CN113622324A - Reinforcing structure of bridge abutment and construction method thereof - Google Patents
Reinforcing structure of bridge abutment and construction method thereof Download PDFInfo
- Publication number
- CN113622324A CN113622324A CN202111112666.2A CN202111112666A CN113622324A CN 113622324 A CN113622324 A CN 113622324A CN 202111112666 A CN202111112666 A CN 202111112666A CN 113622324 A CN113622324 A CN 113622324A
- Authority
- CN
- China
- Prior art keywords
- bridge
- pier
- abutment
- shoulder pole
- opposite sides
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 24
- 238000010276 construction Methods 0.000 title claims abstract description 15
- 239000002689 soil Substances 0.000 claims abstract description 23
- 230000002787 reinforcement Effects 0.000 claims abstract description 4
- 230000000149 penetrating effect Effects 0.000 claims description 5
- 210000002435 tendon Anatomy 0.000 claims description 2
- 238000000034 method Methods 0.000 abstract description 7
- 239000011150 reinforced concrete Substances 0.000 abstract description 3
- 101100334009 Caenorhabditis elegans rib-2 gene Proteins 0.000 description 6
- 239000004567 concrete Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 210000003205 muscle Anatomy 0.000 description 3
- 230000000087 stabilizing effect Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002513 implantation Methods 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
Abstract
The invention discloses a reinforced structure of bridge abutment and a construction method thereof, wherein the lower part of the abutment is buried in a soil body, a bearing platform supported at the lower part of the abutment is poured in the soil body, and the reinforcement of the bridge abutment comprises the following steps: the two clamping beams are bonded to two opposite sides of the abutment, embedded bars are embedded in the clamping beams, and the embedded bars are embedded in the abutment; the shoulder pole rib penetrates through the pier and two ends of the shoulder pole rib are respectively anchored in the two clamping beams; and a plurality of miniature cast-in-place piles, wherein the miniature cast-in-place piles are poured in the soil body, the upper ends of the miniature cast-in-place piles are supported on the clamping beams, the lower ends of the miniature cast-in-place piles are inserted in the sandstone layer below the soil body, and the miniature cast-in-place piles are arranged at intervals along the length direction of the clamping beams. The method solves the problems of high cost and long time consumption of the traditional method for reinforcing the reinforced concrete abutment of the bridge.
Description
Technical Field
The invention relates to the technical field of bridge construction, in particular to a reinforcing structure of a bridge abutment and a construction method thereof.
Background
For reinforcing the reinforced concrete pier of the bridge, a method of removing and rebuilding or a method of reinforcing a pile foundation is generally adopted. The method for breaking the re-construction is high in cost, long in time consumption and uneconomical; for the reinforcement method of the supplement pile foundation, the original foundation bearing platform needs to be enlarged, the connection construction difficulty of the new bearing platform and the old bearing platform is higher, and certain requirements are provided for surrounding fields.
Disclosure of Invention
In order to overcome the defects in the prior art, the reinforcing structure of the bridge abutment and the construction method thereof are provided, so that the problems of high cost and long consumed time of the traditional reinforcing method of the reinforced concrete abutment of the bridge are solved.
In order to realize above-mentioned purpose, provide a reinforced structure of bridge pier, the lower part of pier is buried underground in the soil body, pour in the soil body support in the cushion cap of the lower part of pier, the reinforcement of bridge pier includes:
the two clamping beams are bonded to two opposite sides of the abutment, embedded bars are embedded in the clamping beams, and the embedded bars are embedded in the abutment;
the shoulder pole rib penetrates through the pier and two ends of the shoulder pole rib are respectively anchored in the two clamping beams; and
the soil body is provided with a plurality of miniature filling piles, the miniature filling piles are poured in the soil body, the upper ends of the miniature filling piles are supported on the clamping beams, the lower ends of the miniature filling piles are inserted in the sandstone layer below the soil body, and the miniature filling piles are arranged at intervals along the length direction of the clamping beams.
Further, the miniature cast-in-place pile penetrates through the bearing platform.
Further, the clamping beam is arranged along the width direction of the bridge.
Furthermore, the quantity of carrying pole muscle is many, the carrying pole muscle is followed the length direction of bridge sets up, many the carrying pole muscle is followed the length direction interval of centre gripping roof beam sets up.
Furthermore, two layers of carrying pole ribs penetrate through the pier, the upper layer of carrying pole ribs are anchored in the upper part of the clamping beam, and the lower layer of carrying pole ribs are anchored in the lower part of the clamping beam.
Furthermore, the end reinforcing bar bundles of the miniature filling pile extend into the clamping beam in a trumpet shape.
Furthermore, the outer diameter of the micro cast-in-place pile is 150 mm-300 mm.
The invention provides a construction method of a reinforced structure of a bridge abutment, which comprises the following steps:
respectively pouring a plurality of micro filling piles in soil bodies on two opposite sides of a pier of the bridge, so that the lower ends of the micro filling piles are inserted into a sandstone layer below the soil body, and the plurality of micro filling piles are arranged at intervals along the width direction of the bridge;
the shoulder pole rib is arranged in the pier in a penetrating mode, so that two ends of the shoulder pole rib respectively extend to the outer portions of two opposite sides of the pier;
implanting embedded bars in opposite sides of the abutment so that the embedded bars extend to the outside of the opposite sides of the abutment;
chiseling the side walls on the two opposite sides of the pier and pouring clamping beams on the outer sides of the side walls on the two opposite sides of the pier along the width direction of the bridge, so that the two clamping beams are bonded on the side walls on the two opposite sides of the pier, and the upper end of the miniature cast-in-place pile, the embedded bars and the shoulder pole bars are embedded in the clamping beams.
The reinforcing structure of the bridge abutment has the advantages that the reinforcing structure of the bridge abutment has the effect of stabilizing the abutment and preventing continuous settlement by adopting the combination of the micro cast-in-place piles and the shoulder pole ribs penetrating through the abutment on the two sides of the abutment, is particularly suitable for the conditions that concrete structures such as piers, abutments, culverts and the like have large settlement and have large requirements on construction period and cost control, not only ensures that original concrete structures are not damaged and requirements on the construction period are met, but also ensures that the abutment of a bridge to be reinforced is reinforced to achieve the expected reinforcing effect.
Drawings
Other features, objects and advantages of the present application will become more apparent upon reading of the following detailed description of non-limiting embodiments thereof, made with reference to the accompanying drawings in which:
fig. 1 is a schematic structural view of a bridge to be reinforced.
Fig. 2 is a schematic structural view of a reinforcing structure of a bridge abutment according to an embodiment of the present invention.
Fig. 3 is a cross-sectional view of a clamping beam of an embodiment of the invention.
Fig. 4 is a top view of a clamping beam of an embodiment of the present invention.
Detailed Description
The present application will be described in further detail with reference to the following drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the relevant invention and not restrictive of the invention. It should be noted that, for convenience of description, only the portions related to the present invention are shown in the drawings.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 1, in the present embodiment, a bridge 4 to be reinforced spans over a river 8, and two ends of the bridge 4 are erected on two banks of the river through abutments 6. The bearing platforms 5 are poured in soil bodies on two sides of the river channel, and the bearing platforms 5 are supported at the bottoms of the abutments 6.
Referring again to fig. 2 to 4, the present invention provides a reinforcing structure of a bridge abutment, including: two clamping beams 1, a shoulder pole rib 2 and a plurality of miniature cast-in-place piles 3.
Wherein the two clamping beams 1 are bonded to opposite sides of the abutment 6. The clamping beam 1 is embedded with embedded bars 11. The planting bars 11 are planted in the abutment 6.
The shoulder pole rib 2 penetrates through the pier 6, and two ends of the shoulder pole rib 2 are respectively anchored in the two clamping beams 1.
And a plurality of micro cast-in-place piles 3 are poured in the soil body. The upper end of the micro cast-in-place pile 3 is supported on the clamping beam 1. The lower end of the micro filling pile 3 is inserted into the sandstone layer 7 below the soil body. A plurality of micro cast-in-place piles 3 are arranged at intervals along the length direction of the clamping beam 1.
According to the reinforcing structure of the bridge abutment, the micro cast-in-place piles and the shoulder pole ribs penetrating through the abutment are combined to support and reinforce the abutment on two sides of the abutment, so that the effect of stabilizing the abutment and preventing continuous settlement is achieved, the reinforcing structure is particularly suitable for the situation that concrete structures such as piers, abutments, culverts and the like are greatly settled and construction period and cost control have large requirements, the original concrete structure is not damaged, the requirement of the construction period is met, and the abutment of a bridge to be reinforced is reinforced to achieve the expected reinforcing effect.
In this embodiment, the outer diameter of the bearing platform is larger than that of the abutment, and the micro cast-in-place pile 3 penetrates through the bearing platform 5.
As a preferred embodiment, the clamp beam 1 is arranged along the width direction of the bridge beam 4.
In the present embodiment, the number of the shoulder pole ribs 2 is plural. The shoulder pole ribs 2 are arranged along the length direction of the bridge 4. A plurality of shoulder pole ribs 2 are arranged at intervals along the length direction of the clamping beam 1.
Two layers of shoulder pole ribs 2 penetrate through the pier 6. Wherein, the upper-layer shoulder pole rib 2 is anchored in the upper part of the clamping beam 1; the lower-layer shoulder pole rib 2 is anchored in the lower part of the clamping beam 1.
In this embodiment, the diameter of the shoulder pole rib 2 is greater than 32mm, and the upper and lower two-layer is along the bridge to running through the abutment, and the horizontal bridge is less than 40cm to the interval, plays the shoulder pole effect, supports the abutment, prevents that the abutment from continuing to subside.
The diameter of the implanted bar 11 is larger than 32mm, the implantation depth is larger than 30cm, and the distance in the transverse bridge direction is smaller than 50 cm.
In this embodiment, the end tendons of micro-cast-in-place piles 3 extend in a trumpet shape into the clamping beam 1. The outer diameter of the micro cast-in-place pile 3 is 150 mm-300 mm.
The invention provides a construction method of a reinforced structure of a bridge abutment, which comprises the following steps:
s1: a plurality of micro cast-in-place piles 3 are respectively poured in soil bodies on two opposite sides of a pier 6 of the bridge 4, so that the lower ends of the micro cast-in-place piles 3 are inserted into a sandstone layer 7 below the soil bodies, and the micro cast-in-place piles 3 are arranged at intervals in the width direction of the bridge 4.
S2: the shoulder pole 2 is arranged in the pier 6 in a penetrating mode, so that two ends of the shoulder pole 2 respectively extend to the outer portions of two opposite sides of the pier 6.
S3: the planted bars 11 are implanted in opposite sides of the abutment 6 such that the planted bars 11 extend to the outside of the opposite sides of the abutment 6.
S4: chiseling the side walls on the two opposite sides of the pier 6 and pouring the clamping beams 1 on the outer sides of the side walls on the two opposite sides of the pier 6 along the width direction of the bridge 4, so that the two clamping beams 1 are bonded on the side walls on the two opposite sides of the pier 6, and the upper end of the miniature cast-in-place pile 3, the embedded bars 11 and the carrying pole bars 2 are embedded in the clamping beams 1.
The above description is only a preferred embodiment of the application and is illustrative of the principles of the technology employed. It will be appreciated by a person skilled in the art that the scope of the invention as referred to in the present application is not limited to the embodiments with a specific combination of the above-mentioned features, but also covers other embodiments with any combination of the above-mentioned features or their equivalents without departing from the inventive concept. For example, the above features may be replaced with (but not limited to) features having similar functions disclosed in the present application.
Claims (8)
1. The utility model provides a reinforced structure of bridge pier, its characterized in that, the lower part of pier is buried underground in the soil body, pour in the soil body support in the cushion cap of the lower part of pier, the reinforcement of bridge pier includes:
the two clamping beams are bonded to two opposite sides of the abutment, embedded bars are embedded in the clamping beams, and the embedded bars are embedded in the abutment;
the shoulder pole rib penetrates through the pier and two ends of the shoulder pole rib are respectively anchored in the two clamping beams; and
the soil body is provided with a plurality of miniature filling piles, the miniature filling piles are poured in the soil body, the upper ends of the miniature filling piles are supported on the clamping beams, the lower ends of the miniature filling piles are inserted in the sandstone layer below the soil body, and the miniature filling piles are arranged at intervals along the length direction of the clamping beams.
2. The reinforcing structure of bridge abutment according to claim 1, wherein said micro cast-in-place pile penetrates said bearing platform.
3. The reinforcing structure of a bridge abutment according to claim 1, wherein the clamping beam is provided in a width direction of the bridge.
4. The reinforcing structure of a bridge pier of claim 3, wherein the number of the shoulder pole ribs is plural, the shoulder pole ribs are arranged along a length direction of the bridge, and the plural shoulder pole ribs are arranged at intervals along the length direction of the clamping beam.
5. The reinforcing structure of a bridge pier of claim 4, wherein two layers of the shoulder pole ribs penetrate through the pier, the upper layer of the shoulder pole ribs are anchored in the upper part of the clamping beam, and the lower layer of the shoulder pole ribs are anchored in the lower part of the clamping beam.
6. The reinforcing structure of bridge abutment according to claim 1, wherein the head tendons of the micro cast-in-place piles extend in a trumpet shape into the clamping beams.
7. The reinforcing structure of a bridge abutment according to claim 6, wherein the micro cast-in-place pile has an outer diameter of 150mm to 300 mm.
8. A construction method of the reinforcing structure of bridge abutments according to any one of claims 1 to 7, characterized by comprising the steps of:
respectively pouring a plurality of micro filling piles in soil bodies on two opposite sides of a pier of the bridge, so that the lower ends of the micro filling piles are inserted into a sandstone layer below the soil body, and the plurality of micro filling piles are arranged at intervals along the width direction of the bridge;
the shoulder pole rib is arranged in the pier in a penetrating mode, so that two ends of the shoulder pole rib respectively extend to the outer portions of two opposite sides of the pier;
implanting embedded bars in opposite sides of the abutment so that the embedded bars extend to the outside of the opposite sides of the abutment;
chiseling the side walls on the two opposite sides of the pier and pouring clamping beams on the outer sides of the side walls on the two opposite sides of the pier along the width direction of the bridge, so that the two clamping beams are bonded on the side walls on the two opposite sides of the pier, and the upper end of the miniature cast-in-place pile, the embedded bars and the shoulder pole bars are embedded in the clamping beams.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111112666.2A CN113622324A (en) | 2021-09-23 | 2021-09-23 | Reinforcing structure of bridge abutment and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111112666.2A CN113622324A (en) | 2021-09-23 | 2021-09-23 | Reinforcing structure of bridge abutment and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113622324A true CN113622324A (en) | 2021-11-09 |
Family
ID=78390527
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111112666.2A Pending CN113622324A (en) | 2021-09-23 | 2021-09-23 | Reinforcing structure of bridge abutment and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113622324A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101565931A (en) * | 2009-05-27 | 2009-10-28 | 重庆市勘测院 | Cast in-situ piling pile reinforcement bridge pier structure and construction method |
CN203701129U (en) * | 2013-11-11 | 2014-07-09 | 江西省交通设计研究院有限责任公司 | Bridge reinforcement foundation and bridge |
KR101440392B1 (en) * | 2013-12-31 | 2014-09-17 | 권은태 | Bridge structure and construction method thereof |
KR101751724B1 (en) * | 2016-08-31 | 2017-06-29 | (주)한맥기술 | Concrete structure constructed integral abutment bridge having shallow height psc i girder due to moment redistribution through control of member stiffness |
CN107100093A (en) * | 2017-05-22 | 2017-08-29 | 胥悦微 | A kind of cast in-situ piling pile reinforcement bridge pier structure and building method |
CN108755453A (en) * | 2018-06-06 | 2018-11-06 | 石家庄铁道大学 | A kind of water punching is damaged the composite reinforcement structure and its reinforcement means of bridge pier |
CN110820819A (en) * | 2019-10-31 | 2020-02-21 | 山西省交通建设工程质量检测中心(有限公司) | Method for adding pile on existing bridge pile foundation |
-
2021
- 2021-09-23 CN CN202111112666.2A patent/CN113622324A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101565931A (en) * | 2009-05-27 | 2009-10-28 | 重庆市勘测院 | Cast in-situ piling pile reinforcement bridge pier structure and construction method |
CN203701129U (en) * | 2013-11-11 | 2014-07-09 | 江西省交通设计研究院有限责任公司 | Bridge reinforcement foundation and bridge |
KR101440392B1 (en) * | 2013-12-31 | 2014-09-17 | 권은태 | Bridge structure and construction method thereof |
KR101751724B1 (en) * | 2016-08-31 | 2017-06-29 | (주)한맥기술 | Concrete structure constructed integral abutment bridge having shallow height psc i girder due to moment redistribution through control of member stiffness |
CN107100093A (en) * | 2017-05-22 | 2017-08-29 | 胥悦微 | A kind of cast in-situ piling pile reinforcement bridge pier structure and building method |
CN108755453A (en) * | 2018-06-06 | 2018-11-06 | 石家庄铁道大学 | A kind of water punching is damaged the composite reinforcement structure and its reinforcement means of bridge pier |
CN110820819A (en) * | 2019-10-31 | 2020-02-21 | 山西省交通建设工程质量检测中心(有限公司) | Method for adding pile on existing bridge pile foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107142856B (en) | Abutment reconstruction method, abutment reconstruction pier and jacking reconstruction bridge | |
JP2003519307A (en) | Prestressed module retaining wall system and method | |
CN107386310B (en) | Building supporting structure applied to hillside topography and construction method thereof | |
CN102966119A (en) | Geogrid reinforced wall and construction method thereof | |
CN107059882A (en) | Arch anchor net and Anchor-Pile Retaining Structure structure | |
CN103452120B (en) | A kind of stake apical cap girder construction of the high-strength Prestressed Pipe Pile for pattern foundation pit supporting structure and construction method thereof | |
CN110055906A (en) | The Reinforcement of existing bridge when high-speed rail bridge is worn under shield | |
CN108316309A (en) | The double-row pile composite construction and its construction method of deep basal pit supporting and retaining system | |
CN111305219A (en) | Existing tunnel crossing system based on foundation pit jumping excavation and arch cover conversion and construction method | |
CN106702840A (en) | Anchored pile reinforced earth retaining wall embankment for treating shoreside soft soil roadbed | |
CN111749288B (en) | Load-reducing heightening structure of existing retaining wall and construction method thereof | |
CN101718098B (en) | Micro-pile combined dug composite foundation and construction method thereof | |
CN106758890B (en) | Campshed box culvert structure and its construction method | |
CN111395354A (en) | Multi-stage large-row-spacing pile combined supporting structure and foundation pit excavation method thereof | |
CN206941425U (en) | The bridge of abutment, the bridge pier of abutment transformation and lifting reconstruction | |
CN206157594U (en) | Campshed box culvert structure | |
CN218622201U (en) | Hidden reinforced structure system of existing friction pile | |
CN113622324A (en) | Reinforcing structure of bridge abutment and construction method thereof | |
CN111851532A (en) | Improved expansive soil high and steep slope structure | |
CN111236278A (en) | Slope soft land foundation pile-cable reinforcing structure, reinforcing system and construction method | |
CN114032932B (en) | Construction method of hybrid retaining structure | |
CN212026286U (en) | Retaining structure of anti-slide pile and structural pile | |
CN208717919U (en) | A kind of road based on contrary sequence method changes bridge section foundation pit supporting construction | |
CN208309592U (en) | Foundation pit supporting structure | |
CN1043482C (en) | Retaining wall structure and method for constructing same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20211109 |