- CN113700314A CN113700314A CN202110915347.9A CN202110915347A CN113700314A CN 113700314 A CN113700314 A CN 113700314A CN 202110915347 A CN202110915347 A CN 202110915347A CN 113700314 A CN113700314 A CN 113700314A
- Authority
- CN
- China
- Prior art keywords
- plate
- lifting mechanism
- limiting
- base
- chain wheel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/167—Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F7/00—Lifting frames, e.g. for lifting vehicles; Platform lifts
- B66F7/10—Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks
- B66F7/16—Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F7/00—Lifting frames, e.g. for lifting vehicles; Platform lifts
- B66F7/28—Constructional details, e.g. end stops, pivoting supporting members, sliding runners adjustable to load dimensions
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to the field of concrete wallboards, in particular to an auxiliary mounting device of a concrete wallboard, which comprises a first supporting plate, a second supporting plate and a lifting mechanism arranged between the first supporting plate and the second supporting plate, wherein the bottom end of the first supporting plate is provided with a same-direction driving mechanism, and the lifting mechanism is driven by the same-direction driving mechanism to lift; the upper end of second backup pad is provided with the first lifting mechanism of lateral position adjustable, and first lifting mechanism includes first rotor plate and second rotor plate, and fixed mounting has the fixture that is used for the centre gripping to the concrete wallboard on first rotor plate and the second rotor plate, and fixture includes the base, and the side of base is provided with second lifting mechanism. The auxiliary mounting device designed by the invention can be used for mounting wallboards 1m-2m away from the ground and wallboards more than 2m away from the ground, and can be mounted one by one through transverse movement, so that the working efficiency is improved, high-altitude operation is avoided, and the risk is reduced.
Description
Technical Field
The invention relates to the field of concrete wallboards, in particular to an auxiliary mounting device for a concrete wallboard.
Background
The reinforced concrete plate-type member for building assembly, referred to as wallboard or wall plate, is processed and manufactured in a prefabrication plant or building site. The prefabricated concrete wallboard is adopted to build the assembled large-plate building, so that the factory and mechanical construction degree can be improved, the field wet operation is reduced, the field labor is saved, the seasonal influence is overcome, and the building construction period is shortened. The external wall board comprises a front external wall board, a gable wall board and a cornice wall board, wherein the front external wall board is a self-bearing wall board, and the gable wall board and the cornice wall board are bearing wall boards.
Among the prior art, the installation of concrete wall panel all realizes the installation through the manual work, and to the higher side fascia of height, the operational hazard is big and inconvenient transports the wallboard to the eminence, has reduced work efficiency, has also improved the operational risk simultaneously.
Disclosure of Invention
To overcome the above-mentioned shortcomings in the prior art, the present invention provides an auxiliary installation device for concrete wall panels.
The purpose of the invention can be realized by the following technical scheme:
an auxiliary installation device of a concrete wallboard comprises a first support plate, a second support plate and a lifting mechanism arranged between the first support plate and the second support plate, wherein a same-direction driving mechanism is arranged at the bottom end of the first support plate, and the lifting mechanism is driven by the same-direction driving mechanism to lift;
the upper end of second backup pad is provided with the first lifting mechanism of lateral position adjustable, and first lifting mechanism includes first rotor plate and second rotor plate, and fixed mounting has the fixture that is used for the centre gripping to the concrete wallboard on first rotor plate and the second rotor plate, and fixture includes the base, and the side of base is provided with second lifting mechanism.
Furthermore, the bottom of first backup pad is installed the truckle, and open the upper end of first backup pad has two through holes.
Further, syntropy actuating mechanism is provided with two, and syntropy actuating mechanism includes the first motor of installing in first backup pad bottom through the motor support, and the output of first motor is fixed with first sprocket, and the side of first sprocket is provided with the second sprocket, is connected with the chain between first sprocket and the second sprocket and first sprocket and second sprocket all rotate with first backup pad and set up, and the through hole setting is between first sprocket and second sprocket.
Further, elevating system parallel arrangement has two, elevating system includes two parallel arrangement's dwang, the bottom of dwang respectively with first sprocket, second sprocket fixed mounting, the inside cavity that is of dwang, the lateral wall of dwang is opened has two parallel arrangement's first helicla flute and second helicla flute, be provided with spacing post in the side clearance of first helicla flute and second helicla flute, spacing post and first helicla flute, the equal tangent setting of second helicla flute, the both ends of spacing post all are provided with the side shield who sets up with the dwang is tangent, be located and be fixed with the support horizontal pole between the inboard side shield, the vertical direction of supporting the horizontal pole is provided with the sleeve pipe, threaded through-hole has been seted up to the cover intraductally, threaded through-hole female connection has the threaded rod, threaded rod and through hole set up with one heart, the upper end of threaded rod is provided with the limiting plate.
Furthermore, the bottom of second backup pad is opened there is the counter bore, and the spacing setting of counter bore and limiting plate activity is provided with linear guide in the upper end of second backup pad, and linear guide's upper end slides and is provided with the guide rail slider, and linear guide passes through the drive of outside driving source.
Further, first lifting mechanism includes the bottom support, bottom support and guide rail slider fixed mounting, the second motor is installed to the upper end one side of bottom support, the output of second motor is fixed with the lead screw, be connected with screw nut on the lead screw, the both sides of lead screw all are provided with the guide bar of installing on the bottom support, it is provided with the guide block to slide on the guide bar, install on screw nut and the guide block and accept the board, the upper end central point who accepts the board puts and is provided with the fixed plate, it is connected with the gangbar to rotate between fixed plate and the first rotor plate, the second rotor plate passes through the bearing frame and rotates the setting on the bottom support.
Furthermore, the base is fixedly connected with the first rotating plate and the second rotating plate, a support is arranged at one side end of the base, a T-shaped limiting groove is formed in the upper end of the base, an outer baffle is arranged above the other side end of the base, a cavity is arranged inside the base, a first limiting opening is formed in one side of the cavity, and a second limiting opening is formed in the other side of the cavity.
Further, a third motor is installed to the side of base, and the output of third motor is provided with the gear post, and the top and the below of gear post are provided with first L template and second L template respectively, and first L template, second L template and first spacing mouthful, the spacing mouthful of second are spacing slip setting respectively, and first rack and second rack have been opened respectively to the bottom of first L template and the upper end of second L template, and first rack, second rack and gear post all mesh the transmission.
Further, the inboard of first L template and second L template all is provided with the grip block, and the outside end of grip block all is provided with the gag lever post that runs through first L template and second L template lateral wall, and the cover is equipped with expanding spring on the gag lever post, and the bottom of grip block is provided with the stopper that is the T type, grip block and spacing groove sliding fit.
Further, the second lifting mechanism comprises two pneumatic cylinders arranged in parallel, the bottom ends of the pneumatic cylinders are fixedly installed on the support, and the lifting plate is installed at the output ends of the pneumatic cylinders.
The invention has the beneficial effects that:
1. the auxiliary installation device can be used for installing wallboards 1m-2m away from the ground and wallboards more than 2m away from the ground, when the auxiliary installation device is used, the whole structure is close to the wall edge, the concrete wallboard is placed above the base, the bottom of the concrete wallboard is limited by the outer baffle plate, the third motor is driven, and the clamping plates on the two sides clamp the concrete wallboard; then a second motor is driven, the inclination angles of the first rotating plate and the second rotating plate are increased until the included angle between the first rotating plate and the second rotating plate is close to 90 degrees, the clamping of the clamping plate is removed, a pneumatic cylinder is driven, the lifting plate drives the end part of the concrete wallboard to be lifted upwards, the concrete wallboard is manually installed on the wall surface, and when the concrete wallboard is used, the guide rail sliding blocks drive the first lifting mechanism to transversely move under the driving of an external driving source, so that the concrete wallboard is installed one by one, and the working efficiency is improved;
2. when the wall plate is used, the first motor is driven, the first chain wheel and the second chain wheel rotate in the same direction, the two rotating rods also rotate in the same direction, the limiting column vertically moves upwards while the rotating rods rotate in the same direction, and then the threaded rod and the second supporting plate are driven to move upwards, the integral height of the threaded rod can be adjusted by adjusting the depth of the threaded rod connected in the threaded through hole, a wall plate with the height of more than 2m can be conveniently installed, high-altitude operation is avoided, and risks are reduced.
Drawings
In order to more clearly illustrate the embodiments or technical solutions in the prior art of the present invention, the drawings used in the description of the embodiments or prior art will be briefly described below, and it is obvious for those skilled in the art to obtain other drawings without creative efforts;
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the connection of the first support plate and the co-directional driving mechanism of the present invention;
FIG. 3 is a schematic view of the lift mechanism of the present invention;
FIG. 4 is a schematic view of a rotating lever according to the present invention;
FIG. 5 is a schematic diagram of a second support plate structure according to the present invention;
FIG. 6 is a schematic view of a first lifting mechanism of the present invention;
FIG. 7 is a schematic view of a clamping mechanism of the present invention;
FIG. 8 is a schematic cross-sectional view of a clamping mechanism of the present invention;
FIG. 9 is a schematic view of a clamping plate structure according to the present invention;
FIG. 10 is a schematic view of a second lifting mechanism of the present invention;
fig. 11 is a schematic view of the overall structure of the present invention with the first support plate, the same direction driving mechanism and the lifting mechanism removed.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The reinforced concrete plate-type member for building assembly, referred to as wallboard or wall plate, is processed and manufactured in a prefabrication plant or building site. The prefabricated concrete wallboard is adopted to build the assembled large-plate building, so that the factory and mechanical construction degree can be improved, the field wet operation is reduced, the field labor is saved, the seasonal influence is overcome, and the building construction period is shortened.
The external wall board comprises a front external wall board, a gable wall board and a cornice wall board, wherein the front external wall board is a self-bearing wall board, and the gable wall board and the cornice wall board are bearing wall boards. The external wall panel not only has the functions of sound insulation and fire prevention, but also has the functions of heat insulation, seepage resistance, freeze thawing resistance, carbonization resistance and the like and meets the requirements of architectural art decoration, and can be made of a single light aggregate material or a composite material (a structural layer, a heat insulation layer and a decorative layer).
As shown in fig. 1 to 11, the present invention provides an auxiliary installation device for a concrete wall panel, the auxiliary installation device includes a first support plate 1, a second support plate 4 and a lifting mechanism 3 disposed between the first support plate 1 and the second support plate 4, a same-direction driving mechanism 2 is disposed at the bottom end of the first support plate 1, and the lifting mechanism 3 is driven by the same-direction driving mechanism 2 to lift;
the upper end of the second supporting plate 4 is provided with a first lifting mechanism 5 with an adjustable transverse position, the first lifting mechanism 5 comprises a first rotating plate 56 and a second rotating plate 59, a clamping mechanism 6 used for clamping the concrete wall plate is fixedly mounted on the first rotating plate 56 and the second rotating plate 59, the clamping mechanism 6 comprises a base 61, and a second lifting mechanism 7 is arranged at the side end of the base 61.
As shown in FIG. 2, the bottom end of the first supporting plate 1 is provided with a caster 11, the caster 11 is a horse wheel, the installation is stable, and the upper end of the first supporting plate 1 is provided with two through holes 12.
Syntropy actuating mechanism 2 is provided with two, syntropy actuating mechanism 2 includes the first motor 21 of installing in 1 bottom of first backup pad through the motor support, and the output of first motor 21 is fixed with first sprocket 22, and the side of first sprocket 22 is provided with second sprocket 23, is connected with chain 24 between first sprocket 22 and the second sprocket 23 and first sprocket 22 and second sprocket 23 all rotate with first backup pad 1 and set up, and through hole 12 sets up between first sprocket 22 and second sprocket 23. The first motor 21 is driven, and the first chain wheel 22 and the second chain wheel 23 rotate in the same direction.
As shown in fig. 3 and 4, two lifting mechanisms 3 are arranged in parallel, each lifting mechanism 3 includes two rotating rods 31 arranged in parallel, the bottom ends of the rotating rods 31 are respectively and fixedly mounted on the first chain wheel 22 and the second chain wheel 23 to drive the first motor 21, and the two rotating rods 31 also rotate in the same direction.
Inside cavity that is of dwang 31, the lateral wall of dwang 31 is opened has two parallel arrangement's first helicla flute 311 and second helicla flute 312, is provided with spacing post 32 in the side clearance of first helicla flute 311 and second helicla flute 312, and spacing post 32 and first helicla flute 311, second helicla flute 312 homogeneous phase are surely set up, and the both ends of spacing post 32 all are provided with the side shield 321 with the tangent setting of dwang 31, and in the same direction pivoted of dwang 31, the vertical rebound of spacing post 32.
The supporting cross rods 33 are fixed between the side baffles 321 on the inner side, the sleeves 34 are arranged in the vertical direction of the supporting cross rods 33, threaded through holes 341 are formed in the sleeves 34, threaded rods 35 are connected to the threaded through holes 341 in an internal thread mode, nuts can be selectively connected to the threaded rods 35 and attached to the top ends of the sleeves 34, supporting capacity is improved, the threaded rods 35 and the through holes 12 are concentrically arranged, and limiting plates 351 are arranged at the upper ends of the threaded rods 35. The height of the whole threaded rod 35 can be adjusted by adjusting the depth of the threaded rod 35 connected in the threaded through hole 341.
As shown in fig. 5, a countersunk hole 41 is formed at the bottom end of the second support plate 4, the countersunk hole 41 and the limiting plate 351 are movably limited, a linear guide rail 42 is arranged at the upper end of the second support plate 4, a guide rail slider 43 is slidably arranged at the upper end of the linear guide rail 42, the linear guide rail 42 is driven by an external drive source, and the guide rail slider 43 can move on the linear guide rail 42 by the drive of the external drive source.
As shown in fig. 6, the first lifting mechanism 5 includes a bottom bracket 51, the bottom bracket 51 and the rail slider 43 are fixedly mounted, the second motor 52 is mounted on one side of the upper end of the bottom bracket 51, a lead screw 521 is fixed to an output end of the second motor 52, a lead screw nut 522 is connected to the lead screw 521, guide rods 54 mounted on the bottom bracket 51 are respectively disposed on two sides of the lead screw 521, a guide block 541 is slidably disposed on the guide rods 54, a receiving plate 53 is mounted on the lead screw nut 522 and the guide block 541, and the lead screw nut 522 and the receiving plate 53 slide on the lead screw 521 by driving the second motor 52.
A fixing plate 55 is arranged at the center of the upper end of the bearing plate 53, a linkage rod 57 is rotatably connected between the fixing plate 55 and the first rotating plate 56, and the second rotating plate 59 is rotatably arranged on the bottom bracket 51 through a bearing block 58. The angle at which the first and second rotating plates 56 and 59 are inclined can be adjusted while the receiving plate 53 is horizontally moved.
As shown in fig. 7-9, the base 61 is fixedly connected to the first rotating plate 56 and the second rotating plate 59, a bracket 611 is disposed at one side end of the base 61, a T-shaped limiting groove 612 is formed at the upper end of the base 61, an external baffle 613 is disposed above the other side end of the base 61, a cavity 614 is disposed inside the base 61, a first limiting opening 615 is formed at one side of the cavity 614, and a second limiting opening 616 is formed at the other side of the cavity 614. Concrete wall panel has been placed to base 61's upper end, and concrete wall panel's bottom is spacing through outer baffle 613.
The inboard of first L template 63 and second L template 64 all is provided with grip block 65, and the outside end of grip block 65 all is provided with gag lever post 651 that runs through first L template 63 and second L template 64 lateral wall, and the cover is equipped with expanding spring 652 on the gag lever post 651, and the bottom of grip block 65 is provided with the stopper 653 that is the T type, grip block 65 and spacing groove 612 sliding fit. When the first L-shaped plate 63 and the second L-shaped plate 64 can be drawn close to each other, the extension spring 652 is compressed, and the clamping plates 65 on both sides clamp the concrete wall panel.
As shown in fig. 10, the second lifting mechanism 7 includes two pneumatic cylinders 71 arranged in parallel, the bottom ends of the pneumatic cylinders 71 and the bracket 611 are fixedly installed, and the output ends of the pneumatic cylinders 71 are installed with lifting plates 712. The clamping force of the clamping plate 65 is released, the pneumatic cylinder 71 is driven, and the lifting plate 712 drives the end of the concrete wall panel to lift upwards.
For the installation of external wall panels, three situations are distinguished:
aiming at the installation of a wallboard close to the ground, the installation of the external wallboard can be realized manually;
secondly, the installation of the wall board 1m-2m away from the ground is labor-consuming through manual installation;
and thirdly, the installation of the wall plate which is more than 2m away from the ground needs to be carried out by means of an auxiliary tool.
In the first case, the installation can be achieved by manual operation, and the auxiliary installation structure is not applicable in the invention.
In the second situation, the installation is realized through partial structure in the invention, as shown in fig. 11, the whole structure after the first supporting plate 1, the same-direction driving mechanism 2 and the lifting mechanism 3 are removed, so that the whole structure is close to the wall edge, the concrete wallboard is placed above the base 61, the bottom of the concrete wallboard is limited by the outer baffle 613, the third motor 62 is driven, when the first L-shaped plate 63 and the second L-shaped plate 64 can be drawn close to each other, the expansion spring 652 is compressed, and the clamping plates 65 on the two sides clamp the concrete wallboard; then the second motor 52 is driven, the bearing plate 53 slides on the screw 521, while the bearing plate 53 moves horizontally, the inclination angles of the first rotating plate 56 and the second rotating plate 59 are increased more and more until the included angle between the first rotating plate and the horizontal plane is close to 90 degrees, the clamping of the clamping plate 65 is released, the driving pneumatic cylinder 71 is driven, the lifting plate 712 drives the end part of the concrete wallboard to lift upwards, and the concrete wallboard is manually installed on the wall surface; when the lifting device is used, the guide rail sliding block 43 drives the first lifting mechanism 5 to move transversely by the driving of an external driving source, and the first lifting mechanism 5 is installed one by one;
in the third situation, the installation is realized through the integral structure in the invention, as shown in fig. 1, the main difference between the third situation and the second situation lies in that the integral height can be adjusted, the bottom end of the second support plate 4 is provided with the first support plate 1, the lifting mechanism 3 and the equidirectional driving mechanism 2 to drive the first motor 21, the first chain wheel 22 and the second chain wheel 23 rotate in the same direction, the two rotating rods 31 also rotate in the same direction, the limiting column 32 vertically moves upwards while the rotating rods 31 rotate in the same direction, and then drives the threaded rod 35 and the second support plate 4 to move upwards, the integral height of the threaded rod 35 can be adjusted by adjusting the depth of the threaded rod 35 connected in the threaded through hole 341, and a wallboard with the height of more than 2m can be conveniently installed. The specific mounting and lateral movement is the same as in the second case.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are described in the specification and illustrated only to illustrate the principle of the present invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the present invention, which fall within the scope of the invention as claimed.
Claims (10)
1. The auxiliary mounting device for the concrete wallboard is characterized by comprising a first support plate (1), a second support plate (4) and a lifting mechanism (3) arranged between the first support plate (1) and the second support plate (4), wherein a same-direction driving mechanism (2) is arranged at the bottom end of the first support plate (1), and the lifting mechanism (3) is driven by the same-direction driving mechanism (2) to lift;
the upper end of second backup pad (4) is provided with horizontal position adjustable first lifting mechanism (5), and first lifting mechanism (5) are including first rotor plate (56) and second rotor plate (59), and fixed mounting has fixture (6) that are used for the centre gripping to the concrete wallboard on first rotor plate (56) and second rotor plate (59), and fixture (6) are including base (61), and the side of base (61) is provided with second lifting mechanism (7).
2. An auxiliary installation device of concrete wall panel according to claim 1, characterized in that the bottom end of the first supporting plate (1) is installed with casters (11), and the upper end of the first supporting plate (1) is opened with two through holes (12).
3. The auxiliary mounting device for the concrete wall panel is characterized in that two equidirectional driving mechanisms (2) are arranged, each equidirectional driving mechanism (2) comprises a first motor (21) mounted at the bottom end of the first support plate (1) through a motor support, a first chain wheel (22) is fixed at the output end of each first motor (21), a second chain wheel (23) is arranged on the side of each first chain wheel (22), a chain (24) is connected between each first chain wheel (22) and each second chain wheel (23), each first chain wheel (22) and each second chain wheel (23) are rotatably arranged with the first support plate (1), and the through holes (12) are formed between the first chain wheels (22) and the second chain wheels (23).
4. The auxiliary installation device of the concrete wall panel according to claim 1, wherein two lifting mechanisms (3) are arranged in parallel, each lifting mechanism (3) comprises two rotating rods (31) arranged in parallel, the bottom ends of the rotating rods (31) are respectively and fixedly installed with a first chain wheel (22) and a second chain wheel (23), a cavity is formed inside each rotating rod (31), the outer side wall of each rotating rod (31) is provided with a first spiral groove (311) and a second spiral groove (312) which are arranged in parallel, a limiting column (32) is arranged in a side gap between the first spiral groove (311) and the second spiral groove (312), the limiting column (32) and the first spiral groove (311) and the second spiral groove (312) are arranged in a cutting manner, side baffles (321) arranged in a cutting manner with the rotating rods (31) are arranged at two ends of the limiting column (32), and a supporting cross bar (33) is fixed between the side baffles (321) positioned at the inner side, the vertical direction of supporting horizontal pole (33) is provided with sleeve pipe (34), has screw thread through-hole (341) in sleeve pipe (34), and screw thread through-hole (341) female connection has threaded rod (35), and threaded rod (35) and through-hole (12) set up with one heart, and the upper end of threaded rod (35) is provided with limiting plate (351).
5. The auxiliary installation device of the concrete wall panel is characterized in that a countersunk hole (41) is formed in the bottom end of the second support plate (4), the countersunk hole (41) and the limiting plate (351) are movably arranged in a limiting manner, a linear guide rail (42) is arranged at the upper end of the second support plate (4), a guide rail sliding block (43) is arranged at the upper end of the linear guide rail (42) in a sliding manner, and the linear guide rail (42) is driven by an external driving source.
6. The auxiliary mounting device of the concrete wall panel according to claim 1, wherein the first lifting mechanism (5) comprises a bottom bracket (51), the bottom bracket (51) and the guide rail sliding block (43) are fixedly mounted, a second motor (52) is mounted on one side of the upper end of the bottom bracket (51), a lead screw (521) is fixed at the output end of the second motor (52), a lead screw nut (522) is connected onto the lead screw (521), guide rods (54) mounted on the bottom bracket (51) are respectively arranged on two sides of the lead screw (521), a guide block (541) is slidably arranged on the guide rods (54), a bearing plate (53) is mounted on the lead screw nut (522) and the guide block (541), a fixing plate (55) is arranged at the center position of the upper end of the bearing plate (53), and a linkage rod (57) is rotatably connected between the fixing plate (55) and the first rotating plate (56), the second rotating plate (59) is rotatably arranged on the bottom bracket (51) through a bearing seat (58).
7. The auxiliary mounting device of the concrete wall panel according to claim 1, wherein the base (61) is fixedly connected with the first rotating plate (56) and the second rotating plate (59), a bracket (611) is arranged at one side end of the base (61), a T-shaped limiting groove (612) is formed in the upper end of the base (61), an outer baffle (613) is arranged above the other side end of the base (61), a cavity (614) is arranged inside the base (61), a first limiting opening (615) is formed in one side of the cavity (614), and a second limiting opening (616) is formed in the other side of the cavity (614).
8. The auxiliary mounting device for the concrete wall panel according to claim 7, wherein a third motor (62) is mounted at a side end of the base (61), a gear column (621) is arranged at an output end of the third motor (62), a first L-shaped plate (63) and a second L-shaped plate (64) are respectively arranged above and below the gear column (621), the first L-shaped plate (63), the second L-shaped plate (64), a first limit port (615) and a second limit port (616) are respectively arranged in a limit sliding manner, a first rack (631) and a second rack (632) are respectively arranged at a bottom end of the first L-shaped plate (63) and an upper end of the second L-shaped plate (64), and the first rack (631), the second rack (632) and the gear column (621) are all in meshing transmission.
9. The auxiliary installation device of a concrete wallboard according to claim 8, wherein the inner sides of the first L-shaped plate (63) and the second L-shaped plate (64) are both provided with a clamping plate (65), the outer side ends of the clamping plates (65) are both provided with a limiting rod (651) penetrating through the side walls of the first L-shaped plate (63) and the second L-shaped plate (64), the limiting rod (651) is sleeved with a telescopic spring (652), the bottom end of the clamping plate (65) is provided with a limiting block (653) in a T shape, and the clamping plate (65) and the limiting groove (612) are in sliding fit.
10. An auxiliary mounting device for concrete wall panel according to claim 1, characterized in that said second lifting mechanism (7) comprises two parallel arranged pneumatic cylinders (71), the bottom ends of the pneumatic cylinders (71) and the bracket (611) are fixedly mounted, the output ends of the pneumatic cylinders (71) are mounted with lifting plates (712).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110915347.9A CN113700314B (en) | 2021-08-10 | 2021-08-10 | Auxiliary mounting device for concrete wall board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110915347.9A CN113700314B (en) | 2021-08-10 | 2021-08-10 | Auxiliary mounting device for concrete wall board |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113700314A true CN113700314A (en) | 2021-11-26 |
CN113700314B CN113700314B (en) | 2023-04-07 |
Family
ID=78652189
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110915347.9A Active CN113700314B (en) | 2021-08-10 | 2021-08-10 | Auxiliary mounting device for concrete wall board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113700314B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115045514A (en) * | 2022-06-22 | 2022-09-13 | 高宝军 | Auxiliary device suitable for damper installation |
CN115492406A (en) * | 2022-10-31 | 2022-12-20 | 山东中信恒远项目管理有限公司 | Automatic lifting equipment of steel construction |
CN115807551A (en) * | 2022-12-14 | 2023-03-17 | 西安建工第一建筑集团有限公司 | Super high-rise core tube structure steel reinforced concrete slab wall connecting device |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4286934A (en) * | 1980-01-14 | 1981-09-01 | Mikhail Linetsky | Precast house manufacturing and erecting plant |
RU2152495C1 (en) * | 1994-03-17 | 2000-07-10 | Юкка Инкеройнен | Device for installation of light-weight panels |
CN108547462A (en) * | 2018-04-26 | 2018-09-18 | 青岛联合智造科技有限公司 | A kind of building exterior wall heat preserving cystosepiment conveys mounting device automatically |
CN110469129A (en) * | 2019-08-28 | 2019-11-19 | 安徽宝业建工集团有限公司 | A kind of assembly concrete wallboard is with regard to station moving device |
CN111927113A (en) * | 2020-08-11 | 2020-11-13 | 孙乐洋 | Prefabricated plate erection equipment of prefabricated building |
CN212405993U (en) * | 2020-09-28 | 2021-01-26 | 金螳螂精装科技(苏州)有限公司 | Mounting and adjusting structure of assembled decorative wall surface |
CN112392264A (en) * | 2020-11-06 | 2021-02-23 | 池程怀 | Recycled concrete wallboard mounting equipment |
CN212773549U (en) * | 2020-06-30 | 2021-03-23 | 中建八局第一建设有限公司 | Sliding device for hoisting truss |
CN212984663U (en) * | 2020-07-02 | 2021-04-16 | 赣州荣兴钢结构工程有限公司 | Steel member slope fixing device |
CN213418523U (en) * | 2020-08-06 | 2021-06-11 | 杭州临安简诚办公用品有限公司 | Supporting device for mounting assembly type wallboard |
CN213418535U (en) * | 2020-10-14 | 2021-06-11 | 昆山清阳净化系统工程有限公司 | Prefabricated wallboard auxiliary installation mechanism |
CN113123611A (en) * | 2021-04-28 | 2021-07-16 | 肖尧 | Method for mounting and reinforcing fabricated concrete prefabricated part |
-
2021
- 2021-08-10 CN CN202110915347.9A patent/CN113700314B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4286934A (en) * | 1980-01-14 | 1981-09-01 | Mikhail Linetsky | Precast house manufacturing and erecting plant |
RU2152495C1 (en) * | 1994-03-17 | 2000-07-10 | Юкка Инкеройнен | Device for installation of light-weight panels |
CN108547462A (en) * | 2018-04-26 | 2018-09-18 | 青岛联合智造科技有限公司 | A kind of building exterior wall heat preserving cystosepiment conveys mounting device automatically |
CN110469129A (en) * | 2019-08-28 | 2019-11-19 | 安徽宝业建工集团有限公司 | A kind of assembly concrete wallboard is with regard to station moving device |
CN212773549U (en) * | 2020-06-30 | 2021-03-23 | 中建八局第一建设有限公司 | Sliding device for hoisting truss |
CN212984663U (en) * | 2020-07-02 | 2021-04-16 | 赣州荣兴钢结构工程有限公司 | Steel member slope fixing device |
CN213418523U (en) * | 2020-08-06 | 2021-06-11 | 杭州临安简诚办公用品有限公司 | Supporting device for mounting assembly type wallboard |
CN111927113A (en) * | 2020-08-11 | 2020-11-13 | 孙乐洋 | Prefabricated plate erection equipment of prefabricated building |
CN212405993U (en) * | 2020-09-28 | 2021-01-26 | 金螳螂精装科技(苏州)有限公司 | Mounting and adjusting structure of assembled decorative wall surface |
CN213418535U (en) * | 2020-10-14 | 2021-06-11 | 昆山清阳净化系统工程有限公司 | Prefabricated wallboard auxiliary installation mechanism |
CN112392264A (en) * | 2020-11-06 | 2021-02-23 | 池程怀 | Recycled concrete wallboard mounting equipment |
CN113123611A (en) * | 2021-04-28 | 2021-07-16 | 肖尧 | Method for mounting and reinforcing fabricated concrete prefabricated part |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115045514A (en) * | 2022-06-22 | 2022-09-13 | 高宝军 | Auxiliary device suitable for damper installation |
CN115492406A (en) * | 2022-10-31 | 2022-12-20 | 山东中信恒远项目管理有限公司 | Automatic lifting equipment of steel construction |
CN115492406B (en) * | 2022-10-31 | 2024-02-23 | 山东中信恒远项目管理有限公司 | Automatic lifting equipment for steel structure |
CN115807551A (en) * | 2022-12-14 | 2023-03-17 | 西安建工第一建筑集团有限公司 | Super high-rise core tube structure steel reinforced concrete slab wall connecting device |
Also Published As
Publication number | Publication date |
---|---|
CN113700314B (en) | 2023-04-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113700314B (en) | Auxiliary mounting device for concrete wall board | |
CN214575827U (en) | Auxiliary installation equipment for glass curtain wall | |
CN111980380A (en) | Assembled partition wall and furred ceiling body structure | |
CN113503043A (en) | Assembly type building installation equipment | |
CN112854763B (en) | Construction device of energy-saving building and working method thereof | |
CN213793933U (en) | Fixed bending device for steel bar prefabrication | |
CN220133536U (en) | Suspended ceiling installation equipment for building decoration construction | |
CN217205413U (en) | Wallboard installation device for building engineering | |
CN2858855Y (en) | Dual-purpose wall plastering machine | |
CN216785439U (en) | Assembled concrete superimposed sheet floor hoisting structure | |
CN213143786U (en) | Jacking transmission mechanism | |
CN212315477U (en) | Assembled is exterior wallboard production upset platform for building | |
CN220313651U (en) | Novel prefabricated building structure | |
CN112112403A (en) | Jacking transmission mechanism | |
CN219638451U (en) | Wall body builds by laying bricks or stones and uses appurtenance | |
CN221191333U (en) | Assembled building construction auxiliary device | |
CN214696986U (en) | Assembled wall positioning frame for assembly type building | |
CN220487147U (en) | Positioning device for curtain wall construction | |
CN218539002U (en) | Various steel sheet construction installation hoist and mount frame with prevent empting function | |
CN221567929U (en) | Safe and quick installation device for assembled building | |
CN218746369U (en) | Assembled plate grooving machine for building | |
CN214691166U (en) | Assembled superimposed sheet mould piling bin | |
CN117263017B (en) | Novel steel construction house AAC board hoist and mount are supplementary device | |
CN219316128U (en) | Prefabricated wallboard and precast beam installation connection structure | |
CN221761258U (en) | Positioning and mounting equipment for building curtain wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |