CN113668386A - Dust-settling and noise-preventing green construction process for viaduct - Google Patents
Dust-settling and noise-preventing green construction process for viaduct Download PDFInfo
- Publication number
- CN113668386A CN113668386A CN202010408899.6A CN202010408899A CN113668386A CN 113668386 A CN113668386 A CN 113668386A CN 202010408899 A CN202010408899 A CN 202010408899A CN 113668386 A CN113668386 A CN 113668386A
- Authority
- CN
- China
- Prior art keywords
- dust
- noise
- monitoring
- site
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 52
- 238000000034 method Methods 0.000 title claims abstract description 19
- 230000008569 process Effects 0.000 title claims abstract description 17
- 238000012544 monitoring process Methods 0.000 claims abstract description 50
- 239000000428 dust Substances 0.000 claims abstract description 32
- 239000007921 spray Substances 0.000 claims abstract description 11
- 238000012806 monitoring device Methods 0.000 claims abstract description 8
- 239000013618 particulate matter Substances 0.000 claims description 6
- 230000002159 abnormal effect Effects 0.000 claims description 3
- 230000005540 biological transmission Effects 0.000 claims description 3
- 238000007418 data mining Methods 0.000 claims description 3
- 230000007613 environmental effect Effects 0.000 claims description 3
- 210000001503 joint Anatomy 0.000 claims description 3
- 238000007619 statistical method Methods 0.000 claims description 3
- 230000001960 triggered effect Effects 0.000 claims description 2
- 238000005507 spraying Methods 0.000 abstract description 8
- 230000000694 effects Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01D—MEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
- G01D21/00—Measuring or testing not otherwise provided for
- G01D21/02—Measuring two or more variables by means not covered by a single other subclass
Abstract
The invention discloses a dust-falling and noise-preventing green construction process for viaducts, which comprises the steps of establishing a noise monitoring system, monitoring noise decibel values at the periphery of a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, automatically alarming and optimizing according to relevant department data, establishing a dust monitoring system, monitoring dust concentration at the periphery of the construction site by arranging the outdoor dust monitoring device, transmitting all concentration values to the cloud server for cloud computing processing, linking a dust raising device with spraying equipment such as a fog gun on site, and automatically triggering the fog gun, a spraying tower crane and a surrounding shield spraying when the dust raising exceeds the standard on site. According to the invention, a noise monitoring system, a dust monitoring system and a temperature and humidity monitoring system are established, and meanwhile, dust raising equipment and spray equipment such as a fog gun can be linked on site, so that control can be well carried out in the construction process, and the noise and dust during construction are reduced to the minimum.
Description
Technical Field
The invention relates to the field of viaduct construction, in particular to a dust-settling and noise-preventing green construction process for a viaduct.
Background
The urban railway viaduct is an important part in urban construction, various problems can be generated in construction, meanwhile, urban railways are commuting railways and suburban railways, and refer to a passenger transport rail transit system in a metropolitan area range, which serves cities and suburbs, a central city and a satellite city and key cities and towns, a large amount of dust and noise can be generated in the construction of the urban railways, the improvement of a construction process can be timely performed, huge damage can be brought to the environment, in the existing construction process, the control part of the noise and the dust is very poor, the environment is damaged when construction is performed, and the repair cannot be well performed.
Disclosure of Invention
The invention aims to provide a dust-settling and noise-preventing green construction process for an viaduct, which aims to solve the problems in the background art.
In order to achieve the purpose, the invention provides the following technical scheme: a dust-settling and noise-preventing green construction process for a viaduct comprises the following steps:
s1: establishing a noise monitoring system, monitoring noise decibel values around a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, and automatically alarming and optimizing according to relevant department data;
s2: establishing a dust monitoring system, monitoring dust concentration at the periphery of a construction site by arranging an outdoor dust monitoring device, transmitting all concentration values to a cloud server for cloud computing processing, and automatically alarming and optimizing according to the data of meteorological departments;
s3: a temperature and humidity monitoring system is established, the temperature and humidity condition of the construction site can be detected in real time by the temperature and humidity monitoring system, the current temperature and humidity situation of the construction site is confirmed according to the signal content identified by the reading and writing equipment, and when the temperature and humidity are abnormal, the system can rapidly give an alarm and prompt a hidden danger area;
s4: the dust raising equipment and the spray equipment such as the fog gun can be linked on site, and the fog gun, the tower crane and the enclosure are automatically triggered to spray under the condition that the raised dust exceeds the standard on site.
Preferably, when the exceeding times of the noise in a set time period exceed the specified allowable times, the alarm is given to the monitoring center and the related responsible persons through the mobile phone short messages immediately, a data statistical table is formed and uploaded to the command center, and a supervision unit is enabled to be well documented and can rely on the evidence.
Preferably, the fog gun and the tower crane spray and the enclosure spray are provided with manual switches, and the fog gun and the tower crane can be manually closed after a mistake.
Preferably, a pollution source on-line monitor is installed, and the pollution source on-line monitor comprises a particulate matter concentration monitor, a meteorological five-parameter monitor, a noise monitor and a video monitoring camera, and is used for continuously and automatically monitoring the particulate matter concentration, meteorological parameters, noise and on-site video on line.
Preferably, adopt wired, wireless, various monitoring data of 3G mode transmission, the platform layer: the data service cloud platform relies on data of a dust emission and noise monitoring platform in a construction site to carry out system analysis and provide cross-regional, full-time and multi-level data mining and comparison, and provides data support for scientific haze treatment.
Preferably, the system is oriented to client systems of different environmental protection bureaus and project construction sites, realizes Web-based pollution source real-time data online monitoring, site image and video monitoring, pollution source overproof alarm and various management and statistical analysis oriented to different management layers, supports seamless butt joint with a construction and commission intelligent construction site system, and ensures data interconnection and intercommunication.
Preferably, the monitoring system is installed and deployed at the construction entrance and exit, and can be set according to actual field.
The invention has the technical effects and advantages that: establish noise monitoring system, establish dust monitoring system, establish humiture monitoring system, the scene can be linked with spraying equipment such as raise dust equipment and fog gun simultaneously, monitors through a plurality of systems, uses spraying equipment such as raise dust equipment and fog gun to link simultaneously, can in time carry out the management and control when monitoring unusually, at the in-process that carries out the construction, can be fine carry out the management and control for noise and dust during the construction fall to minimumly.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a dust-settling and noise-preventing green construction process for a viaduct, which comprises the following steps:
the method comprises the steps of establishing a noise monitoring system, monitoring noise decibel values at the periphery of a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, automatically alarming and optimizing according to relevant department data, establishing a dust monitoring system, monitoring dust concentration at the periphery of the construction site by arranging the outdoor dust monitoring device, transmitting all concentration values to the cloud server for cloud computing processing, automatically alarming and optimizing according to meteorological department data, establishing a temperature and humidity monitoring system, detecting the temperature and humidity conditions of the construction site in real time by the temperature and humidity monitoring system, confirming the current temperature and humidity conditions of the construction site according to the signal content identified by a read-write device, rapidly alarming when abnormal temperature and humidity occur, prompting a hidden danger area, linking dust raising equipment and spraying equipment such as a fog gun on site, and automatically triggering the fog gun under the condition that the dust raising exceeds the standard occurs on site, Tower crane spraying and enclosure spraying;
when the exceeding times of the noise exceed the specified allowable times within the set time period, the alarm is immediately sent to the monitoring center and the related responsible persons through the mobile phone short messages, a data statistical table is formed and uploaded to the command center, and the supervision unit is enabled to be well documented and can be relied on by the evidence.
Fog gun, tower crane spray, enclose to keep off and spray and be provided with hand switch, but manual closing after the mistake, installation pollution sources on-line monitoring appearance, including particulate matter concentration monitor, meteorological five-parameter monitor, noise monitoring appearance and video surveillance camera machine, carry out automatic on-line monitoring in succession to particulate matter concentration, meteorological parameter, noise and on-the-spot video, adopt wired, wireless, the various monitoring data of 3G mode transmission, the platform layer: the data service cloud platform is based on data of a dust and noise monitoring platform in a construction site, carries out system analysis, provides cross-region, full-time and multi-level data mining and comparison, provides data support for scientific haze treatment, is oriented to client systems of different environmental protection bureaus and project sites, realizes Web-based pollution source real-time data online monitoring, site image and video monitoring, pollution source overproof alarm and various management and statistical analysis oriented to different management layers, supports seamless butt joint with a construction and commission smart site system, ensures interconnection and intercommunication of data, is installed and deployed at a construction entrance and exit, and can be set according to site practice.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.
Claims (7)
1. A dust-settling and noise-preventing green construction process for a viaduct comprises the following steps:
s1: establishing a noise monitoring system, monitoring noise decibel values around a construction site by arranging an outdoor noise monitoring device, transmitting all data to a cloud server for cloud computing processing, and automatically alarming and optimizing according to relevant department data;
s2: establishing a dust monitoring system, monitoring dust concentration at the periphery of a construction site by arranging an outdoor dust monitoring device, transmitting all concentration values to a cloud server for cloud computing processing, and automatically alarming and optimizing according to the data of meteorological departments;
s3: a temperature and humidity monitoring system is established, the temperature and humidity condition of the construction site can be detected in real time by the temperature and humidity monitoring system, the current temperature and humidity situation of the construction site is confirmed according to the signal content identified by the reading and writing equipment, and when the temperature and humidity are abnormal, the system can rapidly give an alarm and prompt a hidden danger area;
s4: the dust raising equipment and the spray equipment such as the fog gun can be linked on site, and the fog gun, the tower crane and the enclosure are automatically triggered to spray under the condition that the raised dust exceeds the standard on site.
2. The viaduct dust-settling noise-preventing green construction process according to claim 1, characterized in that: when the exceeding times of the noise exceed the specified allowable times within the set time period, the alarm is immediately sent to the monitoring center and the related responsible persons through the mobile phone short messages, a data statistical table is formed and uploaded to the command center, and the supervision unit is enabled to be well documented and can be relied on by the evidence.
3. The viaduct dust-settling noise-preventing green construction process according to claim 2, characterized in that: the fog gun and the tower crane spray and the enclosure spray are provided with manual switches, and can be manually closed after a mistake.
4. The viaduct dust-settling noise-preventing green construction process according to claim 3, characterized in that: and (3) installing a pollution source on-line monitor, wherein the pollution source on-line monitor comprises a particulate matter concentration monitor, a meteorological five-parameter monitor, a noise monitor and a video monitoring camera, and continuously and automatically monitoring the particulate matter concentration, meteorological parameters, noise and on-site video on line.
5. The viaduct dust-settling noise-preventing green construction process according to claim 4, characterized in that: adopt wired, wireless, various monitoring data of 3G mode transmission, the platform layer: the data service cloud platform relies on data of a dust emission and noise monitoring platform in a construction site to carry out system analysis and provide cross-regional, full-time and multi-level data mining and comparison, and provides data support for scientific haze treatment.
6. The viaduct dust-settling noise-preventing green construction process according to claim 5, characterized in that: the system is oriented to client systems of different environmental protection bureaus and project construction sites, realizes Web-based pollution source real-time data online monitoring, site image and video monitoring, pollution source standard exceeding alarm, and various management and statistical analysis oriented to different management layers, supports seamless butt joint with a construction and commission intelligent construction site system, and ensures interconnection and intercommunication of data.
7. The viaduct dust-settling noise-preventing green construction process according to claim 6, characterized in that: the monitoring system is installed and deployed at the construction entrance and exit, and can be set according to the actual field.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010408899.6A CN113668386A (en) | 2020-05-14 | 2020-05-14 | Dust-settling and noise-preventing green construction process for viaduct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010408899.6A CN113668386A (en) | 2020-05-14 | 2020-05-14 | Dust-settling and noise-preventing green construction process for viaduct |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113668386A true CN113668386A (en) | 2021-11-19 |
Family
ID=78537352
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010408899.6A Pending CN113668386A (en) | 2020-05-14 | 2020-05-14 | Dust-settling and noise-preventing green construction process for viaduct |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113668386A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116933984A (en) * | 2023-09-19 | 2023-10-24 | 珠海乐创通信技术有限公司 | Management method and system based on intelligent building site cloud platform |
-
2020
- 2020-05-14 CN CN202010408899.6A patent/CN113668386A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116933984A (en) * | 2023-09-19 | 2023-10-24 | 珠海乐创通信技术有限公司 | Management method and system based on intelligent building site cloud platform |
CN116933984B (en) * | 2023-09-19 | 2023-12-01 | 珠海乐创通信技术有限公司 | Management method and system based on intelligent building site cloud platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207301750U (en) | Power grid construction intelligence control platform system | |
CN106707939B (en) | A kind of substation equipment maintenance and repair site intelligent control device | |
CN101634852B (en) | Fire linking control system applied to urban rail transit and method | |
CN211908986U (en) | Intelligent operation and maintenance early warning management platform for high-speed electromechanical system | |
CN103376783B (en) | A kind of supervisory system | |
CN106296045B (en) | Safety management control device and method for power grid foreign matter laser cleaning equipment | |
CN201527696U (en) | Fire hazard linkage control system applied to urban rail transit | |
CN110689689A (en) | Online wisdom supervisory systems of social unit fire control room | |
CN112288984A (en) | Three-dimensional visual unattended substation intelligent linkage system based on video fusion | |
CN104329120A (en) | Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method | |
CN104269936A (en) | Comprehensive monitoring method and system | |
CN113298444A (en) | Private cloud-based intelligent power safety control platform | |
CN104699057A (en) | Intelligent control system for substation facilities | |
CN112072798A (en) | Fire-fighting auxiliary control integrated monitoring system and monitoring method for intelligent substation | |
CN106157564A (en) | A kind of method of vcehicular tunnel anomalous event emergency processing | |
CN113668386A (en) | Dust-settling and noise-preventing green construction process for viaduct | |
CN114705959A (en) | Power cable and channel on-line monitoring system | |
CN115757902A (en) | Three-dimensional visual management and control system and method for ultralow atmospheric emission of iron and steel enterprises | |
CN116052350A (en) | Fire disaster early warning and rescue system and method based on road-asking guiding navigation mode | |
CN106428129A (en) | Railway crossing barrier remote control system and method | |
CN112994230A (en) | Environment monitoring system for intelligent substation auxiliary system and use method thereof | |
CN113765218A (en) | GIS (geographic information System) and BIM (building information modeling + building information modeling) -based power distribution overhead line and power facility inspection system | |
CN211653805U (en) | Railway platform intrusion alarm system | |
CN102611193B (en) | The interaction control method of power system, Apparatus and system | |
CN210743124U (en) | Online wisdom supervisory systems of social unit fire control room |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20211119 |