CN110792449A - Rapid underground excavation construction method for large-span shallow tunnel - Google Patents

Rapid underground excavation construction method for large-span shallow tunnel Download PDF

Info

Publication number
CN110792449A
CN110792449A CN201911036069.9A CN201911036069A CN110792449A CN 110792449 A CN110792449 A CN 110792449A CN 201911036069 A CN201911036069 A CN 201911036069A CN 110792449 A CN110792449 A CN 110792449A
Authority
CN
China
Prior art keywords
tunnel
excavation
span
core
reserved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911036069.9A
Other languages
Chinese (zh)
Inventor
凌贤长
赵莹莹
唐亮
Original Assignee
凌贤长
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 凌贤长 filed Critical 凌贤长
Priority to CN201911036069.9A priority Critical patent/CN110792449A/en
Publication of CN110792449A publication Critical patent/CN110792449A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

The invention provides a quick underground excavation construction method for a large-span shallow tunnel, wherein a large section of the large-span tunnel is decomposed into a plurality of small sections by using a middle partition wall and a cross brace, so that the tunnel is excavated in a segmented batch mode and a core earth pillar is reserved in the middle, and the difficulty of full-section excavation of the large-span tunnel is reduced. Excavating from the guide pits on two sides of the arch crown at the upper part, so that the supporting effect of the soil arch at the top of the tunnel can be effectively utilized, and the tunnel can also be used as a construction channel for subsequent excavation; the synchronous symmetrical excavation on the two sides can keep the stress balance in the excavation and avoid uneven stress; the reserved core soil column can be used as a stress supporting point in the whole construction process, so that the integral instability and damage of the tunnel are prevented; the temporary support of the middle partition wall and the cross braces can ensure the collapse of the top and the expansion and extrusion damage of the side walls and the bottom.

Description

Rapid underground excavation construction method for large-span shallow tunnel
Technical Field
The invention belongs to the technical field of tunnel engineering, and particularly relates to a quick underground excavation construction method for a large-span shallow tunnel.
Background
With the continuous development of social and economic construction and the increasing of underground space engineering, the tunnel underground excavation method is only used for excavating the cavern underground without damaging the ground, and is widely applied to the characteristics of small influence on the environment and no influence on traffic and ground buildings. The shallow-buried underground excavation method is a construction method for underground caverns with shallow underground excavation distances from the ground surface. In the current stage, the shallow-buried underground excavation method is basically mature in the construction technology of tunnels and underground engineering, but for the engineering with shallow buried depth, poor geological conditions and complex environment, a plurality of adverse factors exist in the shallow-buried underground excavation engineering of the large-span tunnel, and some engineering accidents also occur. The existing tunnel excavation technology has the problems of uneven stress, insufficient support and support strength, easy settlement at the vault, unstable integrity and the like.
Disclosure of Invention
Aiming at the defects of the prior art, the method for quickly and secretly excavating the large-span shallow-buried tunnel is provided based on the problems of large construction difficulty, multiple potential safety hazards, slow construction progress and the like of the traditional tunnel excavation construction method for the large-span tunnel, and is used for underground engineering with poor geological conditions and unstable rock masses.
In order to achieve the purpose of the invention, the invention is realized by the following technical scheme: a quick underground excavation construction method for a large-span shallow tunnel comprises the following steps:
step 1, synchronously and symmetrically excavating guide pits on two sides of the upper part of a tunnel along the longitudinal direction of the tunnel to form a left upper section and a right upper section in a horizontal state, and reserving an upper core earth pillar in the middle position;
step 2, supporting the left upper section and the right upper section dug at the upper part of the tunnel, permanently supporting two outer side walls of the arch crown part, and building two vertical upper middle partition walls and transverse cross brace temporary supports at two sides of the reserved upper core soil column;
step 3, synchronously and symmetrically excavating the lower part of the tunnel by adopting a step excavation method on the lower steps along the longitudinal direction of the tunnel to form a left lower section and a right lower section in a horizontal state, reserving a lower core earth pillar in the middle position, wherein the width of the lower core earth pillar is larger than that of the upper core earth pillar;
step 4, supporting left and right lower sections excavated at the lower part of the tunnel, permanently supporting two outer side walls of the tunnel, and building two vertical lower middle partition wall temporary supports at two sides of a reserved lower core soil column;
step 5, performing arc excavation on the reserved upper core soil column by adopting an annular excavation method, and performing permanent support on the vault;
step 6, excavating the remaining trapezoidal core soil of the reserved upper core soil column;
step 7, adopting a step excavation method to excavate the reserved lower core soil column;
step 8, after the arch part of the tunnel is supported to form a ring, primary lining pouring of an inverted arch at the bottom of the tunnel;
and 9, removing the vertical upper middle partition wall, the cross brace and the vertical lower middle partition wall in sequence, arranging a waterproof layer and a heat insulation layer after each removal, and performing full-section secondary lining construction.
The invention also has the following technical characteristics:
1. the two vertical upper middle partition walls are respectively positioned at the 2/5 and 4/5 positions of the cross-sectional span of the tunnel.
2. The two lower vertical middle partition walls are respectively positioned at the 1/3 and 2/3 positions of the cross-sectional span of the tunnel.
The invention has the advantages and beneficial effects that: the invention adopts a construction method of sectional batch excavation, synchronous symmetrical excavation at two sides, core soil column reservation and supporting while excavation. The large section of the large-span tunnel is decomposed into a plurality of small section forms by the aid of the middle partition wall and the cross braces, the tunnel is excavated in batches in a segmented mode, and difficulty in full-section excavation of the large-span tunnel is reduced. Excavating from the guide pits on two sides of the arch crown at the upper part, so that the supporting effect of the soil arch at the top of the tunnel can be effectively utilized, and the tunnel can also be used as a construction channel for subsequent excavation; the synchronous symmetrical excavation on the two sides can keep the stress balance in the excavation and avoid uneven stress; the reserved core soil column can be used as a stress supporting point in the whole construction process, and the integral instability and damage of the tunnel are prevented. Meanwhile, supporting support measures are taken after each excavation step, and the permanent support of the arch part side wall and the arch crown after excavation plays a role in stress support and prevents the arch crown from collapsing and settling; the temporary support of the middle partition wall can effectively protect the reserved core soil column from collapsing and damaging in the excavation process, and simultaneously plays a role of bearing stress with the core soil column to avoid the overall instability and damage of the tunnel; the arrangement of the cross braces can balance the stress on two sides of the core soil column clamped by the middle partition wall, and play an effective temporary supporting role on the arch crown and the side wall; the permanent support of the side wall and the primary lining pouring of the inverted arch can prevent the expansion extrusion deformation of the side wall and the bottom and can be used as a primary lining. The supporting structure and the construction method thereof provided by the invention are safe and practical, reasonable in step sequence, simple in construction, low in operation difficulty and efficient in process.
Drawings
FIG. 1 is a schematic construction view of a large-span shallow tunnel rapid subsurface excavation supporting structure provided by the invention;
FIG. 2 is a three-dimensional schematic diagram of the rapid subsurface excavation construction of a large-span shallow tunnel according to the present invention;
in the figure: 1. upper fracture surface; 2. permanently supporting the side wall of the vault; 3. a vertical upper middle bulkhead; 4. a cross brace; 5. lower section; 6. permanent support of the side wall; 7. a vertical lower middle bulkhead; 8. a trapezoidal core soil; 9. permanent vault support; 10. putting arc core soil; 11. a lower core column; 12. inverted arch, 13, upper core column.
Detailed Description
The invention will be further illustrated by the following examples in conjunction with the accompanying drawings:
example 1
As shown in fig. 1-2, a method for constructing a large-span shallow tunnel by fast subsurface excavation comprises the following steps:
step 1, synchronously and symmetrically excavating guide pits at two sides of the upper part of a tunnel along the longitudinal direction of the tunnel to form a left upper section and a right upper section in a horizontal state, and reserving an upper core earth pillar in the middle, wherein the width of the upper core earth pillar is 1/5 of the span of the section of the tunnel;
step 2, supporting the left and right upper sections excavated at the upper part of the tunnel, and permanently supporting two outer side walls of the arch crown part, wherein the left and right upper sections can be used as a primary lining in a form of sprayed concrete and/or anchor rod and sprayed concrete and steel frame combined support; two vertical upper middle partition walls and transverse cross brace temporary supports are built on two sides of a reserved upper core soil column, the two vertical upper middle partition walls are respectively positioned at 2/5 and 4/5 of the cross section span of the tunnel and are well attached to the reserved upper core soil column, and the vertical upper middle partition walls and the transverse cross brace temporary supports are made of I-shaped steel;
step 3, synchronously and symmetrically excavating the lower part of the tunnel by adopting a step excavation method on the lower steps along the longitudinal direction of the tunnel to form a left lower section and a right lower section in a horizontal state, reserving a lower core earth pillar in the middle, and ensuring that the width of the lower core earth pillar is 1/3 of the span of the section of the tunnel;
step 4, supporting the excavated lower section, and permanently supporting two outer side walls of the tunnel, wherein the form of sprayed concrete and/or anchor rod and sprayed concrete and steel frame combined support can be adopted and can be used as a primary lining; two vertical lower middle partition wall temporary supports are built on two sides of a lower core soil column and are well attached to the lower core soil column, the two lower vertical middle partition walls are respectively located at 1/3 and 2/3 of the cross section span of a tunnel, and the vertical lower middle partition walls are made of I-shaped steel;
step 5, performing arc excavation on the reserved upper core soil column by adopting an annular excavation method, and performing permanent support on the vault to be used as a primary lining;
step 6, excavating the residual trapezoidal core soil of the upper core soil column;
step 7, adopting a step excavation method to excavate the reserved lower core soil column;
step 8, after the arch part of the tunnel is supported and looped, primary lining pouring is carried out on an inverted arch at the bottom of the tunnel, and the inverted arch is of a reinforced concrete structure;
and 9, removing the upper vertical middle partition wall, the cross brace and the lower vertical middle partition wall in sequence, arranging a waterproof layer and a heat insulation layer after each removal, and performing full-section secondary lining construction.

Claims (3)

1. A quick underground excavation construction method for a large-span shallow tunnel is characterized by comprising the following steps:
step 1, synchronously and symmetrically excavating guide pits on two sides of the upper part of a tunnel along the longitudinal direction of the tunnel to form a left upper section and a right upper section in a horizontal state, and reserving an upper core earth pillar in the middle position;
step 2, supporting the left upper section and the right upper section dug at the upper part of the tunnel, permanently supporting two outer side walls of the arch crown part, and building two vertical upper middle partition walls and transverse cross brace temporary supports at two sides of the reserved upper core soil column;
step 3, synchronously and symmetrically excavating the lower part of the tunnel by adopting a step excavation method on the lower steps along the longitudinal direction of the tunnel to form a left lower section and a right lower section in a horizontal state, reserving a lower core earth pillar in the middle position, wherein the width of the lower core earth pillar is larger than that of the upper core earth pillar;
step 4, supporting left and right lower sections excavated at the lower part of the tunnel, permanently supporting two outer side walls of the tunnel, and building two vertical lower middle partition wall temporary supports at two sides of a reserved lower core soil column;
step 5, performing arc excavation on the reserved upper core soil column by adopting an annular excavation method, and performing permanent support on the vault;
step 6, excavating the remaining trapezoidal core soil of the reserved upper core soil column;
step 7, adopting a step excavation method to excavate the reserved lower core soil column;
step 8, after the arch part of the tunnel is supported to form a ring, primary lining pouring of an inverted arch at the bottom of the tunnel;
and 9, removing the vertical upper middle partition wall, the cross brace and the vertical lower middle partition wall in sequence, arranging a waterproof layer and a heat insulation layer after each removal, and performing full-section secondary lining construction.
2. The quick underground excavation construction method for the large-span shallow tunnel according to claim 1, characterized in that: the two vertical upper middle partition walls are respectively positioned at the 2/5 and 4/5 positions of the cross-sectional span of the tunnel.
3. The quick underground excavation construction method for the large-span shallow tunnel according to claim 1, characterized in that: the two lower vertical middle partition walls are respectively positioned at the 1/3 and 2/3 positions of the cross-sectional span of the tunnel.
CN201911036069.9A 2019-10-29 2019-10-29 Rapid underground excavation construction method for large-span shallow tunnel Pending CN110792449A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911036069.9A CN110792449A (en) 2019-10-29 2019-10-29 Rapid underground excavation construction method for large-span shallow tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911036069.9A CN110792449A (en) 2019-10-29 2019-10-29 Rapid underground excavation construction method for large-span shallow tunnel

Publications (1)

Publication Number Publication Date
CN110792449A true CN110792449A (en) 2020-02-14

Family

ID=69441772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911036069.9A Pending CN110792449A (en) 2019-10-29 2019-10-29 Rapid underground excavation construction method for large-span shallow tunnel

Country Status (1)

Country Link
CN (1) CN110792449A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN103775092A (en) * 2014-01-09 2014-05-07 长业建设集团有限公司 Tunnel shallow-buried excavation reserved core soil improved CRD construction method
CN104879131A (en) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 Large-span tunnel excavation method for upper soft and lower hard compound strata
CN106979013A (en) * 2017-04-07 2017-07-25 中交第二航务工程局有限公司 A kind of excavation construction method for the large section tunnel for biasing Shallow-Buried Soft Rock
CN107288653A (en) * 2017-06-27 2017-10-24 中铁十局集团第四工程有限公司 A kind of the benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three and construction method
CN108166979A (en) * 2017-12-01 2018-06-15 长安大学 A kind of construction method of super-span tunnel top bar two side-wall pilot tunnel
CN109882185A (en) * 2019-03-25 2019-06-14 中铁十六局集团第二工程有限公司 The construction method in the soft or hard uneven tunnel of rock matter under a kind of large ground pressure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN103775092A (en) * 2014-01-09 2014-05-07 长业建设集团有限公司 Tunnel shallow-buried excavation reserved core soil improved CRD construction method
CN104879131A (en) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 Large-span tunnel excavation method for upper soft and lower hard compound strata
CN106979013A (en) * 2017-04-07 2017-07-25 中交第二航务工程局有限公司 A kind of excavation construction method for the large section tunnel for biasing Shallow-Buried Soft Rock
CN107288653A (en) * 2017-06-27 2017-10-24 中铁十局集团第四工程有限公司 A kind of the benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three and construction method
CN108166979A (en) * 2017-12-01 2018-06-15 长安大学 A kind of construction method of super-span tunnel top bar two side-wall pilot tunnel
CN109882185A (en) * 2019-03-25 2019-06-14 中铁十六局集团第二工程有限公司 The construction method in the soft or hard uneven tunnel of rock matter under a kind of large ground pressure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李满: "复杂环境下地铁暗挖车站双侧壁导坑法支撑体系优化", 《施工技术》 *

Similar Documents

Publication Publication Date Title
CN107060840B (en) A kind of construction method of large cross-section tunnel V grades of country rock excavation supportings
CN101737061B (en) Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN102226403B (en) Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102182466B (en) Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN102606167B (en) Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel
CN104653197B (en) Method for constructing extra-large variable cross section tunnel
CN102071947B (en) Construction method for soft surrounding rock section of large-span tunnel portal
CN105464686B (en) Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility
CN102134998B (en) Construction method for wind-blown sand tunnel
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN105350973A (en) Construction method for large-span section loess tunnel under-crossing highway
CN104863597B (en) A kind of construction method transverse direction hole lid method in shallow buried covered excavation Large Underground space
CN104653187B (en) Water-rich sand layer geology large cross-section tunnel excavation method
CN102536273B (en) 26-meter large-span space one-step forming construction method
CN103775092B (en) Tunnels in Shallow Buried tunneling remaining core soil in advance improvement CRD construction
CN106351670B (en) A kind of closed pre support tunnel structure
CN103244130B (en) Quick excavation and expanding construction method of herringbone tunnel section
CN103628894B (en) Method is repaiied in a kind of rich water fault belt based on angle umbrella pre-grouting lane, tunnel of collapsing
CN102758632B (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN104612698A (en) Method for constructing upper step middle partition wall of shallow-buried excavation tunnel
CN102852525B (en) Underground tunnel enlarging and excavating method from small section of single-line tunnel to large section of double-line tunnel
CN102733827B (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN105804760B (en) Super-large-section tunnel drilling and blasting method extends constructing structure and construction method in situ
CN102305077A (en) Rapid construction method of large-section multi-arc tunnel

Legal Events