CN113505513A - Calculation method for stress concentration coefficient of rusted suspender - Google Patents

Calculation method for stress concentration coefficient of rusted suspender Download PDF

Info

Publication number
CN113505513A
CN113505513A CN202110847316.4A CN202110847316A CN113505513A CN 113505513 A CN113505513 A CN 113505513A CN 202110847316 A CN202110847316 A CN 202110847316A CN 113505513 A CN113505513 A CN 113505513A
Authority
CN
China
Prior art keywords
suspender
stress concentration
concentration coefficient
corrosion
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110847316.4A
Other languages
Chinese (zh)
Other versions
CN113505513B (en
Inventor
王�华
张子墨
杨涛
王龙林
王希瑞
于孟生
彭曦
蒋国富
黄凯楠
杨雨厚
何清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Jiaoke Group Co Ltd
Original Assignee
Guangxi Jiaoke Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Jiaoke Group Co Ltd filed Critical Guangxi Jiaoke Group Co Ltd
Priority to CN202110847316.4A priority Critical patent/CN113505513B/en
Publication of CN113505513A publication Critical patent/CN113505513A/en
Application granted granted Critical
Publication of CN113505513B publication Critical patent/CN113505513B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/14Force analysis or force optimisation, e.g. static or dynamic forces

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

The invention discloses a calculation method of a stress concentration coefficient of a rusted suspender, which considers the radius r of a rusted pit on the suspender, the depth D of the rusted pit and a functional relation between the diameter D of the suspender and the stress concentration coefficient K of the rusted suspender, obtains a plurality of groups of stress concentration data by establishing a model and calculating based on the model, fits the data and further obtains an expression of the stress concentration coefficient K of the rusted suspender. The expression can replace a finite element method to obtain the stress concentration coefficient of the corroded ball pit suspender, simplifies the calculation of the stress concentration coefficient of the corroded ball pit suspender, provides a quick method for the stress concentration coefficient of the corroded ball pit suspender in subsequent engineering, avoids the problem that the calculation by the finite element method is time-consuming and complicated, and saves time cost.

Description

Calculation method for stress concentration coefficient of rusted suspender
Technical Field
The invention relates to the field of bridge suspender corrosion, in particular to a calculation method for a stress concentration coefficient of a corroded suspender.
Background
The suspender plays an important role in various bridges as a key component of the bridge, and is an important stressed component in a tied arch bridge and a suspension bridge, so that the safety of the suspender is concerned with the safety of the whole bridge. However, as the service time increases, the hanger rod is often corroded under the combined action of the external environment and the fatigue load, and the corrosion phenomenon weakens the section of the hanger rod, so that the fatigue performance of the hanger rod is reduced, the fatigue life is shortened, and the safety of the hanger rod is seriously threatened. Therefore, in order to better judge the danger degree of the corrosion to the weakening of the cross section of the suspender, the stress concentration coefficient is introduced as an important index for judging the safety of the corrosion suspender structure. However, the traditional calculation of the stress concentration coefficient is mostly determined by theoretical gradual derivation or experiment by using a finite element method, which is too time-consuming and complex to be beneficial to the subsequent research on the corrosion of the bridge hanger rod. Therefore, it is necessary to provide a method for rapidly calculating the stress concentration coefficient of the rusty suspender.
Disclosure of Invention
In view of the foregoing, there is a need to provide a method for calculating a stress concentration coefficient of a rusty boom, so as to quickly and accurately calculate the stress concentration coefficient of the rusty boom, and the method has strong applicability.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
a calculation method of a stress concentration coefficient of a corrosion suspender considers a functional relation between the radius r of a corrosion pit on the suspender, the depth D of the corrosion pit and the diameter D of the suspender and the stress concentration coefficient K of the corrosion suspender, and the expression of the stress concentration coefficient K of the corrosion suspender is as follows:
Figure BDA0003173904480000011
further, the depth d of the rust pit ranges from 0< d <2 r.
For the above corrosion suspender stress concentration coefficient K expression, it is obtained by the following method: firstly, establishing a plurality of groups of corrosion suspender finite element models with different corrosion pit radiuses r, corrosion pit depths D and suspender diameters D by using an ANSYS (ANSYS) based on a finite element method; then, according to the existing research on the V-shaped groove of the rod, establishing the same V-shaped groove model by using ANSYS, calculating a stress concentration coefficient K, comparing the stress concentration coefficient K with the existing research data, verifying the reliability of the established ANSYS corrosion suspender model, and solving the corresponding stress concentration coefficient by using the established finite element model after verifying the reliability of the established model; and finally, fitting a functional relation among the radius r of the corrosion pit, the depth D of the corrosion pit, the diameter D of the suspender and the stress concentration coefficient K of the corrosion suspender according to a plurality of groups of data to obtain an expression of the stress concentration coefficient K of the corrosion suspender.
Therefore, compared with the prior art, the invention has the following beneficial effects:
1. aiming at the problem that the stress concentration coefficient of the existing corrosion suspender is difficult to obtain quickly and simply, the invention provides a functional relation formula, and the required stress concentration coefficient can be quickly calculated by simply measuring the diameter of the suspender, the radius of a corrosion pit and the depth. The formula can replace a finite element method to obtain the stress concentration coefficient of the corroded ball pit suspender, simplify the calculation of the stress concentration coefficient of the corroded ball pit suspender, provide a quick method for the stress concentration coefficient of the corroded ball pit suspender in subsequent engineering, avoid the problem that the calculation by the finite element method is time-consuming and complicated, and save time and cost.
2. The method is suitable for calculating the stress concentration coefficients of various rusted ball pit suspenders, and has the advantages of simple structure calculation, convenience in operation and high popularization value.
Drawings
FIG. 1 is a model of a hanger bar for ball pit corrosion, an overall grid division and an enlarged view of a portion of the corrosion pit;
FIG. 2 is a rod model of the same V-shaped groove as in the prior study, created using ANSYS;
FIG. 3 is a mesh division diagram of the created V-shaped groove rod model;
FIG. 4 is a plot of the fitted stress concentration versus the ANSYS finite element calculated stress concentration.
Detailed Description
The invention is further explained below with reference to the drawings and the embodiments.
Firstly, establishing a corrosion suspender model
1. Selecting the shape of the model rust pit: it has been studied to classify the shape of a steel bar corrosion pit into an open type and a deep and narrow type by observing the shape of the corrosion pit. Wherein, the shape of the open type corrosion pit is divided into a spherical crown type, a hemisphere and the like, so the corrosion pit can be simplified into a sphere-like corrosion pit. Another deep and narrow type corrosion pit shape includes a cone shape, a frustum shape, etc., and researchers (such as Pidaparti, etc.) have found that the cone-shaped corrosion pit gradually changes into a hemispherical corrosion pit with the increase of corrosion time. Therefore, according to the conclusion of the research, the hanger rod with the spherical rust pit is selected and established for experimental simulation.
2. A boom model with spherical rust was created with ANSYS: the model selects structural steel as a material, and the material characteristics are set, specifically, the density is 7800kg/m3Young's modulus of 3X 1011The Poisson's ratio was 0.3. The height of the suspender model is 12mm, the diameter of the suspender is D, and the center of the surface of the suspender is provided with a corrosion ball pit with the radius of r and the depth of D.
3. Grid division: and cutting the model, and cutting the model at the positions of 1mm above, below, left and right of the edge of the sphere of the hemispherical pit, wherein the whole part except the sphere pit part is divided by 0.2mm per unit in a sweeping way, and the sphere pit part is divided by 0.06mm per unit in a hexahedron way.
The above model and meshing are shown in fig. 1.
Secondly, verifying the reliability of the model
To ensure the reliability of the model, the calculation of the stress concentration coefficient of the V-shaped groove of the bar in the low-stress blanking [ J ] is based on the existing research on the V-shaped groove of the bar (Zhang Li Jun, Zhang De Bao, Zhou Tree En, Wang Xiao Qiang, Wang Han Xiang, Zhao Sheng ton, Liu Yong hong, Linjing school)]The plastic engineering journal (2018) 254-
Figure BDA0003173904480000031
60 degrees are taken, the depth q is taken as 1mm, the diameter of the rod model is taken as 15mm, the length of the rod is 40mm, and the V-shaped groove is positioned at the position of 5mm at the left end of the rod. Keeping the parameters unchanged, changing the radius rho of the bottom arc, and solving the stress concentration coefficient K. Grid division: the two sides of the V-shaped groove are divided at a position 1mm away from the center of the V-shaped groove, the rod model is divided into three parts, wherein the V-shaped groove part is mapped and divided in 0.3mm per unit, and the other two parts are swept and divided in 0.6mm per unit, as shown in figure 3. Operating the model and calculating to obtain the stress concentration coefficient K1The resulting stress concentration coefficient K is measured1And the actual stress concentration coefficient K obtained by the test in the prior research2For comparison, the results are shown in Table 1 below.
TABLE 1
ρ(mm) K1 K2 Error of the measurement
0.2 2.657 2.62 1.41%
0.3 2.252 2.27 0.799%
0.4 2.074 2.09 0.77%
0.5 1.829 1.81 1.05%
As can be seen from Table 1, the stress concentration coefficient K calculated by ANSYS in the present application1Within the tolerance of 8.4% allowed by the prior studies described above, the models created by the present invention are considered to be substantially identical, i.e., the corrosion models created by the present invention using ANSYS are proven to be reliable.
And thirdly, fitting a functional relation among the radius r of the corrosion pit, the depth D of the corrosion pit, the diameter D of the suspender and the stress concentration coefficient K of the corrosion suspender.
Selecting a plurality of groups of rusted ball pits and hanging rods with different sizes, and calculating the corresponding stress concentration coefficient by using the established finite element model, which is specifically shown in the following table 2.
TABLE 2 stress concentration coefficients corresponding to the sizes of multiple groups of rusty ball pits and the sizes of suspenders
Figure BDA0003173904480000041
Figure BDA0003173904480000051
Based on the correlation study (mavialong; study on mechanical properties of uneven corrosion paired arch bridge hanger bar [ D ]; Chongqing traffic university; 2016), it was found that the stress concentration coefficient and the size of the corrosion pit, and the stress concentration coefficient and the size of the hanger bar have a mutual relationship between each other, and therefore, the stress concentration coefficient can be represented by the size of the corrosion pit and the size of the hanger bar. Then, according to the data in table 2 above, the formula K fitted with 1stOpt is (r, D) as follows:
Figure BDA0003173904480000052
in summary, the calculation method of the stress concentration coefficient of the corrosion suspender provided by the invention considers the radius r of the corrosion pit on the suspender, the depth D of the corrosion pit and a functional relation between the diameter D of the suspender and the stress concentration coefficient K of the corrosion suspender, so as to obtain the stress concentration coefficient K expression of the corrosion suspender as follows:
Figure BDA0003173904480000053
the depth d of the rust pit is set in a range of 0< d <2 r.
In addition, in order to verify the calculation accuracy of the corrosion suspender stress concentration coefficient K expression provided by the invention, the invention compares and analyzes the value of the corrosion suspender stress concentration coefficient K obtained by solving through a finite element method and the value of the corrosion suspender stress concentration coefficient K' obtained by calculating through the expression provided by the invention, the comparison data is shown in a table 3, and the data in the table 3 is drawn into a broken line diagram, particularly shown in a figure 4.
TABLE 3 comparison data of stress concentration coefficient calculated by the present invention and that calculated by ANSYS finite element
Figure BDA0003173904480000061
Figure BDA0003173904480000071
Based on the above table 3, it can be seen that the value of the stress concentration coefficient K of the corrosion boom calculated by the finite element method and the value of the stress concentration coefficient K' of the corrosion boom calculated by the expression given by the present invention are very close, the error is 4.01% at the maximum, and within the allowable error range of the research, the expression of the stress concentration coefficient K of the corrosion boom given by the present invention is considered to be accurate, and the present invention can be applied to practical engineering.
The above description is intended to describe in detail the preferred embodiments of the present invention, but the embodiments are not intended to limit the scope of the claims of the present invention, and all equivalent changes and modifications made within the technical spirit of the present invention should fall within the scope of the claims of the present invention.

Claims (2)

1. A calculation method of the stress concentration coefficient of a corrosion suspender is characterized by comprising the following steps: considering the radius r of a corrosion pit on the suspender, the depth D of the corrosion pit and a functional relation between the diameter D of the suspender and the stress concentration coefficient K of the corrosion suspender, the expression of the stress concentration coefficient K of the corrosion suspender is as follows:
Figure FDA0003173904470000011
2. the method for calculating the stress concentration coefficient of the rusty suspender as claimed in claim 1, wherein: the depth d of the corrosion pit ranges from 0< d <2 r.
CN202110847316.4A 2021-07-21 2021-07-21 Calculation method for stress concentration coefficient of rusted suspender Active CN113505513B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110847316.4A CN113505513B (en) 2021-07-21 2021-07-21 Calculation method for stress concentration coefficient of rusted suspender

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110847316.4A CN113505513B (en) 2021-07-21 2021-07-21 Calculation method for stress concentration coefficient of rusted suspender

Publications (2)

Publication Number Publication Date
CN113505513A true CN113505513A (en) 2021-10-15
CN113505513B CN113505513B (en) 2022-06-07

Family

ID=78014585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110847316.4A Active CN113505513B (en) 2021-07-21 2021-07-21 Calculation method for stress concentration coefficient of rusted suspender

Country Status (1)

Country Link
CN (1) CN113505513B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107545099A (en) * 2017-07-31 2018-01-05 上海大学 A kind of fast appraisement method of the lower tool joint Amplification effect of complex load effect
CN206887683U (en) * 2017-02-16 2018-01-16 华南理工大学 A kind of rectangle composite dowel bar for cement concrete pavement
CN108804783A (en) * 2018-05-25 2018-11-13 南昌航空大学 A kind of assessment method of blank initial residual stress
CN109614678A (en) * 2018-11-30 2019-04-12 南京航空航天大学 The method for scratching defect bottom stress coefficient of concentration for calculating alloy surface
CN110020497A (en) * 2019-04-18 2019-07-16 长沙理工大学 Treatment rates hoist cable fatigue life probability evaluation method of failure
CN110987389A (en) * 2019-11-27 2020-04-10 南京航空航天大学 Foreign object damage notch calibration method with stress concentration coefficient not less than 3
CN111625985A (en) * 2020-06-01 2020-09-04 中国人民解放军海军航空大学青岛校区 Fatigue notch coefficient data processing method considering corrosion and residual stress
US20210199560A1 (en) * 2018-08-27 2021-07-01 Changsha University Of Science & Technology Method and system for predicting corrosion fatigue life of prestressed concrete bridges

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206887683U (en) * 2017-02-16 2018-01-16 华南理工大学 A kind of rectangle composite dowel bar for cement concrete pavement
CN107545099A (en) * 2017-07-31 2018-01-05 上海大学 A kind of fast appraisement method of the lower tool joint Amplification effect of complex load effect
CN108804783A (en) * 2018-05-25 2018-11-13 南昌航空大学 A kind of assessment method of blank initial residual stress
US20210199560A1 (en) * 2018-08-27 2021-07-01 Changsha University Of Science & Technology Method and system for predicting corrosion fatigue life of prestressed concrete bridges
CN109614678A (en) * 2018-11-30 2019-04-12 南京航空航天大学 The method for scratching defect bottom stress coefficient of concentration for calculating alloy surface
CN110020497A (en) * 2019-04-18 2019-07-16 长沙理工大学 Treatment rates hoist cable fatigue life probability evaluation method of failure
CN110987389A (en) * 2019-11-27 2020-04-10 南京航空航天大学 Foreign object damage notch calibration method with stress concentration coefficient not less than 3
CN111625985A (en) * 2020-06-01 2020-09-04 中国人民解放军海军航空大学青岛校区 Fatigue notch coefficient data processing method considering corrosion and residual stress

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
GUODONG WANG ET AL.: "Experimental study and residual fatigue life assessment of corroded high-tensile steel wires using 3D scanning technology", 《ENGINEERING FAILURE ANALYSIS》 *
LI,R ET AL.: "Effect of characteristic parameters of pitting on strength and stress concentration factor of cable steel wire", 《CONSTRUCTION AND BUILDING MATERIALS》 *
YIFEI YAN ET AL.: "A study on the influence of double ellipsoidal pitting corrosion on the collapsing strength of the casing", 《ENGINEERING FAILURE ANALYSIS》 *
凡林: "拱桥吊杆钢丝疲劳寿命分析的跨尺度方法", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》 *
楼纪昂等: "不均匀锈蚀对高强钢丝应力集中影响的研究", 《建筑科学》 *

Also Published As

Publication number Publication date
CN113505513B (en) 2022-06-07

Similar Documents

Publication Publication Date Title
CN110020497B (en) Method for evaluating fatigue life probability of suspension cable of service bridge
Ham et al. Forming limit curves in single point incremental forming
WO2017008356A1 (en) Oscillation start-up wind speed evaluation method and type selection method for composite insulator
CN106294984B (en) A method of Rock Damage threshold is determined based on micro-mechanical model growth rate
CN108763839B (en) A kind of centrifugal impeller boss crack propagation characteristic simulation part design method
CN113505513B (en) Calculation method for stress concentration coefficient of rusted suspender
CN109813612A (en) A kind of test method of oil well pipe anti-H 2 S stress corrosion performance
CN112784347B (en) Cable-stayed bridge cable force reliability evaluation method based on bridge tower deformation and considering cable breakage
CN107180123B (en) A kind of high strength steel submersible pressurized spherical shell ultimate bearing capacity evaluation method
CN114564868A (en) Anchor chain fatigue life prediction method
CN113505427B (en) Method for calculating stress concentration coefficient of suspender with upper and lower rusted ball pits
CN108090263B (en) Verification method for pneumatic damping of deicing vibration scale test of power transmission line
CN108595794A (en) A kind of pipeline structure oscillating load analysis method
CN109580464B (en) Method for detecting and evaluating coating quality of power grid equipment
CN111651942A (en) Spring air hole sleeve structure performance analysis method
CN103267987B (en) Monsoon vortex localization method
CN111721647B (en) Low-cycle fatigue test data processing and internal stress evaluation method
CN115936257A (en) Lead crimping key parameter optimization method
CN107066728A (en) A kind of titanium alloy submersible pressurized spherical shell ultimate bearing capacity evaluation method
CN105466844A (en) Aluminum lithium alloy corrosion resistance evaluation method
CN216484427U (en) Test device for generating cracks by impacting concrete
CN107729654B (en) Method for determining corresponding relation between maximum value of wind drift tension of wire and wind speed
Pan et al. Material plastic properties characterization using a generic algorithm and finite element method modelling of the plane-strain small punch test
CN112598219A (en) Transmission tower structure damage assessment method and system
CN111122357A (en) Method for testing fatigue life of aluminum alloy conductor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant