CN113668386A - Dust-settling and noise-preventing green construction process for viaduct - Google Patents

Dust-settling and noise-preventing green construction process for viaduct Download PDF

Info

Publication number
CN113668386A
CN113668386A CN202010408899.6A CN202010408899A CN113668386A CN 113668386 A CN113668386 A CN 113668386A CN 202010408899 A CN202010408899 A CN 202010408899A CN 113668386 A CN113668386 A CN 113668386A
Authority
CN
China
Prior art keywords
dust
noise
monitoring
site
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010408899.6A
Other languages
Chinese (zh)
Inventor
黄登启
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou CRRC Construction Engineering Co Ltd
Original Assignee
Suzhou CRRC Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou CRRC Construction Engineering Co Ltd filed Critical Suzhou CRRC Construction Engineering Co Ltd
Priority to CN202010408899.6A priority Critical patent/CN113668386A/en
Publication of CN113668386A publication Critical patent/CN113668386A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01DMEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
    • G01D21/00Measuring or testing not otherwise provided for
    • G01D21/02Measuring two or more variables by means not covered by a single other subclass

Abstract

The invention discloses a dust-falling and noise-preventing green construction process for viaducts, which comprises the steps of establishing a noise monitoring system, monitoring noise decibel values at the periphery of a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, automatically alarming and optimizing according to relevant department data, establishing a dust monitoring system, monitoring dust concentration at the periphery of the construction site by arranging the outdoor dust monitoring device, transmitting all concentration values to the cloud server for cloud computing processing, linking a dust raising device with spraying equipment such as a fog gun on site, and automatically triggering the fog gun, a spraying tower crane and a surrounding shield spraying when the dust raising exceeds the standard on site. According to the invention, a noise monitoring system, a dust monitoring system and a temperature and humidity monitoring system are established, and meanwhile, dust raising equipment and spray equipment such as a fog gun can be linked on site, so that control can be well carried out in the construction process, and the noise and dust during construction are reduced to the minimum.

Description

Dust-settling and noise-preventing green construction process for viaduct
Technical Field
The invention relates to the field of viaduct construction, in particular to a dust-settling and noise-preventing green construction process for a viaduct.
Background
The urban railway viaduct is an important part in urban construction, various problems can be generated in construction, meanwhile, urban railways are commuting railways and suburban railways, and refer to a passenger transport rail transit system in a metropolitan area range, which serves cities and suburbs, a central city and a satellite city and key cities and towns, a large amount of dust and noise can be generated in the construction of the urban railways, the improvement of a construction process can be timely performed, huge damage can be brought to the environment, in the existing construction process, the control part of the noise and the dust is very poor, the environment is damaged when construction is performed, and the repair cannot be well performed.
Disclosure of Invention
The invention aims to provide a dust-settling and noise-preventing green construction process for an viaduct, which aims to solve the problems in the background art.
In order to achieve the purpose, the invention provides the following technical scheme: a dust-settling and noise-preventing green construction process for a viaduct comprises the following steps:
s1: establishing a noise monitoring system, monitoring noise decibel values around a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, and automatically alarming and optimizing according to relevant department data;
s2: establishing a dust monitoring system, monitoring dust concentration at the periphery of a construction site by arranging an outdoor dust monitoring device, transmitting all concentration values to a cloud server for cloud computing processing, and automatically alarming and optimizing according to the data of meteorological departments;
s3: a temperature and humidity monitoring system is established, the temperature and humidity condition of the construction site can be detected in real time by the temperature and humidity monitoring system, the current temperature and humidity situation of the construction site is confirmed according to the signal content identified by the reading and writing equipment, and when the temperature and humidity are abnormal, the system can rapidly give an alarm and prompt a hidden danger area;
s4: the dust raising equipment and the spray equipment such as the fog gun can be linked on site, and the fog gun, the tower crane and the enclosure are automatically triggered to spray under the condition that the raised dust exceeds the standard on site.
Preferably, when the exceeding times of the noise in a set time period exceed the specified allowable times, the alarm is given to the monitoring center and the related responsible persons through the mobile phone short messages immediately, a data statistical table is formed and uploaded to the command center, and a supervision unit is enabled to be well documented and can rely on the evidence.
Preferably, the fog gun and the tower crane spray and the enclosure spray are provided with manual switches, and the fog gun and the tower crane can be manually closed after a mistake.
Preferably, a pollution source on-line monitor is installed, and the pollution source on-line monitor comprises a particulate matter concentration monitor, a meteorological five-parameter monitor, a noise monitor and a video monitoring camera, and is used for continuously and automatically monitoring the particulate matter concentration, meteorological parameters, noise and on-site video on line.
Preferably, adopt wired, wireless, various monitoring data of 3G mode transmission, the platform layer: the data service cloud platform relies on data of a dust emission and noise monitoring platform in a construction site to carry out system analysis and provide cross-regional, full-time and multi-level data mining and comparison, and provides data support for scientific haze treatment.
Preferably, the system is oriented to client systems of different environmental protection bureaus and project construction sites, realizes Web-based pollution source real-time data online monitoring, site image and video monitoring, pollution source overproof alarm and various management and statistical analysis oriented to different management layers, supports seamless butt joint with a construction and commission intelligent construction site system, and ensures data interconnection and intercommunication.
Preferably, the monitoring system is installed and deployed at the construction entrance and exit, and can be set according to actual field.
The invention has the technical effects and advantages that: establish noise monitoring system, establish dust monitoring system, establish humiture monitoring system, the scene can be linked with spraying equipment such as raise dust equipment and fog gun simultaneously, monitors through a plurality of systems, uses spraying equipment such as raise dust equipment and fog gun to link simultaneously, can in time carry out the management and control when monitoring unusually, at the in-process that carries out the construction, can be fine carry out the management and control for noise and dust during the construction fall to minimumly.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a dust-settling and noise-preventing green construction process for a viaduct, which comprises the following steps:
the method comprises the steps of establishing a noise monitoring system, monitoring noise decibel values at the periphery of a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, automatically alarming and optimizing according to relevant department data, establishing a dust monitoring system, monitoring dust concentration at the periphery of the construction site by arranging the outdoor dust monitoring device, transmitting all concentration values to the cloud server for cloud computing processing, automatically alarming and optimizing according to meteorological department data, establishing a temperature and humidity monitoring system, detecting the temperature and humidity conditions of the construction site in real time by the temperature and humidity monitoring system, confirming the current temperature and humidity conditions of the construction site according to the signal content identified by a read-write device, rapidly alarming when abnormal temperature and humidity occur, prompting a hidden danger area, linking dust raising equipment and spraying equipment such as a fog gun on site, and automatically triggering the fog gun under the condition that the dust raising exceeds the standard occurs on site, Tower crane spraying and enclosure spraying;
when the exceeding times of the noise exceed the specified allowable times within the set time period, the alarm is immediately sent to the monitoring center and the related responsible persons through the mobile phone short messages, a data statistical table is formed and uploaded to the command center, and the supervision unit is enabled to be well documented and can be relied on by the evidence.
Fog gun, tower crane spray, enclose to keep off and spray and be provided with hand switch, but manual closing after the mistake, installation pollution sources on-line monitoring appearance, including particulate matter concentration monitor, meteorological five-parameter monitor, noise monitoring appearance and video surveillance camera machine, carry out automatic on-line monitoring in succession to particulate matter concentration, meteorological parameter, noise and on-the-spot video, adopt wired, wireless, the various monitoring data of 3G mode transmission, the platform layer: the data service cloud platform is based on data of a dust and noise monitoring platform in a construction site, carries out system analysis, provides cross-region, full-time and multi-level data mining and comparison, provides data support for scientific haze treatment, is oriented to client systems of different environmental protection bureaus and project sites, realizes Web-based pollution source real-time data online monitoring, site image and video monitoring, pollution source overproof alarm and various management and statistical analysis oriented to different management layers, supports seamless butt joint with a construction and commission smart site system, ensures interconnection and intercommunication of data, is installed and deployed at a construction entrance and exit, and can be set according to site practice.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (7)

1. A dust-settling and noise-preventing green construction process for a viaduct comprises the following steps:
s1: establishing a noise monitoring system, monitoring noise decibel values around a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, and automatically alarming and optimizing according to relevant department data;
s2: establishing a dust monitoring system, monitoring dust concentration at the periphery of a construction site by arranging an outdoor dust monitoring device, transmitting all concentration values to a cloud server for cloud computing processing, and automatically alarming and optimizing according to the data of meteorological departments;
s3: a temperature and humidity monitoring system is established, the temperature and humidity condition of the construction site can be detected in real time by the temperature and humidity monitoring system, the current temperature and humidity situation of the construction site is confirmed according to the signal content identified by the reading and writing equipment, and when the temperature and humidity are abnormal, the system can rapidly give an alarm and prompt a hidden danger area;
s4: the dust raising equipment and the spray equipment such as the fog gun can be linked on site, and the fog gun, the tower crane and the enclosure are automatically triggered to spray under the condition that the raised dust exceeds the standard on site.
2. The viaduct dust-settling noise-preventing green construction process according to claim 1, characterized in that: when the exceeding times of the noise exceed the specified allowable times within the set time period, the alarm is immediately sent to the monitoring center and the related responsible persons through the mobile phone short messages, a data statistical table is formed and uploaded to the command center, and the supervision unit is enabled to be well documented and can be relied on by the evidence.
3. The viaduct dust-settling noise-preventing green construction process according to claim 2, characterized in that: the fog gun and the tower crane spray and the enclosure spray are provided with manual switches, and can be manually closed after a mistake.
4. The viaduct dust-settling noise-preventing green construction process according to claim 3, characterized in that: and (3) installing a pollution source on-line monitor, wherein the pollution source on-line monitor comprises a particulate matter concentration monitor, a meteorological five-parameter monitor, a noise monitor and a video monitoring camera, and continuously and automatically monitoring the particulate matter concentration, meteorological parameters, noise and on-site video on line.
5. The viaduct dust-settling noise-preventing green construction process according to claim 4, characterized in that: adopt wired, wireless, various monitoring data of 3G mode transmission, the platform layer: the data service cloud platform relies on data of a dust emission and noise monitoring platform in a construction site to carry out system analysis and provide cross-regional, full-time and multi-level data mining and comparison, and provides data support for scientific haze treatment.
6. The viaduct dust-settling noise-preventing green construction process according to claim 5, characterized in that: the system is oriented to client systems of different environmental protection bureaus and project construction sites, realizes Web-based pollution source real-time data online monitoring, site image and video monitoring, pollution source standard exceeding alarm, and various management and statistical analysis oriented to different management layers, supports seamless butt joint with a construction and commission intelligent construction site system, and ensures interconnection and intercommunication of data.
7. The viaduct dust-settling noise-preventing green construction process according to claim 6, characterized in that: the monitoring system is installed and deployed at the construction entrance and exit, and can be set according to the actual field.
CN202010408899.6A 2020-05-14 2020-05-14 Dust-settling and noise-preventing green construction process for viaduct Pending CN113668386A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010408899.6A CN113668386A (en) 2020-05-14 2020-05-14 Dust-settling and noise-preventing green construction process for viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010408899.6A CN113668386A (en) 2020-05-14 2020-05-14 Dust-settling and noise-preventing green construction process for viaduct

Publications (1)

Publication Number Publication Date
CN113668386A true CN113668386A (en) 2021-11-19

Family

ID=78537352

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010408899.6A Pending CN113668386A (en) 2020-05-14 2020-05-14 Dust-settling and noise-preventing green construction process for viaduct

Country Status (1)

Country Link
CN (1) CN113668386A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116933984A (en) * 2023-09-19 2023-10-24 珠海乐创通信技术有限公司 Management method and system based on intelligent building site cloud platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116933984A (en) * 2023-09-19 2023-10-24 珠海乐创通信技术有限公司 Management method and system based on intelligent building site cloud platform
CN116933984B (en) * 2023-09-19 2023-12-01 珠海乐创通信技术有限公司 Management method and system based on intelligent building site cloud platform

Similar Documents

Publication Publication Date Title
CN207301750U (en) Power grid construction intelligence control platform system
CN106707939B (en) A kind of substation equipment maintenance and repair site intelligent control device
CN101634852B (en) Fire linking control system applied to urban rail transit and method
CN211908986U (en) Intelligent operation and maintenance early warning management platform for high-speed electromechanical system
CN103376783B (en) A kind of supervisory system
CN106296045B (en) Safety management control device and method for power grid foreign matter laser cleaning equipment
CN201527696U (en) Fire hazard linkage control system applied to urban rail transit
CN110689689A (en) Online wisdom supervisory systems of social unit fire control room
CN112288984A (en) Three-dimensional visual unattended substation intelligent linkage system based on video fusion
CN104329120A (en) Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN104269936A (en) Comprehensive monitoring method and system
CN113298444A (en) Private cloud-based intelligent power safety control platform
CN104699057A (en) Intelligent control system for substation facilities
CN112072798A (en) Fire-fighting auxiliary control integrated monitoring system and monitoring method for intelligent substation
CN106157564A (en) A kind of method of vcehicular tunnel anomalous event emergency processing
CN113668386A (en) Dust-settling and noise-preventing green construction process for viaduct
CN114705959A (en) Power cable and channel on-line monitoring system
CN115757902A (en) Three-dimensional visual management and control system and method for ultralow atmospheric emission of iron and steel enterprises
CN116052350A (en) Fire disaster early warning and rescue system and method based on road-asking guiding navigation mode
CN106428129A (en) Railway crossing barrier remote control system and method
CN112994230A (en) Environment monitoring system for intelligent substation auxiliary system and use method thereof
CN113765218A (en) GIS (geographic information System) and BIM (building information modeling + building information modeling) -based power distribution overhead line and power facility inspection system
CN211653805U (en) Railway platform intrusion alarm system
CN102611193B (en) The interaction control method of power system, Apparatus and system
CN210743124U (en) Online wisdom supervisory systems of social unit fire control room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20211119