipeline and pressurizing the water supply pipeline and comprises a primary pressurizing pump and a secondary pressurizing pump, wherein the primary pressurizing pump is arranged on the water supply main pipeline, and the secondary pressurizing pump is arranged on a water supply branch corresponding to each building;
the pressure detection module is used for detecting the water pressure in front of the primary booster pump and the secondary booster pump and sending the detected water pressure in front of the pump to the main control module;
the flow detection module is used for detecting the real-time water consumption and sending the real-time water consumption to the main control module;
the information acquisition module is used for acquiring information influencing water consumption, including precipitation information, temperature information and real-time power utilization information, and sending the collected precipitation information, temperature information and real-time power utilization information to the main control module;
the main control module sends precipitation information, temperature information, real-time electricity information, water pressure before pumping and water consumption in time to the model calculation module, the water pressure calculation model is arranged in the model calculation module, and the precipitation information, the temperature information, the real-time electricity information, the water pressure before pumping and the water consumption in time are used for obtaining the pressurizing power of the first-stage pressurizing pump and the pressurizing power of the second-stage pressurizing pump.
The flow detection module comprises a flow detection controller, a wireless communication module, an abnormity alarm module and a detection terminal;
the detection terminal is arranged on a water supply pipeline of each user and used for collecting the real-time water consumption of each user and sending data to the detection controller;
each terminal corresponds to a unique code in the flow detection controller;
the wireless communication module is used for sending the collected real-time water consumption to the main control module;
the abnormity alarm module is used for sending out a leakage alarm when the continuous water consumption of a certain terminal obviously exceeds a threshold value.
The primary pressure pump is used for providing integral pressurization for the main pipeline, and the secondary pressure pump is used for providing fine pressurization for water supply of each building;
the water pressure before the pump of the primary booster pump is P1, and the water pressure after the pump is P2; the water pressure before the pump of the secondary booster pump is P3, and the water pressure after the pump is P4;
the total real-time water consumption detected by the flow detection module is V1, and the total real-time water consumption of all users corresponding to a single building is V2;
the rainfall probability corresponding to the rainfall information is k, the temperature corresponding to the temperature information is T, and the power consumption corresponding to the real-time power consumption information is C;
therefore, P1 corresponds to the initial water pressure of the water supply, P2 corresponds to the pressure to which the primary pressure pump needs to be increased, and the pressure power needed by the primary pressure pump can be calculated through P1 and P2; p3 corresponds to the initial water pressure of a single building, P4 corresponds to the pressure to which the secondary booster pump needs to be increased, and the required boosting power of the secondary booster pump can be calculated through P3 and P4;
a correlation coefficient model is prestored in the model calculation module and is respectively a precipitation correlation coefficient model, an air temperature correlation coefficient model, an electricity consumption correlation coefficient model and a time correlation coefficient model;
the model of the precipitation correlation coefficient is a corresponding change curve of the daily water consumption under the condition of different precipitation probabilities k, namely the daily water consumption can be obtained by inputting the precipitation probabilities k;
the temperature correlation coefficient model is a change curve of the water consumption of the corresponding day under the condition of different temperatures T, namely the water consumption of the day can be obtained by inputting the temperatures T;
the power consumption correlation coefficient model is a corresponding real-time water consumption change curve under the condition of different power consumption C, namely the real-time water consumption can be obtained by inputting the power consumption C;
the time correlation coefficient model is a change curve of the corresponding real-time water consumption at different moments, namely the real-time water consumption can be obtained by inputting the time t;
the calculation method of P2 is P2= P1 · (f (k)/f (k0)) · (g (T)/g (T0)) · (V1/V0);
wherein f (k)/f (k0) represents the water pressure proportion required to be adjusted when the precipitation probability is changed from k0 to k, g (T)/g (T0) represents the water pressure proportion required to be adjusted when the air temperature is changed from T0 to T, f (k0) represents the precipitation probability corresponding to P1, and g (T0) represents the air temperature corresponding to P1; specific expressions of f () and g () are obtained by an empirical model, V0 represents the allowable water consumption without pressurization when the initial water pressure is P1, and the allowable water consumption does not influence the water consumption used by a user;
the calculation method of P4 is P4= P3 (h (C)/h (C0)) (s (t)/s (t0)) (V2/V3);
wherein h (C)/h (C0) represents the proportion of the water pressure required to be regulated when the electricity consumption is changed from C0 to C, s (t)/s (t0) represents the proportion of the water pressure required to be regulated when the time is changed from t0 to t, C0 represents the electricity consumption corresponding to P3, and t0 represents the time corresponding to P3; the concrete expressions of h () and s () are obtained by an empirical model, and V3 represents the allowable water consumption when the building water pressure is P3 without pressurization, and the allowable water consumption does not influence the water consumption used by a user.
Before the model is set in the model calculation module, all water consumption information, precipitation information, temperature information and real-time electricity utilization information for at least 3 months need to be counted; then, carrying out correlation analysis on the water consumption information, the rainfall information, the temperature information and the real-time power utilization information, averaging all water consumption corresponding to the same rainfall probability, and then drawing a relation curve between the rainfall probability and the water consumption; averaging all water consumption corresponding to the same air temperature, and then drawing a relation curve of the air temperature and the water consumption; averaging all water consumption corresponding to the same power consumption in any one hour every day, and then drawing a relation curve of the power consumption and the water consumption; and then segmenting the time of each day according to 5 minutes, calculating the average value of the water consumption in each time period, and drawing a relation curve of the time and the water consumption to obtain the required models.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention, and the changes or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the appended claims.

Claims (4)

1. A self-induction pressure pumping pipe conveying system comprises a main control module, a model calculation module, an information acquisition module, a flow detection module, a pressure detection module and a pressure pump module; the method is characterized in that:
the model calculation module, the information acquisition module, the flow detection module, the pressure detection module and the pressure pump module are all connected to the main control module;
the pressurizing pump module is arranged on the water supply pipeline, is used for controlling the pressure of the water supply pipeline and pressurizing the water supply pipeline and comprises a primary pressurizing pump and a secondary pressurizing pump, wherein the primary pressurizing pump is arranged on the water supply main pipeline, and the secondary pressurizing pump is arranged on a water supply branch corresponding to each building;
the pressure detection module is used for detecting the water pressure in front of the primary booster pump and the secondary booster pump and sending the detected water pressure in front of the pump to the main control module;
the flow detection module is used for detecting the real-time water consumption and sending the real-time water consumption to the main control module;
the information acquisition module is used for acquiring information influencing water consumption, including precipitation information, temperature information and real-time power utilization information, and sending the collected precipitation information, temperature information and real-time power utilization information to the main control module;
the main control module sends precipitation information, temperature information, real-time electricity information, water pressure before pumping and water consumption in time to the model calculation module, the water pressure calculation model is arranged in the model calculation module, and the precipitation information, the temperature information, the real-time electricity information, the water pressure before pumping and the water consumption in time are used for obtaining the pressurizing power of the first-stage pressurizing pump and the pressurizing power of the second-stage pressurizing pump.
2. A self-induction pressurized pumping pipe system according to claim 1, wherein:
the flow detection module comprises a flow detection controller, a wireless communication module, an abnormity alarm module and a detection terminal;
the detection terminal is arranged on a water supply pipeline of each user and used for collecting the real-time water consumption of each user and sending data to the detection controller;
each terminal corresponds to a unique code in the flow detection controller;
the wireless communication module is used for sending the collected real-time water consumption to the main control module;
the abnormity alarm module is used for sending out a leakage alarm when the continuous water consumption of a certain terminal obviously exceeds a threshold value.
3. A self-induction pressurized pumping pipe system according to claim 1, wherein:
the primary pressure pump is used for providing integral pressurization for the main pipeline, and the secondary pressure pump is used for providing fine pressurization for water supply of each building;
the water pressure before the pump of the primary booster pump is P1, and the water pressure after the pump is P2; the water pressure before the pump of the secondary booster pump is P3, and the water pressure after the pump is P4;
the total real-time water consumption detected by the flow detection module is V1, and the total real-time water consumption of all users corresponding to a single building is V2;
the rainfall probability corresponding to the rainfall information is k, the temperature corresponding to the temperature information is T, and the power consumption corresponding to the real-time power consumption information is C;
therefore, P1 corresponds to the initial water pressure of the water supply, P2 corresponds to the pressure to which the primary pressure pump needs to be increased, and the pressure power needed by the primary pressure pump can be calculated through P1 and P2; p3 corresponds to the initial water pressure of a single building, P4 corresponds to the pressure to which the secondary booster pump needs to be increased, and the required boosting power of the secondary booster pump can be calculated through P3 and P4;
a correlation coefficient model is prestored in the model calculation module and is respectively a precipitation correlation coefficient model, an air temperature correlation coefficient model, an electricity consumption correlation coefficient model and a time correlation coefficient model;
the model of the precipitation correlation coefficient is a corresponding change curve of the daily water consumption under the condition of different precipitation probabilities k, namely the daily water consumption can be obtained by inputting the precipitation probabilities k;
the temperature correlation coefficient model is a change curve of the water consumption of the corresponding day under the condition of different temperatures T, namely the water consumption of the day can be obtained by inputting the temperatures T;
the power consumption correlation coefficient model is a corresponding real-time water consumption change curve under the condition of different power consumption C, namely the real-time water consumption can be obtained by inputting the power consumption C;
the time correlation coefficient model is a change curve of the corresponding real-time water consumption at different moments, namely the real-time water consumption can be obtained by inputting the time t;
the calculation method of P2 is P2= P1 · (f (k)/f (k0)) · (g (T)/g (T0)) · (V1/V0);
wherein f (k)/f (k0) represents the water pressure proportion required to be adjusted when the precipitation probability is changed from k0 to k, g (T)/g (T0) represents the water pressure proportion required to be adjusted when the air temperature is changed from T0 to T, f (k0) represents the precipitation probability corresponding to P1, and g (T0) represents the air temperature corresponding to P1; specific expressions of f () and g () are obtained by an empirical model, V0 represents the allowable water consumption without pressurization when the initial water pressure is P1, and the allowable water consumption does not influence the water consumption used by a user;
the calculation method of P4 is P4= P3 (h (C)/h (C0)) (s (t)/s (t0)) (V2/V3);
wherein h (C)/h (C0) represents the proportion of the water pressure required to be regulated when the electricity consumption is changed from C0 to C, s (t)/s (t0) represents the proportion of the water pressure required to be regulated when the time is changed from t0 to t, C0 represents the electricity consumption corresponding to P3, and t0 represents the time corresponding to P3; the concrete expressions of h () and s () are obtained by an empirical model, and V3 represents the allowable water consumption when the building water pressure is P3 without pressurization, and the allowable water consumption does not influence the water consumption used by a user.
4. A self-induction pressurized pumping pipe system according to claim 3, wherein:
before the model is set in the model calculation module, all water consumption information, precipitation information, temperature information and real-time electricity utilization information for at least 3 months need to be counted; then, carrying out correlation analysis on the water consumption information, the rainfall information, the temperature information and the real-time power utilization information, averaging all water consumption corresponding to the same rainfall probability, and then drawing a relation curve between the rainfall probability and the water consumption; averaging all water consumption corresponding to the same air temperature, and then drawing a relation curve of the air temperature and the water consumption; averaging all water consumption corresponding to the same power consumption in any one hour every day, and then drawing a relation curve of the power consumption and the water consumption; and then segmenting the time of each day according to 5 minutes, calculating the average value of the water consumption in each time period, and drawing a relation curve of the time and the water consumption to obtain the required models.
CN202111129668.2A 2021-09-26 2021-09-26 Self-induction booster pump send pipe system Active CN113756396B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111129668.2A CN113756396B (en) 2021-09-26 2021-09-26 Self-induction booster pump send pipe system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111129668.2A CN113756396B (en) 2021-09-26 2021-09-26 Self-induction booster pump send pipe system

Publications (2)

Publication Number Publication Date
CN113756396A true CN113756396A (en) 2021-12-07
CN113756396B CN113756396B (en) 2023-02-24

Family

ID=78797645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111129668.2A Active CN113756396B (en) 2021-09-26 2021-09-26 Self-induction booster pump send pipe system

Country Status (1)

Country Link
CN (1) CN113756396B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08326109A (en) * 1995-06-02 1996-12-10 Hitachi Ltd Water supply direct-connection water service system
CN101937220A (en) * 2010-08-13 2011-01-05 深圳市建恒测控股份有限公司 Building water supply intelligent management system and method thereof
CN104420508A (en) * 2013-09-03 2015-03-18 西安志越机电科技有限公司 Monitoring system of non-negative pressure water supply equipment
KR101704385B1 (en) * 2016-07-18 2017-02-08 화랑시스템(주) Water Supply System and Control Method Thereof
CN206752576U (en) * 2017-05-26 2017-12-15 李永建 A kind of plural serial stage tandem type laminating water supply equipment step by step
CN208899573U (en) * 2018-10-11 2019-05-24 深圳市科信洁源低碳环保科技有限公司 A kind of water supply network water-saving system
CN111364559A (en) * 2020-05-28 2020-07-03 浙江和达科技股份有限公司 Secondary water supply system
CN212224042U (en) * 2019-12-26 2020-12-25 四川悦宏达科技有限公司 Management device for urban water supply system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08326109A (en) * 1995-06-02 1996-12-10 Hitachi Ltd Water supply direct-connection water service system
CN101937220A (en) * 2010-08-13 2011-01-05 深圳市建恒测控股份有限公司 Building water supply intelligent management system and method thereof
CN104420508A (en) * 2013-09-03 2015-03-18 西安志越机电科技有限公司 Monitoring system of non-negative pressure water supply equipment
KR101704385B1 (en) * 2016-07-18 2017-02-08 화랑시스템(주) Water Supply System and Control Method Thereof
CN206752576U (en) * 2017-05-26 2017-12-15 李永建 A kind of plural serial stage tandem type laminating water supply equipment step by step
CN208899573U (en) * 2018-10-11 2019-05-24 深圳市科信洁源低碳环保科技有限公司 A kind of water supply network water-saving system
CN212224042U (en) * 2019-12-26 2020-12-25 四川悦宏达科技有限公司 Management device for urban water supply system
CN111364559A (en) * 2020-05-28 2020-07-03 浙江和达科技股份有限公司 Secondary water supply system

Also Published As

Publication number Publication date
CN113756396B (en) 2023-02-24

Similar Documents

Publication Publication Date Title
US10832555B2 (en) Remote monitoring system
CN109139930B (en) Energy-saving environment-friendly intelligent pressure regulating valve
CN113756396B (en) Self-induction booster pump send pipe system
CN105373092A (en) Intelligent control system special for water plant and control method thereof
CN113789829B (en) District water supply method and system based on big data
CN203452130U (en) Non-negative-pressure secondary water supply system
CN106896740A (en) House water resource managing and control system and its method
CN103977978A (en) High pressure water gun pump station with bolt interlocking device
CN209782246U (en) Automatic pressure-regulating compressed air centralized air supply system
CN108035400A (en) A kind of secondary water-supply device intelligence pump house
CN201428158Y (en) Pressure monitoring device for non-negative pressure water supply device
JP2017091124A (en) Monitoring controller of water-supply-facilities plant and method for managing water level of distribution reservoir using monitoring controller
CN207331813U (en) Small flow differential pressure Water supply device
CN206956840U (en) Peak regulation system
CN210792807U (en) Rail vehicle and foot pump pantograph device thereof
KR20180043060A (en) Distributed power control apparatus and system
CN103324184B (en) Gas transmission and distribution supervisory system
JPH07259142A (en) Water distribution block monitor
CN112564618B (en) Cooling control method, device and system for photovoltaic module
CN102118120A (en) Solar power supply system and method for increasing power supply efficiency thereof
CN206035780U (en) Intelligence pump control method
CN203452132U (en) Compression system for secondary water supply
CN205557702U (en) Intelligent pipe network pressure -superposed water supply equipment
CN110360649A (en) A kind of heat changes station control system
CN216815572U (en) Urban water network management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant