CN113684763A - Special-shaped box girder erection construction process based on bow-string type center line positioning method - Google Patents

Special-shaped box girder erection construction process based on bow-string type center line positioning method Download PDF

Info

Publication number
CN113684763A
CN113684763A CN202110945290.7A CN202110945290A CN113684763A CN 113684763 A CN113684763 A CN 113684763A CN 202110945290 A CN202110945290 A CN 202110945290A CN 113684763 A CN113684763 A CN 113684763A
Authority
CN
China
Prior art keywords
positioning
pile
bow
special
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110945290.7A
Other languages
Chinese (zh)
Other versions
CN113684763B (en
Inventor
潘红伟
张玉鹏
王瑜
侯永红
赵建彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd filed Critical First Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Priority to CN202110945290.7A priority Critical patent/CN113684763B/en
Publication of CN113684763A publication Critical patent/CN113684763A/en
Application granted granted Critical
Publication of CN113684763B publication Critical patent/CN113684763B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a construction process for erecting a special-shaped box girder based on an arch chord type center line positioning method, which comprises the following steps of S1, constructing a track extension pile foundation and establishing a stable slide rail foundation; s2, after the construction of the slide rail foundation is finished, prefabricating a special-shaped track beam and installing a rail bearing beam embedded part; s3, erecting the special-shaped box girder by adopting a method based on bow string type center line positioning, and assembling the special-shaped box girder and the slide rail foundation; the process effectively solves the problem that the traditional line positioning method has more restrictions in the special-shaped beam erection by erecting the special-shaped beam by the bow-string type center line positioning method, and has the characteristics of less investment personnel, high precision, safe operation, strong dynamic property and no great influence of local wind and sand.

Description

Special-shaped box girder erection construction process based on bow-string type center line positioning method
Technical Field
The invention relates to the technical field of special-shaped beam erection, in particular to a construction process for erecting a special-shaped box beam based on an arch-chord type center line positioning method.
Background
The rocket sled is aerodynamic test equipment, a rocket booster with strong thrust is utilized to push a test object to advance on a special slide rail similar to a railway at a high speed, and a high-speed camera and other equipment are used for recording data so as to analyze the aerodynamic performance of the test object; the figure is that: you can see it as a rocket launched on a rail; the rocket sled can be used for developing tip equipment such as nuclear weapons, hypersonic missiles, aircrafts, ejectors on aircraft carriers, fighter rocket ejection seats, spacecraft escape towers, electronic warfare weapons and the like; the device is an important device for carrying out supersonic tests on land, and only a few countries such as America, English, China, Russia, Law and the like have the equipment all over the world at present;
the rocket sled test slide rail is large ground dynamic simulation test equipment, is used for researching various technical problems encountered when a test piece runs at high speed and high acceleration in the air, and has the technical core of one-million rail linearity relative precision; the method requires a stable slide rail foundation, a high-straightness collimation datum line and a smooth steel rail as basic conditions; therefore, in the experimental process, the rocket sled test high-speed slide rail is required to be a straight line with good absolute space straight line flatness and straightness accuracy, and the rail accuracy requires that the flatness error of each 60m reference section in the rail plane direction is less than or equal to 2 mm; the flatness error of the track elevation is less than or equal to 2mm in every 60m of reference section straightness; the distance single point gauge error 1435 +/-0.2 mm of the inner side surface of the left track and the right track of the same mileage section of the track, and the altitude error is less than or equal to +/-0.2 mm, so that in the process of foundation engineering construction of the rocket sled test high-speed slide rail: (1) how to control the relative position deviation of the pre-embedding process of the pre-embedded parts to be 2mm by controlling the pre-embedding precision (pre-embedding position) of the steel rail pre-embedded parts, and accurately pre-embedding each set of rail bearing beam pre-embedded parts is a difficult point of engineering technology; (2) how to control the height reference position of the embedded part steel plate to control the left-right deviation taking the beam center line as the reference to be not more than 2mm, and the beam center line formed by the middle points of the bolt connecting lines of each beam is placed on the designed center line to be the engineering technical difficulty;
for carrying out the accurate location of above-mentioned rail built-in fitting at special-shaped box girder erection center line, traditional locate mode includes: the method comprises a bearing platform center line and beam bottom center line overlapping method, a plumb hanging point threading method, a laser level instrument branching threading method and a total station positioning method, and the method has the following problems: (1) the overlapping method of the center line of the bearing platform and the center line of the beam bottom has large measurement error, and is not suitable for high-precision engineering positioning; (2) the plumb bob hanging point threading method is greatly influenced by weather, cannot be positioned when in wind blowing, and has larger measurement data contingency, (3) the laser level branching threading method can be completed by generally needing 5 persons to cooperate, so that more personnel are invested, and the laser level is time-consuming in leveling and aligning; (4) the real-time reading of the total station positioning method has a lag condition, cannot be synchronously carried out with hoisting equipment, data can be fed back only after a beam body is stabilized, the timeliness is poor, and the phenomenon of work-wasting of the hoisting equipment exists;
therefore, the method and the structure which can be used for accurately positioning the steel rail embedded part on the special-shaped box girder erection center line are designed, so that the accurate positioning of the special-shaped box girder erection center line becomes a problem which needs to be solved urgently in the construction process in the field.
Disclosure of Invention
Aiming at the existing problems, the invention aims to provide a special-shaped box girder erection construction process based on an arch-chord type center line positioning method, the process is used for erecting a special-shaped girder by the arch-chord type center line positioning method, the problem that the traditional line positioning method is limited by a large amount in the special-shaped girder erection process is effectively solved, and the special-shaped box girder erection process has the characteristics of less investment personnel, high precision, safe operation, strong dynamic property and no great influence of local wind and sand.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
a construction process for erecting a special-shaped box girder based on an arch chord type center line positioning method comprises the following steps
S1, constructing a rail extension pile foundation and establishing a stable slide rail foundation;
s2, after the construction of the slide rail foundation is finished, prefabricating a special-shaped track beam and installing a rail bearing beam embedded part;
s3, erecting the special-shaped box girder by adopting a method based on bow-string type center line positioning, and assembling the special-shaped box girder and the slide rail foundation
S301, manufacturing an arch string type center line positioning tool;
s302, positioning is carried out by using a bow-string type center line positioning tool, and a special-shaped box girder is erected.
Preferably, the slide rail foundation in step S1 includes a reference pile, a control pile, a construction pile and a pile cap, and the slide rail foundation is built by:
s101, pile foundation point positions are arranged according to design requirements, and after pile position positioning and pile test construction are finished, pile foundation construction is carried out by adopting a long spiral drilling pile-pouring post-dowel construction process;
wherein: in the pile foundation construction process, adopting a long spiral drilling machine to carry out dry hole forming construction, and simultaneously adopting a pile jumping method to carry out construction;
s102, pile foundation construction is completed, pile body integrity and bearing capacity detection is carried out after design strength is achieved, and pile foundation construction can be carried out when detection is qualified;
s103, after the construction of the main body structure of the upper portion of the pile foundation is completed, the construction of the pile and the beam of the top elevation upper portion of the standard pile cap is carried out, secondary pile splicing is needed, reinforcing steel bars are bound, iron pieces are embedded in advance, a circular pile template and a rectangular beam template are supported, concrete is poured, and the template is detached after the strength meets the requirements.
Preferably, the specific construction process of the post-dowel construction process for the long auger bored concrete pile in the step S101 includes:
(1) measuring and paying off, positioning and rechecking;
(2) the drilling machine is in place, after the drill bit drills to the designed depth at the drilling speed of 1-1.50 m/min, concrete is pressed to the bottom of the drill bit at the pressure of 30Kpa through a pump pipe, the drill rod is lifted at the speed of 2.5m/min, the drill rod and the soil column rise while drilling, the concrete in the hole is fully pressed, high pressure is accumulated in the hole and the suction effect of the drill rod is achieved, the concrete can be greatly filled to form an expanded pile, and the concrete is poured to the top of the designed pile by 500 mm;
(3) and then hoisting the reinforcement cage and the vibration hammer, inserting the reinforcement cage at the speed of 1.2-1.5 m/min, starting the vibration hammer, inserting the reinforcement cage to the designed elevation, and transferring the drilling machine to circulate to the next pile position.
Preferably, the prefabricating process of the special-shaped track beam in the step S2 includes accurate embedding of the rail bearing beam embedded part:
s201, controlling the position of an embedded part of a special-shaped track beam by adopting a fastener positioning and clamping device on channel steel of an external mold of a beam body, simultaneously adding channel steel on the top of the external mold of a track bearing beam template, wherein one channel steel is arranged at each meter, the position of each channel steel is consistent with the position of the embedded part, and a through hole of an embedded bolt of the embedded part is reserved on the channel steel;
s202, after the embedded part is pre-installed on a positioning channel steel, the embedded part is hung to an installation position by using a gantry crane, the embedded part is fixed on an outer template through the positioning channel steel, 1mm steel wires are respectively pulled at two ends of the template to carry out horizontal direction positioning, the steel wire rope is ensured to be 470mm away from the inner side of an outer template, the distance between the two steel wires is 1260mm, the steel wires need to be tensioned and cannot be loosened, the measurement error is avoided, each group of bolt center holes are aligned with the steel wires and then fixed and abutted, and the horizontal direction position of the embedded part is ensured;
s203, after the horizontal position of the embedded part is well positioned, performing high-range positioning, and measuring the top surface elevation of each group of embedded bolts to ensure that the difference error of the position elevation of the embedded part on each beam is less than 1 mm;
s204, after the elevation positioning of the embedded part is finished, in order to prevent the groove die from floating upwards in the concrete pouring process, a steel rail is additionally arranged as a pressing bar to load the groove die;
s205, after the concrete pouring is finished, timely finishing and collecting the concrete surface, and completing checking of the position of the embedded part before the initial setting of the concrete, wherein the checking mode is a plane position and elevation adjusting method when the embedded part is installed, and if the embedded part is displaced, dislocated or inclined, the embedded part needs to be corrected in time.
Preferably, the specific step of positioning the elevation of the embedded part in step S203 includes:
(1) preparing a steel plate strip with the thickness of 1mm to 5mm in advance, measuring the elevation of the end heads of all the embedded bolts A, and adjusting the positions of the rest bolts after taking the arithmetic mean value;
(2) if the bolts need to be raised, steel base plates with corresponding thicknesses are added at the joints of the positioning channel steels and the outer templates, if the bolts need to be lowered, the steel base plates with corresponding thicknesses are added between the positioning channel steels and the embedded part steel plates, and the installed embedded part is checked for perpendicularity and levelness by using an instrument.
Preferably, in the concrete pouring process for the profiled rail beam in step S203, the following steps should be followed:
(1) pouring concrete from one end of the special-shaped track beam to the other end, pushing the two sides of the special-shaped track beam forwards at the same time, and vibrating while pouring, wherein the layering thickness of the poured concrete is about 30cm, and the distance between the front layer and the rear layer is more than 1.5 m;
(2) the moving distance of the concrete during vibration is not more than 1.5 times of the acting radius of the vibrator, the distance between the vibrator and the side mold is kept to be 5-10 cm, the vibrator is inserted into the concrete on the lower layer by 5-10 cm, the vibrator is slowly lifted out after being vibrated and compacted, and the phenomenon that the vibrator collides with a template, a reinforcing steel bar and other embedded parts to cause the deformation of the template and the displacement of the embedded parts is avoided.
Preferably, the manufacturing process of the bow-string type centerline positioning tool in step S301 includes fixed end bolt machining and positioning bow manufacturing;
the stiff end bolt course of working includes:
(1) two vertical diameter lines are found on a nut matched with the bolt, a 0.5mm wide wire groove is formed on the edge of the nut along the line, the depth is 1mm, the intersection point of the two lines is the middle point of the nut, and the intersection point position after the two lines are sleeved on the bolt is also the middle point of the bolt; (2) anchoring a 0.5mm steel wire along a wire slot on one line for fixing, wherein the two slots on the outer side of the unfixed steel wire are connected by the steel wire, and the steel wire naturally passes through the two slots on the inner side to ensure that the fixed steel wire is parallel to the reference line;
the manufacturing process of the positioning bow comprises the following steps:
(1) the deformed steel bar with the diameter of 12mm is used as a bow handle after being bent; (2) intercepting one section of the tape as a target object, punching holes on two sides, wherein the aperture is not more than 0.5mm, the length of the tape is preferably 10cm, and the middle data is a multiple of 5; (3) taking a steel wire with the thickness of 0.5mm to penetrate into the cut and processed tape measure, and penetrating steel wire clamps at two sides of the tape measure; (4) the steel wire is used as a bow string and fixed on a bow handle, the tool bow is processed, and the length of the bow cannot exceed the distance between the bolts on the outer side.
Preferably, the bow-string type center line positioning tool comprises a positioning nut, a bow handle, a center line positioning ruler and a steel wire bow string;
the positioning nut is matched with the embedded bolt for use, two mutually perpendicular wire grooves passing through the circle center are formed in the positioning nut, the width of each wire groove is 0.5mm, and the depth of each wire groove is 1 mm;
the middle line positioning ruler is arranged in the middle of the steel wire bowstring and is connected with the steel wire bowstring through a steel wire clamp, scales are arranged on the middle line positioning ruler, the length of the middle line positioning ruler is 10cm, and the middle data is multiples of 5;
the steel wire bowstring is made of steel wires with the thickness of 0.5mm, two ends, far away from the center line positioning ruler, of the steel wire bowstring are connected with the bow handle through the clamping mechanism, and the diameter of the bow handle is 12 mm.
Preferably, the both ends connecting portion of bow handle be provided with trapezoidal clamping groove, clamping mechanism sets up in clamping groove, including adjusting bolt and locating piece, the adjusting bolt runs through clamping groove both sides curb plate setting, and with one side curb plate threaded connection who presss from both sides the clamping groove, all be provided with the guide way on clamping groove's the both sides curb plate, the guide way uses with the guide rail cooperation that sets up at the locating piece dorsal part, just the front side dislocation of two locating pieces is provided with presss from both sides the tooth, it uses with the cooperation of steel wire bow string to press from both sides the tooth.
Preferably, the central line positioning ruler is provided with a connecting hole, the connecting hole is matched with a steel wire clip for use, the steel wire clip comprises a locking strip, a clip seat and a locking assembly, the locking strip is a flexible locking strip provided with inner locking teeth, an inclined locking tooth is arranged at the tail end of one end of the locking strip and is connected with the clip seat through the inclined locking tooth, the clip seat is arranged on one side of the connecting hole, the clip seat is provided with an adjusting groove and a mounting groove which are mutually communicated, and the locking assembly is movably mounted in the mounting groove; the locking assembly comprises a locking block, a first spring and a limiting part, the locking block is movably mounted in the mounting groove, a latch and an inner latch are arranged at the lower end of the locking block and matched for use, the first spring is symmetrically arranged on guide posts at two sides of the tail end of the locking block, the limiting part is arranged at two sides of the tail end adjusting block of the locking block, and a second spring is arranged at the tail part of the limiting part.
Preferably, the positioning method using the bow-string type centerline positioning tool in step S302 includes:
(1) using a total station to find any point on a design central line as a reference point, and erecting a theodolite to enable the direction of the theodolite to be consistent with the direction of the design central line;
(2) the positioning nuts are sleeved on the embedded bolts at the symmetrical inner sides, so that the positioning nuts are convenient to put and take and are not suitable to be sleeved too deeply;
(3) the bowstring of the tool bow is hung in the wire grooves of the two positioning nuts, the positioning nuts are adjusted to enable the two grooves on the inner side to naturally penetrate through the grooves on the inner side of the tool nut, the steel wire bowstring can not be bent, and the bow is fixed by using a steel wire clamp so as not to shake left and right;
(4) measuring the distance between the two fixed steel wire bowstrings by using a measuring tape, taking the middle value of the upper measuring tape of the bowstring as a target object to move to a middle point after the middle value is taken, wherein the position of the middle value of the middle line positioning tape is the middle line position formed by the middle points of the connecting lines of the embedded bolts;
(5) and after the beam body is lifted by the hoisting equipment, the target object is coincided with the sighting axis of the positioned theodolite, and then the positioning work is finished.
The invention has the beneficial effects that: the invention discloses a construction process for erecting a special-shaped box girder based on an arch string type center line positioning method, which has the improvement that compared with the prior art:
(1) the invention designs a construction process for erecting a special-shaped box girder based on an arch chord type center line positioning method, which adopts a construction technology of inserting a reinforcement cage after concrete is pressed by a long spiral pore-forming pump to construct a cast-in-place pile in the construction process of a slide rail foundation, solves the problem that a pore-forming of aeolian sandy soil is easy to collapse after water loss, has the characteristics of high pile-forming efficiency, small environmental pollution and high quality qualification rate, and provides stable foundation guarantee for engineering;
(2) meanwhile, in the process of prefabricating the special-shaped track beam, the tool for positioning the inner die, the outer die and the embedded part is processed by adopting the accurate embedding construction technology of the embedded part of the bearing track beam, so that the influence of a reinforcing steel bar on the position of the embedded part in the concrete vibrating process is reduced, the yield of finished products is high, the technical guarantee is provided for the smooth completion of engineering, the special-shaped track beam obtained by prefabrication meets the design requirement due to the application of the accurate embedding construction technology of the embedded part of the bearing track beam, the broken beam is reduced, and the cost is effectively saved;
(3) in the construction process, the technology for erecting the special-shaped box girder based on the bow-string type center line positioning method is adopted, the problem that the traditional method for positioning the center line of the special-shaped girder erection is limited more is solved, and the special-shaped box girder erection technology has the characteristics of less investment personnel, high precision, safe operation, strong dynamic property, no big influence of local wind and sand and the like, greatly improves the working efficiency, and effectively saves the construction cost.
Drawings
Fig. 1 is a construction flow chart of the construction process for erecting the special-shaped box girder based on the bow-string type center line positioning method.
FIG. 2 is a schematic view of the fastener installation of the present invention.
Fig. 3 is a processing drawing of the positioning channel steel of the invention.
Fig. 4 is a big picture of the upper part of the special-shaped box girder.
Fig. 5 is a schematic structural view of the positioning nut of the present invention.
Fig. 6 is a schematic structural view of the bow of the invention.
Fig. 7 is a sectional view of the bow of the present invention at a front view angle.
Fig. 8 is a top view in cross section of a bow a of the present invention.
Fig. 9 is a schematic structural view of a side view at the position B of the bow handle of the present invention.
Fig. 10 is a side view in cross-section of a bow of the present invention at side view B.
Fig. 11 is a schematic structural view of the wire clip of the present invention.
Wherein: 1. the novel steel wire bow comprises a positioning nut, 11 wire grooves, 2 bow handles, 21 clamping grooves, 22 guide grooves, 3 central line positioning rules, 31 connecting holes, 4 steel wire bowstrings, 5 adjusting bolts, 6 positioning blocks, 61 guide rails, 62 clamping teeth, 7 channel steel, 71 through holes, 8 embedded bolts, 9 steel wire clamps, 91 fastening bars, 911 oblique locking teeth, 912 inner locking teeth, 92 clamping seats, 921 adjusting grooves, 922 mounting grooves, 93 locking blocks, 931 guide columns, 94 first springs, 95 limiting pieces, 96 second springs, 10 special-shaped beams and A beam section central lines.
Detailed Description
In order to make those skilled in the art better understand the technical solution of the present invention, the following further describes the technical solution of the present invention with reference to the drawings and the embodiments.
Example 1: the construction process for erecting the special-shaped box girder based on the bow-string type center line positioning method is shown in the attached drawings 1-11 in the specification.
Engineering background and project content
1. Item profiles
The project is a project of extension line bearing platform and bearing rail beam of rocket sled sliding rail of certain test research institute, the total length of the extension line is 7000 m, and the extension line is located in a certain place of inner Mongolia, the project content comprises concrete pile bearing platform, prefabricated bearing rail beam and installation, track fastener pre-embedding and the like;
the location of the project is located in a remote experimental area of a base, the field is a grassland, the terrain is flat, the soil of the field is of type II, and the standard freezing depth of the field is 1.0 m. The main strata from top to bottom in the field are:
the first layer of fine sand is slightly dense to medium dense and is distributed on the surface layer of the field, the general thickness is 1.0-3.0 m, the maximum thickness is 5.0m, the surface layer is loose air-formed sand with the thickness of 0.5-1.0 m, and the strength is lower;
fine sand layer, dense, thick and high strength.
2. Project background
The high-speed slide rail for the rocket sled test is an absolute space straight line, the requirements on flatness and straightness accuracy are high, and the flatness error of each 60m reference section in the plane direction of the rail is required to be less than or equal to 2mm by the rail accuracy; the flatness error of the track elevation is less than or equal to 2mm in every 60m of reference section straightness; the distance between the inner side surfaces of the left and right tracks at the same mileage section of the track is 1435 +/-0.2 mm of single-point track gauge error, and the height error is less than or equal to +/-0.2 mm; the project is a rocket sled test high-speed slide rail foundation project, namely a bearing platform and a bearing rail beam project.
3. Engineering features
(1) And (3) construction period tightening: the project construction period is 350 days calendar, the climate environment and the project characteristics of the project are considered, the winter pause period is long, the effective construction period is short, the actual construction period is only 7 months, and the construction period is very tight;
(2) the prefabrication engineering quantity is large: the method comprises the following steps that (1) pieces of simply supported box girders 477 are prefabricated, each box girder is provided with 30 groups of embedded parts, 14340 sets of the accumulated embedded parts are totally formed, and the workload is large;
(3) the process requirement is high: the engineering requires that the top surface of each bearing platform is a spatial straight line, so the engineering measurement control requirement is high;
(4) the project is a land test facility for an important air weapon project, and has high starting point and strict requirement on quality.
4. Technical difficulties
(1) The engineering pile foundation is a concrete cast-in-place pile, the location of the engineering is located in a certain place of inner Mongolia, the main stratum in the site from top to bottom is loose air-formed sand, the general thickness is 1.0-3.0 m, the maximum thickness is 5.0m, the underground water level burial depth is generally larger than the pile end burial depth, holes are easy to collapse after the holes are formed, how to carry out the construction of the concrete cast-in-place pile is the technical difficulty of the engineering, and a stable foundation is provided for a bearing rail beam;
(2) according to the engineering prefabricated simply supported box girder 477 piece, each box girder is provided with 30 groups of embedded parts, 14340 sets of accumulated embedded parts are provided, the embedded parts are steel rail fastener installation bases, the relative position deviation is 2mm, the embedded parts and the girder body are poured simultaneously, the installation precision determines whether the girder is qualified, and how to accurately embed each set of rail bearing girder embedded parts is the technical difficulty of the engineering;
(3) the erection of the box girder requires: the height deviation based on the embedded part steel plate is not more than 2mm, the left and right deviation based on the beam center line formed by the middle points of the bolt connecting lines is not more than 2mm, and the technical difficulty of the engineering is how to place the beam center line formed by the middle points of the bolt connecting lines on the designed center line of each beam.
Secondly, the construction process (the construction process for erecting the special-shaped box girder based on the bow-string type center line positioning method) comprises the steps
S1, setting a rail extension pile foundation and establishing a stable slide rail foundation
The track extension pile foundation engineering of a certain test research institute comprises a reference pile, a control pile, a construction pile and a pile cap; 117 standard piles, 33 control piles, 951 engineering piles (bearing platform piles), 800mm pile diameter and 477 pile bearing platforms;
construction preparation:
(1) mastering meteorological data so as to comprehensively organize the balanced construction of the whole process, formulating the construction measures of rain prevention, skid prevention, wind and sand prevention and freeze prevention, and correspondingly taking effective water prevention and drainage measures according to hydrogeology and meteorological conditions; (2) because the construction needs a large number of varieties of material resources, the production and supply conditions, price, varieties and the like of various material resources are investigated in detail so as to make the supply and demand connection as soon as possible and fulfill the supply and demand requirements; (3) understanding local customs, and the composition of local personnel, respecting local customs; relevant personnel at the organization project department carefully learn drawings and carry out self-check and review work so as to facilitate correct construction; learning, familiarizing with the drawing content, knowing the technical standard which the design requirement construction meets, and defining the process flow; and (4) carrying out self-inspection, and organizing construction managers of various types to examine the drawings related to the type of the work, and familiarizing and mastering the details in the drawings. Organizing each professional construction team to learn construction drawings together and agree on construction matching matters; the method comprises the following steps of organizing a drawing to be reviewed, meeting by a design party, understanding design intention and construction quality standard, and accurately mastering details in the design drawing; (5) and (4) before construction, the construction organization design is perfected according to the design scheme of the final edition, and supervision and the audit of an owner unit are reported as an instructive file of engineering construction production.
Pile testing and detection:
(1) the purpose of the test pile is to determine the construction process of the deep sand layer reinforced concrete cast-in-place pile, the site test determines whether the construction process of inserting the reinforcement cage after the concrete is cast in by adopting the long auger drilling machine pore-forming pump pressure, the construction of the test pile is carried out before the pile foundation construction, the number of the test piles is 3, and the pile length is 13.0 m;
(2) the test pile mainly verifies the feasibility of a hole forming mode, the hole forming quality, the feasible hoisting and inserting mode of a reinforcement cage and the pouring quality of concrete; and maintaining after pile testing is finished, detecting the integrity and the bearing capacity of the pile body after the strength of the pile body reaches the design requirement, and constructing the pile foundation after the pile body is detected to be qualified.
Pile foundation construction scheme:
s101, construction content mainly includes construction of a reinforced concrete cast-in-place pile, including pile foundation construction under the pile cap height, a reference pile and a control pile cap, wherein the engineering pile cap adopts a long spiral drilling machine to form the reinforced concrete cast-in-place pile, and a post-inserted bar construction process is determined by data collection and on-site soil layer engineering geological conditions, the diameter of the pile is phi 0.8m, and the length of the pile is 13.0 m-18.0 m;
s102, pile foundation construction is completed, and pile body integrity and bearing capacity detection is carried out after design strength is achieved;
s103, after the construction of the main body structure of the upper part of the pile foundation is finished, constructing a standard pile cap top elevation upper part pile and a beam, connecting piles for the second time, binding reinforcing steel bars, embedding iron pieces, supporting a circular pile template and a rectangular beam template, pouring concrete, and removing the template after the strength meets the requirement;
according to the engineering geological survey report, the cast-in-situ bored pile is drilled in a general area of the engineering, the underground water level burial depth is generally greater than the pile end burial depth, and in order to save the construction period and maintain a good construction environment on site, a long spiral drilling machine is adopted for dry-process hole forming construction;
the construction sequence is as follows: firstly, testing piles and controlling the construction of the piles, detecting the integrity and the bearing capacity of a pile body after the tested piles reach the design strength, and performing pile foundation construction if the tested piles are qualified; simultaneously constructing a bearing platform pile and a reference pile, and detecting the integrity and the bearing capacity of a pile body according to a design scheme after the strength of the bearing platform pile meets the design requirement; after the construction of the main structure at the upper part of the bearing platform is finished, the construction of the overground part of the reference pile and the beam is carried out;
the long screw bored pile post-dowel construction process flow of the step S101 includes:
the long spiral drilling method is a quick dry drilling method of a long spiral hollow drill rod driven by a large-torque power head, most of soil in a drill hole is conveyed to a blade of the spiral drill rod except for a part of the soil which is extruded, the soil is extruded and compacted when the soil rises to form a soil column with the drill rod, the clearance between the soil column and the drill hole is only a few millimeters, the soil column is similar to a long piston, and the drill hole is not collapsed by the soil column before the drill hole is lifted;
the concrete construction process comprises the following steps: (1) measuring and paying off, positioning and rechecking; (2) the drilling machine is in place, after the drill bit drills to the designed depth at the drilling speed of 1-1.50 m/min, the one-way valve is opened, concrete is pressed to the bottom of the drill bit at the pressure of 30Kpa through the pump pipe, the concrete is pressed out, the drill rod is pushed to lift the drill rod at the speed of 2.5m/min, the concrete in the hole is fully pressed while the drill rod soil column rises, the concrete in the hole is fully pressed, and the concrete can be filled to form an expanded pile due to the high pressure accumulated in the hole and the suction effect of the drill rod, so that the bearing capacity of the pile is improved, and the concrete is poured to the top of the designed pile by 500 mm; (3) then hoisting a reinforcement cage and a vibration hammer, inserting the reinforcement cage downwards at the speed of 1.2-1.5 m/min, starting the vibration hammer, inserting the reinforcement cage to the designed elevation, and transferring the drilling machine to circulate to the next pile position;
note that: the cage in-process must use earlier the plummer and the steel reinforcement cage dead weight to impress down, presses to restart the plummer when can't impressing, prevents the steel reinforcement cage skew that leads to by the plummer vibration.
The construction sequence is measuring and paying off and positioning the pile, rechecking → positioning the drilling machine → drilling to the designed depth → checking and accepting the final hole → pouring concrete → cleaning and lifting the drill rod, simultaneously pouring the concrete to the top of the designed pile by 500mm → lifting the steel reinforcement cage and the vibration hammer → inserting the steel reinforcement cage downwards, starting the vibration hammer → inserting the steel reinforcement cage to the designed elevation → transferring the drilling machine to circulate the next pile position → completing the construction → detecting and checking and accepting the finished pile product; the hole forming acceptance index and deviation requirement are shown in table 1;
table 1: checking and accepting index and deviation requirement for hole forming
Figure BDA0003216448630000111
Quality standard and inspection method
Pile body concrete strength: taking a concrete sample for inspection, and measuring the cubic compressive strength of the concrete sample;
concrete slump: measuring a slump cone;
pile top elevation: the distance exceeding the designed pile top is not less than 0.50 m;
filling coefficient: 1.1-1.2, and checking the actual pouring amount of each pile.
Note that: in the process of hoisting and positioning the steel reinforcement cage: (1) trial hoisting is carried out on the reinforcement cage on site, and if the reinforcement cage is damaged during trial hoisting, the hoisting quality is ensured by increasing stiffening ribs; two-point hoisting is adopted during hoisting of the reinforcement cage, so that permanent deformation of the reinforcement cage is prevented; (2) the long spiral construction pouring and the lower reinforcement cage need to be integrated, cage insertion is started immediately within three minutes after concrete pouring, time difference is reduced, and cage insertion difficulty is reduced; (3) forming holes by a long spiral drilling machine, pouring concrete to the ground, then timely cleaning earth surface earthwork, and immediately performing post-inserting reinforcement cage construction; sleeving a steel bar cage qualified in inspection on the steel pipe, and hanging the steel bar cage on a hook arranged on the flange by using a steel wire rope; (4) because the steel reinforcement cage is longer, the steel reinforcement cage is inserted downwards and two-way verticality observation is required, a two-way line is used for vertically arranging to form a vertical angle, when the verticality deviation is over large, an operator is informed to stop the machine for correction in time, and a cage-descending operator needs to right the steel reinforcement cage to align to the pile position which is poured; (5) in the cage lowering process, a vibration hammer and a reinforcement cage are firstly used for dead weight pressing, and the vibration hammer is started when the reinforcement cage cannot be pressed, so that the reinforcement cage is prevented from shifting caused by vibration of the vibration hammer, and the insertion speed is preferably controlled to be 1.2-1.5 m/min; (6) after the reinforcement cage is inserted to the designed position, the power supply of the vibration hammer is closed, then the steel wire rope is picked off, the steel pipe and the vibration hammer are lifted out of the hole, and the vibration hammer is started once every 3m in the lifting process so as to ensure the compactness of concrete; (7) the installation quality standard and the detection method comprise the following steps: tolerance deviation of installation of the reinforcement cage: and (3) allowing deviation of installation elevation of the steel reinforcement cage: +/-50 mm, and measuring by using a level gauge; thickness tolerance of the steel bar protective layer: 50mm, and is controlled by a pilot steel bar welded on the main steel bar.
Note that: the problems and precautions to be taken during the construction of the cast-in-place pile are shown in table 2:
table 2: common problems and preventive measures of cast-in-place piles
Figure BDA0003216448630000121
Figure BDA0003216448630000131
The pile foundation construction by adopting the long spiral bored pile post-dowel construction process has the following advantages: (1) because the long spiral hole is formed into a dry drilling hole, no slurry is generated, and the environmental pollution is small; (2) because the whole pile length is spirally drilled in place at one time, the pile forming efficiency is greatly improved, and each drilling machine (with the pile length of about 20 m) can form about 20-50 piles per day on average; (3) the construction method has high pile forming efficiency and is dry hole operation, so the construction consumes electric energy, water energy is less and the cost is lower; (4) because there is no retaining wall mud, so there is no mud cake around concrete and pile hole, but this, because of the pressure-cast concrete, so the concrete and pile hole combine closely, even the stone will imbed the soil body around the pile hole in the concrete, so the peripheral friction resistance of pile increases, because there is no hole bottom deficient soil, so the end resistance of pile is higher than traditional bored concrete pile too; (5) the construction method of long spiral pore-forming pump pressure concrete post-inserted reinforcement cage successfully solves the problem of easy hole collapse and pile breakage after pore-forming and water loss under the geological condition of fine sand.
S2, after the construction of the slide rail foundation is finished, prefabricating the special-shaped track beam and installing the rail bearing beam embedded part
The engineering is a land test facility of an important air weapon project, has a high starting point, requires the top surface of each bearing platform to be a spatial straight line, allows the deviation of embedded parts of box girders to be 2mm, has 30 groups of embedded parts for each box girder, accumulates 14340 sets of embedded parts, and has a large engineering quantity, so the key technology of the engineering is engineering measurement and embedded part embedding precision control in the construction of bearing rails;
construction preparation:
the construction drawing is familiar before construction, technical background and safe background are carried out on construction workers and construction technicians, necessary test detection is carried out on the raw materials entering a field, concrete is tried out, the concrete mixing ratio result is reported to a test supervision engineer for approval, the embedded part entering the field is qualified in check, and relevant construction work is completed;
cleaning the bottom die:
before box girder prefabrication construction, rust, sundries and the like on the surface of a bottom die need to be cleaned, whether the surface of the bottom die is flat or not is checked, and defects are timely treated;
processing and installing steel bars:
the steel bar framework is arranged on the steel bar binding pedestal, the steel bars of various types are positioned according to the design size, the bottom plate, the framework and the web steel bar are bound, the binding sequence is from bottom to top, the operation is performed in sequence, the steel bar interval is checked at any time, and the stirrups are kept to be vertical to the main bars; after the binding of the web plate and the bottom plate steel bars is finished, the installation and adjustment of the inner template and the outer template are carried out, finally, the top plate steel bars and the wing plate steel bars are bound, and embedded parts are embedded;
installing a template:
(1) and (3) outer die installation: the installation, the removal and the hoisting transportation of the outer die are carried out by matching a gantry crane with manpower. Installing side templates after the bottom plate and the web plate steel bars are bound, installing a middle part side template, and then installing two end side templates; the outer side die is inclined according to the design requirement, supported and adjusted through the side die, and fixed by adopting a top counter-pull rod (phi 16) and a bottom counter-pull rod (phi 16); when the template is installed, an adhesive tape with the thickness of 3mm is stuck between the template and the template, so that the sealing property of the template is enhanced, and slurry leakage is avoided; (2) core mold installation: the installation of the core mould is carried out after the binding of the reinforcing steel bars of the bottom plate and the reinforcing steel bars of the web plate is finished; when the core mould is installed, a gantry crane is adopted to hoist the core mould into position in a partitioning manner; the core mold falls on a positioning steel bar welded on the bottom plate in advance and is tightly propped and fixed with the outer mold through the steel bar; skylight is reserved on the bottom template and the top template of the core mold, so that air bubbles in the concrete can be discharged conveniently; (3) installing an end template: the end of the two ends of the prefabricated box girder is reserved with wet joint longitudinal steel bars, and the end formworks at the two ends are reserved with steel bar holes according to requirements;
the template should be noted during use for the following points: the method comprises the following steps of firstly, carefully maintaining a template in a using process, ensuring the template to be in a complete state in the whole construction process, polishing surface laitance and rusty spots, and brushing a separant for later use; secondly, when the template is assembled, a rubber belt is added to ensure that the template joint is smooth and tight and does not leak slurry; the template is inspected in the process of installing the template and pouring concrete, so that the difficulty in removing the template due to deformation is prevented; and fourthly, strictly avoiding collision with the rail bearing beam during loading, unloading and hoisting.
Installing an embedded part:
the engineering is a land test facility for an important air weapon project, and has strict requirements on the position quality of various embedded parts of a rail bearing beam; the straightness of the fastener must satisfy: the vertical direction is +/-2 mm, the horizontal direction is +/-2 mm, and the finished line is a spatial straight line; therefore, the position control of the beam body embedded part is a key technology of engineering construction, and the fastener plane layout is shown as 2;
the project is mainly characterized in that the plane and elevation positioning of the embedded bolt A is controlled, and the method is as follows: (1) plane position: namely, the connecting line of the bolts A is a horizontal line after the same beam and all the beams are spliced, and the distance between the line A, the line B and the line A, B shown in the following figures can be formed by controlling the connecting line of the bolts A at each side of each beam; (2) vertical position: the length L of the same beam is 15 meters, the distance L between two adjacent bolts is 1 meter, and according to the geodetic leveling, half kilogram R of the earth is 6371 kilometre, which can be approximately regarded as the length of the beam, namely the arc length; namely, the elevations of the embedded parts are consistent when the beam body is prefabricated, and the height difference of the two ends can be adjusted when the beam is erected;
the construction quality of the embedded part is mainly controlled by the following links:
(1) template processing: before the template is processed, a designer carefully rechecks the drawing, the position of the embedded part is completely consistent with the design drawing, the design is carefully lofted in the processing process, after the template is processed, a professional technician strictly checks and accepts, and the I-steel position and the fastener positioning device system are taken as key points in the checking and accepting, and if the position error exceeds an allowable range, the adjustment and the correction are required in time;
(2) processing an embedded part: the size of the embedded part is strictly processed according to a drawing, the embedded column needs to be welded with a double-end bolt and then embedded, a steel plate and a reinforcing steel bar as well as the bolt and the steel plate need to be welded, the height of a welding seam is not less than 8mm, the embedded part is processed by a professional manufacturer entrusted by Party A, and the embedded part is used after being accepted by a second time after entering a field;
(3) the installation of the embedded part specifically comprises the following steps:
s201, controlling the position of an embedded part of a special-shaped track beam by adopting a fastener positioning and clamping device on a beam body external mold channel steel, simultaneously adding a channel steel 7 on the top of an external mold of a track bearing beam template, wherein one channel steel is arranged at each meter, the position of each channel steel is consistent with the position of the embedded part, and a through hole 71 of an embedded part embedded bolt 8 is reserved on the channel steel;
s202, after the embedded part is pre-installed on a positioning channel steel 7, a gantry crane is used for hoisting the embedded part to an installation position, the embedded part is fixed on an outer template through the positioning channel steel, 1mm steel wires are respectively pulled at two ends of the template for horizontal positioning, the steel wire rope is guaranteed to be 470mm away from the inner side of the outer template, the distance between the two steel wires is 1260mm, the steel wires need to be tensioned and cannot be loosened, measurement errors are avoided, each group of bolt center holes are aligned with the steel wires and then fixed and abutted, and the horizontal position of the embedded part is guaranteed;
s203, after the horizontal position of the embedded part is well positioned, performing high-range positioning, and measuring the top surface elevation of each group of embedded bolts 8 to ensure that the difference error of the position elevation of the embedded part on each beam is less than 1 mm;
s204, concrete can not be directly poured after the installation and adjustment of the embedded part are finished, and because a horizontal upper surface template is used for a water groove part between the rail bearing beam platforms, a groove mold is easy to float upwards in the concrete pouring process, 20 steel rails need to be additionally arranged to serve as pressure bars to load the groove mold, and the influence of the floating mold of the groove mold on the position of the embedded part is avoided;
s205, after concrete pouring is finished, timely finishing and collecting concrete surface, and completing checking work of the position of the embedded part before initial setting of the concrete, wherein the checking mode is a plane position and elevation adjusting method when the embedded part is installed, and if displacement, dislocation or inclination exists, the correction must be timely carried out;
s206. concrete curing and finished product protection
After the position of the embedded part is checked to be correct, processing the surrounding disturbed concrete in time, after the concrete is leveled to be grouted, slightly hardening the concrete, and then performing secondary plastering; after the slurry is collected, covering and maintaining the exposed concrete surface by using geotextile, and watering for maintaining; watering for covering and maintaining for at least 7 days, wherein the watering frequency is set to be a degree that the surface of the concrete can be kept in a wet state every day, and a specially-assigned person is assigned to water for maintaining; and the template is dismantled after the concrete strength reaches 2.5MPa, so that the surface and edges and corners are not damaged during dismantling. After the template is dismantled, cleaning mortar and dirt on the surface of the template, maintaining and finishing, coating a release agent on the template, and waiting for the next use; after the template is dismantled, the site is cleaned in time, and the templates are stacked orderly; cleaning the filler of the reserved opening in time after the mold is removed; the exposed part of the bolt is fully coated with grease in the storage process of the bearing rail beam, the PVC sleeve is used for protecting the bearing rail beam, and the stable steel wire rope does not collide with the embedded part to the greatest extent in the transportation process of the beam so as to avoid inclined deformation.
Wherein: the specific steps of the elevation positioning of the embedded part in the step S203 comprise (1) preparing a steel plate strip with the thickness of 1mm to 5mm in advance, measuring the elevation of the end heads of all embedded bolts A, and adjusting the positions of the rest bolts after taking the arithmetic mean value; (2) if the bolts need to be raised, steel backing plates with corresponding thicknesses are added at the connecting positions of the positioning channel steel and the outer template, if the bolts need to be lowered, the steel backing plates with corresponding thicknesses are added between the positioning channel steel and the embedded part steel plates, and the verticality and the levelness of the installed embedded part are checked by using an instrument;
in the concrete pouring process for the special-shaped track beam in the step S203, the concrete should be poured from one end of the special-shaped track beam to the other end according to the following step (1), the two sides of the special-shaped track beam are simultaneously pushed forwards, the pouring and vibrating are carried out simultaneously, the layered thickness of the poured concrete is about 30cm, and the distance between the front layer and the rear layer is more than 1.5 m; (2) the moving distance of the concrete during vibration cannot exceed 1.5 times of the action radius of the vibrator, the distance between the vibrator and the side mold should be kept to be 5-10 cm, the vibrator is inserted into the concrete on the lower layer by 5-10 cm, the vibrating rod is slowly lifted out after the concrete is compacted, and the phenomenon that the vibrating rod collides a template, a reinforcing steel bar and other embedded parts to cause template deformation and embedded part displacement is avoided; (3) the compact mark is that the concrete surface stops sinking and no air bubble appears, and the surface is flat and slurry.
The construction method for processing the inner die, the outer die and the positioning tool adopted by the special-shaped track beam comprises the following steps: (1) the method for finding the overall center line of the embedded part is simplified by directly using the embedded bolt for positioning, the efficiency is greatly improved, the accumulated error in the operation process is reduced, and the precision is higher; (2) the channel steel and the outer mold are used for positioning, so that the influence of the steel bars on the position of the embedded part in the concrete vibrating process is reduced, and the qualified rate of finished products is high; (3) the use of a suspension mold is reduced by one-step molding of the rail bearing beam, pouring is not needed after the initial setting of the concrete at the lower part, and no transverse seam exists among the concrete, so that the integrity of the beam body is better, and the effect is improved; (4) and the secondary checking of the embedded part must be completed before the initial setting of the concrete, otherwise, the accurate checking cannot be carried out, and the requirement on the timeliness is high.
S3, erecting the special-shaped box girder by adopting a method based on bow-string type center line positioning, and assembling the special-shaped box girder and the slide rail foundation
The track extension construction project comprises 7006.6m/1 of track extension bridge engineering and 164.94m/1 of turning bridge engineering, and the upper structure is a 15m reinforced concrete simply-supported box girder; the whole line is provided with 477 bearing platforms, 477 pieces of prefabricated simply supported box beams, 1 piece of cast-in-place box beam and 14340 sleeves of embedded parts; the engineering is a land test facility, the starting point is high, the line is required to be a space straight line, the height error of the double tracks is less than 0.2mm, the error relative to the central line is less than 0.2mm, and the track gauge is less than 0.2 mm; the erection of the box girder requires: the height deviation taking the embedded part steel plate C as a reference is not more than 2mm, and the left-right deviation taking a beam center line formed by the middle points of the connecting lines of the bolts A as a reference is not more than 2 mm; the precast beam allowable deviation, the number of inspections and the method are shown in table 3:
table 3: precast beam tolerance, number of inspections and method
Figure BDA0003216448630000171
Figure BDA0003216448630000181
The engineering embedded part is processed by a professional manufacturer, the error is controlled within the allowable deviation and passes the acceptance; the deviation between a straight line formed by connecting bolts A on one side of each beam and a reference line is 2mm, the deviation accords with the design requirement and passes the acceptance, so that the important difficulty of the project is how to position the beam center line formed by the connecting midpoints of the bolts A and place the beam center line on a set reference line when the beam is erected, and how to quickly and accurately find the beam center line formed by the connecting midpoints of the bolts A as the research direction of the project, and the specific process of the construction process is as follows:
s301, make bow string formula central line positioning tool, including fixed end bolt processing and location bow preparation:
the stiff end bolt course of working includes:
(1) two vertical diameter lines are found on a nut matched with the bolt, a 0.5mm wide wire groove is formed on the edge of the nut along the line, the depth is 1mm, the intersection point of the two lines is the middle point of the nut, and the intersection point position after the two lines are sleeved on the bolt is also the middle point of the bolt; (2) anchoring a 0.5mm steel wire along a wire slot on one line for fixing, wherein the two slots on the outer side of the unfixed steel wire are connected by the steel wire, and the steel wire naturally passes through the two slots on the inner side to ensure that the fixed steel wire is parallel to the reference line;
the manufacturing process of the positioning bow comprises the following steps:
(1) the deformed steel bar with the diameter of 12mm is used as a bow handle after being bent; (2) intercepting one section of the tape as a target object, punching holes on two sides, wherein the aperture is not more than 0.5mm, the length of the tape is preferably 10cm, and the middle data is a multiple of 5; (3) taking a steel wire with the thickness of 0.5mm to penetrate into the cut and processed tape measure, and penetrating steel wire clamps at two sides of the tape measure; (4) the steel wire is used as a bow string and fixed on a bow handle, the tool bow is processed, and the length of the bow cannot exceed the distance between the bolts on the outer side.
S302, a bow-string type center line positioning tool is used for positioning, a special-shaped box girder is erected, and the specific process comprises the following steps: the method comprises the following steps that (1) a total station is used for finding any point on a design center line as a datum point, and a theodolite is erected, so that the direction of the theodolite is consistent with the direction of the design center line; (2) the positioning nuts are sleeved on the embedded bolts at the symmetrical inner sides, so that the positioning nuts are convenient to put and take and are not suitable to be sleeved too deeply; (3) the bowstring of the tool bow is hung in the wire grooves of the two positioning nuts, the positioning nuts are adjusted to enable the two grooves on the inner side to naturally penetrate through the grooves on the inner side of the tool nut, the steel wire bowstring can not be bent, and the bow is fixed by using a steel wire clamp so as not to shake left and right; (4) measuring the distance between the two fixed steel wire bowstrings by using a measuring tape, taking the middle value of the upper measuring tape of the bowstring as a target object to move to a middle point after the middle value is taken, wherein the position of the middle value (the target object) of the middle line positioning tape is the middle line position formed by the middle points of the connecting lines of the embedded bolts; (5) and after the beam body is lifted by the hoisting equipment, the target object is coincided with the sighting axis of the positioned theodolite, and then the positioning work is finished.
The tool arch midline positioning method has the advantages that: (1)1, the operation can be completed by 1 person, and the personnel investment is less than that of the traditional positioning method; (2) the operation method is simple, and the requirement on the personnel technology is not high; (3) the manufacturing method is simple, the cost is low, and the steel bar waste is used; (4) the two ends of the beam can be used simultaneously, so that operators do not need to identify target objects back and forth, and the labor intensity is reduced; (5) the two ends can be rechecked at any time, so that the phenomenon that the displacement of the fixed end cannot be found when the other end of the beam body is moved after one end of the beam is fixed is avoided; (6) the method is not influenced by natural factors such as wind power and the like, and accidental errors are reduced; (7) offset data can be read at any time, and data reference is provided for lifting personnel; (8) the timeliness is high, and the beam erecting speed can be improved; (9) the operation of operators under the hoisting equipment is avoided, and the safety risk is reduced; (10) the design center line can be found on the accurately positioned beam at any time, and the operation times of the total station can be reduced.
The bow string type center line positioning tool obtained in the step S301 comprises a positioning nut 1, a bow handle 2, a center line positioning ruler 3 and a steel wire bow string 4;
the positioning nut 1 is matched with the embedded bolt A for use, two mutually perpendicular wire grooves 11 passing through the center of a circle are formed in the positioning nut 1, the width of each wire groove 11 is 0.5mm, and the depth of each wire groove 11 is 1 mm;
the middle line positioning ruler 3 is arranged in the middle of the steel wire bowstring 4, is connected with the steel wire bowstring 4 through a steel wire clamp 9, is provided with scales, and is 10cm long and the middle data is multiples of 5;
the steel wire bowstring 4 is made of steel wires with the thickness of 0.5mm, two ends, far away from the center line positioning ruler 3, of the steel wire bowstring 4 are connected with the bow handle 2 through the clamping mechanism, and the diameter of the bow handle 2 is 12 mm.
Preferably, the bow is provided with trapezoidal clamping groove 21 at 2's both ends connecting portion, clamping mechanism sets up in clamping groove 21, including adjusting bolt 5 and locating piece 6, adjusting bolt 5 runs through the setting of clamping groove 21 both sides curb plate, and with one side curb plate threaded connection of clamping groove 21, all be provided with guide way 22 on the both sides curb plate of clamping groove 21, guide way 22 uses with the cooperation of setting at 6 dorsal guide rails 61 of locating piece, and is in the front side dislocation of two locating pieces 6 is provided with presss from both sides tooth 62, press from both sides tooth 62 and steel wire bow string 4 cooperation use.
Preferably, in order to connect the center line positioning ruler 3 with the steel wire bowstring 4 conveniently, a connecting hole 31 is formed in the center line positioning ruler 3, the connecting hole 31 is matched with the steel wire clamp 9 for use, the steel wire bowstring 4 is clamped, and the center line positioning ruler 3 is connected with the steel wire bowstring 4; the steel wire card 9 include locking strip 91, cassette 92 and locking subassembly, locking strip 91 is for being provided with the flexible locking strip of interior lock tooth 912, is provided with oblique lock tooth 911 at the one end of locking strip 91, is connected with cassette 92 through oblique lock tooth 911, cassette 92 sets up in one side of connecting hole 31, and is provided with the adjustment tank 921 and the mounting groove 922 that communicate each other on cassette 92, locking subassembly movable mounting is in mounting groove 922.
Preferably, the locking assembly comprises a locking block 93, a first spring 94 and a limiting member 95, the locking block 93 is movably mounted in the mounting groove 922, a latch is arranged at the lower end of the locking block 93, the latch extends out of the adjusting groove 921 to be matched with the inner latch 912 for use, so as to lock the locking bar 91, the first springs 94 are symmetrically arranged on the guide posts 931 at two sides of the tail end of the locking block 93, so as to support the locking block 93, and the latch at the lower end of the locking block 93 and the inner latch 912 realize locking; the limiting pieces 95 are arranged on two sides of the adjusting block at the tail end of the locking piece 93, the second spring 96 is arranged at the tail of the limiting piece 95, the locking piece 93 is fixed by the limiting piece 95 so as to be adjustable in the longitudinal direction, when the steel wire bow string fixing device is used, the steel wire bow string 4 is placed on one side of the connecting hole 31 far away from one side of the clamping seat 92, then the free end of the locking strip 91 penetrates through the adjusting groove 921 and is pulled, so that the locking strip 91 locks the steel wire bow string 4, and the connection of the midline positioning ruler 3 and the steel wire bow string 4 is completed; when the bowstring 4 needs to be removed, the locking piece 93 can be moved backwards by adjusting the wrench.
The construction process for erecting the special-shaped box girder based on the bow-string type center line positioning method has the following achievements:
(1) the project has a contract construction period of 350 days, an actual construction period of 180 days, an original planned girder erection of 120 days and a girder adjustment of 30 days, and the practical girder erection and the actual girder adjustment share 90 days due to the fact that a tool is used for carrying out a center line positioning method, so that economic benefits and social benefits with high effects are obtained in the aspects of cost and work efficiency improvement.
The specific benefit analysis is shown in the following table:
table 4: economic benefit analysis table
Figure BDA0003216448630000211
(2) Economic benefits
The construction method for erecting the track-supporting beam by using the tool method for central line positioning is simple, convenient and efficient, the actual beam erecting and beam adjusting share 90 days, the investment of personnel and machinery is effectively reduced, the cost expenditure is saved by 104 ten thousand yuan, and economic benefits with high efficiency are obtained in the aspects of cost and work efficiency;
the method comprises the following specific steps:
crane lease is saved: 6.5 ten thousand yuan/month × 2 month × 26 ten thousand yuan;
and (3) renting the gantry crane saves: 4 ten thousand yuan/one station/month multiplied by 1 station multiplied by 2 month which is 8 ten thousand yuan;
project original plan configuration erector 5, actual erection 3, balance: 5000 yuan/person/month × 2 person × 5 month ═ 5 ten thousand yuan;
saving project management cost: 9000 yuan/person/month × 12 persons × 6 months ═ 65 ten thousand yuan;
newly increased profit: 26 ten thousand yuan +8 ten thousand yuan +5 ten thousand yuan +65 ten thousand yuan is 104 ten thousand yuan.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are described in the specification and illustrated only to illustrate the principle of the present invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the present invention, which fall within the scope of the invention as claimed. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (10)

1. A special-shaped box girder erection construction process based on an arch string type center line positioning method is characterized by comprising the following steps:
comprises the steps of
S1, constructing a rail extension pile foundation and establishing a stable slide rail foundation;
s2, after the construction of the slide rail foundation is finished, prefabricating a special-shaped track beam and installing a rail bearing beam embedded part;
s3, erecting the special-shaped box girder by adopting a method based on bow-string type center line positioning, and assembling the special-shaped box girder and the slide rail foundation
S301, manufacturing an arch string type center line positioning tool;
s302, positioning is carried out by using a bow-string type center line positioning tool, and a special-shaped box girder is erected.
2. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 1, is characterized in that: the slide rail foundation of the step S1 includes a reference pile, a control pile, a construction pile and a pile cap, and the building process of the slide rail foundation includes:
s101, pile foundation point positions are arranged according to design requirements, and after pile position positioning and pile test construction are finished, pile foundation construction is carried out by adopting a long spiral drilling pile-pouring post-dowel construction process;
s102, pile foundation construction is completed, pile body integrity and bearing capacity detection is carried out after design strength is achieved, and pile foundation construction can be carried out when detection is qualified;
s103, after the construction of the main body structure of the upper portion of the pile foundation is completed, the construction of the pile and the beam of the top elevation upper portion of the standard pile cap is carried out, secondary pile splicing is needed, reinforcing steel bars are bound, iron pieces are embedded in advance, a circular pile template and a rectangular beam template are supported, concrete is poured, and the template is detached after the strength meets the requirements.
3. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 2, is characterized in that: the specific construction process of the long spiral cast-in-place pile post-dowel construction process in the step S101 comprises the following steps:
(1) measuring and paying off, positioning and rechecking;
(2) a drilling machine is in place, after a drill bit drills to a designed depth at a drilling speed of 1-1.50 m/min, concrete is pressed to the bottom of the drill bit through a pump pipe at a pressure of 30Kpa, a drill rod is lifted at a speed of 2.5m/min, and the concrete is poured to the top of a designed pile for 500 mm;
(3) and then hoisting the reinforcement cage and the vibration hammer, inserting the reinforcement cage at the speed of 1.2-1.5 m/min, starting the vibration hammer, inserting the reinforcement cage to the designed elevation, and transferring the drilling machine to circulate to the next pile position.
4. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 1, is characterized in that: step S2 the prefabrication process of dysmorphism track roof beam include the accurate pre-buried process of support rail roof beam built-in fitting, specifically include:
s201, controlling the position of an embedded part of the special-shaped track beam by adopting a fastener positioning and clamping device on channel steel of an external mold of the beam body, simultaneously adding channel steel (7) on the top of the external mold of the track bearing beam template, wherein one channel steel is arranged at each meter, the position of each channel steel is consistent with the position of the embedded part, and a through hole (71) of an embedded part embedded bolt (8) is reserved on the channel steel (7);
s202, after the embedded part is pre-installed on a positioning channel steel (7), a gantry crane is used for hoisting the embedded part to an installation position, the embedded part is fixed on an outer template through the positioning channel steel, 1mm steel wires are respectively pulled at two ends of the template for horizontal positioning, the distance between a steel wire rope and the inner side of an outer template is guaranteed to be 470mm, the distance between two steel wires is 1260mm, a central hole of each group of bolts is aligned with the steel wires and then fixed and abutted, and the horizontal position of the embedded part is guaranteed;
s203, after the horizontal position of the embedded part is well positioned, performing high-range positioning, and measuring the top surface elevation of each group of embedded bolts (8) to ensure that the difference error of the position elevation of the embedded part on each beam is less than 1 mm;
s204, after the elevation positioning of the embedded part is finished, in order to prevent the groove die from floating upwards in the concrete pouring process, a steel rail is additionally arranged as a pressing bar to load the groove die;
s205, after the concrete pouring is finished, timely finishing and collecting the concrete surface, and completing checking the position of the embedded part before the concrete is initially set.
5. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 4, wherein the construction process comprises the following steps: the specific steps of the elevation positioning of the embedded part in step S203 include:
(1) preparing a steel plate strip with the thickness of 1mm to 5mm in advance, measuring the elevation of the end heads of all the embedded bolts, and adjusting the positions of the rest bolts after taking the arithmetic mean value;
(2) if the bolts need to be raised, steel base plates with corresponding thicknesses are added at the joints of the positioning channel steels and the outer templates, if the bolts need to be lowered, the steel base plates with corresponding thicknesses are added between the positioning channel steels and the embedded part steel plates, and the installed embedded part is checked for perpendicularity and levelness by using an instrument.
6. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 1, is characterized in that: the manufacturing process of the bow-string type center line positioning tool in the step S301 comprises fixed end bolt machining and positioning bow manufacturing;
the stiff end bolt course of working includes:
(1) two vertical diameter lines are found on a nut matched with the bolt, a 0.5mm wide wire groove is formed on the edge of the nut along the line, the depth is 1mm, the intersection point of the two lines is the middle point of the nut, and the intersection point position after the two lines are sleeved on the bolt is also the middle point of the bolt; (2) anchoring a 0.5mm steel wire along a wire slot on one line for fixing, wherein the two slots on the outer side of the unfixed steel wire are connected by the steel wire, and the steel wire naturally passes through the two slots on the inner side to ensure that the fixed steel wire is parallel to the reference line;
the manufacturing process of the positioning bow comprises the following steps:
(1) the deformed steel bar with the diameter of 12mm is used as a bow handle after being bent; (2) intercepting one section of the tape as a target object, punching holes on two sides, wherein the aperture is not more than 0.5mm, the length of the tape is preferably 10cm, and the middle data is a multiple of 5; (3) taking a steel wire with the thickness of 0.5mm to penetrate into the cut and processed tape measure, and penetrating steel wire clamps at two sides of the tape measure; (4) the steel wire is used as a bow string and fixed on a bow handle, the tool bow is processed, and the length of the bow cannot exceed the distance between the bolts on the outer side.
7. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 6, wherein the construction process comprises the following steps: the bow-string type center line positioning tool comprises a positioning nut (1), a bow handle (2), a center line positioning ruler (3) and a steel wire bow string (4);
the positioning nut (1) is matched with the embedded bolt (8) for use, two mutually perpendicular wire grooves (11) passing through the circle center are formed in the positioning nut (1), the width of each wire groove (11) is 0.5mm, and the depth of each wire groove is 1 mm;
the middle line positioning ruler (3) is arranged in the middle of the steel wire bowstring (4) and is connected with the steel wire bowstring (4) through a steel wire clamp (9), scales are arranged on the middle line positioning ruler (3), the length of the middle line positioning ruler (3) is 10cm, and the middle data is multiples of 5;
the steel wire bowstring (4) is made of steel wires with the thickness of 0.5mm, two ends, far away from the center line positioning ruler (3), of the steel wire bowstring (4) are connected with the bow handle (2) through the clamping mechanism, and the diameter of the bow handle (2) is 12 mm.
8. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 7, is characterized in that: the bow be provided with trapezoidal clamping groove (21) to the both ends connecting portion of (2), clamping mechanism sets up in clamping groove (21), including adjusting bolt (5) and locating piece (6), adjusting bolt (5) run through clamping groove (21) both sides curb plate setting, and with one side curb plate threaded connection who presss from both sides clamping groove (21), all be provided with guide way (22) on the both sides curb plate of clamping groove (21), guide way (22) are used with setting up guide rail (61) cooperation at locating piece (6) dorsal part, and the front side dislocation of two locating pieces (6) is provided with presss from both sides tooth (62), press from both sides tooth (62) and steel wire bow string (4) cooperation use.
9. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 7, is characterized in that: the middle line positioning ruler (3) is provided with a connecting hole (31), the connecting hole (31) is matched with a steel wire clamp (9) for use, the steel wire clamp (9) comprises a locking strip (91), a clamping seat (92) and a locking assembly, the locking strip (91) is a flexible locking strip provided with inner locking teeth (912), the tail end of one end of the locking strip (91) is provided with oblique locking teeth (911), the locking strip is connected with the clamping seat (92) through the oblique locking teeth (911), the clamping seat (92) is arranged on one side of the connecting hole (31), the clamping seat (92) is provided with an adjusting groove (921) and a mounting groove (922) which are communicated with each other, and the locking assembly is movably mounted in the mounting groove (922); the locking assembly comprises a locking block (93), a first spring (94) and a limiting part (95), the locking block (93) is movably mounted in a mounting groove (922), a latch and an inner latch (912) are arranged at the lower end of the locking block (93) to be matched for use, the first spring (94) is symmetrically arranged on guide columns (931) at two sides of the tail end of the locking block (93), the limiting part (95) is arranged at two sides of a tail end adjusting block of the locking block (93), and a second spring (96) is arranged at the tail part of the limiting part (95).
10. The special-shaped box girder erection construction process based on the arch-chord type center line positioning method according to claim 7, is characterized in that: the positioning method using the bow-string centerline positioning tool for positioning in step S302 includes:
(1) using a total station to find any point on a design central line as a reference point, and erecting a theodolite to enable the direction of the theodolite to be consistent with the direction of the design central line;
(2) the positioning nuts are sleeved on the embedded bolts at the symmetrical inner sides, so that the positioning nuts are convenient to put and take and are not suitable to be sleeved too deeply;
(3) the bowstring of the tool bow is hung in the wire grooves of the two positioning nuts, the positioning nuts are adjusted to enable the two grooves on the inner side to naturally penetrate through the grooves on the inner side of the tool nut, the steel wire bowstring can not be bent, and the bow is fixed by using a steel wire clamp so as not to shake left and right;
(4) measuring the distance between the two fixed steel wire bowstrings by using a measuring tape, taking the middle value of the upper measuring tape of the bowstring as a target object to move to a middle point after the middle value is taken, wherein the position of the middle value of the middle line positioning tape is the middle line position formed by the middle points of the connecting lines of the embedded bolts;
(5) and after the beam body is lifted by the hoisting equipment, the target object is coincided with the sighting axis of the positioned theodolite, and then the positioning work is finished.
CN202110945290.7A 2021-08-17 2021-08-17 Special-shaped box girder erection construction process based on bow-string type center line positioning method Active CN113684763B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110945290.7A CN113684763B (en) 2021-08-17 2021-08-17 Special-shaped box girder erection construction process based on bow-string type center line positioning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110945290.7A CN113684763B (en) 2021-08-17 2021-08-17 Special-shaped box girder erection construction process based on bow-string type center line positioning method

Publications (2)

Publication Number Publication Date
CN113684763A true CN113684763A (en) 2021-11-23
CN113684763B CN113684763B (en) 2023-02-03

Family

ID=78580365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110945290.7A Active CN113684763B (en) 2021-08-17 2021-08-17 Special-shaped box girder erection construction process based on bow-string type center line positioning method

Country Status (1)

Country Link
CN (1) CN113684763B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114482149A (en) * 2022-01-25 2022-05-13 张文元 Municipal construction foundation pile foundation construction method
CN114703756A (en) * 2022-04-08 2022-07-05 中铁大桥局武汉桥梁特种技术有限公司 Beam bottom centering device and method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5596856A (en) * 1993-08-04 1997-01-28 Campenon Bernard Sge Metal girder element for constructing a hybrid elongate structure having a box-type cross section, method for employing this element, and elongate structure constructed by implementing this method
CN102505585A (en) * 2011-12-07 2012-06-20 山西四建集团有限公司 Construction process of rocket sled
CN103954302A (en) * 2014-05-12 2014-07-30 北京航天控制仪器研究所 Flat track design method of rocket sled test
CN107255539A (en) * 2017-06-15 2017-10-17 深圳大学 A kind of rust test specimen stress calibrating installation and answer force calibration method
CN207326961U (en) * 2017-11-01 2018-05-08 中国化学工程第三建设有限公司 A kind of positioning marking tool
CN109778607A (en) * 2019-03-14 2019-05-21 中铁隧道集团一处有限公司 Continuous rigid frame PC track girder precise measurement positioning device and erection localization method
CN110219251A (en) * 2019-07-03 2019-09-10 中南建设集团有限公司 A kind of double-block type ballastless track bridge pedestal cross form positioning device
CN111206508A (en) * 2020-02-27 2020-05-29 中交一公局海威工程建设有限公司 Method and device for controlling central axis of suspension casting construction of linear bridge
CN111827123A (en) * 2020-07-27 2020-10-27 田育民 Bridge cantilever quick positioning device
CN112461099A (en) * 2020-10-28 2021-03-09 太原重工股份有限公司 Herringbone tooth centering detection device and method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5596856A (en) * 1993-08-04 1997-01-28 Campenon Bernard Sge Metal girder element for constructing a hybrid elongate structure having a box-type cross section, method for employing this element, and elongate structure constructed by implementing this method
CN102505585A (en) * 2011-12-07 2012-06-20 山西四建集团有限公司 Construction process of rocket sled
CN103954302A (en) * 2014-05-12 2014-07-30 北京航天控制仪器研究所 Flat track design method of rocket sled test
CN107255539A (en) * 2017-06-15 2017-10-17 深圳大学 A kind of rust test specimen stress calibrating installation and answer force calibration method
CN207326961U (en) * 2017-11-01 2018-05-08 中国化学工程第三建设有限公司 A kind of positioning marking tool
CN109778607A (en) * 2019-03-14 2019-05-21 中铁隧道集团一处有限公司 Continuous rigid frame PC track girder precise measurement positioning device and erection localization method
CN110219251A (en) * 2019-07-03 2019-09-10 中南建设集团有限公司 A kind of double-block type ballastless track bridge pedestal cross form positioning device
CN111206508A (en) * 2020-02-27 2020-05-29 中交一公局海威工程建设有限公司 Method and device for controlling central axis of suspension casting construction of linear bridge
CN111827123A (en) * 2020-07-27 2020-10-27 田育民 Bridge cantilever quick positioning device
CN112461099A (en) * 2020-10-28 2021-03-09 太原重工股份有限公司 Herringbone tooth centering detection device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114482149A (en) * 2022-01-25 2022-05-13 张文元 Municipal construction foundation pile foundation construction method
CN114703756A (en) * 2022-04-08 2022-07-05 中铁大桥局武汉桥梁特种技术有限公司 Beam bottom centering device and method

Also Published As

Publication number Publication date
CN113684763B (en) 2023-02-03

Similar Documents

Publication Publication Date Title
CN113684763B (en) Special-shaped box girder erection construction process based on bow-string type center line positioning method
CN106284341B (en) A kind of prestress anchorage cable hillside wall construction technology
CN105298153B (en) Building integral shift is vehicle-mounted to underpin system and method
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN111441604A (en) Old house wall body reinforcing device and construction process thereof
CN110952586A (en) Construction process for bearing platform below expressway
CN110644363A (en) Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN114134928B (en) Construction method of steel pipe column tower crane foundation
CN113829493B (en) Processing method of prefabricated greening retaining wall
CN112412467B (en) Construction method of ventilation vertical shaft (200-600 m) with extra-long highway tunnel by' well reversing method
CN114370188A (en) Construction method for public pipe gallery of industrial plant area in severe cold region
British Tunnelling Society Specification for tunnelling
CN108414362B (en) Multipurpose model test platform
CN113417215A (en) Bridge construction method
CN110453592B (en) Bearing platform construction process method in prefabricated stand column range
CN109811771B (en) Simple method for preventing anchor rod steel waist beam from bending during tensioning
CN111364413A (en) Construction process of outfitting wharf
CN110565634A (en) Method for repeatedly constructing and utilizing ultra-long steel casing
CN110284509A (en) Anchored frame beam slope protection construction technique in road engineering
CN212340860U (en) Test system for longitudinal loading of riser composite pipe column
CN212270945U (en) Existing railway line foundation pit supporting system
CN111663779A (en) Closed construction method for metallurgical industry factory building
CN111721637A (en) Test system and test method for longitudinal loading of riser composite pipe column
CN111648248A (en) Method for constructing cliff abutment of rhinestone
CN114627740B (en) Assembled comprehensive pipe rack penetrating collapsible loess field model test system and test method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Pan Hongwei

Inventor after: Zhang Yupeng

Inventor after: Chen Ying

Inventor after: Wang Yu

Inventor after: Hou Yonghong

Inventor after: Zhao Jianbin

Inventor before: Pan Hongwei

Inventor before: Zhang Yupeng

Inventor before: Wang Yu

Inventor before: Hou Yonghong

Inventor before: Zhao Jianbin