CN113668504B - Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall - Google Patents

Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall Download PDF

Info

Publication number
CN113668504B
CN113668504B CN202110960919.5A CN202110960919A CN113668504B CN 113668504 B CN113668504 B CN 113668504B CN 202110960919 A CN202110960919 A CN 202110960919A CN 113668504 B CN113668504 B CN 113668504B
Authority
CN
China
Prior art keywords
diaphragm
collapse
wall
construction method
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110960919.5A
Other languages
Chinese (zh)
Other versions
CN113668504A (en
Inventor
林海
钱福健
钮峰
刘亚松
全有维
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202110960919.5A priority Critical patent/CN113668504B/en
Publication of CN113668504A publication Critical patent/CN113668504A/en
Application granted granted Critical
Publication of CN113668504B publication Critical patent/CN113668504B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention provides a grooving emergency reinforcing construction method for an intermediate diaphragm underground diaphragm wall, which comprises the following steps: s1, protecting a collapse section guide wall and a groove section; s2, ultrasonic groove section detection; s3, forming holes at two sides of the groove section, and arranging partition steel bars; s4, filling collapse sections; and S5, performing double-liquid reinforcement treatment. The method is quick and efficient in treating the surface layer collapse of the groove wall of the middle partition underground continuous wall, and improves the construction quality of the middle partition underground continuous wall on the basis of guaranteeing the life safety of construction personnel.

Description

Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall
Technical Field
The invention relates to the technical field of underground continuous walls, in particular to a grooving emergency reinforcing construction method for an intermediate underground continuous wall.
Background
The underground continuous wall is a foundation engineering, and adopts a trenching machine on the ground, a long and narrow deep groove is excavated under the condition of slurry wall protection along the peripheral axis of the deep excavation engineering, after the groove is cleaned, a steel reinforcement cage is hung in the groove, then underwater concrete is poured by a conduit method to form a unit groove section, and the steps are carried out section by section, so that a continuous reinforced concrete wall is built underground to be used as a structure for intercepting water, preventing seepage, bearing and retaining water. The method has the characteristics of small construction vibration, high wall rigidity, good integrity, high construction speed, capability of saving earth and stone, capability of constructing deep foundation pit support in dense building groups and performing reverse construction, capability of being used for construction in various geological conditions including sandy soil layers and gravel layers with the particle size of less than 50mm, and the like. The method is suitable for building basements, underground markets, parking lots, underground oil depots, retaining walls, deep foundations of high-rise buildings, reverse construction building envelopes, deep pools and pits of industrial buildings, vertical shafts and the like of buildings.
At present, in the construction process of the middle-partition underground continuous wall, the groove wall of the middle-partition underground continuous wall is not designed for reinforcement, and thick filling soil exists on the surface layer in a construction site, so that the surface layer of the groove wall of the middle-partition underground continuous wall is easy to collapse.
Disclosure of Invention
Aiming at the prior art, the invention provides a grooving emergency reinforcing construction method for an intermediate diaphragm underground continuous wall, so as to improve the construction quality of the intermediate diaphragm underground continuous wall.
The invention provides a grooving emergency reinforcing construction method for an intermediate diaphragm underground diaphragm wall, which comprises the following steps of:
s1, protecting the guide wall and the groove section of the collapse section;
s2, detecting the ultrasonic groove section; the method comprises the following specific steps: carrying out fine measurement on the collapse condition of the groove section by utilizing ultrasonic waves, and forming a plane position diagram and a depth shape diagram of the collapse hole condition;
s3, forming holes at two sides of the groove section, and arranging partition steel bars; the method comprises the following specific steps: a plurality of drill holes are formed in the landslide section guide wall along the length direction, phi 12 or phi 14 partition steel bars are vertically inserted into the drill holes, and the partition steel bars vertically penetrate through the lower layer of the landslide soil body and are fixed;
s4, filling collapse sections; the method specifically comprises the following steps: according to the hole collapse situation plane position graph and the depth shape graph, a plurality of backfill holes are formed in the collapsed section guide wall or the temporary sidewalk along the length direction, and backfill soil is filled in the backfill holes; in filling, stirring the backfill soil in the backfill holes by using low pressure by using high-pressure rotary spraying equipment until the backfill soil is backfilled to the lower opening of a concrete surface layer to form a backfill soil body;
s5, performing double-liquid reinforcement treatment; the method specifically comprises the following steps: and (4) pouring mixed slurry in the gaps on the backfilled soil body.
Preferably, in S1, specifically: and (3) preliminarily determining the collapse range by utilizing ultrasonic wave, then closing the site, and forbidding various heavy-duty vehicles to pass in the collapse range influence area and the peripheral 5m range.
Preferably, in S2, the precise measurement includes: the length of each underground continuous wall is 6m, the detection is carried out every 1m along the length direction, and a plane position diagram and a depth shape diagram of the hole collapse condition are formed by utilizing 5 groups of ultrasonic grooving result diagrams.
Preferably, in S3, the distance between the drill holes is 200-250mm, and the hole diameter of the drill holes is 15-20 mm.
Preferably, in S4, the pore diameter of the backfill hole is 400-500 mm; the backfill soil is composed of adjusting slurry and broken stones with the particle size of less than or equal to 20mm, and the parameters of the adjusting slurry are as follows: the mud specific gravity is not less than 1.15, and the consistency is not less than 28 seconds.
Preferably, in S5, the diffusion radius of the mixed slurry is controlled to be 2m, and the initial setting time of the mixed slurry is controlled to be within 2 min.
Preferably, in S5, the depth of the perfusion is controlled to be 1-10m below a natural floor, the pressure of the perfusion is controlled to be 0.7-3.5MPa, and the perfusion concentration of the mixed slurry is gradually changed from thin to thick.
Preferably, in S5, the mixed slurry is a cement slurry-water glass double liquid.
Preferably, the cement slurry is a silicate cement slurry; the water glass is a water glass stock solution with the concentration of Be =30-40 and the modulus M = 2.8-3.1.
Preferably, the volume ratio of the cement paste to the water glass is 1: 1.
Compared with the prior art, the invention has the beneficial effects that
1. The invention adopts measures of adjusting slurry, cutting off reinforcing steel bars and the like, can effectively prevent the continuous collapse of the soil body of the groove section, and provides favorable conditions for the filling and the double-liquid reinforcement treatment of the subsequent collapse section. The partition reinforcing steel bars can also prevent backfill or common soil from entering the groove section in a large quantity, and waste is avoided. And the gap is filled by adopting double-liquid grouting, and loose low-pressure rotary-jetting backfill glue is integrated, so that the stability of the groove wall is improved.
2. The method has the advantages that the surface layer collapse treatment of the groove wall of the intermediate underground diaphragm wall is rapid and efficient, and the construction quality of the intermediate underground diaphragm wall is improved on the basis of guaranteeing the life safety of construction personnel.
3. The invention has the advantages of common machinery, simple process and method, quick disposal, meeting the requirement of emergency disposal, ensuring the construction safety and simultaneously ensuring the construction progress.
Drawings
Fig. 1 is a schematic flow chart of an emergency reinforcement construction method for grooving of a diaphragm underground diaphragm wall according to an embodiment of the invention.
Fig. 2-4 are schematic construction structures of the embodiment of the invention.
In the figure, 1, a groove section; 2. an underground diaphragm wall; 3. a landslide section guide wall; 4. drilling; 5. separating the reinforcing steel bars; 6. backfilling the hole; 7. original reinforcing steel bars.
Detailed Description
In order to make the technical means, the creation characteristics, the achievement purposes and the effects of the invention easy to understand, the invention is further explained below by combining the specific drawings.
Examples
As shown in fig. 1-4, a construction method for grooving and emergency reinforcing of an intermediate underground diaphragm wall comprises the following steps:
s1, protecting the guide wall and the groove section of the collapse section: preliminarily measuring by using an ultrasonic detector, preliminarily determining a collapse range, and then closing the site, wherein various heavy-duty vehicles are forbidden to pass through in an affected area of the collapse range and a peripheral 5m range;
s2, ultrasonic wave groove section detection: in order to determine the position and the quantity of subsequent drilling holes, an ultrasonic detector is utilized to carry out fine measurement on the collapse condition of the groove section 1, each length of the underground continuous wall 2 is 6m, the detection is carried out once every 1m along the length direction, and 5 groups of ultrasonic grooving result graphs are utilized to form a hole collapse condition plane position graph and a depth shape graph;
s3, holes are formed in two sides of the groove section, and partition steel bars are arranged: referring to FIGS. 2-4, a plurality of drill holes 4 are formed in the position, 300mm away from the inner side edge of the guide wall 3 of the collapse section along the length direction by adopting an electric hammer, phi 12 partition steel bars 5 are vertically inserted into the drill holes 4 according to the staggered arrangement of the original steel bars 7 in the guide wall 3 of the collapse section, and the partition steel bars 5 vertically penetrate into the lower layer of the collapse soil body and are fixed by matching with manual work of a digging machine; wherein the distance between adjacent drill holes 4 is 230mm, and the aperture of each drill hole 4 is 18 mm;
s4, filling collapse section: referring to fig. 4, according to the plan position diagram and the depth shape diagram of the hole collapse situation, a backfill hole 6 is arranged on the collapse section guide wall 3 along the length direction by adopting a water drilling machine and a pickaxe at each 1.5m, the backfill hole 6 is formed from the outer side edge of the collapse section guide wall 3 to 1/3 of the groove section 1, and backfill soil is filled in the backfill hole 6 by adopting a PC60 excavator;
in filling, the filling speed is controlled, the deformation condition of the partition steel bars 5 is observed, whether the partition steel bars 5 are completely deformed or dislocated is judged, and if the dislocated partition steel bars are completely deformed or dislocated, the partition steel bars are immediately supplemented;
during filling, the backfill cannot be tamped tightly, gaps are still quite dispersed, the backfill in the backfill holes 6 is stirred by a high-pressure rotary spraying machine through low pressure for continuous construction for 15min, equipment is removed after rotary spraying and uniform stirring, whether the soil body is settled or not is observed, and if the settlement is obvious, the backfill is manually filled again to the lower opening of the concrete surface layer to form the backfill soil body; wherein, the high-pressure jet grouting machine is adopted to reduce the cement slurry pressure of the jet grouting pile, the pressure is controlled to be about 1MP a, and the cement slurry and the backfill soil are uniformly mixed and solidified into a solidified body so as to achieve the effect of stabilizing the wall of the tank;
in the process, an ultrasonic detector is adopted for continuous ultrasonic detection;
wherein the aperture of the backfilling hole 6 is 450 mm; the backfill consists of adjusting slurry and crushed stones with the particle size less than or equal to 20mm, and the parameters of the adjusting slurry are as follows: the mud has the specific gravity of 1.15 and the consistency of 28 seconds, so as to prevent the soil body of the groove section 1 from continuously collapsing;
s5, double-liquid reinforcement treatment: filling mixed slurry in gaps existing in the backfilled soil body by adopting a double-liquid grouting machine; aiming at the analysis that the backfill soil body influences the stability of the wall of the underground continuous wall, and combining the construction condition of the prior low-pressure jet grouting pile reinforcement, the slurry proportion is reasonably selected to ensure the effective diffusion radius of the mixed slurry;
the diffusion radius of the mixed slurry is controlled to be 2m, the initial setting time of the mixed slurry is controlled to be 2min, the filling depth is controlled to be 5m below a natural terrace, the filling pressure is controlled to be 2.5MPa, and the filling concentration of the mixed slurry is gradually changed from dilute to concentrated.
The mixed slurry is a cement slurry-water glass double liquid, and the cement slurry is silicate cement slurry; the water glass is selected from water glass stock solution with the concentration Be =35 and the modulus M =3.0, the volume ratio of the cement paste to the water glass is 1:1, and the cement mixing amount in the cement paste is not too large in consideration of excavation difficulty in the future and is controlled to be 10%.
Along with the requirement of the country and the industry on green environmental protection is higher and higher, this embodiment has promoted mesophragma underground continuous wall construction quality through ways such as adjustment dado parameter, add the wall reinforcing bar, low pressure jet grouting and biliquid slip casting of mud, has avoided the condition that midboard "belly" and later stage excavation were abolished, has practiced thrift concrete and material, and economic benefits and environmental benefit are showing, and to similar engineering, this embodiment has fabulous popularization and application and worth.
In the implementation process of the embodiment, the use of concrete and materials is reduced, the construction period is shortened, the emission of construction waste is reduced, the environment is protected, the method is economical and applicable, and the national environment-friendly policy for improving the resource utilization rate is met.
The above description is only an embodiment of the present invention, and is not intended to limit the scope of the present invention, and all equivalent structures made by using the contents of the present specification and the drawings can be directly or indirectly applied to other related technical fields, and are also within the scope of the present invention.

Claims (10)

1. The emergency reinforcing construction method for the groove forming of the diaphragm underground diaphragm wall is characterized by comprising the following steps of:
s1, protecting a collapse section guide wall and a groove section;
s2, ultrasonic groove section detection; the method specifically comprises the following steps: carrying out fine measurement on the collapse condition of the groove section by utilizing ultrasonic waves, and forming a plane position diagram and a depth shape diagram of the collapse hole condition;
s3, forming holes at two sides of the groove section, and arranging partition steel bars; the method comprises the following specific steps: a plurality of drill holes are formed in the landslide section guide wall along the length direction, partition reinforcing steel bars are vertically inserted into the drill holes, and the partition reinforcing steel bars vertically penetrate through the lower layer of the landslide soil body and are fixed;
s4, filling collapse sections; the method comprises the following specific steps: according to the hole collapse situation plane position graph and the depth shape graph, a plurality of backfill holes are formed in the collapsed section guide wall or the temporary sidewalk along the length direction, and backfill soil is filled in the backfill holes; in filling, stirring the backfill soil in the backfill hole by using low pressure by adopting high-pressure rotary spraying equipment until the backfill soil is backfilled to the lower opening of the concrete surface layer to form a backfill soil body;
s5, performing double-liquid reinforcement treatment; the method specifically comprises the following steps: and (4) pouring mixed slurry in the gaps on the backfilled soil body.
2. The grooving emergency reinforcing construction method for the diaphragm underground diaphragm wall according to claim 1, wherein in the step S1, the concrete steps are as follows: and (3) preliminarily determining the collapse range by utilizing ultrasonic wave, then closing the site, and forbidding various heavy-duty vehicles to pass in the collapse range influence area and the peripheral 5m range.
3. The grooving emergency reinforcing construction method for the diaphragm underground diaphragm wall according to claim 1, wherein in S2, the precise measurement specifically comprises: the length of each underground continuous wall is 6m, detection is carried out every 1m along the length direction, and a plane position diagram and a depth shape diagram of hole collapse conditions are formed by utilizing 5 groups of ultrasonic grooving result diagrams.
4. The emergency reinforcement construction method for the partitioning underground continuous wall as claimed in claim 1, wherein in S3, the distance between the drill holes is 200-250mm, and the aperture of the drill holes is 15-20 mm.
5. The emergency reinforcement construction method for the middle and underground diaphragm wall as claimed in claim 1, wherein in S4, the diameter of the backfill hole is 400-500 mm; the backfill consists of adjusting slurry and crushed stones with the particle size less than or equal to 20mm, and the parameters of the adjusting slurry are as follows: the mud weight is not less than 1.15, and the consistency is not less than 28 seconds.
6. The trenching emergency reinforcement construction method for the diaphragm underground continuous wall as claimed in claim 1, wherein in S5, the spreading radius of the mixed slurry is controlled to be 2m, and the initial setting time of the mixed slurry is controlled to be within 2 min.
7. The trenching emergency reinforcement construction method for the diaphragm underground diaphragm wall as claimed in claim 1, wherein in S5, the depth of the pouring is controlled to be 1-10m below the natural terrace, the pressure of the pouring is controlled to be 0.7-3.5MPa, and the pouring concentration of the mixed slurry is gradually changed from thin to thick.
8. The grooving emergency reinforcing construction method for the diaphragm underground diaphragm wall according to claim 1, wherein in the step S5, the mixed slurry is a cement slurry-water glass double liquid.
9. The grooving emergency reinforcing construction method for the diaphragm underground continuous wall according to claim 8, wherein the cement paste is silicate cement paste; the water glass is a water glass stock solution with the concentration of Be =30-40 and the modulus M = 2.8-3.1.
10. The grooving emergency reinforcing construction method for the diaphragm underground continuous wall according to claim 8 or 9, wherein a volume ratio of the cement paste to the water glass is 1: 1.
CN202110960919.5A 2021-08-20 2021-08-20 Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall Active CN113668504B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110960919.5A CN113668504B (en) 2021-08-20 2021-08-20 Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110960919.5A CN113668504B (en) 2021-08-20 2021-08-20 Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall

Publications (2)

Publication Number Publication Date
CN113668504A CN113668504A (en) 2021-11-19
CN113668504B true CN113668504B (en) 2022-07-22

Family

ID=78544548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110960919.5A Active CN113668504B (en) 2021-08-20 2021-08-20 Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall

Country Status (1)

Country Link
CN (1) CN113668504B (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3098457B2 (en) * 1997-05-27 2000-10-16 利根地下技術株式会社 Construction method of multi-functional underground diaphragm wall
CN105804049A (en) * 2014-12-31 2016-07-27 云南省第三建筑工程公司 Anti-hole-collapsing foundation reinforced structure during underground diaphragm wall construction
CN107761692A (en) * 2016-08-17 2018-03-06 彭建明 Based on the detection method to the groove section after continuous wall trench underground
CN108118727A (en) * 2017-12-22 2018-06-05 上海市基础工程集团有限公司 Ground wall leads the cell wall post-reinforcing construction technology led after wall is implemented outside wall side wall

Also Published As

Publication number Publication date
CN113668504A (en) 2021-11-19

Similar Documents

Publication Publication Date Title
JP6166264B2 (en) How to build a retaining wall
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN108612086A (en) A kind of crack geotechnical boring cast-in-place pile construction method
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN112323819A (en) Soft soil foundation pit bottom in-situ curing method and soft soil foundation pit bottom curing structure
CN106948340A (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN112064751A (en) Deep groove construction method for drainage pipeline
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
US7025537B2 (en) Subterranean structures and methods for constructing subterranean structures
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN108149682A (en) A kind of slip casting casing device and the pile foundation drilling construction method using the casing device
CN109252433A (en) Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit
CN207862925U (en) A kind of slip casting casing device
CN110700270B (en) Construction method for non-drainage earthwork excavation of ultra-deep foundation pit
CN110512649B (en) Underground excavation construction method for additionally arranging basement and communication channel structure under existing building
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN113668504B (en) Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN213897154U (en) Soft soil foundation pit bottom curing structure
CN104878763B (en) Main building basement supporting construction with annex
CN102409668A (en) Cast-in-situ bored pile and expansion and compaction construction method thereof
CN106049516A (en) Corrugated steel cofferdam hollow digging pile and manufacturing technique thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant