CN113684852B - Construction method of composite pile foundation and composite pile foundation - Google Patents

Construction method of composite pile foundation and composite pile foundation Download PDF

Info

Publication number
CN113684852B
CN113684852B CN202111161651.5A CN202111161651A CN113684852B CN 113684852 B CN113684852 B CN 113684852B CN 202111161651 A CN202111161651 A CN 202111161651A CN 113684852 B CN113684852 B CN 113684852B
Authority
CN
China
Prior art keywords
steel pipe
pile
column
pipe column
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111161651.5A
Other languages
Chinese (zh)
Other versions
CN113684852A (en
Inventor
吴俊锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Kejia Design Group Co ltd
Original Assignee
Jiangsu Kejia Engineering Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Kejia Engineering Design Co ltd filed Critical Jiangsu Kejia Engineering Design Co ltd
Priority to CN202111161651.5A priority Critical patent/CN113684852B/en
Publication of CN113684852A publication Critical patent/CN113684852A/en
Application granted granted Critical
Publication of CN113684852B publication Critical patent/CN113684852B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明提供一种组合桩基础的施工方法,包括以下步骤:在地面下沉钢管立柱,并开挖钢管立柱内的土;所述钢管立柱侧壁设有钢管斜桩的施工孔;通过钢管立柱向下钻孔,形成钻孔灌注桩的灌注桩孔;通过钢管立柱下钢筋笼,钢筋笼自灌注桩孔底部向上延伸至进入钢管立柱内底部一段;然后在灌注桩孔内和钢管立柱底部一段灌注混凝土,所灌注的混凝土覆盖钢筋笼进入钢管立柱内的笼段;在钢管立柱内通过千斤顶向斜下方斜顶钢管斜柱段,多个依次斜顶的钢管斜柱段相连形成钢管斜桩;在斜顶过程中,千斤顶通过千斤顶反力座支撑于钢管立柱内壁;逐个完成各钢管斜桩的斜顶施工;在钢管立柱内灌注混凝土。最终实现提供竖向承载力、水平承载力、抗剪功能的组合桩基础。

Figure 202111161651

The invention provides a construction method for a composite pile foundation, comprising the following steps: sinking a steel pipe column on the ground, and excavating the soil inside the steel pipe column; the side wall of the steel pipe column is provided with a construction hole for a steel pipe inclined pile; Drill down to form the cast-in-place pile hole of the bored pile; pass the steel cage under the steel pipe column, and the reinforcement cage extends upward from the bottom of the cast-in-place pile hole to the inner bottom section of the steel pipe column; Concrete is poured, and the poured concrete covers the steel cage and enters the cage section in the steel pipe column; in the steel pipe column, the steel pipe inclined column section is tilted downward through the jack, and multiple steel pipe inclined column sections that are inclined in turn are connected to form a steel pipe inclined pile; During the inclined jacking process, the jack is supported on the inner wall of the steel pipe column through the jack reaction seat; the inclined roof construction of each steel pipe inclined pile is completed one by one; concrete is poured into the steel pipe column. Finally, the composite pile foundation that provides vertical bearing capacity, horizontal bearing capacity and shear resistance function is realized.

Figure 202111161651

Description

组合桩基础的施工方法及组合桩基础Construction method of composite pile foundation and composite pile foundation

技术领域technical field

本发明涉及土木工程中的基础,尤其是一种组合桩基础的施工方法及组合桩基础。The invention relates to a foundation in civil engineering, in particular to a construction method of a composite pile foundation and the composite pile foundation.

背景技术Background technique

钻孔灌注桩是常用是基础形式,在桥梁工程、建筑工程、码头工程等几乎所有的土木工程中不可或缺,其能提供很好的竖向承载力,但其水平承载力很差。Bored piles are commonly used as foundation forms and are indispensable in almost all civil engineering projects such as bridge engineering, construction engineering, and wharf engineering. They can provide good vertical bearing capacity, but their horizontal bearing capacity is very poor.

对于一般需要提供大水平承载力的基础,如大桥桥墩、抗撞墩、拱桥桥墩台基础等等,几乎采用的都是钻孔灌注桩群桩基础,其显著特征就是由原来的水平力产生的弯矩转换为桩基轴力,并且由桩基承担剪力,然而,桩基的抗剪水平往往较低,而由桩基承担基础弯矩效应的效率是比较低的。For foundations that generally need to provide large horizontal bearing capacity, such as bridge piers, anti-collision piers, arch bridge pier foundations, etc., almost all of them are pile group foundations of bored piles, and their remarkable feature is that they are generated by the original horizontal force. The bending moment is converted into the axial force of the pile foundation, and the shear force is borne by the pile foundation. However, the shear resistance level of the pile foundation is often low, and the efficiency of the pile foundation to bear the foundation bending moment effect is relatively low.

发明内容Contents of the invention

本发明的目的是在于克服现有技术中存在的不足,提供一种组合桩基础的施工方法,能够在施工过程中,构件相互间为其他施工工序提供有利的条件,提高了施工可靠度,降低施工成本,达到了很好的协调作用;最终实现提供竖向承载力、水平承载力、抗剪功能的组合桩基础;本发明也提供了通过上述施工方法形成的组合桩基础。为实现以上技术目的,本发明实施例采用的技术方案是:The purpose of the present invention is to overcome the deficiencies in the prior art and provide a construction method for combined pile foundations, which can provide favorable conditions for other construction procedures between components during the construction process, improve construction reliability, reduce The construction cost has achieved a good coordination effect; finally, a combined pile foundation that provides vertical bearing capacity, horizontal bearing capacity and shear resistance function is realized; the invention also provides a combined pile foundation formed by the above construction method. In order to achieve the above technical purpose, the technical solution adopted in the embodiment of the present invention is:

本发明实施例提供了一种组合桩基础的施工方法,包括以下步骤:The embodiment of the present invention provides a kind of construction method of composite pile foundation, comprises the following steps:

步骤S1,在地面下沉钢管立柱,并开挖钢管立柱内的土;所述钢管立柱侧壁设有钢管斜桩的施工孔;Step S1, sinking the steel pipe column on the ground, and excavating the soil in the steel pipe column; the side wall of the steel pipe column is provided with a construction hole for a steel pipe inclined pile;

步骤S2,通过钢管立柱向下钻孔,形成钻孔灌注桩的灌注桩孔,钻孔过程中泥浆护壁;Step S2, drilling down through the steel pipe column to form the cast-in-place pile hole of the bored pile, and the mud retaining wall during the drilling process;

步骤S3,通过钢管立柱下钢筋笼,钢筋笼自灌注桩孔底部向上延伸至进入钢管立柱内底部一段;然后在灌注桩孔内和钢管立柱底部一段灌注混凝土,所灌注的混凝土覆盖钢筋笼进入钢管立柱内的笼段;第一次灌注混凝土后,形成了钻孔灌注桩;In step S3, the reinforcement cage is lowered through the steel pipe column, and the reinforcement cage extends upward from the bottom of the cast-in-place pile hole to the bottom section of the steel pipe column; then, concrete is poured into the cast-in-place pile hole and the bottom section of the steel pipe column, and the poured concrete covers the reinforcement cage and enters the steel pipe The cage section inside the column; after the first pour of concrete, the bored pile is formed;

步骤S4,在钢管立柱内通过千斤顶向斜下方斜顶钢管斜柱段,多个依次斜顶的钢管斜柱段相连形成钢管斜桩;在斜顶过程中,千斤顶通过千斤顶反力座支撑于钢管立柱内壁;Step S4, in the steel pipe column, use the jack to tilt the steel pipe inclined column section downwards, and the steel pipe inclined column sections that are inclined in turn are connected to form a steel pipe inclined pile; during the inclined jacking process, the jack is supported on the steel pipe through the jack reaction seat column inner wall;

步骤S5,根据设计要求,逐个完成各钢管斜桩的斜顶施工,然后将各钢管斜桩与钢管立柱连接;Step S5, according to the design requirements, complete the inclined roof construction of each steel pipe inclined pile one by one, and then connect each steel pipe inclined pile to the steel pipe column;

步骤S6,在钢管立柱内灌注混凝土,第二次灌注混凝土后形成钢管混凝土立柱。Step S6, pouring concrete into the steel pipe column, and forming the steel pipe concrete column after pouring concrete for the second time.

优选地,钢管立柱的直径不小于2.5m。Preferably, the diameter of the steel pipe column is not less than 2.5m.

优选地,步骤S3中,钢筋笼进入钢管立柱内的距离为1m~2m。Preferably, in step S3, the distance for the reinforcement cage to enter into the steel pipe column is 1 m to 2 m.

进一步地,所述钢筋笼顶部延伸出桩顶钢筋;步骤S4中对妨碍钢管斜柱段斜顶施工的桩顶钢筋先临时掰开再进行斜顶施工。Further, the top of the reinforcement cage extends out of the pile top reinforcement; in step S4, the pile top reinforcement that hinders the construction of the inclined roof of the steel pipe inclined column section is temporarily broken apart and then the inclined roof is constructed.

进一步地,所述钢筋笼顶部延伸出桩顶钢筋;步骤S6中第二次灌注的混凝土与桩顶钢筋连接。Further, the pile top reinforcement extends from the top of the reinforcement cage; in step S6, the concrete poured for the second time is connected with the pile top reinforcement.

优选地,第二次灌注的混凝土填充钢管斜桩顶部的钢管斜柱段。Preferably, the second poured concrete fills the steel pipe inclined column section at the top of the steel pipe inclined pile.

通过以上施工方法得到一种组合桩基础,包括:钢管混凝土立柱、钻孔灌注桩、钢管斜桩;A composite pile foundation is obtained through the above construction methods, including: steel pipe concrete columns, bored piles, and steel pipe inclined piles;

所述钻孔灌注桩竖向设置,用于竖向置入地基中;The bored piles are arranged vertically for being placed vertically into the foundation;

所述钢管混凝土立柱连接在钻孔灌注桩顶端,竖向设置,用于竖向置入地基中;The concrete-filled steel pipe column is connected to the top of the bored pile and arranged vertically for vertical insertion into the foundation;

所述钢管斜桩斜向连接钢管混凝土立柱,用于向斜下方置入地基中。The steel pipe inclined pile is obliquely connected to the steel pipe concrete column, and is used to be inserted into the foundation obliquely downward.

可选地,所述钢管斜桩连接在钢管混凝土立柱的一侧或两侧。Optionally, the steel pipe inclined pile is connected to one side or both sides of the steel pipe concrete column.

进一步地,所述钻孔灌注桩通过在灌注桩孔中设置钢筋笼并灌注混凝土形成;所述钢管混凝土立柱包括钢管立柱;所述钢筋笼自钻孔灌注桩向上延伸至进入钢管立柱内底部一段;所述钢筋笼顶部延伸出桩顶钢筋;所述钢管立柱中灌注有混凝土。Further, the bored cast-in-place pile is formed by setting a reinforcement cage in the cast-in-place pile hole and pouring concrete; the steel pipe concrete column includes a steel pipe column; the steel cage extends upward from the bored cast-in-place pile to a section at the bottom of the steel pipe column ; the top of the reinforcement cage extends out of the pile top reinforcement; the steel pipe column is poured with concrete.

更进一步地,所述钢管斜桩与钢管立柱连接,且钢管斜桩顶部的钢管斜柱段与钢管立柱一起灌注有混凝土。Furthermore, the steel pipe inclined pile is connected with the steel pipe column, and the steel pipe inclined column section at the top of the steel pipe inclined pile is poured with concrete together with the steel pipe column.

本发明实施例提供的技术方案带来的有益效果是:本申请通过钢管混凝土立柱、钻孔灌注桩和钢管斜桩组合构成组合桩基础,在施工过程中,构件相互间为其他施工工序提供有利的条件,提高了施工可靠度,降低施工成本,达到了很好的协调作用;最终实现提供竖向承载力、水平承载力、抗剪功能的组合桩基础。相较于现有的钻孔灌注桩群桩基础,本申请既可以降低成本,又能够提供竖向承载力和水平承载力俱佳的桩基础。The beneficial effect brought by the technical solution provided by the embodiment of the present invention is: the application forms a combined pile foundation through the combination of steel pipe concrete columns, bored piles and steel pipe inclined piles. During the construction process, the components provide advantages for other construction processes. The condition improves the construction reliability, reduces the construction cost, and achieves a good coordination effect; finally realizes the composite pile foundation that provides vertical bearing capacity, horizontal bearing capacity, and shear resistance. Compared with the existing pile group foundation of bored piles, the present application can not only reduce the cost, but also provide a pile foundation with excellent vertical bearing capacity and horizontal bearing capacity.

附图说明Description of drawings

图1为本发明实施例中的下沉钢管立柱示意图。Fig. 1 is a schematic diagram of a sinking steel pipe column in an embodiment of the present invention.

图2为本发明实施例中的钻灌注桩孔示意图。Fig. 2 is a schematic diagram of the drilled cast-in-situ pile hole in the embodiment of the present invention.

图3为本发明实施例中的下钢筋笼和第一次灌注混凝土示意图。Fig. 3 is a schematic diagram of the lower reinforcement cage and the first pouring of concrete in the embodiment of the present invention.

图4为本发明实施例中的钢管斜桩斜顶施工示意图。Fig. 4 is a schematic diagram of the construction of the inclined roof of steel pipe inclined piles in the embodiment of the present invention.

图5为本发明实施例中的逐个完成各钢管斜桩斜顶施工和连接示意图。Fig. 5 is a schematic diagram of the construction and connection of the inclined roofs of steel pipe inclined piles one by one in the embodiment of the present invention.

图6为本发明实施例中的第二次灌注混凝土后形成钢管混凝土立柱示意图。Fig. 6 is a schematic diagram of forming a concrete-filled steel tube column after pouring concrete for the second time in an embodiment of the present invention.

具体实施方式Detailed ways

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

本发明的实施例提供一种组合桩基础的施工方法,包括以下步骤:Embodiments of the present invention provide a construction method for a combined pile foundation, comprising the following steps:

步骤S1,如图1所示,在地面1下沉钢管立柱201,并开挖钢管立柱201内的土;所述钢管立柱201侧壁设有钢管斜桩的施工孔;钢管立柱201可作为挖土维护结构,以及作为后续钻孔灌注桩3的施工护筒;Step S1, as shown in Figure 1, sinks the steel pipe column 201 on the ground 1, and excavates the soil in the steel pipe column 201; the side wall of the steel pipe column 201 is provided with a construction hole for a steel pipe inclined pile; the steel pipe column 201 can be used as an excavation Soil maintenance structure, and as the construction casing of follow-up bored pile 3;

为了方便后续钢管斜桩4的施工,钢管立柱201的直径不小于2.5m,其空间作为施工斜桩的空间;钢管立柱201的高度为5m~10m;In order to facilitate the subsequent construction of the steel pipe inclined pile 4, the diameter of the steel pipe column 201 is not less than 2.5m, and its space is used as a space for constructing the inclined pile; the height of the steel pipe column 201 is 5m to 10m;

步骤S2,如图2所示,通过钢管立柱201向下钻孔,形成钻孔灌注桩3的灌注桩孔301,钻孔过程中泥浆护壁;钢管立柱201可作为钻孔灌注桩3的施工护筒;Step S2, as shown in Figure 2, drills down through the steel pipe column 201 to form the cast-in-place pile hole 301 of the bored pile 3, and the mud wall during the drilling process; the steel pipe column 201 can be used as the construction protection of the bored pile 3 cylinder;

步骤S3,如图3所示,通过钢管立柱201下钢筋笼302,钢筋笼302自灌注桩孔301底部向上延伸至进入钢管立柱201内底部一段;然后在灌注桩孔301内和钢管立柱201底部一段灌注混凝土,所灌注的混凝土覆盖钢筋笼302进入钢管立柱201内的笼段;Step S3, as shown in FIG. 3 , the reinforcement cage 302 is lowered through the steel pipe column 201, and the reinforcement cage 302 extends upward from the bottom of the cast-in-place pile hole 301 to a section at the bottom of the steel pipe column 201; Concrete is poured in one section, and the poured concrete covers the steel cage 302 and enters the cage section in the steel pipe column 201;

第一次灌注混凝土后,就形成了钻孔灌注桩3;After pouring concrete for the first time, the bored pile 3 is formed;

作为本实施例的优化,钢筋笼302进入钢管立柱201内的距离为1m~2m;以便在第一次灌注混凝土时,钢管立柱201能够与钻孔灌注桩3形成结构连接,便于在后续施工钢管斜桩时,钢管立柱201和钻孔灌注桩3一起作为顶推施工的反力装置;由于在顶进斜桩的过程中,有较大是竖向反力(向上),需要已经施工好的钻孔灌注桩承担,因而需要钻孔灌注桩与钢管立柱的可靠连接;As an optimization of this embodiment, the distance for the steel cage 302 to enter the steel pipe column 201 is 1m to 2m; so that when the concrete is poured for the first time, the steel pipe column 201 can form a structural connection with the bored pile 3, which is convenient for subsequent construction of the steel pipe When the inclined pile is used, the steel pipe column 201 and the bored pile 3 are used together as the reaction force device for the jacking construction; since there is a relatively large vertical reaction force (upward) during the process of jacking the inclined pile, it needs to be constructed Bored cast-in-place piles bear the burden, so a reliable connection between bored piles and steel pipe columns is required;

作为本实施例的优化,钢筋笼302顶部延伸出桩顶钢筋303;桩顶钢筋303可以在第二次灌注混凝土时,加强与第一次灌注的混凝土的连接;As an optimization of this embodiment, the top of the reinforcement cage 302 extends out of the pile top reinforcement 303; the pile top reinforcement 303 can strengthen the connection with the first poured concrete when the concrete is poured for the second time;

步骤S4,如图4所示,在钢管立柱201内通过千斤顶5向斜下方斜顶钢管斜柱段401,多个依次斜顶的钢管斜柱段401相连形成钢管斜桩4;在斜顶过程中,千斤顶5通过千斤顶反力座6支撑于钢管立柱201内壁,通过钢管立柱201内壁获得很大的反作用力,此反作用力通过相连接的钢管立柱201和钻孔灌注桩3一起提供;Step S4, as shown in FIG. 4 , in the steel pipe column 201, the steel pipe inclined column section 401 is inclined downward through the jack 5, and a plurality of steel pipe inclined column sections 401 that are inclined in turn are connected to form a steel pipe inclined pile 4; Among them, the jack 5 is supported on the inner wall of the steel pipe column 201 through the jack reaction force seat 6, and a large reaction force is obtained through the inner wall of the steel pipe column 201, and the reaction force is provided together by the connected steel pipe column 201 and the bored pile 3;

当钢筋笼302顶部具有桩顶钢筋303时,可以对妨碍钢管斜柱段401斜顶施工的桩顶钢筋303先临时掰开再进行斜顶施工;When there is a pile top reinforcement 303 on the top of the reinforcement cage 302, the pile top reinforcement 303 that hinders the construction of the steel pipe inclined column section 401 can be temporarily broken apart and then the construction of the slope can be carried out;

步骤S5,如图5所示,根据设计要求,逐个完成各钢管斜桩4的斜顶施工,然后将各钢管斜桩4与钢管立柱201连接;例如通过焊接进行连接;Step S5, as shown in Figure 5, according to the design requirements, complete the construction of the inclined roof of each steel pipe inclined pile 4 one by one, and then connect each steel pipe inclined pile 4 with the steel pipe column 201; for example, connect by welding;

根据组合桩基础的受力需求,各钢管斜桩4可以分布在钢管立柱201的一侧或两侧;According to the stress requirements of the combined pile foundation, each steel pipe inclined pile 4 can be distributed on one side or both sides of the steel pipe column 201;

步骤S6,如图6所示,在钢管立柱201内灌注混凝土,第二次灌注混凝土后形成钢管混凝土立柱2;Step S6, as shown in FIG. 6 , pour concrete into the steel pipe column 201, and form the steel pipe concrete column 2 after pouring concrete for the second time;

当钢筋笼302顶部具有桩顶钢筋303时,第二次灌注的混凝土可以与桩顶钢筋303连接,以便加强前后两次灌注的混凝土之间的连接牢固程度;When the top of the reinforcement cage 302 has a pile top reinforcement 303, the concrete poured for the second time can be connected with the pile top reinforcement 303, so as to strengthen the connection firmness between the concrete poured twice before and after;

作为本实施例的优化,第二次灌注的混凝土填充钢管斜桩4顶部的钢管斜柱段401;可以增强钢管斜桩4与钢管混凝土立柱2的连接强度;As an optimization of this embodiment, the concrete poured for the second time fills the steel pipe inclined column section 401 at the top of the steel pipe inclined pile 4; the connection strength between the steel pipe inclined pile 4 and the steel pipe concrete column 2 can be enhanced;

通过以上施工方法,得到一种组合桩基础,包括:钢管混凝土立柱2、钻孔灌注桩3、钢管斜桩4;Through the above construction method, a composite pile foundation is obtained, including: steel pipe concrete column 2, bored cast-in-place pile 3, steel pipe inclined pile 4;

所述钻孔灌注桩3竖向设置,用于竖向置入地基中,主要提供竖向承载力;The bored cast-in-place pile 3 is arranged vertically, and is used for vertically inserting into the foundation, mainly providing vertical bearing capacity;

所述钢管混凝土立柱2连接在钻孔灌注桩3顶端,竖向设置,用于竖向置入地基中,主要承担基础的抗剪承载力;The concrete-filled steel pipe column 2 is connected to the top of the bored cast-in-situ pile 3, and is vertically arranged for being vertically inserted into the foundation, and mainly bears the shear bearing capacity of the foundation;

所述钢管斜桩4斜向连接钢管混凝土立柱2,用于向斜下方置入地基中;The steel pipe inclined pile 4 is obliquely connected to the steel pipe concrete column 2, and is used to be inserted into the foundation obliquely downward;

可选地,所述钢管斜桩4连接在钢管混凝土立柱2的一侧或两侧,对于单向水平力基础,如拱桥基础,仅在单侧设置,对于双向水平力基础,如特大桥桥墩基础,则可采用双侧设置;Optionally, the steel pipe inclined pile 4 is connected to one or both sides of the steel pipe concrete column 2. For a one-way horizontal force foundation, such as an arch bridge foundation, it is only set on one side; for a two-way horizontal force foundation, such as an extra-large bridge pier foundation, you can use bilateral settings;

作为本实施例的优化,所述钻孔灌注桩3通过在灌注桩孔301中设置钢筋笼302并灌注混凝土形成;所述钢管混凝土立柱2包括钢管立柱201;所述钢筋笼302自钻孔灌注桩3向上延伸至进入钢管立柱201内底部一段;所述钢筋笼302顶部延伸出桩顶钢筋303;所述钢管立柱201中灌注有混凝土;As an optimization of this embodiment, the bored cast-in-place pile 3 is formed by setting a reinforcement cage 302 in the cast-in-place pile hole 301 and pouring concrete; the steel pipe concrete column 2 includes a steel pipe column 201; the steel cage 302 is poured from the borehole The pile 3 extends upwards to a section at the bottom of the steel pipe column 201; the top of the steel cage 302 extends out of the pile top steel bar 303; the steel pipe column 201 is poured with concrete;

作为本实施例的优化,所述钢管斜桩4与钢管立柱201连接,且钢管斜桩4顶部的钢管斜柱段401与钢管立柱201一起灌注有混凝土;As an optimization of this embodiment, the steel pipe inclined pile 4 is connected to the steel pipe column 201, and the steel pipe inclined column section 401 at the top of the steel pipe inclined pile 4 is poured with concrete together with the steel pipe column 201;

上述组合桩基础中,钻孔灌注桩3主要提供竖向承载力,钢管斜桩4可以提供水平承载力和竖向承载力,钢管混凝土立柱2可以提供水平推力,也提供了竖向承载力;最终实现提供竖向承载力、水平承载力、抗剪功能的组合桩基础。In the above composite pile foundation, the bored cast-in-situ pile 3 mainly provides vertical bearing capacity, the steel pipe inclined pile 4 can provide horizontal bearing capacity and vertical bearing capacity, and the steel pipe concrete column 2 can provide horizontal thrust and also provide vertical bearing capacity; Finally, the composite pile foundation that provides vertical bearing capacity, horizontal bearing capacity and shear resistance function is realized.

最后所应说明的是,以上具体实施方式仅用以说明本发明的技术方案而非限制,尽管参照实例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的精神和范围,其均应涵盖在本发明的权利要求范围当中。Finally, it should be noted that the above specific embodiments are only used to illustrate the technical solutions of the present invention without limitation, although the present invention has been described in detail with reference to examples, those of ordinary skill in the art should understand that the technical solutions of the present invention can be carried out Modifications or equivalent replacements without departing from the spirit and scope of the technical solution of the present invention shall be covered by the claims of the present invention.

Claims (3)

1.一种组合桩基础的施工方法,其特征在于,包括以下步骤:1. A construction method of combined pile foundation, is characterized in that, comprises the following steps: 步骤S1,在地面(1)下沉钢管立柱(201),并开挖钢管立柱(201)内的土;所述钢管立柱(201)侧壁设有钢管斜桩的施工孔;Step S1, sinking the steel pipe column (201) on the ground (1), and excavating the soil inside the steel pipe column (201); the side wall of the steel pipe column (201) is provided with a construction hole for steel pipe inclined piles; 步骤S2,通过钢管立柱(201)向下钻孔,形成钻孔灌注桩(3)的灌注桩孔(301),钻孔过程中泥浆护壁;Step S2, drilling down through the steel pipe column (201) to form the cast-in-place pile hole (301) of the bored cast-in-place pile (3), and the mud retaining wall during the drilling process; 步骤S3,通过钢管立柱(201)下钢筋笼(302),钢筋笼(302)自灌注桩孔(301)底部向上延伸至进入钢管立柱(201)内底部一段;然后在灌注桩孔(301)内和钢管立柱(201)底部一段灌注混凝土,所灌注的混凝土覆盖钢筋笼(302)进入钢管立柱(201)内的笼段;第一次灌注混凝土后,形成了钻孔灌注桩(3);Step S3, lower the reinforcement cage (302) through the steel pipe column (201), and the reinforcement cage (302) extends upward from the bottom of the cast-in-place pile hole (301) to a section at the inner bottom of the steel pipe column (201); Concrete is poured into the bottom section of the inner and steel pipe column (201), and the poured concrete covers the reinforcement cage (302) and enters the cage section in the steel pipe column (201); after the first pouring of concrete, a bored cast-in-place pile (3) is formed; 步骤S4,在钢管立柱(201)内通过千斤顶(5)向斜下方斜顶钢管斜柱段(401),多个依次斜顶的钢管斜柱段(401)相连形成钢管斜桩(4);在斜顶过程中,千斤顶(5)通过千斤顶反力座(6)支撑于钢管立柱(201)内壁;Step S4, in the steel pipe column (201), the steel pipe inclined column section (401) is tilted downward through the jack (5), and a plurality of steel pipe inclined column sections (401) are connected to form a steel pipe inclined column section (4); During the inclined jacking process, the jack (5) is supported on the inner wall of the steel pipe column (201) through the jack reaction seat (6); 步骤S5,根据设计要求,逐个完成各钢管斜桩(4)的斜顶施工,然后将各钢管斜桩(4)与钢管立柱(201)连接;Step S5, according to the design requirements, complete the inclined roof construction of each steel pipe inclined pile (4) one by one, and then connect each steel pipe inclined pile (4) with the steel pipe column (201); 步骤S6,在钢管立柱(201)内灌注混凝土,第二次灌注混凝土后形成钢管混凝土立柱(2);Step S6, pouring concrete into the steel pipe column (201), and forming the steel pipe concrete column (2) after pouring concrete for the second time; 所述钢筋笼(302)顶部延伸出桩顶钢筋(303);步骤S4中对妨碍钢管斜柱段(401)斜顶施工的桩顶钢筋(303)先临时掰开再进行斜顶施工;The pile top reinforcement (303) is extended from the top of the reinforcement cage (302); in step S4, the pile top reinforcement (303) that hinders the construction of the inclined roof of the steel pipe inclined column section (401) is temporarily broken apart and then the inclined roof construction is performed; 所述钢筋笼(302)顶部延伸出桩顶钢筋(303);步骤S6中第二次灌注的混凝土与桩顶钢筋(303)连接;The pile top reinforcement (303) is extended from the top of the reinforcement cage (302); the concrete poured for the second time in step S6 is connected with the pile top reinforcement (303); 第二次灌注的混凝土填充钢管斜桩(4)顶部的钢管斜柱段(401)。The concrete poured for the second time fills the steel pipe inclined column section (401) at the top of the steel pipe inclined pile (4). 2.如权利要求1所述的组合桩基础的施工方法,其特征在于,2. the construction method of composite pile foundation as claimed in claim 1, is characterized in that, 钢管立柱(201)的直径不小于2.5m。The diameter of the steel pipe column (201) is not less than 2.5m. 3.如权利要求1所述的组合桩基础的施工方法,其特征在于,3. the construction method of composite pile foundation as claimed in claim 1, is characterized in that, 步骤S3中,钢筋笼(302)进入钢管立柱(201)内的距离为1m~2m。In step S3, the distance for the reinforcement cage (302) to enter into the steel pipe column (201) is 1m-2m.
CN202111161651.5A 2021-09-30 2021-09-30 Construction method of composite pile foundation and composite pile foundation Active CN113684852B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111161651.5A CN113684852B (en) 2021-09-30 2021-09-30 Construction method of composite pile foundation and composite pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111161651.5A CN113684852B (en) 2021-09-30 2021-09-30 Construction method of composite pile foundation and composite pile foundation

Publications (2)

Publication Number Publication Date
CN113684852A CN113684852A (en) 2021-11-23
CN113684852B true CN113684852B (en) 2023-02-28

Family

ID=78587579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111161651.5A Active CN113684852B (en) 2021-09-30 2021-09-30 Construction method of composite pile foundation and composite pile foundation

Country Status (1)

Country Link
CN (1) CN113684852B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059063A (en) * 2022-07-22 2022-09-16 广州环投南沙环保能源有限公司 A kind of pile foundation with large settlement and reinforcement method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100803558B1 (en) * 2007-09-11 2008-02-15 현대엔지니어링 주식회사 Reinforced single casting site foundation and construction method
CN101139837A (en) * 2007-08-02 2008-03-12 夏良站 Construction plant for tree-root shaped pile
CN109487811A (en) * 2018-12-18 2019-03-19 温州电力设计有限公司 A kind of lateral tree root caisson and its installation equipment
CN110453720A (en) * 2019-08-21 2019-11-15 中交二公局第五工程有限公司 A kind of steel pipe post of big load falsework structure and basic connecting structure and its construction method
CN111364494A (en) * 2020-04-02 2020-07-03 中国电建集团华东勘测设计研究院有限公司 An offshore high pile cap foundation supported by anchor cables and inclined straight piles and its construction method
CN213267973U (en) * 2020-08-26 2021-05-25 广东宏泰建设有限公司 Pile foundation reinforced structure constructed by adopting composite piles

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101139837A (en) * 2007-08-02 2008-03-12 夏良站 Construction plant for tree-root shaped pile
KR100803558B1 (en) * 2007-09-11 2008-02-15 현대엔지니어링 주식회사 Reinforced single casting site foundation and construction method
CN109487811A (en) * 2018-12-18 2019-03-19 温州电力设计有限公司 A kind of lateral tree root caisson and its installation equipment
CN110453720A (en) * 2019-08-21 2019-11-15 中交二公局第五工程有限公司 A kind of steel pipe post of big load falsework structure and basic connecting structure and its construction method
CN111364494A (en) * 2020-04-02 2020-07-03 中国电建集团华东勘测设计研究院有限公司 An offshore high pile cap foundation supported by anchor cables and inclined straight piles and its construction method
CN213267973U (en) * 2020-08-26 2021-05-25 广东宏泰建设有限公司 Pile foundation reinforced structure constructed by adopting composite piles

Also Published As

Publication number Publication date
CN113684852A (en) 2021-11-23

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down construction method using ready-made concrete pillar member
CN201280720Y (en) Minor diameter self-balancing filling pile root key pushing device
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN109235507B (en) A ground reinforcement system and method for reinforcing existing tunnels
CN107642041A (en) Super large diameter hollow pile group anchorage
CN114439015A (en) Construction method for improving rock-socketed depth of large-diameter cast-in-place pile
CN104389315B (en) Consolidation grouting drilled pile wall and construction method thereof
CN108316670B (en) Steel pipe underpinning construction method under existing building foundation
CN111236241B (en) Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method
CN209923935U (en) Co-location combined pile wall supporting structure in upper-soft and lower-hard stratum
CN205242441U (en) Oval contrary shaft of doing of suspension type
CN107642040A (en) The construction method heavy stone used as an anchor of the hollow clump of piles anchorage of super-large diameter
CN113684852B (en) Construction method of composite pile foundation and composite pile foundation
CN105220720A (en) Building foundation, Collapsible Loess District reinforcing pile and pressing pile construction method thereof
CN114635580B (en) Underground storey-adding underpinning structure utilizing existing building foundation structure and construction method thereof
CN116479897A (en) Shallow foundation pit collapse rapid reinforcement supporting method with depth smaller than 10m
CN115198787B (en) Steel tube column type tower crane foundation and construction method thereof, and cover-excavation reverse construction method
CN210766861U (en) Pile foundation underpinning structure of portal-type building under narrow space
CN118911155A (en) Deep foundation pit supporting device and construction method
CN217870431U (en) Subside pile foundation
CN217053396U (en) Long steel pile casing for combined construction of vibration hammer and rotary drilling
CN212317545U (en) An existing foundation upper and lower column connection structure for expanding underground space
CN109989415B (en) Construction method of fabricated foundation
CN115653024A (en) A Deviation Correction Method for Valve Plate Foundation Building
CN114482071A (en) Device for improving rock-socketed depth of large-diameter cast-in-place pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 214000 21-14a, Jiefang North Road, Wuxi City, Jiangsu Province

Patentee after: Jiangsu Kejia Design Group Co.,Ltd.

Country or region after: China

Address before: 214000 21-14a, Jiefang North Road, Liangxi District, Wuxi City, Jiangsu Province

Patentee before: JIANGSU KEJIA ENGINEERING DESIGN Co.,Ltd.

Country or region before: China