CN113668398A - Construction method of river-crossing steel structure arch bridge - Google Patents

Construction method of river-crossing steel structure arch bridge Download PDF

Info

Publication number
CN113668398A
CN113668398A CN202110969115.1A CN202110969115A CN113668398A CN 113668398 A CN113668398 A CN 113668398A CN 202110969115 A CN202110969115 A CN 202110969115A CN 113668398 A CN113668398 A CN 113668398A
Authority
CN
China
Prior art keywords
channel
bridge
construction
steel structure
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110969115.1A
Other languages
Chinese (zh)
Inventor
黄振威
蒋德林
王安文
于策
李晔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202110969115.1A priority Critical patent/CN113668398A/en
Publication of CN113668398A publication Critical patent/CN113668398A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The invention relates to a method for constructing a cross-river steel structure arch bridge, which comprises the steps of firstly erecting a channel trestle into a river on two banks, erecting a crawler crane construction channel along the design position of the bridge, wherein the construction channel adopts steel pipe piles as lower supports, directly utilizing a cross beam of the steel structure bridge as a distribution beam of the construction channel, paving a bridge deck on the cross beam, utilizing the crawler crane to install a longitudinal beam of the steel structure bridge on the construction channel, then erecting arch rib mounting supports at two ends of the cross beam and installing arch ribs, and finally connecting slings between the arch ribs and the longitudinal beam. The construction process is simple and the efficiency is high; the construction equipment mainly adopts the crawler crane, does not need to invest a large-scale floating crane, can greatly reduce the construction cost, is not limited by the height of the water level of the river channel, and is favorable for ensuring the construction period.

Description

Construction method of river-crossing steel structure arch bridge
Technical Field
The invention belongs to the technical field of steel structure arch bridge construction, and particularly relates to a river (river) -crossing large-span steel structure arch bridge construction method.
Background
The steel structure arch bridge is not provided with piers, depends on arch ribs to suspend the bridge deck system through slings, has strong spanning capability, does not influence navigation, and is widely applied to river (river) bridge spanning construction. At present, a common method for constructing a large-span river-crossing steel structure arch bridge is to mount steel arch ribs by using a large floating crane, and then to hoist longitudinal beams (steel structure bridge main beams) and cross beams by using the floating crane after the arch ribs are erected; or firstly adopting a lifting method to install arch ribs, and then adopting a floating crane to install main beams and cross beams. The two methods both need to invest in large-scale floating cranes, and the latter method needs to additionally erect arch rib lifting supports, so that the construction cost is high, and the large-scale floating crane is easily limited by the river water level in the dry season, and the construction period cannot be guaranteed.
Disclosure of Invention
The invention aims to solve the problems and provides a construction method of a large-span river-crossing steel structure arch bridge with less equipment investment and low construction cost.
The technical scheme of the invention is as follows:
a construction method of a river-crossing steel structure arch bridge is characterized by comprising the following steps:
(1) respectively erecting a channel trestle in the river at the position, close to the design position of the bridge, of the two banks, and respectively erecting a section of construction channel at the two ends of the design position of the bridge along the bridge direction; the channel trestle and the construction channel both adopt steel pipe piles as lower supports, wherein the construction channel adopts a Bailey beam which is erected on the top of the steel pipe pile in the bridge direction as a bearing beam, a cross beam of the steel structure bridge is erected on the Bailey beam in the transverse bridge direction, bridge decks of the steel structure bridge are laid on the cross beam along two sides of the center line of the bridge, and top surfaces of two ends of the cross beam are respectively reserved with a certain length and are not laid firstly; installing a bearing beam, a cross beam and a bridge deck of the construction channel on the shore by adopting a crawler crane; laying a bridge deck between the channel trestle and the construction channel, and communicating the channel trestle with the construction channel;
(2) the crawler crane runs onto a construction channel through a channel trestle, the construction channel is continuously extended and erected from two banks to a midspan, a steel pipe pile is not driven at the midspan position of the construction channel, the construction channel is not closed, and a navigation hole with a certain width is reserved; driving steel pipe pile supports on two sides of the construction channel to serve as mounting supports of the steel structure bridge girder;
(3) the method comprises the following steps that longitudinal beam sections of the ship water-borne steel structure bridge are adopted, two crawler cranes are used on a construction channel, a lifting mode is adopted, longitudinal beams on two sides of the steel structure bridge are installed from two banks to a midspan, and two ends of each transverse beam are respectively welded with the longitudinal beams on the two sides; closing the longitudinal beams at the midspan position of the construction channel, welding a cross beam between the longitudinal beams at two sides of the midspan, paving a bridge deck on the cross beam, and communicating the construction channel;
(4) erecting an arch rib mounting bracket on the construction channel by adopting a crawler crane; the lower ends of the arch rib mounting brackets are supported at two ends of the cross beam where the bridge deck is not laid, and the cross beam at the midspan position is avoided;
(5) hoisting arch ribs from two banks to midspan on a construction channel by adopting a crawler crane; the arch ribs at the midspan position are hoisted on the construction channels at two sides of the navigation channel by the crawler crane, and the crawler crane can only run in no-load when passing through the midspan position of the construction channel;
(6) after the arch ribs are closed, installing arch rib crossbars;
(7) slings are arranged between the arch ribs and the longitudinal beams, and the longitudinal beams are supported by the steel pipe pile supports and are converted into suspension by the arch ribs;
(8) and (4) sequentially removing the arch rib support, the longitudinal beam mounting support, the Bailey beam and the steel pipe pile at the lower part of the construction channel and the channel trestle, and mounting bridge decks on the top surfaces of two ends of the cross beam to complete the river-crossing steel structure arch bridge construction.
According to the construction method, firstly, a crawler crane construction channel is erected along the design position of a bridge, a steel pipe pile is adopted as a lower support for the construction channel, a cross beam of a steel structure bridge is directly used as a distribution beam of the construction channel, a bridge deck is laid on the cross beam, a longitudinal beam of the steel structure bridge is installed on the construction channel by utilizing the crawler crane, then arch rib installation supports are erected at two ends of the cross beam and arch ribs are installed, the construction process is simple, and the construction efficiency is high; the construction equipment mainly adopts the crawler crane, and a large-scale floating crane is not required to be input, so that the construction cost can be greatly reduced; the construction of the invention is not restricted by the water level of the river channel, which is beneficial to ensuring the construction period.
Drawings
FIG. 1 is a construction flow chart of the present invention.
Detailed Description
FIG. 1 is a construction flow chart of the present invention, and the specific construction process is as follows:
(1) respectively erecting a channel trestle in the river at the position, close to the design position of the bridge, of the two banks, and respectively erecting a section of construction channel at the two ends of the design position of the bridge along the bridge direction; the channel trestle and the construction channel both adopt steel pipe piles as lower supports, wherein the construction channel adopts a Bailey beam which is erected on the top of the steel pipe pile along the bridge direction as a bearing beam, a cross beam of the steel structure bridge is erected on the Bailey beam in the transverse bridge direction as a distribution beam of the construction channel, and the erection space of the cross beam is consistent with the design space of the cross beam of the steel structure bridge; and bridge decks of the steel structure bridge are laid on the cross beams along two sides of the center line of the bridge, and certain lengths of top surfaces of two ends of the cross beams are reserved respectively, and the bridge decks are not laid firstly.
The length of the construction channel is within the construction range of the crawler crane on the bank, and the bearing beam, the cross beam and the bridge deck of the construction channel can be installed on the bank by adopting the crawler crane.
And laying a bridge deck between the channel trestle and the construction channel, and communicating the channel trestle with the construction channel.
(2) The crawler crane on the bank runs to the construction channel erected in the step (1) through the channel trestle, the construction channel is continuously erected from two banks to the midspan, the construction channel is not closed at the midspan position, and a steel pipe pile is not erected, so that a navigation hole with a certain width is reserved, and influence on river navigation is avoided.
And (4) driving steel pipe pile supports on two sides of the construction channel by using the crawler crane to serve as mounting supports of the steel structure bridge girder.
(3) The method comprises the following steps that a longitudinal beam section of the ship water-borne steel structure bridge is adopted, two crawler cranes are used on a construction channel in a lifting and hanging mode, longitudinal beams on two sides of the steel structure bridge are installed from two banks to a midspan, and the longitudinal beams are supported on longitudinal beam installation supports firstly; closing the longitudinal beam at the midspan position of the construction channel;
welding two ends of each cross beam with longitudinal beams on two sides respectively;
a cross beam is also welded between the longitudinal beams on the two sides of the midspan, and a bridge deck is laid on the cross beam to communicate the top surface of the construction channel; because no steel pipe pile is erected at the navigation hole, the construction channel can still be navigated under the midspan after the construction channel is communicated with the midspan.
(4) Erecting an arch rib mounting bracket on the construction channel by adopting a crawler crane; the arch rib mounting brackets are supported at two ends of the cross beam where the bridge deck is not laid. Because the cross beam at the midspan position is not supported by the steel pipe piles and has limited bearing capacity, the installation of the arch rib bracket needs to avoid the cross beam at the midspan position.
(5) Hoisting arch rib segments from two banks to midspan on the construction channel by adopting a crawler crane; the arch ribs at the midspan position are hoisted on the construction channels at two sides of the navigation hole by the crawler crane, and the crawler crane can only run in no-load when passing through the midspan position of the construction channel, so that the bearing capacity of the midspan position of the construction channel is avoided being exceeded.
(6) After the arch ribs are closed, installing arch rib crossbars; the arch rib cross brace is also hoisted by adopting a crawler crane.
(7) And slings are arranged between the arch ribs and the longitudinal beams, and the longitudinal beams are supported by the steel pipe pile supports and are converted into suspension by the arch ribs.
(8) And (3) sequentially removing the arch rib mounting supports, the longitudinal beam mounting supports, the Bailey beams and the steel pipe piles at the lower part of the construction channel, removing the channel trestle, and mounting the rest bridge decks, namely the bridge decks on the top surfaces of the two ends of the cross beam to complete the river-crossing steel structure arch bridge construction.

Claims (1)

1. A construction method of a river-crossing steel structure arch bridge is characterized by comprising the following steps:
(1) respectively erecting a channel trestle in the river at the position, close to the design position of the bridge, of the two banks, and respectively erecting a section of construction channel at the two ends of the design position of the bridge along the bridge direction; the channel trestle and the construction channel both adopt steel pipe piles as lower supports, wherein the construction channel adopts a Bailey beam which is erected on the top of the steel pipe pile in the bridge direction as a bearing beam, a cross beam of the steel structure bridge is erected on the Bailey beam in the transverse bridge direction, bridge decks of the steel structure bridge are laid on the cross beam along two sides of the center line of the bridge, and top surfaces of two ends of the cross beam are respectively reserved with a certain length and are not laid firstly; installing a bearing beam, a cross beam and a bridge deck of the construction channel on the shore by adopting a crawler crane; laying a bridge deck between the channel trestle and the construction channel, and communicating the channel trestle with the construction channel;
(2) the crawler crane runs onto a construction channel through a channel trestle, the construction channel is continuously erected from two banks to a midspan, a steel pipe pile is not arranged at the midspan position of the construction channel, the construction channel is not closed, and a navigation hole with a certain width is reserved; driving steel pipe pile supports on two sides of the construction channel to serve as mounting supports of the steel structure bridge girder;
(3) the method comprises the following steps that longitudinal beam sections of the ship water-borne steel structure bridge are adopted, two crawler cranes are used on a construction channel, a lifting mode is adopted, longitudinal beams on two sides of the steel structure bridge are installed from two banks to a midspan, and two ends of each transverse beam are respectively welded with the longitudinal beams on the two sides; closing the longitudinal beams at the midspan position of the construction channel, welding a cross beam between the longitudinal beams at two sides of the midspan, paving a bridge deck on the cross beam, and communicating the construction channel;
(4) erecting an arch rib mounting bracket on the construction channel by adopting a crawler crane; the lower ends of the arch rib mounting brackets are supported at two ends of the cross beam where the bridge deck is not laid, and the cross beam at the midspan position is avoided;
(5) hoisting arch ribs from two banks to midspan on a construction channel by adopting a crawler crane; the arch ribs at the midspan position are hoisted on the construction channels at two sides of the navigation channel by the crawler crane, and the crawler crane can only run in no-load when passing through the midspan position of the construction channel;
(6) after the arch ribs are closed, installing arch rib crossbars;
(7) slings are arranged between the arch ribs and the longitudinal beams, and the longitudinal beams are supported by the steel pipe pile supports and are converted into suspension by the arch ribs;
(8) and (4) sequentially removing the arch rib support, the longitudinal beam mounting support, the Bailey beam and the steel pipe pile at the lower part of the construction channel and the channel trestle, and mounting bridge decks on the top surfaces of two ends of the cross beam to complete the river-crossing steel structure arch bridge construction.
CN202110969115.1A 2021-08-23 2021-08-23 Construction method of river-crossing steel structure arch bridge Pending CN113668398A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110969115.1A CN113668398A (en) 2021-08-23 2021-08-23 Construction method of river-crossing steel structure arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110969115.1A CN113668398A (en) 2021-08-23 2021-08-23 Construction method of river-crossing steel structure arch bridge

Publications (1)

Publication Number Publication Date
CN113668398A true CN113668398A (en) 2021-11-19

Family

ID=78545285

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110969115.1A Pending CN113668398A (en) 2021-08-23 2021-08-23 Construction method of river-crossing steel structure arch bridge

Country Status (1)

Country Link
CN (1) CN113668398A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002201609A (en) * 2000-12-28 2002-07-19 Ps Corp Construction method for concrete arch bridge
JP2007205139A (en) * 2006-02-06 2007-08-16 Sumitomo Mitsui Construction Co Ltd Construction method of arch bridge
CN102367650A (en) * 2011-08-05 2012-03-07 中铁一局集团厦门建设工程有限公司 Construction method of steel pipe arch bridge
CN109056548A (en) * 2018-09-19 2018-12-21 中交二公局第六工程有限公司 A kind of steel arch frame construction method
CN110886237A (en) * 2019-12-25 2020-03-17 中交路桥华南工程有限公司 Arch bridge construction method
CN111155411A (en) * 2020-02-20 2020-05-15 中国水利水电第五工程局有限公司 Cast-in-place arch bridge combined support structure and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002201609A (en) * 2000-12-28 2002-07-19 Ps Corp Construction method for concrete arch bridge
JP2007205139A (en) * 2006-02-06 2007-08-16 Sumitomo Mitsui Construction Co Ltd Construction method of arch bridge
CN102367650A (en) * 2011-08-05 2012-03-07 中铁一局集团厦门建设工程有限公司 Construction method of steel pipe arch bridge
CN109056548A (en) * 2018-09-19 2018-12-21 中交二公局第六工程有限公司 A kind of steel arch frame construction method
CN110886237A (en) * 2019-12-25 2020-03-17 中交路桥华南工程有限公司 Arch bridge construction method
CN111155411A (en) * 2020-02-20 2020-05-15 中国水利水电第五工程局有限公司 Cast-in-place arch bridge combined support structure and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄结团: "拱桥支架吊装施工技术探析", 《公路交通科技(应用技术版)》 *

Similar Documents

Publication Publication Date Title
CN101418543B (en) Self-anchored rope-suspension bridge inclined drawing construction method
CN101736699B (en) Accurate positioning method of sliding of full-support frame steel box girder
CN111172882A (en) Beam section transportation method for assembling bridge girder cantilever
CN105088957A (en) Construction method for underwater reinforced concrete composite pile of cast-in-situ support of concrete ballast box beam of cable-stayed bridge
CN110258293A (en) Cable-stayed bridge steel truss girder main pylon pier top erection construction method
CN201560397U (en) Whole support for steel box girder precise location installation
CN201102544Y (en) Hanging train traffic system of hanging rail
CN112252212A (en) Method for dismantling prestressed concrete variable cross-section continuous beam bridge
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN102206934B (en) Method for block-by-block casting of concrete continuous beam bridge by using military truss shift mould
CN113668398A (en) Construction method of river-crossing steel structure arch bridge
CN111350135A (en) Large-span steel truss girder floating towing frame facility construction method
CN110904861A (en) Cable-stayed bridge girder erection crane and construction method thereof
CN214401780U (en) Buoyancy tank platform suitable for ultra-low clearance existing steel pipe pile removing system
CN206359894U (en) Naked rock geology combined type cast-in-place box beam bracket system in a kind of water
CN113668399B (en) Construction method of half-through tied steel box arch bridge
CN115748513A (en) Construction method of ultra-small high-span-ratio all-welded steel truss girder bridge based on cantilever aerial work platform
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN113897968B (en) Mounting system for assembling, sinking and positioning water surface under water-moving condition of block-type hydraulic building
CN111472285A (en) Method for mounting main bridge variable-section continuous steel truss girder by using cable crane
CN219637728U (en) Aerial working platform for cantilever assembly ultra-small high span ratio all-welded steel truss bridge
CN214993124U (en) Lifting mechanism of through tied arch bridge
JPH0913329A (en) Installation method of bridge
CN212641217U (en) Support system for asymmetric installation of steel box short-tower cable-stayed bridge
CN217104777U (en) Interim landing stage demolishs device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20211119

WD01 Invention patent application deemed withdrawn after publication