CN113684852A - Construction method of combined pile foundation and combined pile foundation - Google Patents
Construction method of combined pile foundation and combined pile foundation Download PDFInfo
- Publication number
- CN113684852A CN113684852A CN202111161651.5A CN202111161651A CN113684852A CN 113684852 A CN113684852 A CN 113684852A CN 202111161651 A CN202111161651 A CN 202111161651A CN 113684852 A CN113684852 A CN 113684852A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- pile
- upright post
- steel
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 39
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 186
- 239000010959 steel Substances 0.000 claims abstract description 186
- 239000004567 concrete Substances 0.000 claims abstract description 64
- 230000002787 reinforcement Effects 0.000 claims abstract description 32
- 238000000034 method Methods 0.000 claims abstract description 17
- 238000005553 drilling Methods 0.000 claims abstract description 7
- 239000002689 soil Substances 0.000 claims abstract description 4
- 238000011065 in-situ storage Methods 0.000 claims description 31
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 2
- 239000002002 slurry Substances 0.000 claims description 2
- 239000002131 composite material Substances 0.000 claims 6
- 238000010008 shearing Methods 0.000 abstract description 5
- 238000005457 optimization Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 238000005452 bending Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000002349 favourable effect Effects 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000002457 bidirectional effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
- E02D5/285—Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/665—Mould-pipes or other moulds for making piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/68—Mould-pipes or other moulds for making bulkheads or elements thereof
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention provides a construction method of a combined pile foundation, which comprises the following steps: sinking the steel pipe upright post on the ground, and excavating soil in the steel pipe upright post; the side wall of the steel pipe upright post is provided with a construction hole of the steel pipe inclined pile; drilling downwards through the steel pipe upright column to form a cast-in-place pile hole of the cast-in-place pile; a reinforcement cage is arranged under the steel pipe upright post, and the reinforcement cage extends upwards from the bottom of the pile grouting hole to a section of the reinforcement cage entering the bottom in the steel pipe upright post; then pouring concrete into the hole of the cast-in-place pile and the bottom section of the steel tube upright post, wherein the poured concrete covers a cage section of the steel reinforcement cage entering the steel tube upright post; obliquely ejecting steel pipe inclined column sections in the steel pipe upright column towards the lower part obliquely through a jack, and connecting a plurality of sequentially obliquely ejected steel pipe inclined column sections to form a steel pipe inclined pile; in the process of jacking the inclined top, the jack is supported on the inner wall of the steel pipe upright post through the jack counterforce seat; the construction of the inclined top of each steel pipe inclined pile is completed one by one; and pouring concrete into the steel pipe upright. Finally, the combined pile foundation with the functions of providing vertical bearing capacity, horizontal bearing capacity and shearing resistance is realized.
Description
Technical Field
The invention relates to a foundation in civil engineering, in particular to a construction method of a combined pile foundation and the combined pile foundation.
Background
Cast-in-situ bored piles are commonly used as foundation forms, are indispensable in almost all civil engineering such as bridge engineering, building engineering, wharf engineering, and the like, can provide good vertical bearing capacity, but have poor horizontal bearing capacity.
For the foundations which generally need to provide large horizontal bearing capacity, such as bridge piers, anti-collision piers, arch bridge pier foundation and the like, mostly adopted are bored cast-in-place pile group pile foundations, which are characterized in that bending moment generated by original horizontal force is converted into pile foundation axial force, and the pile foundation bears shearing force, however, the shearing level of the pile foundation is often low, and the efficiency of the pile foundation for bearing foundation bending moment effect is relatively low.
Disclosure of Invention
The invention aims to overcome the defects in the prior art, and provides a construction method of a combined pile foundation, which can provide favorable conditions for other construction procedures among members in the construction process, improve the construction reliability, reduce the construction cost and achieve good coordination; finally, a combined pile foundation with vertical bearing capacity, horizontal bearing capacity and shear resistance functions is realized; the invention also provides a combined pile foundation formed by the construction method. In order to achieve the technical purpose, the embodiment of the invention adopts the technical scheme that:
the embodiment of the invention provides a construction method of a combined pile foundation, which comprises the following steps:
step S1, sinking the steel tube upright post on the ground, and excavating the soil in the steel tube upright post; the side wall of the steel pipe upright post is provided with a construction hole of the steel pipe inclined pile;
step S2, drilling downwards through the steel pipe upright column to form a cast-in-place pile hole of the cast-in-place pile, and performing slurry wall protection in the drilling process;
step S3, putting a reinforcement cage through the steel pipe upright post, wherein the reinforcement cage extends upwards from the bottom of the pile grouting hole to a section of the reinforcement cage entering the bottom in the steel pipe upright post; then pouring concrete into the hole of the cast-in-place pile and the bottom section of the steel tube upright post, wherein the poured concrete covers a cage section of the steel reinforcement cage entering the steel tube upright post; after the concrete is poured for the first time, a cast-in-situ bored pile is formed;
step S4, obliquely ejecting steel pipe inclined column sections in the steel pipe upright column towards the lower part through a jack, and connecting a plurality of sequentially obliquely ejected steel pipe inclined column sections to form a steel pipe inclined pile; in the process of jacking the inclined top, the jack is supported on the inner wall of the steel pipe upright post through the jack counterforce seat;
step S5, finishing the pitched roof construction of each steel pipe inclined pile one by one according to the design requirement, and then connecting each steel pipe inclined pile with the steel pipe upright post;
and step S6, pouring concrete into the steel tube upright post, and forming the steel tube concrete upright post after the concrete is poured for the second time.
Preferably, the diameter of the steel tube column is not less than 2.5 m.
Preferably, in step S3, the distance that the reinforcement cage enters the steel tube column is 1m to 2 m.
Furthermore, pile top steel bars extend out of the top of the steel bar cage; in step S4, pile top reinforcing steel bars that hinder the inclined top construction of the steel pipe inclined column section are temporarily broken off and then inclined top construction is performed.
Furthermore, pile top steel bars extend out of the top of the steel bar cage; and (8) connecting the concrete poured for the second time in the step S6 with the pile top steel bars.
Preferably, the second poured concrete fills the steel pipe batter post section at the top of the steel pipe batter post.
The combined pile foundation obtained by the construction method comprises the following steps: concrete-filled steel tube columns, cast-in-situ bored piles and steel tube inclined piles;
the cast-in-situ bored pile is vertically arranged and is used for being vertically placed into a foundation;
the steel pipe concrete upright is connected to the top end of the cast-in-situ bored pile, is vertically arranged and is vertically placed into a foundation;
the steel pipe inclined pile is obliquely connected with the steel pipe concrete upright post and is used for being placed into the foundation obliquely downwards.
Optionally, the steel pipe batter pile is connected to one side or both sides of the steel pipe concrete upright post.
Further, the cast-in-situ bored pile is formed by arranging a reinforcement cage in a cast-in-situ pile hole and pouring concrete; the steel tube concrete upright column comprises a steel tube upright column; the reinforcement cage extends upwards from the cast-in-situ bored pile to a section of the bottom of the steel pipe column; pile top steel bars extend out of the top of the steel bar cage; concrete is poured into the steel tube upright columns.
Furthermore, the steel pipe inclined pile is connected with the steel pipe upright post, and the steel pipe inclined post section at the top of the steel pipe inclined pile and the steel pipe upright post are poured with concrete.
The technical scheme provided by the embodiment of the invention has the following beneficial effects: according to the combined pile foundation, the steel pipe concrete upright columns, the cast-in-situ bored piles and the steel pipe inclined piles are combined to form the combined pile foundation, and in the construction process, the members provide favorable conditions for other construction procedures, so that the construction reliability is improved, the construction cost is reduced, and a good coordination effect is achieved; finally, the combined pile foundation with the functions of providing vertical bearing capacity, horizontal bearing capacity and shearing resistance is realized. Compared with the existing pile foundation of the bored pile group, the pile foundation of the bored pile group has the advantages that the cost can be reduced, and the pile foundation with good vertical bearing capacity and horizontal bearing capacity can be provided.
Drawings
Fig. 1 is a schematic view of a sinking steel pipe column in the embodiment of the invention.
Fig. 2 is a schematic view of bored concrete pile holes according to an embodiment of the present invention.
Fig. 3 is a schematic view showing the lower cage and the first concrete pouring in accordance with the embodiment of the present invention.
Fig. 4 is a schematic diagram of the construction of the inclined top of the steel pipe inclined pile in the embodiment of the invention.
FIG. 5 is a schematic diagram of the construction and connection of the inclined top of each steel pipe inclined pile completed one by one in the embodiment of the invention.
Fig. 6 is a schematic diagram of a concrete filled steel tube column formed after concrete is poured for the second time in the embodiment of the invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
The embodiment of the invention provides a construction method of a combined pile foundation, which comprises the following steps:
step S1, as shown in fig. 1, sinking the steel pipe upright 201 on the ground 1, and excavating the soil in the steel pipe upright 201; the side wall of the steel pipe upright column 201 is provided with a construction hole of a steel pipe inclined pile; the steel pipe upright 201 can be used as an excavation maintenance structure and a construction casing of a subsequent cast-in-situ bored pile 3;
in order to facilitate the construction of the following steel pipe inclined pile 4, the diameter of the steel pipe upright column 201 is not less than 2.5m, and the space is used as the space for constructing the inclined pile; the height of the steel tube upright 201 is 5 m-10 m;
step S2, as shown in fig. 2, drilling downward through the steel pipe column 201 to form a cast-in-place pile hole 301 of the cast-in-place pile 3, and performing mud wall protection in the drilling process; the steel pipe upright 201 can be used as a construction casing of the cast-in-situ bored pile 3;
step S3, as shown in fig. 3, the steel reinforcement cage 302 is lowered through the steel pipe column 201, and the steel reinforcement cage 302 extends upward from the bottom of the pile grouting hole 301 to a section of the steel pipe column 201; then pouring concrete into the cast-in-place pile hole 301 and the bottom section of the steel tube upright 201, wherein the poured concrete covers a cage section of the reinforcement cage 302 entering the steel tube upright 201;
after the concrete is poured for the first time, a cast-in-situ bored pile 3 is formed;
as optimization of the embodiment, the distance from the reinforcement cage 302 to the steel tube column 201 is 1 m-2 m; so that the steel pipe upright 201 and the cast-in-situ bored pile 3 can form structural connection when concrete is poured for the first time, and the steel pipe upright 201 and the cast-in-situ bored pile 3 can be used as a counterforce device for pushing construction together when a steel pipe inclined pile is constructed subsequently; in the process of jacking the inclined pile, a larger vertical counter force (upwards) exists, and the cast-in-situ bored pile which is constructed needs to bear, so that the cast-in-situ bored pile needs to be reliably connected with the steel pipe upright post;
as optimization of the embodiment, pile top steel bars 303 extend from the top of the steel reinforcement cage 302; the pile top steel bars 303 can strengthen the connection with the first poured concrete when the concrete is poured for the second time;
step S4, as shown in fig. 4, obliquely jacking a steel pipe diagonal column section 401 obliquely downward in the steel pipe column 201 by a jack 5, and connecting a plurality of steel pipe diagonal column sections 401 which are sequentially obliquely jacked to form a steel pipe diagonal pile 4; in the process of the pitched roof, the jack 5 is supported on the inner wall of the steel pipe upright post 201 through the jack counterforce seat 6, and a large counterforce is obtained through the inner wall of the steel pipe upright post 201 and is provided through the connected steel pipe upright post 201 and the cast-in-situ bored pile 3;
when the top of the reinforcement cage 302 is provided with the pile top reinforcements 303, the pile top reinforcements 303 which hinder the inclined top construction of the steel pipe inclined column section 401 can be temporarily broken off and then the inclined top construction can be carried out;
step S5, as shown in fig. 5, completing the pitched roof construction of each steel pipe inclined pile 4 one by one according to the design requirements, and then connecting each steel pipe inclined pile 4 with the steel pipe upright 201; the connection is made, for example, by welding;
according to the stress requirement of the combined pile foundation, the steel pipe inclined piles 4 can be distributed on one side or two sides of the steel pipe upright column 201;
step S6, as shown in fig. 6, pouring concrete into the steel pipe column 201, and forming a steel pipe concrete column 2 after pouring concrete for the second time;
when pile top steel bars 303 are arranged at the top of the steel bar cage 302, the second poured concrete can be connected with the pile top steel bars 303 so as to strengthen the connection firmness degree between the two poured concretes;
as optimization of the embodiment, the concrete poured for the second time fills the steel pipe inclined column section 401 at the top of the steel pipe inclined pile 4; the connection strength of the steel pipe inclined pile 4 and the steel pipe concrete upright post 2 can be enhanced;
through the construction method, the combined pile foundation is obtained and comprises the following steps: the concrete-filled steel tube pile comprises a concrete-filled steel tube column 2, a cast-in-situ bored pile 3 and a steel tube inclined pile 4;
the cast-in-situ bored pile 3 is vertically arranged and is vertically arranged in a foundation and mainly provides vertical bearing capacity;
the steel pipe concrete upright post 2 is connected to the top end of the cast-in-situ bored pile 3, is vertically arranged in a foundation and mainly bears the shear-resistant bearing capacity of the foundation;
the steel pipe inclined pile 4 is obliquely connected with the steel pipe concrete upright post 2 and is used for being placed into a foundation obliquely downwards;
optionally, the steel pipe inclined piles 4 are connected to one side or two sides of the steel pipe concrete upright post 2, and are arranged only on one side for a unidirectional horizontal force foundation such as an arch bridge foundation, and arranged on two sides for a bidirectional horizontal force foundation such as a grand bridge pier foundation;
as optimization of the present embodiment, the cast-in-situ bored pile 3 is formed by disposing a reinforcement cage 302 in a cast-in-situ bored pile hole 301 and pouring concrete; the steel pipe concrete upright 2 comprises a steel pipe upright 201; the reinforcement cage 302 extends upwards from the cast-in-situ bored pile 3 to a section of the bottom of the steel pipe upright 201; pile top steel bars 303 extend out of the top of the steel reinforcement cage 302; concrete is poured into the steel pipe upright 201;
as optimization of the embodiment, the steel pipe batter pile 4 is connected with the steel pipe upright 201, and the steel pipe batter pile section 401 at the top of the steel pipe batter pile 4 and the steel pipe upright 201 are poured with concrete;
in the combined pile foundation, the cast-in-situ bored pile 3 mainly provides vertical bearing capacity, the steel pipe inclined pile 4 can provide horizontal bearing capacity and vertical bearing capacity, and the steel pipe concrete upright 2 can provide horizontal thrust and vertical bearing capacity; finally, the combined pile foundation with the functions of providing vertical bearing capacity, horizontal bearing capacity and shearing resistance is realized.
Finally, it should be noted that the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, and although the present invention has been described in detail with reference to examples, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made on the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, which should be covered by the claims of the present invention.
Claims (10)
1. A construction method of a combined pile foundation is characterized by comprising the following steps:
s1, sinking the steel pipe upright post (201) on the ground (1), and excavating soil in the steel pipe upright post (201); the side wall of the steel pipe upright post (201) is provided with a construction hole of a steel pipe inclined pile;
step S2, drilling downwards through the steel pipe upright post (201) to form a cast-in-place pile hole (301) of the cast-in-place pile (3), and performing slurry wall protection in the drilling process;
step S3, a reinforcement cage (302) is arranged under the steel pipe upright post (201), and the reinforcement cage (302) extends upwards from the bottom of the cast-in-place pile hole (301) to a section of the bottom of the steel pipe upright post (201); then, pouring concrete into the cast-in-place pile hole (301) and a section of the bottom of the steel pipe upright post (201), wherein the poured concrete covers a cage section of the reinforcement cage (302) entering the steel pipe upright post (201); after the concrete is poured for the first time, a cast-in-situ bored pile (3) is formed;
step S4, obliquely ejecting steel pipe inclined column sections (401) towards the lower oblique direction through jacks (5) in the steel pipe upright columns (201), and connecting a plurality of sequentially obliquely ejected steel pipe inclined column sections (401) to form steel pipe inclined piles (4); in the process of jacking the steel pipe column (201), the jack (5) is supported on the inner wall of the steel pipe column (201) through the jack reaction seat (6);
step S5, finishing the inclined top construction of each steel pipe inclined pile (4) one by one according to design requirements, and then connecting each steel pipe inclined pile (4) with a steel pipe upright post (201);
and step S6, pouring concrete into the steel tube upright post (201) and forming the steel tube concrete upright post (2) after pouring the concrete for the second time.
2. The method of constructing a composite pile foundation according to claim 1,
the diameter of the steel pipe upright post (201) is not less than 2.5 m.
3. The method of constructing a composite pile foundation according to claim 1,
in step S3, the distance that the reinforcement cage (302) enters the steel tube upright post (201) is 1-2 m.
4. The method of constructing a composite pile foundation according to claim 1,
pile top steel bars (303) extend out of the top of the steel reinforcement cage (302); in step S4, pile top reinforcing steel bars (303) that hinder the inclined top construction of the steel pipe inclined column section (401) are temporarily broken off and then inclined top construction is performed.
5. The method of constructing a composite pile foundation according to claim 1,
pile top steel bars (303) extend out of the top of the steel reinforcement cage (302); the concrete poured for the second time in the step S6 is connected to the pile top reinforcement (303).
6. The method of constructing a composite pile foundation according to claim 1,
and filling the steel pipe inclined column section (401) at the top of the steel pipe inclined pile (4) with the concrete poured for the second time.
7. A composite pile foundation, comprising: the concrete-filled steel tube pile comprises a concrete-filled steel tube column (2), a cast-in-situ bored pile (3) and a steel tube inclined pile (4);
the cast-in-situ bored pile (3) is vertically arranged and is vertically placed into a foundation;
the steel pipe concrete upright post (2) is connected to the top end of the cast-in-situ bored pile (3), is vertically arranged and is vertically placed into a foundation;
the steel pipe inclined pile (4) is obliquely connected with the steel pipe concrete upright post (2) and is used for being placed into the foundation obliquely downwards.
8. The modular pile foundation of claim 7,
the steel pipe inclined piles (4) are connected to one side or two sides of the steel pipe concrete upright post (2).
9. The modular pile foundation of claim 7,
the cast-in-situ bored pile (3) is formed by arranging a reinforcement cage (302) in a cast-in-situ pile hole (301) and pouring concrete; the steel tube concrete upright post (2) comprises a steel tube upright post (201); the reinforcement cage (302) extends upwards from the cast-in-situ bored pile (3) to a section of the bottom of the steel pipe column (201); pile top steel bars (303) extend out of the top of the steel reinforcement cage (302); concrete is poured into the steel pipe upright column (201).
10. The modular pile foundation of claim 9,
the steel pipe inclined pile (4) is connected with the steel pipe upright post (201), and a steel pipe inclined post section (401) at the top of the steel pipe inclined pile (4) and the steel pipe upright post (201) are poured with concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111161651.5A CN113684852B (en) | 2021-09-30 | 2021-09-30 | Construction method of combined pile foundation and combined pile foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111161651.5A CN113684852B (en) | 2021-09-30 | 2021-09-30 | Construction method of combined pile foundation and combined pile foundation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113684852A true CN113684852A (en) | 2021-11-23 |
CN113684852B CN113684852B (en) | 2023-02-28 |
Family
ID=78587579
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111161651.5A Active CN113684852B (en) | 2021-09-30 | 2021-09-30 | Construction method of combined pile foundation and combined pile foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113684852B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115059063A (en) * | 2022-07-22 | 2022-09-16 | 广州环投南沙环保能源有限公司 | Pile foundation with large settlement and reinforcing method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100803558B1 (en) * | 2007-09-11 | 2008-02-15 | 현대엔지니어링 주식회사 | A reinforcing single column drilled pier foundation and construction method thereof |
CN101139837A (en) * | 2007-08-02 | 2008-03-12 | 夏良站 | Construction plant for tree-root shaped pile |
CN109487811A (en) * | 2018-12-18 | 2019-03-19 | 温州电力设计有限公司 | A kind of lateral tree root caisson and its installation equipment |
CN110453720A (en) * | 2019-08-21 | 2019-11-15 | 中交二公局第五工程有限公司 | A kind of steel pipe post of big load falsework structure and basic connecting structure and its construction method |
CN111364494A (en) * | 2020-04-02 | 2020-07-03 | 中国电建集团华东勘测设计研究院有限公司 | Offshore high-pile bearing platform foundation supported by anchor cables and inclined straight piles and construction method thereof |
CN213267973U (en) * | 2020-08-26 | 2021-05-25 | 广东宏泰建设有限公司 | Pile foundation reinforced structure constructed by adopting composite piles |
-
2021
- 2021-09-30 CN CN202111161651.5A patent/CN113684852B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101139837A (en) * | 2007-08-02 | 2008-03-12 | 夏良站 | Construction plant for tree-root shaped pile |
KR100803558B1 (en) * | 2007-09-11 | 2008-02-15 | 현대엔지니어링 주식회사 | A reinforcing single column drilled pier foundation and construction method thereof |
CN109487811A (en) * | 2018-12-18 | 2019-03-19 | 温州电力设计有限公司 | A kind of lateral tree root caisson and its installation equipment |
CN110453720A (en) * | 2019-08-21 | 2019-11-15 | 中交二公局第五工程有限公司 | A kind of steel pipe post of big load falsework structure and basic connecting structure and its construction method |
CN111364494A (en) * | 2020-04-02 | 2020-07-03 | 中国电建集团华东勘测设计研究院有限公司 | Offshore high-pile bearing platform foundation supported by anchor cables and inclined straight piles and construction method thereof |
CN213267973U (en) * | 2020-08-26 | 2021-05-25 | 广东宏泰建设有限公司 | Pile foundation reinforced structure constructed by adopting composite piles |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115059063A (en) * | 2022-07-22 | 2022-09-16 | 广州环投南沙环保能源有限公司 | Pile foundation with large settlement and reinforcing method |
Also Published As
Publication number | Publication date |
---|---|
CN113684852B (en) | 2023-02-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110777806B (en) | Multi-connecting-rod plane frame permanent supporting structure and construction process thereof | |
CN109403654B (en) | Underpinning and reinforcing method for existing building structure | |
CN114319143A (en) | Bridge top pushes away interim mound structure suitable for in deep soft soil stratum | |
CN113684852B (en) | Construction method of combined pile foundation and combined pile foundation | |
CN111593739A (en) | Cement mixing pile enclosure wall-profile steel cantilever type combined support | |
CN213062136U (en) | Independent foundation underpinning system for storey-adding building | |
CN117646437A (en) | Side slope and foundation pit double-row pile supporting structure and construction method | |
CN210766861U (en) | Portal formula building pile foundation underpins structure under narrow and small space | |
CN112376603A (en) | Assembly type fan foundation and assembly method thereof | |
CN116479897A (en) | Shallow foundation pit collapse rapid reinforcement supporting method with depth smaller than 10m | |
CN215715456U (en) | Combined pile foundation | |
CN215367367U (en) | Pile foundation structure of building engineering on high slope | |
CN213952237U (en) | Take a four corners supporting beam's underground structure | |
CN212317545U (en) | Existing foundation upper and lower column connecting structure for expanding underground space | |
CN114351720A (en) | Construction method for using precast tubular pile as supporting upright post for supporting in foundation pit | |
CN115198787B (en) | Steel tube column type tower crane foundation and construction method thereof, and cover-excavation reverse construction method | |
CN111411791A (en) | Existing foundation upper and lower column connecting structure and method for expanding underground space | |
CN217758990U (en) | Static load testing device for existing building pile raft foundation pile | |
CN105064355A (en) | Anchor rope composite pile structure as stand column of main structure and construction method of anchor rope composite pile structure | |
CN219327122U (en) | Existing foundation reinforcing structure adjacent to side slope | |
CN214497529U (en) | Tunnel foundation pit enclosure device | |
CN218373985U (en) | Low temperature storage tank single pile foundation structure | |
CN220394552U (en) | Three-row pile anchor rope foundation pit supporting structure with diagonal bracing | |
CN212270914U (en) | Supporting structure of wall protection template of non-circular artificial bored pile with super-large section | |
CN219011289U (en) | Aquatic tower crane foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 214000 21-14a, Jiefang North Road, Wuxi City, Jiangsu Province Patentee after: Jiangsu Kejia Design Group Co.,Ltd. Country or region after: China Address before: 214000 21-14a, Jiefang North Road, Liangxi District, Wuxi City, Jiangsu Province Patentee before: JIANGSU KEJIA ENGINEERING DESIGN Co.,Ltd. Country or region before: China |
|
CP03 | Change of name, title or address |