CN113737854A - Underground pipe gallery construction method - Google Patents

Underground pipe gallery construction method Download PDF

Info

Publication number
CN113737854A
CN113737854A CN202111123339.7A CN202111123339A CN113737854A CN 113737854 A CN113737854 A CN 113737854A CN 202111123339 A CN202111123339 A CN 202111123339A CN 113737854 A CN113737854 A CN 113737854A
Authority
CN
China
Prior art keywords
pipe gallery
shield
construction
road
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111123339.7A
Other languages
Chinese (zh)
Inventor
王光明
于洋
敖玉连
吴伟
陈晓庭
张凡
于喜飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202111123339.7A priority Critical patent/CN113737854A/en
Publication of CN113737854A publication Critical patent/CN113737854A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method of an underground pipe gallery, which comprises the following steps: step S1, arranging a temporary road on one side of the main road; step S2, excavating a foundation pit on the pavement of the main road on the other side of the temporary road, and supporting a side slope on one side of the foundation pit close to the temporary road; step S3, arranging a retaining wall at the end part of the constructed underground pipe gallery, backfilling the side pit, arranging a main roadbed and a water stabilization layer, returning the main road of the main road to pass, and turning to the side of the other main road to construct according to the step S1; a soil body of the section of the shield construction pipe gallery is adopted between the step S1 and the step S2; and the soil body of the section of the pipe gallery in the shield construction is positioned at the lower part of the foundation pit excavated in the step S2. The invention adopts a mode of combining open excavation and underground excavation, avoids various defects of the open excavation method, improves the stability of the foundation pit, effectively shortens the construction period of the underground pipe gallery when passing through the urban trunk road, greatly reduces the construction cost and improves the construction safety of the underground pipe gallery.

Description

Underground pipe gallery construction method
Technical Field
The invention relates to the technical field of pipe gallery construction, in particular to a construction method of an underground pipe gallery.
Background
The city pipe gallery is a tunnel space constructed underground in a city, and various pipelines such as electric power, communication, gas, water supply, heating power, drainage and the like are intensively paved in the tunnel space. In the prior art, the construction of underground pipe gallery is carried out by adopting traditional underground excavation method, i.e. the ground is not excavated, and the construction is carried out by adopting underground excavation. However, because urban main road vehicles come and go frequently, the difficulty of precipitation and unearthing construction in the underground pipe gallery construction process is improved, and large-scale equipment adopted in the construction process can damage foundation pits and soil layers below the main road. The underground excavation method obviously cannot meet new requirements of underground pipe gallery construction on construction period and cost, and cannot reduce the influence on daily life of construction perimeter areas in the construction period.
The invention patent with the prior application publication date of 2019.01.04 and the application publication number of CN109137970A discloses a construction method of a main road underground pipe gallery, which comprises the following steps: step S1, arranging a temporary road on one side of the main road, arranging a protective device at the junction of the original road intersection and the construction position of the underground pipe gallery, and arranging a deceleration strip; step S2, excavating a foundation pit on the pavement of the main road on the other side of the temporary road, and supporting a side slope on one side of the foundation pit close to the temporary road; and step S3, arranging a retaining wall at the end part of the constructed underground pipe gallery, backfilling the side pit, returning the main road of the main road, and turning to the side of the other main road for construction.
The technical scheme that the above-mentioned patent application discloses can keep ground road unblocked when the construction through interim road detour construction position to in the work progress, adopt the mode of strutting in side slope department behind the foundation ditch layering excavation, shortened the construction cycle when underground pipe gallery passes through city main road, reduced construction cost, and improved underground pipe gallery construction safety. However, the open cut method has inevitable defects that large-area excavation and environment destruction have great influence on ground facilities such as traffic, buildings and the like, noise, dust and the like interfere normal working and life of surrounding residents, earth excavation and backfilling occupy a large amount of ground space, precipitation operation is needed under the condition of shallow underground water level, foundation pit support is needed when the buried depth is large, the construction mechanization degree is low, the efficiency is not high, and the construction cost is high under special conditions.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides the underground pipe gallery construction method, which solves the technical problem that the existing open cut construction method of the underground pipe gallery has great influence on the construction area environment.
The technical scheme of the invention is realized as follows: a construction method of an underground pipe gallery comprises the following steps:
step S1, arranging a temporary road on one side of the main road, arranging a protective device at the junction of the original road intersection and the construction position of the underground pipe gallery, and arranging a deceleration strip;
step S2, excavating a foundation pit on the road surface of the main road on the other side of the temporary road, and supporting a side slope on one side of the foundation pit close to the temporary road;
step S3, arranging a retaining wall at the end part of the constructed underground pipe gallery, backfilling the side pit, arranging a main roadbed and a water stabilization layer, returning the main road of the main road to pass, and turning to the side of the other main road to construct according to the step S1; a part of soil body on the section of the pipe gallery is constructed by the shield between the step S1 and the step S2, the shield tunnels along the design line of the pipe gallery, forward thrust is provided on the laid pipe joints through the action of an oil cylinder, the belt is used for discharging slag, and shields are arranged on two sides and at the bottom of the shield tail to prevent surrounding slag soil from entering; and the soil body of the section of the pipe gallery in the shield construction is positioned at the lower part of the foundation pit excavated in the step S2.
Furthermore, the pipe gallery structure adopts prefabricated reinforced concrete pipe joints, the pipe joints are hung and placed in the assembly position through an opening at the rear part of the rectangular shield by using an above-ground hoisting device, when the pipe joints are separated from the shield tail after being installed, filling materials are synchronously backfilled at the side parts and the bottom of the pipe joints, and after the pipe joints are separated from the shield tail, earthwork backfilling is carried out at the top parts of the pipe joints.
Further, the shield is an open rectangular shield; the pipe sections adopt prefabricated reinforced concrete pipe sections; after the pipe joints are assembled, backfilling the top with muck; the two sides and the bottom of the shield tail of the open type rectangular shield are provided with shields, and the top of the open type rectangular shield is open and is used for hanging and installing pipe joints; and the retaining plates are inserted into soil bodies above and in front of the shield and serve as temporary supports for open cut construction.
Furthermore, the size of the shield is designed according to the size of the comprehensive pipe gallery, so that the smooth assembly of pipe joints is guaranteed; excavating a soil body through a cutter arranged on the rectangular cutter head; the device is provided with a complete slag discharging system; the top of the shield tail is open, and pipe joints can be hung and assembled; the upper part and the front part of the shield machine body are provided with retaining plates for providing temporary support for the open excavation operation of the upper part and the installation of pipe joints; the shield machine provides jacking force to carry out jacking construction forwards through a hydraulic oil cylinder acting on the pipe joint.
Further, in the step S3, after the side underground pipe gallery is constructed, a retaining wall is disposed at a joint of the side underground pipe gallery and a lower stage pipe gallery construction position, the retaining wall is cast by concrete, and a distance between the retaining wall and the expansion joint is in a range of 550mm to 650 mm.
Further, in step S2, the foundation pit is excavated in layers, and side slopes on two sides of the foundation pit are supported.
The invention adopts a mode of combining open excavation and underground excavation, thereby avoiding the problems that the open excavation method needs large-area excavation and environment destruction, has great influence on ground facilities such as traffic, buildings and the like, causes noise, dust and the like to interfere the normal working life of surrounding residents, occupies a large amount of ground space due to earth excavation and backfilling, needs precipitation operation under the condition of shallow underground water level, needs foundation pit support when the buried depth is large, has low construction mechanization degree, low efficiency and the like. In addition, the temporary road bypasses the construction position, the ground road can be kept smooth during construction, in addition, in the construction process, an underground excavation method in the prior art is replaced, a mode of supporting at the side slope after the foundation pit is excavated in a layered mode is adopted, the stability of the foundation pit is improved, the construction period of the underground pipe gallery when penetrating through the urban trunk road is effectively shortened, the construction cost is greatly reduced, and the construction safety of the underground pipe gallery is improved.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without inventive effort based on the embodiments of the present invention, are within the scope of the present invention.
A construction method of an underground pipe gallery comprises the following steps:
step S1, arranging a temporary road on one side of the main road, arranging a protective device at the junction of the original road intersection and the underground pipe gallery construction position, and arranging a deceleration strip, wherein the temporary road can be paved by C30 concrete, and the protective device can be a color steel enclosure; the deceleration strip can set up in the protector outside, the deceleration strip can be the sand heap, the width of deceleration strip with the width of full width road is unanimous.
And S2, excavating a foundation pit on the road surface of the main road on the other side of the temporary road, and supporting the side slope on one side of the foundation pit close to the temporary road. And a soil nailing wall can be adopted at the side slope of one side of the foundation pit close to the temporary road for supporting. The foundation pit can be excavated in layers, and side slopes on two sides of the foundation pit can be supported.
And step S3, arranging retaining walls at the end parts of the constructed underground pipe gallery, backfilling the side pits, arranging a main roadbed and a water stabilization layer, returning the main road of the main road to pass, and turning to the side of the other main road to construct according to the step S1. Treat this side underground pipe gallery construction completion back, can set up retaining wall in this side underground pipe gallery and lower stage pipe gallery construction position handing-over department, retaining wall passes through concrete placement, the distance between retaining wall and the expansion joint is in 550mm to 650 mm's within range.
A special process is also arranged between the step S1 and the step S2, namely, a part of soil body on the section of the pipe gallery constructed by the shield is adopted, the shield tunnels along the design line of the pipe gallery, forward thrust is provided on the laid pipe joints through the action of an oil cylinder, the slag is discharged by a belt, and shields are arranged on the two sides and the bottom of the shield tail to prevent surrounding slag from entering; and (4) the soil body of the section of the pipe gallery in the shield construction is positioned at the lower part of the foundation pit excavated in the step S2, namely the lower part adopts the shield construction, and the upper part adopts the open excavation construction.
Furthermore, the pipe gallery structure adopts prefabricated reinforced concrete pipe joints, the pipe joints are hung and placed in the assembly position through an opening at the rear part of the rectangular shield by using an above-ground hoisting device, when the pipe joints are separated from the shield tail after being installed, filling materials are synchronously backfilled at the side parts and the bottom of the pipe joints, and after the pipe joints are separated from the shield tail, earthwork backfilling is carried out at the top parts of the pipe joints.
Further, the shield is an open rectangular shield; the pipe sections adopt prefabricated reinforced concrete pipe sections; after the pipe joints are assembled, backfilling the top with muck; the two sides and the bottom of the shield tail of the open type rectangular shield are provided with shields, and the top of the open type rectangular shield is open and is used for hanging and installing pipe joints; and the retaining plates are inserted into soil bodies above and in front of the shield and serve as temporary supports for open cut construction.
Furthermore, the size of the shield is designed according to the size of the comprehensive pipe gallery, so that the smooth assembly of pipe joints is guaranteed; excavating a soil body through a cutter arranged on the rectangular cutter head; the device is provided with a complete slag discharging system; the top of the shield tail is open, and pipe joints can be hung and assembled; the upper part and the front part of the shield machine body are provided with retaining plates for providing temporary support for the open excavation operation of the upper part and the installation of pipe joints; the shield machine provides jacking force to carry out jacking construction forwards through a hydraulic oil cylinder acting on the pipe joint.
Nothing in this specification is intended to be exhaustive of all conventional and well known techniques.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (6)

1. A construction method of an underground pipe gallery comprises the following steps:
step S1, arranging a temporary road on one side of the main road, arranging a protective device at the junction of the original road intersection and the construction position of the underground pipe gallery, and arranging a deceleration strip;
step S2, excavating a foundation pit on the road surface of the main road on the other side of the temporary road, and supporting a side slope on one side of the foundation pit close to the temporary road;
step S3, arranging a retaining wall at the end part of the constructed underground pipe gallery, backfilling the side pit, arranging a main roadbed and a water stabilization layer, returning the main road of the main road to pass, and turning to the side of the other main road to construct according to the step S1;
the method is characterized in that: a part of soil body on the section of the pipe gallery is constructed by the shield between the step S1 and the step S2, the shield tunnels along the design line of the pipe gallery, forward thrust is provided on the laid pipe joints through the action of an oil cylinder, the belt is used for discharging slag, and shields are arranged on two sides and at the bottom of the shield tail to prevent surrounding slag soil from entering; and the soil body of the section of the pipe gallery in the shield construction is positioned at the lower part of the foundation pit excavated in the step S2.
2. The underground pipe gallery construction method according to claim 1, characterized in that: the pipe gallery structure adopts prefabricated reinforced concrete pipe joints, the pipe joints are hung and placed in the assembling position through an opening at the rear part of the rectangular shield by an above-ground hoisting device, when the pipe joints are separated from the shield tail after being installed, filling materials are synchronously backfilled at the side part and the bottom of the pipe joints, and after the pipe joints are separated from the shield tail, earthwork backfilling is carried out at the top of the pipe joints.
3. The underground pipe gallery construction method according to claim 2, characterized in that: the shield is an open rectangular shield; the pipe sections adopt prefabricated reinforced concrete pipe sections; after the pipe joints are assembled, backfilling the top with muck; the two sides and the bottom of the shield tail of the open type rectangular shield are provided with shields, and the top of the open type rectangular shield is open and is used for hanging and installing pipe joints; and the retaining plates are inserted into soil bodies above and in front of the shield and serve as temporary supports for open cut construction.
4. A method of constructing an underground pipe gallery according to any one of claims 1 to 3, characterized in that: the size of the shield is designed according to the size of the comprehensive pipe gallery, so that smooth assembly of pipe joints is guaranteed; excavating a soil body through a cutter arranged on the rectangular cutter head; the device is provided with a complete slag discharging system; the top of the shield tail is open, and pipe joints can be hung and assembled; the upper part and the front part of the shield machine body are provided with retaining plates for providing temporary support for the open excavation operation of the upper part and the installation of pipe joints; the shield machine provides jacking force to carry out jacking construction forwards through a hydraulic oil cylinder acting on the pipe joint.
5. The underground pipe gallery construction method according to claim 4, characterized in that: in the step S3, after the side underground pipe gallery is constructed, a retaining wall is disposed at the joint of the side underground pipe gallery and the lower stage pipe gallery construction position, the retaining wall is poured by concrete, and the distance between the retaining wall and the expansion joint is in the range of 550mm to 650 mm.
6. The underground pipe gallery construction method according to claim 5, characterized in that: in the step S2, the foundation pit is excavated in layers, and side slopes on two sides of the foundation pit are supported.
CN202111123339.7A 2021-09-24 2021-09-24 Underground pipe gallery construction method Pending CN113737854A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111123339.7A CN113737854A (en) 2021-09-24 2021-09-24 Underground pipe gallery construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111123339.7A CN113737854A (en) 2021-09-24 2021-09-24 Underground pipe gallery construction method

Publications (1)

Publication Number Publication Date
CN113737854A true CN113737854A (en) 2021-12-03

Family

ID=78740829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111123339.7A Pending CN113737854A (en) 2021-09-24 2021-09-24 Underground pipe gallery construction method

Country Status (1)

Country Link
CN (1) CN113737854A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110026143A (en) * 2009-09-07 2011-03-15 (주)하경엔지니어링 Underground structure construction method without middle temporary pile
CN105298507A (en) * 2015-11-17 2016-02-03 中铁工程装备集团有限公司 Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion
CN108951641A (en) * 2018-07-25 2018-12-07 中国十七冶集团有限公司 It is a kind of for the compound support method of ultra-deep pipe gallery foundation trench in water river
CN109137970A (en) * 2018-08-24 2019-01-04 中国华冶科工集团有限公司 Arterial highway underground pipe gallery construction method
CN109339096A (en) * 2018-07-02 2019-02-15 刘德堃 A kind of construction integrated constructing device of pipe gallery open cut precast assembly and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110026143A (en) * 2009-09-07 2011-03-15 (주)하경엔지니어링 Underground structure construction method without middle temporary pile
CN105298507A (en) * 2015-11-17 2016-02-03 中铁工程装备集团有限公司 Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion
CN109339096A (en) * 2018-07-02 2019-02-15 刘德堃 A kind of construction integrated constructing device of pipe gallery open cut precast assembly and its construction method
CN108951641A (en) * 2018-07-25 2018-12-07 中国十七冶集团有限公司 It is a kind of for the compound support method of ultra-deep pipe gallery foundation trench in water river
CN109137970A (en) * 2018-08-24 2019-01-04 中国华冶科工集团有限公司 Arterial highway underground pipe gallery construction method

Similar Documents

Publication Publication Date Title
CN111577383B (en) Method for treating tunnel leakage water in alpine region
CN104452809B (en) A kind of super shallow tunnel cover and cut construction method
US6139225A (en) Method for building an underground continuous wall
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN106436720A (en) Small-size deep foundation pit supporting structure for pipe jacking construction
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN107090851B (en) The inverted side-wall construction method of downtown area open cut groove
CN106049532A (en) Supporting and retaining device for open excavation construction of comprehensive pipe gallery and construction method thereof
CN110424988B (en) Tunnel waterproof structure and tunnel waterproof method
CN107514262A (en) The construction method of shield piping lane
CN112983478A (en) Shallow-buried underground tunnel foundation pit construction method under protection of cover plate
CN111365020A (en) Back-pressure backfill construction method suitable for biased hole entry under poor geological conditions
CN109339096A (en) A kind of construction integrated constructing device of pipe gallery open cut precast assembly and its construction method
JP4132442B2 (en) Tunnel construction method
HU226433B1 (en) Foundation slab of underground passage for road
CN115653000A (en) Gravity pipe gallery in-situ protection structure system in foundation pit range and construction method
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN112983461B (en) Construction method for biasing tunnel portal in slope integrated
CN214091881U (en) Structure suitable for bias hole entering under poor geological conditions
CN112112657B (en) New construction method for digging and building inclined shaft of coal mine
CN110820803B (en) Open excavation construction method for transverse connection channel of shield tunnel
CN209083308U (en) A kind of prestress anchorage cable cleaning plant
CN113737854A (en) Underground pipe gallery construction method
CN205013044U (en) Drought -hit area highway tunnel cable duct and escape canal global design structure
CN103154434A (en) Closed trench tunnels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination