CN113486417B - 一种控制主塔和钢梁施工仿真系统 - Google Patents
一种控制主塔和钢梁施工仿真系统 Download PDFInfo
- Publication number
- CN113486417B CN113486417B CN202110595749.5A CN202110595749A CN113486417B CN 113486417 B CN113486417 B CN 113486417B CN 202110595749 A CN202110595749 A CN 202110595749A CN 113486417 B CN113486417 B CN 113486417B
- Authority
- CN
- China
- Prior art keywords
- simulation
- bridge
- construction
- simulated
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004088 simulation Methods 0.000 title claims abstract description 290
- 238000010276 construction Methods 0.000 title claims abstract description 193
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 103
- 239000010959 steel Substances 0.000 title claims abstract description 103
- 238000012544 monitoring process Methods 0.000 claims abstract description 78
- 238000012360 testing method Methods 0.000 claims abstract description 35
- 238000007405 data analysis Methods 0.000 claims abstract description 18
- 238000005516 engineering process Methods 0.000 claims abstract description 10
- 238000006243 chemical reaction Methods 0.000 claims abstract description 9
- 238000004458 analytical method Methods 0.000 claims abstract description 7
- 238000000034 method Methods 0.000 claims description 45
- 238000012545 processing Methods 0.000 claims description 41
- 230000007246 mechanism Effects 0.000 claims description 36
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 35
- 239000007788 liquid Substances 0.000 claims description 33
- 230000008569 process Effects 0.000 claims description 29
- 239000000463 material Substances 0.000 claims description 27
- 239000004567 concrete Substances 0.000 claims description 25
- 238000013461 design Methods 0.000 claims description 17
- 239000002994 raw material Substances 0.000 claims description 5
- 230000007613 environmental effect Effects 0.000 claims description 3
- 230000009467 reduction Effects 0.000 claims description 3
- 238000003860 storage Methods 0.000 claims description 3
- 238000011056 performance test Methods 0.000 abstract description 4
- 238000007599 discharging Methods 0.000 description 12
- 238000006073 displacement reaction Methods 0.000 description 9
- 229910001220 stainless steel Inorganic materials 0.000 description 9
- 239000010935 stainless steel Substances 0.000 description 9
- 239000000725 suspension Substances 0.000 description 8
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 7
- 238000004364 calculation method Methods 0.000 description 6
- 239000011150 reinforced concrete Substances 0.000 description 6
- 230000005540 biological transmission Effects 0.000 description 5
- 230000006870 function Effects 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 239000011148 porous material Substances 0.000 description 3
- 238000004078 waterproofing Methods 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 230000002159 abnormal effect Effects 0.000 description 2
- 238000005452 bending Methods 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000000605 extraction Methods 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 238000005096 rolling process Methods 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- 238000012549 training Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 239000002360 explosive Substances 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 239000002861 polymer material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
- G06F30/23—Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Civil Engineering (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Architecture (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110595749.5A CN113486417B (zh) | 2021-05-29 | 2021-05-29 | 一种控制主塔和钢梁施工仿真系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110595749.5A CN113486417B (zh) | 2021-05-29 | 2021-05-29 | 一种控制主塔和钢梁施工仿真系统 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113486417A CN113486417A (zh) | 2021-10-08 |
CN113486417B true CN113486417B (zh) | 2024-01-19 |
Family
ID=77933289
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110595749.5A Active CN113486417B (zh) | 2021-05-29 | 2021-05-29 | 一种控制主塔和钢梁施工仿真系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113486417B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114770977B (zh) * | 2022-06-17 | 2022-10-25 | 成都飞机工业(集团)有限责任公司 | 一种自动铺丝工装的设计方法、装置、设备及存储介质 |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20080046897A (ko) * | 2006-11-23 | 2008-05-28 | 연세대학교 산학협력단 | 강교량의 정보 제공 및 가공 방법 |
WO2009158559A1 (en) * | 2008-06-26 | 2009-12-30 | Siemens Product Lifecycle Management Software Inc. | System and method for constructing virtual nc controllers for machine tool simulation |
CN101798848A (zh) * | 2010-03-05 | 2010-08-11 | 北京纽曼帝莱蒙膜建筑技术有限公司 | 使用机械运动模拟模型动态模拟张拉结构施工的方法 |
CN102880769A (zh) * | 2012-10-23 | 2013-01-16 | 上海建工集团股份有限公司 | 大跨径混凝土斜拉桥的施工控制方法与预拱度计算方法 |
CN106097819A (zh) * | 2016-07-31 | 2016-11-09 | 重庆交通大学 | 用于实验教学的桥梁仿真检测方法及系统 |
CN107220464A (zh) * | 2017-06-28 | 2017-09-29 | 中国十七冶集团有限公司 | 一种基于bim的桥梁施工过程仿真及风险控制方法 |
WO2019074139A1 (ko) * | 2017-10-12 | 2019-04-18 | (주)태성에스엔아이 | 가상 건설 현장에서의 시뮬레이션 실행 방법 및 이에 사용되는 관리 서버 |
CN109783851A (zh) * | 2018-12-10 | 2019-05-21 | 中国铁路设计集团有限公司 | 基于3dgis和bim技术的铁路系杆拱桥施工仿真系统和方法 |
CN109948222A (zh) * | 2019-03-12 | 2019-06-28 | 北京工业大学 | 一种将建筑工程项目隐蔽信息显性化的方法 |
CN111335186A (zh) * | 2020-03-05 | 2020-06-26 | 青岛理工大学 | 转体桥梁安全监测预警方法、系统、存储介质、预警平台 |
CN111625971A (zh) * | 2020-03-06 | 2020-09-04 | 中国十七冶集团有限公司 | 一种装配式混凝土桥梁预制构件拼装方法 |
CN111733787A (zh) * | 2020-05-14 | 2020-10-02 | 中电建路桥集团有限公司 | 桥梁桩基施工过程中溶洞处理效果检测方法及系统 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2017239878B2 (en) * | 2016-03-30 | 2019-11-07 | Komatsu Ltd. | Simulation system and simulation method |
KR101938352B1 (ko) * | 2018-04-30 | 2019-01-14 | 김도빈 | 상시진동실험 데이터로 교량의 강성계수의 산출이 가능한 것을 특징으로 하는 교량의 강성계수 산출 방법 및 프로그램 |
-
2021
- 2021-05-29 CN CN202110595749.5A patent/CN113486417B/zh active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20080046897A (ko) * | 2006-11-23 | 2008-05-28 | 연세대학교 산학협력단 | 강교량의 정보 제공 및 가공 방법 |
WO2009158559A1 (en) * | 2008-06-26 | 2009-12-30 | Siemens Product Lifecycle Management Software Inc. | System and method for constructing virtual nc controllers for machine tool simulation |
CN101798848A (zh) * | 2010-03-05 | 2010-08-11 | 北京纽曼帝莱蒙膜建筑技术有限公司 | 使用机械运动模拟模型动态模拟张拉结构施工的方法 |
CN102880769A (zh) * | 2012-10-23 | 2013-01-16 | 上海建工集团股份有限公司 | 大跨径混凝土斜拉桥的施工控制方法与预拱度计算方法 |
CN106097819A (zh) * | 2016-07-31 | 2016-11-09 | 重庆交通大学 | 用于实验教学的桥梁仿真检测方法及系统 |
CN107220464A (zh) * | 2017-06-28 | 2017-09-29 | 中国十七冶集团有限公司 | 一种基于bim的桥梁施工过程仿真及风险控制方法 |
WO2019074139A1 (ko) * | 2017-10-12 | 2019-04-18 | (주)태성에스엔아이 | 가상 건설 현장에서의 시뮬레이션 실행 방법 및 이에 사용되는 관리 서버 |
CN109783851A (zh) * | 2018-12-10 | 2019-05-21 | 中国铁路设计集团有限公司 | 基于3dgis和bim技术的铁路系杆拱桥施工仿真系统和方法 |
CN109948222A (zh) * | 2019-03-12 | 2019-06-28 | 北京工业大学 | 一种将建筑工程项目隐蔽信息显性化的方法 |
CN111335186A (zh) * | 2020-03-05 | 2020-06-26 | 青岛理工大学 | 转体桥梁安全监测预警方法、系统、存储介质、预警平台 |
CN111625971A (zh) * | 2020-03-06 | 2020-09-04 | 中国十七冶集团有限公司 | 一种装配式混凝土桥梁预制构件拼装方法 |
CN111733787A (zh) * | 2020-05-14 | 2020-10-02 | 中电建路桥集团有限公司 | 桥梁桩基施工过程中溶洞处理效果检测方法及系统 |
Non-Patent Citations (3)
Title |
---|
"支架施工斜拉桥体系转换方案的优选与施工控制";刘海宽等;《筑路机械与施工机械化》(第5期);第119-124页 * |
"混合梁斜拉桥合理成桥状态确定方法研究";张谢东等;《武汉理工大学学报(交通科学与工程版)》;第39卷(第5期);第920-924页 * |
"独塔空间扭索面-全漂浮体系斜拉桥桥塔施工控制研究";郭锋;《山西交通科技》(03);第49-52页 * |
Also Published As
Publication number | Publication date |
---|---|
CN113486417A (zh) | 2021-10-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631519B (zh) | 复杂荷载作用下桩基承载特性模型试验装置及试验方法 | |
JP6454793B2 (ja) | 健全度判定装置、健全度判定方法および健全度判定プログラム | |
CN102787676B (zh) | 工程结构多目标性能化抗震设计方法 | |
CN103033385B (zh) | 一种自平衡便携式自动控制剪力墙水平竖向荷载共同作用性能试验装置及方法 | |
CN113776965B (zh) | 一种载荷作用下涵洞土拱变化规律的模拟试验装置及方法 | |
CN109991092B (zh) | 变幅荷载下构件的自然暴露实验装置、系统及方法 | |
CN113486417B (zh) | 一种控制主塔和钢梁施工仿真系统 | |
CN105004506A (zh) | 自升式海洋平台桩腿波流载荷系数测试实验系统 | |
WO2023151235A1 (zh) | 一种悬浮隧道完全水弹性响应模型试验装置及方法 | |
CN104713673A (zh) | 基于扩展卡尔曼滤波器的拉索时变索力历程识别方法 | |
CN112962686A (zh) | 一种用于吸力锚出平面测试的离心机加载装置 | |
Chen et al. | Modal parameter identification of a multiple-span post-tensioned concrete bridge using hybrid vibration testing data | |
Bairrao et al. | Shaking table testing of civil engineering structures-The LNEC 3D simulator experience | |
CN110889245B (zh) | 水力式升船机塔柱结构耦联体系流固耦合地震动响应分析方法 | |
CN212427270U (zh) | 模拟土体位移边界条件的被动桩试验装置 | |
CN111175068B (zh) | 一种用于斜拉桥典型损伤模拟装置的方法 | |
Barbosa et al. | The Viana footbridge: construction and dynamic monitoring | |
CN109440843B (zh) | 一种模型桩室内试验组合荷载施加装置及方法 | |
Liu et al. | Pushover analysis of Daikai subway station during the Osaka-Kobe earthquake in 1995 | |
Pipinato | Coupled safety assessment of cable stay bridges | |
CN212321037U (zh) | 大跨连续钢箱梁桥超大比例气弹模型自然风场涡振试验装置 | |
CN115753376A (zh) | 一种多场景模拟微型桩加固模型试验装置 | |
CN113970454A (zh) | 一种连续刚构桥基础异位扭转荷载模型装置及试验方法 | |
CN110132532B (zh) | 一种张力腿网箱模型试验装置 | |
Pan et al. | Behaviour and design of three-tower, self-anchored suspension bridge with a concrete girder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 100160 Nord tower 1, 128 South Fourth Ring Road West, Fengtai District, Beijing. Applicant after: China Railway Construction Engineering Group Applicant after: China Railway Construction Group No.2 Construction Co.,Ltd. Address before: 100160 Nord tower 1, 128 South Fourth Ring Road West, Fengtai District, Beijing. Applicant before: China Railway Construction Engineering Group Applicant before: CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP SHANDONG Co.,Ltd. |
|
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Zhao Mingyan Inventor after: Zang Guozhi Inventor after: Gao Yong Inventor after: Meng Yang Inventor after: Zhang Ziming Inventor after: Chen Lin Inventor after: Zhang Hongyong Inventor after: Zhao Yanbin Inventor after: Zhang He Inventor after: Shan Hongyi Inventor after: Wang Jun Inventor after: Yan Tingda Inventor before: Li Chunyu Inventor before: Zhang Hongyong Inventor before: Meng Yang Inventor before: Zhao Mingyan Inventor before: Chen Lin Inventor before: Gu Chunmao Inventor before: Wang Jun Inventor before: Yan Tingda Inventor before: Gao Yong Inventor before: Zhang He Inventor before: Zhao Yanbin |
|
GR01 | Patent grant | ||