CN113529778A - Construction method for foundation of electric power iron tower in plateau area - Google Patents

Construction method for foundation of electric power iron tower in plateau area Download PDF

Info

Publication number
CN113529778A
CN113529778A CN202110820355.5A CN202110820355A CN113529778A CN 113529778 A CN113529778 A CN 113529778A CN 202110820355 A CN202110820355 A CN 202110820355A CN 113529778 A CN113529778 A CN 113529778A
Authority
CN
China
Prior art keywords
foundation
area
concrete
construction
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110820355.5A
Other languages
Chinese (zh)
Inventor
李佳瑞
李天德
李伟博
高晓微
牛腾飞
郑玉春
王晓东
邓鹏程
任宇笛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Electrification Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Electrification Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Electrification Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN202110820355.5A priority Critical patent/CN113529778A/en
Publication of CN113529778A publication Critical patent/CN113529778A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

A construction method for an electric iron tower foundation in a plateau area belongs to the technical field of electric construction, and can solve the problems of large damage to vegetation in a construction area, large construction amount, inconvenient construction, time and labor waste, low construction efficiency and labor and material waste of a traditional foundation construction method. The invention is completely suitable for the environmental conditions of high-altitude areas such as Sichuan-Tibet and the like, and is beneficial to energy conservation and environmental protection. The damage to the plateau environment is greatly reduced. The foundation quality is ensured, and the construction safety is improved.

Description

Construction method for foundation of electric power iron tower in plateau area
Technical Field
The invention belongs to the technical field of electric power construction, and particularly relates to a construction method of an electric power iron tower foundation in a plateau area.
Background
The highland areas such as the Sichuan province and the like have high terrain, complex geological conditions, rich forest resources, high cold and oxygen deficiency, and fragile environment, and are easy to damage.
The traditional electric power iron tower foundation construction adopts a method of slope excavation, foundation pouring and backfilling, and the method has the advantages of large excavation and filling amount, great damage to original vegetation, inconvenience in construction, time and labor waste, low construction efficiency, labor and material waste and great waste of manpower and material resources. In addition, the method needs to use machines on a large scale, the construction conditions of mountain areas in plateau are harsh, the machines cannot be used on a large scale, and most areas can only be operated manually. The method is invented in order to reduce the environmental damage to high-altitude areas such as Sichuan-Tibet, ensure the construction safety and quality and improve the resource utilization rate and the construction efficiency.
Disclosure of Invention
The invention provides a construction method of a power iron tower foundation in a plateau area, aiming at the problems of great damage to vegetation in a plateau construction area, large construction amount, inconvenience in construction, time and labor waste, low construction efficiency, labor and material waste in the traditional foundation construction method.
The invention adopts the following technical scheme:
a construction method of a power iron tower foundation in a plateau area comprises the following steps:
firstly, arranging a construction field ground plane, measuring and determining a foundation position, and dividing a construction area;
with the central pile as the center, arranging a surface soil curing area, a waste soil stacking area, a household garbage centralized collecting area, a construction tool storage area, a steel bar stacking area, a fine aggregate stacking area, a coarse aggregate stacking area, a concrete stirring and taking and cement stacking area in sequence on a construction site along the counterclockwise direction, wherein fire extinguishers are arranged in the concrete stirring area and the construction tool storage area;
secondly, treating surface soil and spoil;
firstly laying a layer of color stripe cloth in the divided topsoil curing area, then taking down the turf of the basic area and placing the turf on the color stripe cloth in the topsoil curing area, and watering and curing the turf every day to prevent the turf from drying due to water shortage; the spoil stacking mode: the raw soil below the surface soil is spoil, and a temporary conveying channel is paved by using color stripe cloth during conveying and placed in a spoil stacking area;
thirdly, excavating a foundation pit;
the foundation pit excavation adopts a manual excavation mode, the excavation is carried out section by section, the concrete retaining wall of the section is cast after each section is excavated, the first section of the concrete retaining wall is 150mm higher than the pit opening and is provided with a locking opening, the excavation of the next section of the foundation pit is carried out after the strength of the upper section of the concrete retaining wall is more than 3.0MPa, the overlapping length of the upper section of the concrete retaining wall and the lower section of the concrete retaining wall is 280mm, and reinforcing steel bars of the upper section of the concrete retaining wall are embedded into the lower section of the concrete retaining wall;
fourthly, manufacturing a reinforcement cage, placing the reinforcement cage into a foundation pit after weaving, manufacturing a foundation mould by using a wood board above the foundation pit, pouring concrete, completing pouring of each foundation at one time, removing the mould when the strength of the concrete reaches the design strength after the pouring of the concrete is completed and the surface and edges and corners of the foundation can be guaranteed not to be damaged when the mould is removed, and recovering vegetation in the construction area according to the original appearance after the pouring of the foundation is completed;
fifthly, maintaining the foundation, wherein the foundation is maintained by adopting a comprehensive heat storage method;
and sixthly, after the iron tower is assembled, building a protective cap on the top surface of the foundation after the relative bolts on the tower leg inclined material connecting plate are tightened.
The peeling depth of the surface soil is 300-500 mm.
The spoil is stacked according to the trapezoid, the height is not more than 1 meter, and the distance from the bottom layer edge to the color stripe cloth edge is not less than 1.5 meters.
And each section of the foundation pit is set to be 500-1000 m.
The reinforcing mesh of the concrete retaining wall adopts HPB 300-grade reinforcing steel bars, and C30 concrete is cast in the locking notch and the retaining wall.
The steel reinforcement cage includes a plurality of perpendicular muscle, and the equidistant circumference that is arranged, erects the inboard and the outside of muscle and is equipped with a plurality of equidistant interior stirrup and the outer stirrup of arranging respectively, and interior stirrup interval is 350mm, and outer stirrup interval is 220 mm.
The comprehensive heat storage maintenance method comprises the following steps: firstly, laying 2 layers of plastic films on the exposed surface of concrete; covering a layer of geotextile on the plastic film; and thirdly, covering two layers of quilts on the geotextile, binding the quilts with the basic template, covering the quilts with soil, covering the covering layer for 200mm, and measuring the temperature at regular time through a thermometer to observe the temperature change of the concrete.
The invention has the following beneficial effects:
1. the traditional method adopts mechanical construction, and the invention adopts a manual excavation mode, thereby being suitable for the construction environment of high-altitude areas such as Sichuan-Tibet and the like.
2. According to the method, a layer of color stripe cloth is laid in a divided topsoil maintenance area, then the turf in a basic area is taken down and placed on the color stripe cloth in the topsoil maintenance area, and the turf is watered and maintained every day, so that the turf is prevented from drying due to water shortage; the spoil stacking mode: the raw soil below the surface soil is spoil, and a temporary conveying channel is paved by using color strip cloth during conveying and is placed in a spoil stacking area, so that the maintenance of the surface soil is realized, and the damage to the environment is reduced.
3. The invention has small working area and small excavation amount.
4. The invention ensures the construction safety and quality and improves the resource utilization rate and the construction efficiency.
5. After the foundation is poured, the vegetation recovery is carried out on the construction area according to the original appearance, so that the environmental damage to the plateau areas such as Sichuan-Tibet is reduced.
6. The invention can reasonably plan the construction area and also can achieve the purpose of preventing construction waste from polluting the environment.
Drawings
FIG. 1 is a plan layout view of a foundation construction site of an electric power iron tower according to the present invention;
FIG. 2 is a schematic view of a first section of a retaining wall lost-circulation of the present invention;
FIG. 3 is a schematic view of the remaining retaining wall grommets;
FIG. 4 is a front view of a reinforcement bar of the foundation;
FIG. 5 is a top view of a reinforcement bar of the foundation;
FIG. 6 is a schematic view of a basic protective cap;
wherein: 1-a fire extinguisher; 2-locking the notch; 3-protecting the wall steel bar; 4-protecting the wall; 5-a base; 6-vertical ribs; 7-inner stirrups; 8-outer stirrups; 9-basic protective cap.
Detailed Description
The invention is further explained with reference to the accompanying drawings.
As shown in the figure, the construction method of the electric power iron tower foundation in the plateau area comprises the following steps:
(1) and measuring and determining the positions of the center pile and the four foundation centers, and arranging a construction site according to the figure 1. A layer of color stripe cloth is laid in the divided construction areas to prevent the building materials and tools from polluting the environment, and then the building materials are stacked in order after being packaged by woven bags and are placed in the corresponding areas. The bottom of the coarse and fine aggregate and cement stacking area is paved with a layer of straw mat, a layer of color strip cloth is paved on the straw mat, then the material is stacked on the color strip cloth, and the upper surface of the material is covered with a layer of quilt after being paved with the color strip cloth. The construction area storage area and the concrete mixing area are respectively provided with a fire extinguisher.
(2) A layer of color stripe cloth is laid in the divided surface soil maintenance area, then the turf in the basic area is taken down and placed in the surface soil turf and the surface soil maintenance area, and the turf is watered and maintained every day, so that the turf is prevented from drying due to water shortage. The stripping depth of the surface soil is 300-500 mm. The raw soil below the surface soil is paved with the color stripe cloth to form a temporary conveying channel during conveying, the temporary conveying channel is placed in a raw soil stacking area, the raw soil is stacked according to a trapezoid shape, the height of the raw soil is not more than 1 meter, and the distance between the bottom layer edge and the color stripe cloth edge is not less than 1.5 meters.
(3) The foundation pit excavation adopts the mode of manual excavation, and excavation section by section is set to be 500-1000 mm according to the actual geological condition of a construction site. And pouring the concrete retaining wall section after each section is dug, wherein the first concrete retaining wall section is 150mm higher than the pit opening and is provided with a locking opening. And after the strength of the concrete of the upper retaining wall section is more than 3.0MPa, excavating the next section of foundation pit, wherein the lap joint length of the upper and lower retaining wall sections is 280 mm. The wall is cast by C30 concrete, and the reinforcing mesh of the wall is HPB300 grade reinforcing steel. The annular and vertical reinforcing steel bar nets are arranged in the thickness direction of the protective wall. The upper protecting wall steel bar is embedded into the lower protecting wall.
(4) The vertical bars of the steel bar cage adopt three-level HRB400 threaded steel bars, and the stirrups adopt one-level HPB300 steel bars. 19 vertical ribs are uniformly arranged into a circle. The outer stirrup spacing is 220mm, and the inner stirrup spacing is 350 mm. The stirrups and the main reinforcements are bound and connected by adopting 1.0 binding wires. The steel bar binding is firstly marked according to the steel bar interval of the construction drawing, and then the steel bar distribution and binding are carried out; the bound steel bars are required to be horizontal and vertical, the specification, the number, the position and the spacing are correct, and the phenomena of button missing and button loosening cannot occur in binding; the reinforcing steel bar binding buckles can not face to one direction and need to be splayed buckles.
(5) And (4) after the reinforcement cage is woven, putting the reinforcement cage into a foundation pit, and manufacturing a basic die by using a wood board above the foundation pit. And measuring and adjusting the positions of the foundation mold and the foundation bolt by a measurer by using a total station. The mould and the foundation bolt are fixed in proper positions, so that the position deviation is prevented when concrete is poured. The concrete construction adopts a small mixer to carry out on-site mixing according to the mixing proportion. When concrete is poured, no water can be accumulated in the foundation pit, and when the underground water level of the foundation pit is higher or the water seepage amount is too large, measures such as field water interception, precipitation or underwater concrete pouring are taken. When the concrete blanking height exceeds 2m, chute materials are adopted. And pouring concrete of each foundation once. And after the concrete is poured, when the strength of the concrete reaches the design strength, the surface and edges of the foundation are not damaged when the foundation is demolded, and then the formwork is demolded. And after the foundation pouring is finished, carrying out vegetation recovery on the construction area according to the original appearance.
(6) And after the concrete is poured on the foundation, immediately carrying out heat preservation maintenance on the foundation exposed out of the ground. The concrete is maintained by adopting a comprehensive heat storage method. The maintenance method comprises the steps of firstly, laying 2 layers of plastic films on the exposed surface of concrete; covering a layer of geotextile on the plastic film; and thirdly, covering two layers of quilts on the geotextile, tightly binding the quilts with the foundation template, and covering with soil, wherein the covering layer is 200 mm. The temperature is measured regularly by a thermometer to observe the temperature change of the concrete.
(7) After the iron tower is assembled, building a protective cap on the top surface of a foundation after the relative bolts on the inclined material connecting plate of the tower leg are tightened, wherein the protective cap is made of C15 concrete, the size of the protective cap is 50mm, the side length is increased by 50mm according to each side of the outer side of the tower base plate, the height is increased by 50mm according to the exposed height of the foundation bolt, in addition, the upper part is smeared to form a dimensional inclined plane with an alpha angle not less than 15 degrees, and the edge angle of the edge of the protective cap is chamfered.

Claims (7)

1. A construction method of a foundation of an electric power iron tower in a plateau area is characterized by comprising the following steps: the method comprises the following steps:
firstly, arranging a construction field ground plane, measuring and determining a foundation position, and dividing a construction area;
with the central pile as the center, arranging a surface soil curing area, a waste soil stacking area, a household garbage centralized collecting area, a construction tool storage area, a steel bar stacking area, a fine aggregate stacking area, a coarse aggregate stacking area, a concrete stirring and taking and cement stacking area in sequence on a construction site along the counterclockwise direction, wherein fire extinguishers are arranged in the concrete stirring area and the construction tool storage area;
secondly, treating surface soil and spoil;
firstly laying a layer of color stripe cloth in the divided topsoil curing area, then taking down the turf of the basic area and placing the turf on the color stripe cloth in the topsoil curing area, and watering and curing the turf every day to prevent the turf from drying due to water shortage; the spoil stacking mode: the raw soil below the surface soil is spoil, and a temporary conveying channel is paved by using color stripe cloth during conveying and placed in a spoil stacking area;
thirdly, excavating a foundation pit;
the foundation pit excavation adopts a manual excavation mode, the excavation is carried out section by section, the concrete retaining wall of the section is cast after each section is excavated, the first section of the concrete retaining wall is 150mm higher than the pit opening and is provided with a locking opening, the excavation of the next section of the foundation pit is carried out after the strength of the upper section of the concrete retaining wall is more than 3.0MPa, the overlapping length of the upper section of the concrete retaining wall and the lower section of the concrete retaining wall is 280mm, and reinforcing steel bars of the upper section of the concrete retaining wall are embedded into the lower section of the concrete retaining wall;
fourthly, manufacturing a reinforcement cage, placing the reinforcement cage into a foundation pit after weaving, manufacturing a foundation mould by using a wood board above the foundation pit, pouring concrete, completing pouring of each foundation at one time, removing the mould when the strength of the concrete reaches the design strength after the pouring of the concrete is completed and the surface and edges and corners of the foundation can be guaranteed not to be damaged when the mould is removed, and recovering vegetation in the construction area according to the original appearance after the pouring of the foundation is completed;
fifthly, maintaining the foundation, wherein the foundation is maintained by adopting a comprehensive heat storage method;
and sixthly, after the iron tower is assembled, building a protective cap on the top surface of the foundation after the relative bolts on the tower leg inclined material connecting plate are tightened.
2. The method for constructing the foundation of the electric power iron tower in the plateau area according to claim 1, wherein the method comprises the following steps: the peeling depth of the surface soil is 300-500 mm.
3. The method for constructing the foundation of the electric power iron tower in the plateau area according to claim 1, wherein the method comprises the following steps: the spoil is stacked according to the trapezoid, the height is not more than 1 meter, and the distance from the bottom layer edge to the color stripe cloth edge is not less than 1.5 meters.
4. The method for constructing the foundation of the electric power iron tower in the plateau area according to claim 1, wherein the method comprises the following steps: and each section of the foundation pit is set to be 500-1000 m.
5. The method for constructing the foundation of the electric power iron tower in the plateau area according to claim 1, wherein the method comprises the following steps: the reinforcing mesh of the concrete retaining wall adopts HPB 300-grade reinforcing steel bars, and C30 concrete is cast in the locking notch and the retaining wall.
6. The method for constructing the foundation of the electric power iron tower in the plateau area according to claim 1, wherein the method comprises the following steps: the steel reinforcement cage includes a plurality of perpendicular muscle, and the equidistant circumference that is arranged, erects the inboard and the outside of muscle and is equipped with a plurality of equidistant interior stirrup and the outer stirrup of arranging respectively, and interior stirrup interval is 350mm, and outer stirrup interval is 220 mm.
7. The method for constructing the foundation of the electric power iron tower in the plateau area according to claim 1, wherein the method comprises the following steps: the comprehensive heat storage maintenance method comprises the following steps: firstly, laying 2 layers of plastic films on the exposed surface of concrete; covering a layer of geotextile on the plastic film; and thirdly, covering two layers of quilts on the geotextile, binding the quilts with the basic template, covering the quilts with soil, covering the covering layer for 200mm, and measuring the temperature at regular time through a thermometer to observe the temperature change of the concrete.
CN202110820355.5A 2021-07-20 2021-07-20 Construction method for foundation of electric power iron tower in plateau area Pending CN113529778A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110820355.5A CN113529778A (en) 2021-07-20 2021-07-20 Construction method for foundation of electric power iron tower in plateau area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110820355.5A CN113529778A (en) 2021-07-20 2021-07-20 Construction method for foundation of electric power iron tower in plateau area

Publications (1)

Publication Number Publication Date
CN113529778A true CN113529778A (en) 2021-10-22

Family

ID=78100484

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110820355.5A Pending CN113529778A (en) 2021-07-20 2021-07-20 Construction method for foundation of electric power iron tower in plateau area

Country Status (1)

Country Link
CN (1) CN113529778A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446088A (en) * 2008-11-11 2009-06-03 中国电力科学研究院 Construction method for pole and tower foundation in Gobi Desert gravelly soil area
JP2018021322A (en) * 2016-08-02 2018-02-08 東京電力ホールディングス株式会社 Pile foundation and tower reconstruction method
CN109826224A (en) * 2019-03-08 2019-05-31 中国能源建设集团安徽省电力设计院有限公司 A kind of sinking well protection wall digging foundation and its construction method for desert region iron tower of power transmission line
CN111485573A (en) * 2020-03-19 2020-08-04 衡水衡源电力建设有限责任公司 Transmission project prefabricated foundation installation and iron tower assembly coherent construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446088A (en) * 2008-11-11 2009-06-03 中国电力科学研究院 Construction method for pole and tower foundation in Gobi Desert gravelly soil area
JP2018021322A (en) * 2016-08-02 2018-02-08 東京電力ホールディングス株式会社 Pile foundation and tower reconstruction method
CN109826224A (en) * 2019-03-08 2019-05-31 中国能源建设集团安徽省电力设计院有限公司 A kind of sinking well protection wall digging foundation and its construction method for desert region iron tower of power transmission line
CN111485573A (en) * 2020-03-19 2020-08-04 衡水衡源电力建设有限责任公司 Transmission project prefabricated foundation installation and iron tower assembly coherent construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
康朋等: "重庆地区架空线路施工占用地赔偿面积计算方法探索", 《中国电力企业管理》 *
陈永贵等: "高海拔高寒地区输电线路施工环保措施", 《电力建设》 *

Similar Documents

Publication Publication Date Title
CN103669291B (en) The construction method of articulated revetment brick bank protection
CN104790428B (en) Ultrahigh integrated plastic-steel grid reinforced soil abutment retaining wall structure and construction method thereof
CN113322984A (en) Quick repairing structure for shallow landslide of soil slope with more than two levels and construction method thereof
CN102926398A (en) Construction method of inclined column type corrosion resistant foundation for power line in salt lake area
CN106088109A (en) Discarded pit slope ecological recovery covers green construction method
CN110984210A (en) Iron frame foundation of power transmission line and construction method
CN113250240A (en) Combined side slope protection structure and process of layered net type gabion and concrete
CN110761316A (en) Prefabricated foundation ring beam prefabricating method and storage tank construction method applying prefabricated foundation ring beam prefabricating method
CN206844275U (en) Mutual buckle type precast concrete cover ditch and its suspender
CN107090837A (en) Pit-in-pit reinforced concrete retaining wall composite supporting structure and construction method thereof
CN114182745B (en) Ecological slope protection roadbed of high-liquid limit soil ecological retaining wall and construction method
CN110374181A (en) A kind of rainwater collection pool and its construction method
CN113529778A (en) Construction method for foundation of electric power iron tower in plateau area
CN112854254A (en) Construction method for existing railway field level subgrade support in deep artificial waste slag area
CN208023601U (en) A kind of prefabricated pile foundation support table side form of mutual buckle type
CN202899153U (en) Oblique column type anti-corrosion foundation device for power transmission line of salt-lake region
CN108571068A (en) The insertion of steel fabric sheet cross section carries out high-strength concrete pouring construction engineering method
CN114108561A (en) Plant-growing concrete slope protection and construction process thereof
CN114277815A (en) Geogrid reverse-wrapped modified expansive soil flexible ecological slope protection structure and construction method
CN114457846A (en) Road station main body structure construction method
CN107881986B (en) Solidified-formed plane interlocking three-dimensional buckling engineering building block and production method thereof
CN209942380U (en) Windproof dust suppression net structure system for bulk cargo storage yard
CN114481953B (en) Ecological slope protection without damaging integrity of hard slope protection of established embankment and construction method thereof
CN111577330A (en) Construction method for open channel section of large-section inclined shaft and high-strength combined template thereof
CN212561531U (en) Material taking platform structure of cofferdam back slope tower crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211022

RJ01 Rejection of invention patent application after publication