CN113718782A - Secondary excavation and support construction method for deep foundation pit - Google Patents

Secondary excavation and support construction method for deep foundation pit Download PDF

Info

Publication number
CN113718782A
CN113718782A CN202111002095.7A CN202111002095A CN113718782A CN 113718782 A CN113718782 A CN 113718782A CN 202111002095 A CN202111002095 A CN 202111002095A CN 113718782 A CN113718782 A CN 113718782A
Authority
CN
China
Prior art keywords
foundation pit
excavating
excavation
slope
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111002095.7A
Other languages
Chinese (zh)
Inventor
李志强
刘长富
邵忠广
崔济镜
张钦赫
侯英彬
田露
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN202111002095.7A priority Critical patent/CN113718782A/en
Publication of CN113718782A publication Critical patent/CN113718782A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/22Lining sumps in trenches or other foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a secondary excavation and supporting construction method for a deep foundation pit. The invention adopts common excavating equipment and transport vehicles, adopts natural stable slope ratio, only needs simple support, reasonably utilizes the space of an excavation site, by temporarily building the construction access of the excavating equipment and the excavating material transfer point on the slope surface of the foundation pit, a plurality of excavating equipment can convey excavated materials out of the foundation pit while alternately carrying out relay excavation, the construction cost is low, meanwhile, the splicing type supporting structure has high erection and dismantling speed, the lower-layer earthwork can be directly excavated without waiting for strength after the erection is finished, but also can recycle, can the sizing in addition, application scope is wide, and the triangle-shaped support frame makes this supporting construction have higher structural strength moreover, and the guard plate of L type can pass through the support frame with the horizontal power that the curb plate received to bottom plate department, and the atress is more even, sets up safety problems such as domatic slump when the step can effectively avoid excavating in the domatic setting up of foundation ditch.

Description

Secondary excavation and support construction method for deep foundation pit
Technical Field
The invention relates to the technical field of building foundation pit construction, in particular to a secondary excavation and supporting construction method for a deep foundation pit.
Background
When the building foundation pit is constructed, in order to ensure the construction safety and prevent collapse accidents, support measures are required to be taken for the excavated building foundation pit, the factors of engineering geology and hydrogeology conditions, foundation pit types, excavation depth of the foundation pit, drainage conditions, requirements of peripheral environment on the displacement of the side wall of the foundation pit, peripheral load of the foundation pit, construction season, service life of a support structure and the like are comprehensively considered in the support design and construction of the building foundation pit, reasonable design, elaborate construction, economic safety are achieved, along with the construction of a large number of high-rise buildings and the development of underground space, and meanwhile, in order to meet the structural requirements of high-rise buildings such as earthquake resistance, wind resistance and the like, the basement is developed into multiple layers from one layer, the corresponding excavation depth of the foundation pit is increased, along with the increase of the depth of the foundation pit, the instability probability of a support structure in the foundation pit is increased, and the problem of low success rate of the foundation pit engineering in China is highlighted, each big city has an example of an engineering accident of a built foundation pit, when a deeper deep foundation pit is arranged on the side close to the edge of the deep foundation pit, the periphery of the deeper deep foundation pit is close to an important building, so a reasonable construction method is adopted for earth excavation and supporting on the side close to the edge, the construction of large-area foundations of other deep foundation pits is not influenced, and an effective construction method is not available at present.
Disclosure of Invention
The invention aims to provide a secondary excavation and supporting construction method for a deep foundation pit, which has the advantages of good stabilizing effect and high construction efficiency and solves the problems of poor stabilizing effect and low construction efficiency of the conventional method.
In order to achieve the purpose, the invention provides the following technical scheme:
a secondary excavation method for a deep foundation pit comprises the following steps:
s1: clearing and treating underground and overground obstacles in a construction area according to the requirements of a construction scheme, and measuring and setting out the range of the foundation pit to be dug;
s2: driving retaining wall piles downwards along the side wall of the foundation pit to be dug, driving rotary jet piles into the intervals of the retaining wall piles after adjacent retaining wall piles are driven at intervals, and forming the water stop continuous wall;
s3: constructing a well point, arranging wide water dispersion slope protection around a foundation pit, intercepting surface water into an open ditch in a field, precipitating for three times, entering an urban underground water channel, forming a water collecting ditch at the side of a brick moulding bed at the bottom of the foundation pit, excavating water collecting wells at two ends of the water collecting ditch, and draining the foundation pit by adopting a power water pump;
s4: placing slopes according to the designed slope ratio according to the actual condition of foundation pit excavation and layering, arranging steps between every two layers, arranging excavating equipment on the slope surface and the slope top of the foundation pit, and distributing the excavating equipment along the height of the slope surface;
s5: and (4) carrying out support treatment in time after each layer of excavation is finished, carrying out excavation on the next layer after the previous layer of support is finished, and circularly repeating the steps until the preset depth of secondary excavation is reached.
A supporting construction method for secondary excavation of a deep foundation pit is characterized by comprising the following steps: the method comprises the following steps:
s1: inserting a support column into the inner side wall of the secondary foundation pit;
s2: two adjacent support columns are fixedly connected with a protection plate through bolts;
s3: one side of the protection plate, which is far away from the inner wall of the foundation pit, is fixedly connected with a support frame through bolts;
s4: the bottom of the support frame is fixedly connected with the inner side of the protection plate through a bolt.
Preferably, the top end of the retaining wall pile in the step S2 is flush with the ground or higher than the ground, and the top end of the jet grouting pile is higher than the groundwater level by more than one meter.
Preferably, in step S4, the intersection of the effective working ranges of the excavating devices is set at the intersection, so that the excavating devices located relatively below can deliver the excavated materials within the working ranges to the intersection, and the excavating devices located relatively above relay the excavated materials to deliver the excavated materials, so that the excavating devices relay each other to transport the excavated materials to the outside of the foundation pit and excavate the excavation layer by layer according to the designed slope ratio.
Preferably, in step S4, the layering requirement is that each layer has a depth of three to four meters, and the width of the step is not less than three meters.
Preferably, a digging material storage yard is arranged near the position of the side slope edge of the foundation pit, and the distance between the storage yard and the side slope edge of the foundation pit is not less than twenty meters.
Preferably, the power water pump in step S3 may be a motor pump, an electric pump, a vacuum pump, or a siphon pump, and the power water pump should be selected according to the technical performance of the power water pump, and the number and model of the power water pump are determined according to the actual water volume.
Preferably, in the excavation process of the foundation pit in the step S4, in the earthwork which can not be excavated by the mechanical construction, excavation should be performed at any time in cooperation with manual work, and soil is transported to the place where the machine is excavated by a hand truck so as to be excavated by the machine in time.
Preferably, the shape of the shielding plate in the step S2 is an L-shape, and the shape of the supporting frame in the step S3 is a triangle.
Compared with the prior art, the invention has the following beneficial effects:
the invention adopts common excavating equipment and transport vehicles, adopts natural stable slope ratio, only needs simple support, reasonably utilizes the space of an excavation site, by temporarily building the construction access of the excavating equipment and the excavating material transfer point on the slope surface of the foundation pit, a plurality of excavating equipment can convey excavated materials out of the foundation pit while alternately carrying out relay excavation, the construction cost is low, meanwhile, the splicing type supporting structure has high erection and dismantling speed, the lower-layer earthwork can be directly excavated without waiting for strength after the erection is finished, but also can recycle, can the sizing in addition, application scope is wide, and the triangle-shaped support frame makes this supporting construction have higher structural strength moreover, and the guard plate of L type can pass through the support frame with the horizontal power that the curb plate received to bottom plate department, and the atress is more even, sets up safety problems such as domatic slump when the step can effectively avoid excavating in the domatic setting up of foundation ditch.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a technical scheme that:
a secondary excavation method for a deep foundation pit comprises the following steps:
s1: clearing and treating underground and overground obstacles in a construction area according to the requirements of a construction scheme, and measuring and setting out the range of the foundation pit to be dug;
s2: driving retaining wall piles downwards along the side wall of the foundation pit to be dug, driving rotary jet piles into the intervals of the retaining wall piles after adjacent retaining wall piles are driven at intervals, and forming the water stop continuous wall;
s3: constructing a well point, arranging wide water dispersion slope protection around a foundation pit, intercepting surface water into an open ditch in a field, precipitating for three times, entering an urban underground water channel, forming a water collecting ditch at the side of a brick moulding bed at the bottom of the foundation pit, excavating water collecting wells at two ends of the water collecting ditch, and draining the foundation pit by adopting a power water pump;
s4: placing slopes according to the designed slope ratio according to the actual condition of foundation pit excavation and layering, arranging steps between every two layers, arranging excavating equipment on the slope surface and the slope top of the foundation pit, and distributing the excavating equipment along the height of the slope surface;
s5: and (4) carrying out support treatment in time after each layer of excavation is finished, carrying out excavation on the next layer after the previous layer of support is finished, and circularly repeating the steps until the preset depth of secondary excavation is reached.
A supporting construction method for secondary excavation of a deep foundation pit is characterized by comprising the following steps: the method comprises the following steps:
s1: inserting a support column into the inner side wall of the secondary foundation pit;
s2: two adjacent support columns are fixedly connected with a protection plate through bolts;
s3: one side of the protection plate, which is far away from the inner wall of the foundation pit, is fixedly connected with a support frame through bolts;
s4: the bottom of the support frame is fixedly connected with the inner side of the protection plate through a bolt.
The first embodiment is as follows:
s1: clearing and treating underground and overground obstacles in a construction area according to the requirements of a construction scheme, and measuring and setting out the range of the foundation pit to be dug; a digging material storage yard is arranged near the edge of the foundation pit side slope, and the distance between the storage yard and the edge of the foundation pit side slope is twenty meters;
s2: driving retaining wall piles downwards along the side wall of the foundation pit to be dug, driving rotary jet piles into the intervals of the retaining wall piles after adjacent retaining wall piles are driven into the intervals of the retaining wall piles to form a water-stopping continuous wall, wherein the top ends of the retaining wall piles are flush with the ground, and the top ends of the rotary jet piles are higher than the ground water level by one meter;
s3: constructing a well point, arranging wide water dispersion slope protection around a foundation pit, intercepting surface water into an open ditch in a field, precipitating for three times, entering an urban underground water channel, forming a water collecting ditch at the side of a brick moulding bed at the bottom of the foundation pit, excavating water collecting wells at two ends of the water collecting ditch, and draining the foundation pit by adopting a power water pump; the power water pump is a motor pump;
s4: placing slopes according to a designed slope ratio according to the actual condition of foundation pit excavation and layering, arranging steps between every two layers, wherein the layering depth is three meters, the step width is three meters, arranging excavating equipment on the slope surface and the slope top of the foundation pit, distributing a plurality of excavating equipment along the height of the slope surface, intersecting effective operation ranges of the excavating equipment, and arranging an excavating material transfer point at the intersection, so that the excavating equipment relatively positioned below can convey excavating materials in the operation ranges to the excavating material transfer point, and the excavating equipment relatively positioned above relays to convey the excavating materials out of the foundation pit, and thus, the excavating equipment relays to convey the excavating materials to the outside of the foundation pit and excavate in layers according to the designed slope ratio;
s5: the processing of in time strutting after every layer of excavation is accomplished, inserts the support column to the inside wall of secondary foundation ditch now, and two adjacent support columns pass through bolt fixedly connected with guard plate, and bolt fixedly connected with support frame is passed through to one side that the foundation ditch inner wall was kept away from to the guard plate, and the inboard fixed connection of bolt and guard plate is passed through to the bottom of support frame, and the excavation of carrying out the next floor again after accomplishing is strutted by the last layer, so circulate reciprocal until the predetermined degree of depth of secondary excavation.
Example two:
in the first embodiment, the following steps are added:
the depth of layering is four meters, and the width of the step is four meters.
S1: clearing and treating underground and overground obstacles in a construction area according to the requirements of a construction scheme, and measuring and setting out the range of the foundation pit to be dug; a digging material storage yard is arranged near the edge of the foundation pit side slope, and the distance between the storage yard and the edge of the foundation pit side slope is twenty meters;
s2: driving retaining wall piles downwards along the side wall of the foundation pit to be dug, driving rotary jet piles into the intervals of the retaining wall piles after adjacent retaining wall piles are driven into the intervals of the retaining wall piles to form a water-stopping continuous wall, wherein the top ends of the retaining wall piles are flush with the ground, and the top ends of the rotary jet piles are higher than the ground water level by one meter;
s3: constructing a well point, arranging wide water dispersion slope protection around a foundation pit, intercepting surface water into an open ditch in a field, precipitating for three times, entering an urban underground water channel, forming a water collecting ditch at the side of a brick moulding bed at the bottom of the foundation pit, excavating water collecting wells at two ends of the water collecting ditch, and draining the foundation pit by adopting a power water pump; the power water pump is a motor pump;
s4: placing slopes according to a designed slope ratio according to the actual condition of foundation pit excavation and layering, arranging steps between every two layers, arranging excavating equipment on the slope surface and the slope top of the foundation pit, enabling the excavating equipment to be distributed along the height of the slope surface, enabling the effective operating ranges of the excavating equipment to intersect, and arranging an excavating material transfer point at the intersection, so that the excavating equipment which is relatively positioned below can send excavating materials in the operating ranges to the excavating material transfer point, and the excavating equipment which is relatively positioned above can transfer the excavating materials out in a relay mode, and thus, the excavating equipment can transfer the excavating materials to the outside of the foundation pit in a relay mode and excavate in a layered mode according to the designed slope ratio;
s5: the processing of in time strutting after every layer of excavation is accomplished, inserts the support column to the inside wall of secondary foundation ditch now, and two adjacent support columns pass through bolt fixedly connected with guard plate, and bolt fixedly connected with support frame is passed through to one side that the foundation ditch inner wall was kept away from to the guard plate, and the inboard fixed connection of bolt and guard plate is passed through to the bottom of support frame, and the excavation of carrying out the next floor again after accomplishing is strutted by the last layer, so circulate reciprocal until the predetermined degree of depth of secondary excavation.
Example three:
in the second embodiment, the following steps are added:
the top end of the retaining pile is higher than the ground, and the top end of the jet grouting pile is two meters higher than the ground water level; .
S1: clearing and treating underground and overground obstacles in a construction area according to the requirements of a construction scheme, and measuring and setting out the range of the foundation pit to be dug; a digging material storage yard is arranged near the edge of the foundation pit side slope, and the distance between the storage yard and the edge of the foundation pit side slope is twenty meters;
s2: driving retaining wall piles downwards along the side wall of the foundation pit to be dug, driving rotary jet piles into the intervals of the retaining wall piles after adjacent retaining wall piles are driven at intervals, and forming the water stop continuous wall;
s3: constructing a well point, arranging wide water dispersion slope protection around a foundation pit, intercepting surface water into an open ditch in a field, precipitating for three times, entering an urban underground water channel, forming a water collecting ditch at the side of a brick moulding bed at the bottom of the foundation pit, excavating water collecting wells at two ends of the water collecting ditch, and draining the foundation pit by adopting a power water pump; the power water pump is a motor pump;
s4: placing slopes according to a designed slope ratio according to the actual condition of foundation pit excavation and layering, arranging steps between every two layers, wherein the layering depth is three meters, the step width is three meters, arranging excavating equipment on the slope surface and the slope top of the foundation pit, distributing a plurality of excavating equipment along the height of the slope surface, intersecting effective operation ranges of the excavating equipment, and arranging an excavating material transfer point at the intersection, so that the excavating equipment relatively positioned below can convey excavating materials in the operation ranges to the excavating material transfer point, and the excavating equipment relatively positioned above relays to convey the excavating materials out of the foundation pit, and thus, the excavating equipment relays to convey the excavating materials to the outside of the foundation pit and excavate in layers according to the designed slope ratio;
s5: the processing of in time strutting after every layer of excavation is accomplished, inserts the support column to the inside wall of secondary foundation ditch now, and two adjacent support columns pass through bolt fixedly connected with guard plate, and bolt fixedly connected with support frame is passed through to one side that the foundation ditch inner wall was kept away from to the guard plate, and the inboard fixed connection of bolt and guard plate is passed through to the bottom of support frame, and the excavation of carrying out the next floor again after accomplishing is strutted by the last layer, so circulate reciprocal until the predetermined degree of depth of secondary excavation.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. A secondary excavation method for a deep foundation pit is characterized by comprising the following steps: the method comprises the following steps:
s1: clearing and treating underground and overground obstacles in a construction area according to the requirements of a construction scheme, and measuring and setting out the range of the foundation pit to be dug;
s2: driving retaining wall piles downwards along the side wall of the foundation pit to be dug, driving rotary jet piles into the intervals of the retaining wall piles after adjacent retaining wall piles are driven at intervals, and forming the water stop continuous wall;
s3: constructing a well point, arranging wide water dispersion slope protection around a foundation pit, intercepting surface water into an open ditch in a field, precipitating for three times, entering an urban underground water channel, forming a water collecting ditch at the side of a brick moulding bed at the bottom of the foundation pit, excavating water collecting wells at two ends of the water collecting ditch, and draining the foundation pit by adopting a power water pump;
s4: placing slopes according to the designed slope ratio according to the actual condition of foundation pit excavation and layering, arranging steps between every two layers, arranging excavating equipment on the slope surface and the slope top of the foundation pit, and distributing the excavating equipment along the height of the slope surface;
s5: and (4) carrying out support treatment in time after each layer of excavation is finished, carrying out excavation on the next layer after the previous layer of support is finished, and circularly repeating the steps until the preset depth of secondary excavation is reached.
2. A supporting construction method for secondary excavation of a deep foundation pit is characterized by comprising the following steps: the method comprises the following steps:
s1: inserting a support column into the inner side wall of the secondary foundation pit;
s2: two adjacent support columns are fixedly connected with a protection plate through bolts;
s3: one side of the protection plate, which is far away from the inner wall of the foundation pit, is fixedly connected with a support frame through bolts;
s4: the bottom of the support frame is fixedly connected with the inner side of the protection plate through a bolt.
3. The secondary excavation method for the deep foundation pit according to claim 1, characterized in that: and step S2, the top end of the retaining pile is flush with the ground or higher than the ground, and the top end of the jet grouting pile is higher than the ground water level by more than one meter.
4. The secondary excavation method for the deep foundation pit according to claim 1, characterized in that: in the step S4, the intersection of the effective working ranges of the excavating devices is set, and a material digging transfer point is set at the intersection, so that the excavating devices located relatively below can send the excavated materials within the working ranges to the material digging transfer point, and the excavating devices located relatively above relay the excavated materials to send out, so that the excavating devices relay each other to transport the excavated materials to the outside of the foundation pit and excavate in layers according to the designed slope ratio.
5. The secondary excavation method for the deep foundation pit according to claim 1, characterized in that: in step S4, the layering requirements are that the depth of each layer is three to four meters, and the width of the step is not less than three meters.
6. The secondary excavation method for the deep foundation pit according to claim 1, characterized in that: and a digging material storage yard is arranged at a position near the edge of the foundation pit side slope, and the distance between the storage yard and the edge of the foundation pit side slope is not less than twenty meters.
7. The secondary excavation method for the deep foundation pit according to claim 1, characterized in that: in the step S3, the power water pumps may be a motor pump, an electric pump, a vacuum pump, and a siphon pump, and should be selected according to the technical performance of the power water pumps, and the number and model of the power water pumps are determined according to the actual water amount.
8. The secondary excavation method for the deep foundation pit according to claim 1, characterized in that: in the process of excavating the foundation pit in the step S4, earthwork which can not be excavated by mechanical construction is excavated at any time by matching with manual work, and soil is transported to a place where the machine is excavated by a hand truck so as to be excavated by the machine in time.
9. The support construction method for the secondary excavation of the deep foundation pit according to claim 2, characterized in that: the shape of the shielding plate in the step S2 is L-shaped, and the shape of the supporting frame in the step S3 is triangular.
CN202111002095.7A 2021-08-30 2021-08-30 Secondary excavation and support construction method for deep foundation pit Pending CN113718782A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111002095.7A CN113718782A (en) 2021-08-30 2021-08-30 Secondary excavation and support construction method for deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111002095.7A CN113718782A (en) 2021-08-30 2021-08-30 Secondary excavation and support construction method for deep foundation pit

Publications (1)

Publication Number Publication Date
CN113718782A true CN113718782A (en) 2021-11-30

Family

ID=78678902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111002095.7A Pending CN113718782A (en) 2021-08-30 2021-08-30 Secondary excavation and support construction method for deep foundation pit

Country Status (1)

Country Link
CN (1) CN113718782A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967015A (en) * 2014-05-21 2014-08-06 刘绍国 Water-stopping deep foundation pit excavation method and structure thereof
CN110106886A (en) * 2019-04-04 2019-08-09 徐晔 A kind of deep pit digging method of underground high water level
CN110924399A (en) * 2019-11-11 2020-03-27 中国电建集团华东勘测设计研究院有限公司 Deep foundation pit earthwork excavation method
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN211713976U (en) * 2019-12-10 2020-10-20 中铁建大桥工程局集团南方工程有限公司 Large-span foundation pit supporting structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967015A (en) * 2014-05-21 2014-08-06 刘绍国 Water-stopping deep foundation pit excavation method and structure thereof
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN110106886A (en) * 2019-04-04 2019-08-09 徐晔 A kind of deep pit digging method of underground high water level
CN110924399A (en) * 2019-11-11 2020-03-27 中国电建集团华东勘测设计研究院有限公司 Deep foundation pit earthwork excavation method
CN211713976U (en) * 2019-12-10 2020-10-20 中铁建大桥工程局集团南方工程有限公司 Large-span foundation pit supporting structure

Similar Documents

Publication Publication Date Title
CN110374112B (en) Deep foundation pit supporting system for weak soil field and construction method thereof
CN111236241B (en) Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN209923959U (en) Open caisson structure for dry-process operation of high-groundwater-level soft soil field
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN110424372A (en) Along road interval method in a row remove obstacles after construct diaphram wall construction method
CN213038379U (en) Open cut tunnel foundation pit backfilling structure
CN110700270B (en) Construction method for non-drainage earthwork excavation of ultra-deep foundation pit
CN112681376A (en) Construction method of shaft type underground stereo garage
CN110565978B (en) Control method and structure of confined water in existing basement storey-adding construction
CN107326896A (en) One kind combination steel construction support pile and construction method
CN104695446A (en) Basement support construction method
CN106522572A (en) Construction method for constructing large-space underground channel in limited space of historical protection building
CN113718782A (en) Secondary excavation and support construction method for deep foundation pit
CN113585311B (en) Vacuum dewatering method with dewatering well penetrating through deep foundation pit
CN112459834B (en) Water collecting well, counter-slope tunnel and counter-slope tunnel drainage method
CN213897154U (en) Soft soil foundation pit bottom curing structure
CN211257900U (en) Control structure of confined water in existing basement storey-adding construction
CN211547830U (en) Structure for preventing ground from being wetted
CN107700519A (en) One kind lifting tower crane installation method
CN111719575A (en) Foundation pit anti-settling drainage method
CN113931228B (en) Material platform construction method for basement construction
CN111155429A (en) Construction method for bridge sand blowing island building in still water deep water area
CN209760248U (en) Composite type underwater bearing platform foundation pit support structure
CN215715234U (en) River bank foundation protection structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20211130