CN113605901A - Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction - Google Patents

Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction Download PDF

Info

Publication number
CN113605901A
CN113605901A CN202110819280.9A CN202110819280A CN113605901A CN 113605901 A CN113605901 A CN 113605901A CN 202110819280 A CN202110819280 A CN 202110819280A CN 113605901 A CN113605901 A CN 113605901A
Authority
CN
China
Prior art keywords
tunnel
construction
top layer
pilot tunnel
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110819280.9A
Other languages
Chinese (zh)
Inventor
王立川
龚伦
章慧健
郑余朝
王文
于宏伟
钟建
吕琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN202110819280.9A priority Critical patent/CN113605901A/en
Publication of CN113605901A publication Critical patent/CN113605901A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/006Lining anchored in the rock
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction method of a guide tunnel in a strong anchor based on the construction of a tunnel with an extra-large section, and belongs to the technical field of tunnel engineering construction. A strong anchor middle pilot tunnel construction method based on super-large section tunnel construction achieves the effect of reducing span points in mechanics by preferentially excavating a top layer middle pilot tunnel and applying a prestressed long anchor rod on top surrounding rocks, thereby enlarging an excavation working surface, improving working efficiency, facilitating large-scale mechanical construction, avoiding using temporary supports in the construction process of super-large sections and solving the problem that the construction efficiency is influenced by excessive temporary supports during two-side excavation.

Description

Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction
Technical Field
The invention relates to the technical field of tunnel engineering construction, in particular to a construction method of a pilot tunnel in a strong anchor based on extra-large section tunnel construction.
Background
Along with the development of tunnel technology in China, the number of tunnels with extra-large sections is increased sharply, and the V-level surrounding rock excavation section of the tunnel of the passenger special line built or under construction is close to 160m2And the excavation section of the individual built or proposed tunnel exceeds 400m2
The section of the tunnel with the extra-large section is overlarge in the construction process, the traditional excavation modes comprise a double-side-wall pit guiding method, a CD method, a CRD method and other construction methods for realizing the block and span reduction through temporary supports, the construction organization difficulty is high, meanwhile, the construction progress and the blasting efficiency are influenced by a large number of temporary supports, the slag discharging operation space after the block and span reduction is small, the large-scale mechanical construction is not facilitated, and the economic benefit is low. Therefore, the problem that construction efficiency is affected by a large amount of temporary supports during construction of the large-section tunnel exists in the prior art.
Disclosure of Invention
The invention aims to provide a construction method of a pilot tunnel in a strong anchor based on the construction of a tunnel with an extra-large cross section, and the construction method is used for solving the problem that a large number of temporary supports influence the construction efficiency during the construction of the existing tunnel with the extra-large cross section.
The technical scheme for solving the technical problems is as follows:
a construction method of a guide tunnel in a strong anchor based on super-large section tunnel construction comprises the following steps:
s1: determining an excavation line of a tunnel, and determining an excavation line of a pilot tunnel in a top layer in the tunnel excavation line;
s2: excavating along the extending direction of the tunnel in the excavating line of the pilot tunnel in the top layer;
s3: performing top support on the top of the pilot tunnel in the top layer;
s4: excavating the left part of the top layer on the left side and the right part of the top layer on the right side of the pilot tunnel in the top layer;
s5: selecting a reasonable step footage for the middle part of the bottom layer, closely following the step of the pilot tunnel in the top layer according to the step footage, and excavating the middle part of the bottom layer;
s6: selecting reasonable step footings for the left part of the bottom layer on the left side of the middle part of the bottom layer and the right part of the bottom layer on the right side of the middle part of the bottom layer, respectively following the steps on the left part of the top layer and the right part of the top layer according to the step footings, and respectively excavating the left part of the bottom layer and the right part of the bottom layer;
s7: and finally, excavating and using a template trolley to construct a lining.
According to the invention, through preferentially excavating the pilot tunnel in the top layer and constructing the top support on the surrounding rock at the top part, the effect of reducing the span point in mechanics is achieved, so that the excavation working surface is enlarged, the working efficiency is improved, the construction of large machinery is facilitated, the temporary support is not required to be used in the construction process of the super-large section, and the problem that the construction efficiency is influenced by excessive temporary support during two-side excavation is solved.
Further, when the top layer left part, the top layer right part, the bottom layer left part and the bottom layer right part are excavated, a plurality of working faces are adopted to excavate towards the two ends of the tunnel simultaneously.
The invention adopts a method of simultaneously excavating a plurality of working faces in the excavation process, thereby greatly improving the excavation working efficiency of the tunnel.
Further, in step S2, a net-jet support is applied to both sides of the pilot hole in the top floor.
If surrounding rocks on two sides are poor in the process of excavating the pilot tunnel in the top layer, the net-jet support can be adopted to play a role in sealing, and therefore the straight walls on two sides are prevented from falling off.
Furthermore, a steel wire mesh with the diameter of 3-4mm is adopted for the net-spraying support, and the net-spraying support is directly dug when two sides of the pilot tunnel in the top layer are dug.
When the method is used for excavating the two sides of the pilot tunnel in the top layer, the net-jet support with the steel wire net structure can be conveniently and directly excavated, so that the excavating efficiency is improved.
Furthermore, the middle of the bottom layer is excavated by the steps of firstly drawing the groove and then excavating.
When the middle part of the bottom layer is excavated, the groove is firstly pulled to create an unearthed sidewalk, so that the slag discharging efficiency can be improved.
Further, in step S3, the roof support includes: the construction method comprises the following steps of firstly spraying concrete, erecting a steel frame, embedding a prestressed long anchor rod, erecting a reinforcing mesh and spraying concrete again to the designed thickness. .
The prestressed long anchor rod is conveniently and tightly buried in the top surrounding rock through the primary spraying and secondary spraying of concrete, so that the span reduction effect is improved.
Furthermore, the prestressed long anchor rod is arranged in a shape like a Chinese character jing, and the length of the prestressed long anchor rod is 7-9 m.
The prestressed long anchor rod arranged in a shape like a Chinese character jing has better stability, and the length can be selected in a proper range of 7-9m according to actual requirements, so that the prestressed strength can be ensured, and the strength attenuation caused by overlong length can be avoided. The invention has the following beneficial effects:
(1) according to the construction method, the pilot tunnel in the top layer is excavated preferentially, and the prestressed long anchor rod is applied to the surrounding rock at the top of the pilot tunnel, so that the effect of reducing the span point in mechanics is achieved, the excavation working surface is enlarged, the working efficiency is improved, the construction of large machinery is facilitated, temporary supports are not needed in the construction process of the super-large section, and the problem that the construction efficiency is influenced by excessive temporary supports during two-side excavation is solved.
(2) The method for simultaneously excavating a plurality of working faces is adopted in the excavation process, so that the excavation working efficiency of the tunnel is greatly improved; even if the surrounding rocks on the two sides are poor, the net-spray support can be adopted to play a role in sealing, and the straight walls on the two sides can be directly excavated while the blocks are prevented from falling.
Drawings
FIG. 1 is a schematic diagram of an excavation boundary of a construction end face according to the present invention;
FIG. 2 is a three-dimensional illustration of the excavation process of the present invention;
FIG. 3 is a schematic plan view of the present invention for excavating a pilot hole in a top layer;
FIG. 4 is a schematic longitudinal cross-sectional view of a pilot hole in a top layer being excavated according to the present invention;
FIG. 5 is a schematic plan view of the remaining subsections of the excavation of the present invention;
figure 6 is a schematic longitudinal section of the remaining part of the excavation according to the invention.
In the figure: 10-top layer middle pilot hole; 11-prestressed long anchor rod; 20-top left portion; 30-top right part; 40-bottom layer middle; 50-bottom left; 60-bottom right; 70-working surface.
Detailed Description
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth by way of illustration only and are not intended to limit the scope of the invention.
Examples
Referring to fig. 1 and 2, a construction method of a pilot tunnel in a strong anchor based on super-large section tunnel construction includes the following steps:
s1: determining an excavation line of a tunnel, and determining an excavation line of a pilot tunnel 10 in a top layer in the tunnel excavation line;
s2: excavating along the extending direction of the tunnel in the excavation line of the pilot tunnel 10 in the top layer; the extending direction of the tunnel generally refers to the direction from the small mileage end of the station to the large mileage end of the station. During excavation, whether net-spraying support is needed or not can be determined according to surrounding rock conditions on two sides of a pilot tunnel 10 in a top layer, when the surrounding rock is poor, a steel wire net with the diameter of 3-4mm is adopted for net-spraying support, the effect of sealing the surrounding rock is achieved, the two sides of a straight wall are prevented from falling, convenience is brought to later-stage excavation, and independent removal is not needed.
S3: the top of leading hole 10 in the top layer is executed and is made the top and strut, and the top is strutted and is included: the method comprises the following steps of constructing primary spraying concrete, erecting a steel frame, burying a prestressed long anchor rod 11, erecting a reinforcing mesh and spraying concrete again to the designed thickness. By embedding the long prestressed anchor rods 11, the surrounding rock can be stabilized; the concrete is sprayed primarily before the prestressed long anchor rods 11 are embedded, and the concrete is sprayed to the designed thickness after the prestressed long anchor rods 11 are embedded, so that the prestressed long anchor rods 11 can be embedded in the surrounding rock at the top more tightly, and the span reduction effect is improved. The prestressed long anchor rods 11 are arranged in a shape of a Chinese character jing, and the length selection range is 7-9 m. According to the current research situation of the anchor rod anchoring mechanism, the optimal length of the anchor rod anchoring is 7.5m, and the anchoring effect of the long anchor rod begins to decline when the length exceeds 9 m. Therefore, in the present embodiment, on the premise of ensuring the anchoring effect and the length, the prestressed long anchor rod 11 with the length of 8m is selected, and the prestress of the prestressed long anchor rod can reach 200 kN.
Referring to fig. 3 and 4, S4: excavating a left top layer part 20 at the left side and a right top layer part 30 at the right side of the top layer middle pilot tunnel 10; respectively excavating a top left part 20 and a top right part 30 after surrounding rocks at the top of the pilot tunnel 10 in the top layer are stable, wherein the excavating progress of the top left part 20 and the top right part 30 lags behind the excavating progress of the pilot tunnel 10 in the top layer; when the left part 20 and the right part 30 of the top layer are excavated, the previously constructed net-jet support can be directly excavated, so that the influence on the construction efficiency caused by independently dismantling the net-jet support is avoided.
S5: selecting a reasonable step footage for the middle part 40 of the bottom layer, following the step of the pilot tunnel 10 in the top layer according to the step footage, and excavating the middle part 40 of the bottom layer; when the middle part 40 of the bottom layer is excavated, the excavation progress of the middle part 40 of the bottom layer needs to lag behind the excavation progress of the pilot tunnel 10 in the top layer; during excavation, the middle part 40 of the bottom layer can be subjected to groove drawing to create an unearthed sidewalk, so that the slag discharging efficiency is improved.
S6: selecting reasonable step footings for the left bottom layer part 50 on the left side of the middle part 40 of the bottom layer and the right bottom layer part 60 on the right side of the bottom layer, respectively following the steps of the left top layer part 20 and the right top layer part 30 according to the step footings, and respectively excavating the left bottom layer part 50 and the right bottom layer part 60; when the left bottom part 50 and the right bottom part 60 on the left side and the right side of the middle bottom part 40 are excavated, the excavation progress of the left bottom part 50 needs to lag behind the excavation progress of the left top part 20 and the middle bottom part 40; the excavation progress of the bottom right portion 60 lags behind the excavation progress of the top right portion 30 and the bottom middle portion 40;
referring to fig. 5 and 6, when the top left portion 20, the top right portion 30, the bottom left portion 50 and the bottom right portion 60 are excavated, a plurality of working surfaces 70 are adopted to simultaneously excavate both ends of the tunnel, that is, the plurality of working surfaces 70 are excavated from a direction perpendicular to the extending direction of the tunnel, and the excavation is simultaneously performed to both ends after excavation, so that the excavation efficiency of the tunnel is greatly improved. And when the bottom layer is excavated, reasonable partitioning can be carried out according to surrounding rocks and equipment transportation capacity conditions.
S7: and finally, excavating and using a template trolley to construct a lining.
According to the invention, the function of reducing the span point in mechanics is achieved by preferentially adopting the excavation of the pilot tunnel 10 in the top layer and applying the prestressed long anchor rod 11 on the surrounding rock at the top of the pilot tunnel, so that the excavation working surface 70 is enlarged, the working efficiency is improved, the construction of large machinery is facilitated, the temporary support is not required to be used in the construction process of the super-large section, and the problem that the construction efficiency is influenced by excessive temporary support in the excavation of two sides is solved.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (7)

1. A construction method of a strong anchor middle pilot tunnel based on extra-large section tunnel construction is characterized by comprising the following steps:
s1: determining an excavation line of a tunnel, and determining an excavation line of a pilot tunnel (10) in a top layer in the tunnel excavation line;
s2: excavating along the extending direction of the tunnel in the excavating line of the top middle pilot tunnel (10);
s3: top support is applied to the top of the top layer pilot tunnel (10);
s4: excavating a left top layer part (20) at the left side and a right top layer part (30) at the right side of the top layer middle pilot tunnel (10);
s5: selecting a reasonable step footage for the middle part (40) of the bottom layer, following the step of the top layer pilot tunnel (10) according to the step footage, and excavating the middle part (40) of the bottom layer;
s6: selecting reasonable step footings for the left bottom layer part (50) on the left side of the middle part (40) of the bottom layer and the right bottom layer part (60) on the right side of the bottom layer, respectively following the steps of the left top layer part (20) and the right top layer part (30) according to the step footings, and respectively excavating the left bottom layer part (50) and the right bottom layer part (60);
s7: and finally, excavating and using a template trolley to construct a lining.
2. The construction method of the pilot tunnel in the strong anchor based on the construction of the tunnel with the extra large section according to claim 1, characterized in that when the left part (20) of the top layer, the right part (30) of the top layer, the left part (50) of the bottom layer and the right part (60) of the top layer are excavated, a plurality of working faces (70) are adopted to excavate towards the two ends of the tunnel simultaneously.
3. The construction method of the pilot tunnel in the strong anchor based on the construction of the super large section tunnel according to claim 2, characterized in that, in step S2, net-jet support is adopted for both sides of the pilot tunnel (10) in the top layer.
4. The construction method of the pilot tunnel in the strong anchor based on the construction of the extra-large section tunnel according to the claim 3, characterized in that a steel wire mesh with the diameter of 3-4mm is adopted for mesh-shotcreting support, and the mesh-shotcreting support is directly dug out when two sides of the pilot tunnel (10) in the top layer are dug.
5. The construction method of the strong anchor medium pilot tunnel based on the construction of the extra-large section tunnel according to the claim 1, characterized in that the step of firstly pulling the slot and then excavating is adopted when excavating the middle part (40) of the bottom layer.
6. The construction method of a strong anchor medium pilot tunnel based on construction of an extra-large section tunnel according to any one of claims 1 to 5, wherein in the step S3, the top support comprises: the method comprises the steps of firstly spraying concrete, erecting a steel frame, burying a prestressed long anchor rod (11), erecting a reinforcing mesh and spraying concrete again to the designed thickness.
7. The construction method of the pilot tunnel in the strong anchor based on the construction of the tunnel with the extra large section as the claim 6 is characterized in that the prestressed long anchor rods (11) are arranged in a shape like the Chinese character 'jing', and the length of the prestressed long anchor rods is 7-9 m.
CN202110819280.9A 2021-07-20 2021-07-20 Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction Pending CN113605901A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110819280.9A CN113605901A (en) 2021-07-20 2021-07-20 Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110819280.9A CN113605901A (en) 2021-07-20 2021-07-20 Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction

Publications (1)

Publication Number Publication Date
CN113605901A true CN113605901A (en) 2021-11-05

Family

ID=78338044

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110819280.9A Pending CN113605901A (en) 2021-07-20 2021-07-20 Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction

Country Status (1)

Country Link
CN (1) CN113605901A (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03279596A (en) * 1990-03-28 1991-12-10 Hazama Gumi Ltd Excavation method of large section or superlarge section of tunnel
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
CN103410532A (en) * 2013-08-07 2013-11-27 葛洲坝新疆工程局(有限公司) T-typed step-by-step parallel excavation method of soft-rock tunnel cavern
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN106351671A (en) * 2016-10-17 2017-01-25 中铁五局集团第五工程有限责任公司 Excavation and supporting structure for weak surrounding rock super-large cross-section tunnel and construction method thereof
CN108131145A (en) * 2017-12-20 2018-06-08 中铁五局集团有限公司 A kind of construction method of super-span tunnel excavation support
CN108518229A (en) * 2018-04-24 2018-09-11 中铁五局集团第五工程有限责任公司 Large deformation weak broken wall rock outsized section tunnel excavation supporting structure and construction method
CN109595004A (en) * 2018-10-25 2019-04-09 浙江省隧道工程公司 A kind of tunnel two expands four and digs method
CN110284890A (en) * 2019-07-16 2019-09-27 中铁五局集团第四工程有限责任公司 A kind of clast stream formation tunnel excavation construction method and structure
CN210343377U (en) * 2019-06-24 2020-04-17 高军 Surrounding rock structure is consolidated to big section tunnel prestressed anchorage pole of high-speed railway
CN111734450A (en) * 2020-06-30 2020-10-02 高军 Safe and rapid tunneling and supporting method for water-rich fault zone tunnel
CN111874400A (en) * 2020-07-20 2020-11-03 珠海格力电器股份有限公司 A bolster and packing carton for packing carton
CN112282771A (en) * 2020-11-12 2021-01-29 四川省交通勘察设计研究院有限公司 Rapid construction method for super-large-span highway tunnel

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03279596A (en) * 1990-03-28 1991-12-10 Hazama Gumi Ltd Excavation method of large section or superlarge section of tunnel
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
CN103410532A (en) * 2013-08-07 2013-11-27 葛洲坝新疆工程局(有限公司) T-typed step-by-step parallel excavation method of soft-rock tunnel cavern
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN106351671A (en) * 2016-10-17 2017-01-25 中铁五局集团第五工程有限责任公司 Excavation and supporting structure for weak surrounding rock super-large cross-section tunnel and construction method thereof
CN108131145A (en) * 2017-12-20 2018-06-08 中铁五局集团有限公司 A kind of construction method of super-span tunnel excavation support
CN108518229A (en) * 2018-04-24 2018-09-11 中铁五局集团第五工程有限责任公司 Large deformation weak broken wall rock outsized section tunnel excavation supporting structure and construction method
CN109595004A (en) * 2018-10-25 2019-04-09 浙江省隧道工程公司 A kind of tunnel two expands four and digs method
CN210343377U (en) * 2019-06-24 2020-04-17 高军 Surrounding rock structure is consolidated to big section tunnel prestressed anchorage pole of high-speed railway
CN110284890A (en) * 2019-07-16 2019-09-27 中铁五局集团第四工程有限责任公司 A kind of clast stream formation tunnel excavation construction method and structure
CN111734450A (en) * 2020-06-30 2020-10-02 高军 Safe and rapid tunneling and supporting method for water-rich fault zone tunnel
CN111874400A (en) * 2020-07-20 2020-11-03 珠海格力电器股份有限公司 A bolster and packing carton for packing carton
CN112282771A (en) * 2020-11-12 2021-01-29 四川省交通勘察设计研究院有限公司 Rapid construction method for super-large-span highway tunnel

Similar Documents

Publication Publication Date Title
CN110735656B (en) Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN109555527B (en) Five-line parallel small-spacing shallow-buried large-section tunnel group construction method
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN111502696A (en) Dense-mesh type advanced support system of underground excavation tunnel and construction method
CN112963156A (en) Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum
CN110761808A (en) Large-section loess tunnel supporting system and supporting construction method
CN109184752B (en) Supporting structure for coal mine to penetrate through old kiln goaf and supporting method thereof
CN110761795B (en) Construction method of shallow tunnel in loess gully
CN112901182A (en) Eight-part excavation construction method for reserving double rock pillar supports in large-span underground cave depot
CN110671132B (en) Deep loess tunnel deformation control construction structure and method based on sleeve arch
CN113605901A (en) Strong anchor middle pilot tunnel construction method based on extra-large section tunnel construction
CN114622574B (en) Water-rich throwing filling deep foundation pit water interception excavation supporting method and supporting device
CN112664206B (en) Milling and excavating method for soft and weak cladding shallow-buried large-section tunnel
CN110792440B (en) Construction method of water-rich loess tunnel penetrating through loess towards valley
CN211038656U (en) Large-section loess tunnel supporting system
CN109736843B (en) Reverse waterproof method for assembling and pouring two linings of small template
CN113006802A (en) Tunnel reverse step excavation construction method suitable for thin overburden stratum
CN112502042A (en) Construction method for improving jacking efficiency of large frame bridge
CN207554058U (en) Box culvert with thrustor and box culvert pushing block connection structure relays pushing tow system
CN110792449A (en) Rapid underground excavation construction method for large-span shallow tunnel
CN113309525B (en) Construction method for releasing core rock and soil in advance for ultra-large section underground excavation station
CN112879032B (en) Construction method of crossover section tunnel combined with shield tunnel
CN217558352U (en) Upper-span and lower-penetrating proximity structure tunnel reinforcing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination