CN113482034B - A correction method for uneven settlement of transmission towers - Google Patents
A correction method for uneven settlement of transmission towers Download PDFInfo
- Publication number
- CN113482034B CN113482034B CN202110699524.4A CN202110699524A CN113482034B CN 113482034 B CN113482034 B CN 113482034B CN 202110699524 A CN202110699524 A CN 202110699524A CN 113482034 B CN113482034 B CN 113482034B
- Authority
- CN
- China
- Prior art keywords
- inverted
- jacking
- nut
- jack
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2207—Sockets or holders for poles or posts not used
- E04H12/2215—Sockets or holders for poles or posts not used driven into the ground
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2207—Sockets or holders for poles or posts not used
- E04H12/2215—Sockets or holders for poles or posts not used driven into the ground
- E04H12/223—Sockets or holders for poles or posts not used driven into the ground with movable anchoring elements; with separately driven anchor rods
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
一种输电铁塔不均匀沉降的纠偏方法,步骤一:利用井字形倒梁和连梁加固铁塔独立基础;步骤二:开设顶升孔道和锚固孔道;在井字形倒梁的四个开口端的每个端部均开设顶升孔道,并在每根连梁长度方向的两端部均开设锚固孔道;步骤三:安装顶升螺杆和锚杆;在每个顶升孔道中均插装一根顶升螺杆,并使其下端与预埋在地基倒梁中的连接件固定连接;在顶升螺杆的下部安装顶升螺母;在每个锚固孔道中均插装一根锚杆,并使锚杆的下端锚固于地基倒梁中;在锚杆的上部分别套设有垫片和锚杆螺母;步骤四:安放千斤顶并进行调平作业;在井字形倒梁的端部和地基倒梁之间的部分支设千斤顶,通过千斤顶进行纠偏调节。该方法可实现对倾斜的输电铁塔进行快速调整。
A method for rectifying uneven settlement of a power transmission tower, step 1: using a well-shaped inverted beam and a connecting beam to reinforce the independent foundation of the iron tower; step 2: opening a jacking tunnel and an anchor tunnel; Jacking holes are set up, and anchoring holes are set at both ends of each connecting beam in the length direction; Step 3: Install jacking screws and anchor rods; insert a jacking screw in each jacking hole, And make its lower end fixedly connected with the connector embedded in the foundation inverted beam; install jacking nuts on the lower part of the jacking screw; insert an anchor rod in each anchoring hole, and anchor the lower end of the anchor rod In the foundation inverted beam; the upper part of the anchor rod is respectively sleeved with gaskets and anchor bolt nuts; step 4: place the jack and perform leveling operations; the part between the end of the well-shaped inverted beam and the foundation inverted beam Set a jack, and adjust the deviation through the jack. This method can realize the quick adjustment of the inclined transmission tower.
Description
技术领域technical field
本发明涉及输电铁塔的纠偏技术领域,具体涉及一种输电铁塔不均匀沉降的纠偏方法。The invention relates to the technical field of deflection correction of electric transmission towers, in particular to a deflection correction method for uneven settlement of electric transmission towers.
背景技术Background technique
部分区域由于水土流失严重,导致地表变形、开裂、沉陷等问题频发,进而容易造成区域内输电线路铁塔基础的不均匀沉降,这样,会导致铁塔出现倾斜、位移和变形的情况,严重的会导致铁塔内部的应力发生变化,进而会威胁线路的安全。Due to serious water and soil erosion in some areas, problems such as surface deformation, cracking, and subsidence occur frequently, which can easily cause uneven settlement of the tower foundation of the transmission line in the area, which will lead to inclination, displacement, and deformation of the iron tower. As a result, the stress inside the tower changes, which in turn threatens the safety of the line.
对于正常运行的输电线路,常见的处理方法主要有两种:一种是异地改造,即在既有线路的附近重新选线,再次新建一座铁塔进行替换;另一种是对发生倾斜的铁塔进行纠偏处理。考虑到铁塔停电施工带来的经济社会影响,以及铁塔结构所受纠偏荷载的影响,采用输电铁塔不均匀的纠偏方法能够有效实现沉降纠偏功能,这种方法不仅能节省成本,还能提高铁塔的安全性和稳定性,对输电线路的安全运行具有重要的意义。For transmission lines in normal operation, there are two common treatment methods: one is off-site transformation, that is, re-selecting the line near the existing line, and building a new iron tower to replace it; the other is to repair the tilted iron tower. Corrective processing. Considering the economic and social impact caused by the power outage construction of the iron tower, as well as the influence of the correction load on the tower structure, the uneven correction method of the transmission tower can effectively realize the settlement correction function. This method can not only save costs, but also improve the tower Safety and stability are of great significance to the safe operation of transmission lines.
发明内容Contents of the invention
针对上述现有技术存在的问题,本发明提供一种输电铁塔不均匀沉降的纠偏方法,该方法步骤简单、实施成本低,能解决输电铁塔基础发生不均匀沉降后纠编的问题,可实现对倾斜的输电铁塔进行快速调整,能有效确保输电线路的安全运行。Aiming at the problems existing in the above-mentioned prior art, the present invention provides a method for rectifying the uneven settlement of the transmission iron tower. The quick adjustment of the inclined transmission tower can effectively ensure the safe operation of the transmission line.
为了实现上述目的,本发明提供一种输电铁塔不均匀沉降的纠偏方法,包括具有四个铁塔独立基础的输电铁塔,四个铁塔独立基础分布于口字形的四角处,还包括以下步骤:In order to achieve the above object, the present invention provides a method for rectifying the uneven settlement of the power transmission tower, including the power transmission tower with four independent foundations of the iron towers, the four independent foundations of the iron towers are distributed at the four corners of the square shape, and also includes the following steps:
步骤一:加固铁塔独立基础;Step 1: Strengthen the independent foundation of the iron tower;
先在四个铁塔独立基础的上方安装井字形倒梁,并使井字形倒梁的四个交点处对应固定连接在四个铁塔独立基础的上端,将四个铁塔独立基础连成一个开放式的整体;再在井字形倒梁的四个开口端之间分别采用四根连梁进行固定连接,形成闭合式的整体;Install the well-shaped inverted beams on the top of the independent foundations of the four iron towers first, and make the four intersections of the inverted beams correspondingly fixedly connected to the upper ends of the independent foundations of the four iron towers, and connect the four independent foundations of the iron towers into an open Integral; then four connecting beams are fixedly connected between the four open ends of the well-shaped inverted beams to form a closed whole;
步骤二:开设顶升孔道和锚固孔道;Step 2: Open jacking tunnels and anchor tunnels;
在井字形倒梁的四个开口端的每个端部均开设纵向贯通的顶升孔道,并在每根连梁长度方向的两端部均开设有纵向贯通的锚固孔道;Each of the four open ends of the well-shaped inverted beam is provided with a longitudinally penetrating jacking channel, and each end of the length direction of each connecting beam is provided with a longitudinally penetrating anchoring channel;
步骤三:安装顶升螺杆和锚杆;Step 3: Install the jacking screw and anchor;
在每个顶升孔道中均插装一根顶升螺杆,并使顶升螺杆的上端延伸到井字形倒梁上端面的上方,使顶升螺杆的下端延伸到地基倒梁的上端,并与预埋在地基倒梁中的连接件固定连接;同时,在顶升螺杆的下部通过螺纹配合安装顶升螺母,并使顶升螺母的上端与井字形倒梁的下端面相抵接;A jacking screw is inserted in each jacking hole, and the upper end of the jacking screw extends above the upper end surface of the well-shaped inverted beam, and the lower end of the jacking screw extends to the upper end of the foundation inverted beam, and is connected with the upper end of the foundation inverted beam. The connectors pre-buried in the foundation inverted beam are fixedly connected; at the same time, the jacking nut is installed on the lower part of the jacking screw through thread fit, and the upper end of the jacking nut is abutted against the lower end surface of the well-shaped inverted beam;
在每个锚固孔道中均插装一根锚杆,并使锚杆的上端延伸到连梁上端面的上方,使锚杆的下端延伸到地基倒梁的内部,并锚固于地基倒梁中;同时,在锚杆的上部分别套设有垫片和锚杆螺母,且垫片通过锚杆螺母的作用抵接在连梁的上端面;An anchor rod is inserted in each anchor hole, and the upper end of the anchor rod extends above the upper end surface of the connecting beam, and the lower end of the anchor rod extends to the inside of the foundation inverted beam, and is anchored in the foundation inverted beam; At the same time, a gasket and an anchor nut are sleeved on the upper part of the anchor rod, and the gasket abuts against the upper end surface of the connecting beam through the action of the anchor nut;
步骤四:安放千斤顶并进行调平作业;Step 4: Place the jack and perform leveling operations;
在井字形倒梁的端部和地基倒梁之间的部分支设千斤顶,且使千斤顶位于倾斜状态下位置较低的一侧,利用千斤顶顶升提供向上的作用反力,提升井字形倒梁的一侧,以通过调节井字形倒梁倾斜度来对输电铁塔进行纠偏;在千斤顶顶升过程中,向上调节并锁紧位置较低一侧的顶升螺母,并利用顶升螺母对井字形倒梁的下端面进行高度定位支撑,同时,向下调节并锁紧位置较高一侧的锚杆螺母,并通过垫片将连梁的上端面向下压紧并锚固,以利用位置较低一侧的顶升螺母和位置较高一侧的锚杆螺母的相互作用对输电铁塔进行快速有效的纠偏和加固,直至输电铁塔达到水平的状态。A jack is supported at the end of the well-shaped inverted beam and the part between the foundation inverted beam, and the jack is located on the lower side in the inclined state, and the upward reaction force is provided by the jack to lift the well-shaped inverted beam. to correct the deviation of the transmission tower by adjusting the inclination of the well-shaped inverted beam; during the lifting process of the jack, adjust upward and lock the jacking nut on the lower side, and use the jacking nut to align the well-shaped beam. The lower end surface of the inverted beam is used for height positioning and support. At the same time, the anchor nut on the higher side is adjusted downward and locked, and the upper end surface of the connecting beam is pressed down and anchored through the gasket to take advantage of the lower position. The interaction between the jacking nut on the side and the anchor nut on the higher side can quickly and effectively correct and reinforce the transmission tower until the transmission tower reaches a horizontal state.
作业种优选,在步骤三中,所述连接件由预埋在地基倒梁中的预埋螺杆和固定连接在预埋螺杆上端的法兰组成。Preferably, in
作业种优选,在步骤三中,所述预埋螺杆与顶升螺杆同轴的设置。Preferably, in
进一步,为了能实现对井字形倒梁进行有效的位置锁定,在步骤四中,在输电铁塔达到水平状态后,在每根顶升螺杆的上部通过螺纹配合安装锁紧螺母,拧紧并使锁紧螺母抵接在井字形倒梁的上端面上。Further, in order to achieve effective position locking of the well-shaped inverted beam, in
进一步,为了实现稳定可靠的连接,同时,也能方便拆卸维护,所述法兰呈环形,其中心开设有与顶升螺杆相配合的安装孔,其上环绕安装孔的开设有多个定位通孔,所述预埋螺杆的螺帽上对应多个定位通孔的开设有多个定位盲孔,法兰和预埋螺杆通过穿设于定位通孔和定位盲孔中的连接螺栓进行固定连接。Further, in order to achieve a stable and reliable connection, and at the same time facilitate disassembly and maintenance, the flange is in the shape of a ring, and a mounting hole matching the jacking screw is opened in the center, and a plurality of positioning channels are opened around the mounting hole. hole, the nut of the embedded screw rod is provided with a plurality of positioning blind holes corresponding to a plurality of positioning through holes, and the flange and the embedded screw rod are fixedly connected through the connecting bolts that pass through the positioning through holes and the positioning blind holes. .
本发明中的方法操作简单,施工过程方便,且经济成本低,实用性强。该方法在纠偏的同时,在不破坏原有基础结构的情况下还能对基础结构进行加固处理,且施工过程中无冲击纠偏荷载或冲击很小,整个过程操作灵活,能使基础的加固和纠偏调节过程更加安全可靠。同时,能提高原有输电铁塔的安全性和稳定性。The method in the invention has simple operation, convenient construction process, low economic cost and strong practicability. This method can also reinforce the foundation structure without destroying the original foundation structure while correcting the deviation, and there is no impact correction load or small impact during the construction process. The deviation correction adjustment process is safer and more reliable. At the same time, the safety and stability of the original transmission tower can be improved.
附图说明Description of drawings
图1是本发明的结构示意图;Fig. 1 is a structural representation of the present invention;
图2是图1的A-A向剖视图;Fig. 2 is the A-A direction sectional view of Fig. 1;
图3是本发明中法兰的结构示意图;Fig. 3 is the structural representation of flange among the present invention;
图4是本发明中预埋螺栓的结构示意图。Fig. 4 is a structural schematic diagram of the embedded bolt in the present invention.
图中:1、铁塔独立基础,2、井字形倒梁,3、连梁,4、地基倒梁,5、顶升螺杆,6、顶升螺母,7、法兰,8、预埋螺杆,9、锚杆,10、锚杆螺母,11、垫片,12、千斤顶,13、顶升孔道,14、锚固孔道,15、锁紧螺母,16、安装孔,17、定位通孔,18、定位盲孔。In the figure: 1. Independent foundation of the iron tower, 2. Well-shaped inverted beam, 3. Connecting beam, 4. Foundation inverted beam, 5. Jacking screw, 6. Jacking nut, 7. Flange, 8. Embedded screw, 9, anchor rod, 10, anchor rod nut, 11, gasket, 12, jack, 13, jacking tunnel, 14, anchor tunnel, 15, lock nut, 16, installation hole, 17, positioning through hole, 18, Locate blind holes.
具体实施方式Detailed ways
下面结合附图对本发明作进一步说明。The present invention will be further described below in conjunction with accompanying drawing.
如图1至图4所示,一种输电铁塔不均匀沉降的纠偏方法,包括具有四个铁塔独立基础1的输电铁塔,四个铁塔独立基础1分布于口字形的四角处,还包括以下步骤:As shown in Figures 1 to 4, a method for correcting uneven settlement of a power transmission tower includes a power transmission tower with four
步骤一:加固铁塔独立基础1;Step 1: Strengthen the independent foundation of the
先在四个铁塔独立基础1的上方安装井字形倒梁2,并使井字形倒梁2的四个交点处对应固定连接在四个铁塔独立基础1的上端,将四个铁塔独立基础1连成一个开放式的整体;再在井字形倒梁2的四个开口端之间分别采用四根连梁3进行固定连接,形成闭合式的整体;Install the well-shaped inverted
步骤二:开设顶升孔道13和锚固孔道14;Step 2: setting up the
在井字形倒梁2的四个开口端的每个端部均开设纵向贯通的顶升孔道13,并在每根连梁3长度方向的两端部均开设有纵向贯通的锚固孔道14;Each of the four open ends of the well-shaped inverted
步骤三:安装顶升螺杆5和锚杆9;Step 3: Install
在每个顶升孔道13中均插装一根顶升螺杆5,并使顶升螺杆5的上端延伸到井字形倒梁2上端面的上方,使顶升螺杆5的下端延伸到地基倒梁4的上端,并与预埋在地基倒梁4中的连接件固定连接;同时,在顶升螺杆5的下部通过螺纹配合安装顶升螺母6,并使顶升螺母6的上端与井字形倒梁2的下端面相抵接;A
在每个锚固孔道14中均插装一根锚杆9,并使锚杆9的上端延伸到连梁3上端面的上方,使锚杆9的下端延伸到地基倒梁4的内部,并锚固于地基倒梁4中;同时,在锚杆9的上部分别套设有垫片11和锚杆螺母10,且垫片11通过锚杆螺母10的作用抵接在连梁3的上端面;An
步骤四:安放千斤顶12并进行调平作业;Step 4: Place the
在井字形倒梁2的端部和地基倒梁4之间的部分支设千斤顶12,且使千斤顶12位于倾斜状态下位置较低的一侧,利用千斤顶12顶升提供向上的作用反力,提升井字形倒梁2的一侧,以通过调节井字形倒梁2倾斜度来对输电铁塔进行纠偏;在千斤顶12顶升过程中,向上调节并锁紧位置较低一侧的顶升螺母6,并利用顶升螺母6对井字形倒梁2的下端面进行高度定位支撑,同时,向下调节并锁紧位置较高一侧的锚杆螺母10,并通过垫片11将连梁3的上端面向下压紧并锚固;在顶升过程中如果不能一次使输电铁塔达到水平的状态,再根据井字形倒梁2的倾斜状态,改变千斤顶12的位置,使千斤顶12位于倾斜状态下位置较低的一侧,再次利用千斤顶12顶升提供向上的作用反力,提升井字形倒梁2的一侧,以通过调节井字形倒梁2倾斜度来对输电铁塔进行再次纠偏,在顶升过程中,向上调节并锁紧位置较低一侧的顶升螺母6,并利用顶升螺母6对井字形倒梁2的下端面进行高度定位支撑,同时,向下调节并锁紧位置较高一侧的锚杆螺母10,并通过垫片11将连梁3的上端面向下压紧并锚固,以利用位置较低一侧的顶升螺母6和位置较高一侧的锚杆螺母10的相互作用对输电铁塔进行快速有效的纠偏和加固,直至输电铁塔达到水平的状态。A
作业种优选,在步骤三中,所述连接件由预埋在地基倒梁4中的预埋螺杆8和固定连接在预埋螺杆8上端的法兰7组成。Preferably, in
作业种优选,在步骤三中,所述预埋螺杆8与顶升螺杆5同轴的设置。The preferred operation is that in
为了能实现对井字形倒梁进行有效的位置锁定,在步骤四中,在输电铁塔达到水平状态后,在每根顶升螺杆5的上部通过螺纹配合安装锁紧螺母15,拧紧并使锁紧螺母15抵接在井字形倒梁2的上端面上。In order to realize effective position locking of the well-shaped inverted beam, in
为了实现稳定可靠的连接,同时,也能方便拆卸维护,所述法兰7呈环形,其中心开设有与顶升螺杆5相配合的安装孔16,其上环绕安装孔16的开设有多个定位通孔17,所述预埋螺杆8的螺帽上对应多个定位通孔17的开设有多个定位盲孔18,法兰7和预埋螺杆8通过穿设于定位通孔和定位盲孔18中的连接螺栓进行固定连接。In order to achieve a stable and reliable connection, and at the same time, it can also be easily disassembled and maintained. Positioning through
本发明中的方法操作简单,施工过程方便,且经济成本低,实用性强。该方法在纠偏的同时,在不破坏原有基础结构的情况下还能对基础结构进行加固处理,且施工过程中无冲击纠偏荷载或冲击很小,整个过程操作灵活,能使基础的加固和纠偏调节过程更加安全可靠。同时,能提高原有输电铁塔的安全性和稳定性。The method in the invention has simple operation, convenient construction process, low economic cost and strong practicability. This method can also reinforce the foundation structure without destroying the original foundation structure while correcting the deviation, and there is no impact correction load or small impact during the construction process. The deviation correction adjustment process is safer and more reliable. At the same time, the safety and stability of the original transmission tower can be improved.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110699524.4A CN113482034B (en) | 2021-06-23 | 2021-06-23 | A correction method for uneven settlement of transmission towers |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202110699524.4A CN113482034B (en) | 2021-06-23 | 2021-06-23 | A correction method for uneven settlement of transmission towers |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN113482034A CN113482034A (en) | 2021-10-08 |
| CN113482034B true CN113482034B (en) | 2023-07-14 |
Family
ID=77935926
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202110699524.4A Active CN113482034B (en) | 2021-06-23 | 2021-06-23 | A correction method for uneven settlement of transmission towers |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN113482034B (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114084838B (en) * | 2021-12-02 | 2023-07-07 | 国网山西省电力公司阳泉供电公司 | A deviation correction control system and method for a tilted iron tower in a mining area with servo linkage jacking |
| CN113931241B (en) * | 2021-12-02 | 2023-07-07 | 国网山西省电力公司阳泉供电公司 | A deviation correction structure and method for uneven settlement of power transmission tower |
| CN115126014B (en) * | 2022-06-30 | 2024-01-19 | 西安科技大学 | Transmission and transformation line tower base station adjusting device and method based on mining influence |
| CN114991198A (en) * | 2022-08-03 | 2022-09-02 | 山西龙炘电力工程有限公司 | Goaf transmission tower foundation and foundation reinforcing and adjusting method |
| CN115652982A (en) * | 2022-10-13 | 2023-01-31 | 国网河北省电力有限公司建设公司 | Adjusting device for iron tower foundation embedded part |
| CN117627035A (en) * | 2023-12-05 | 2024-03-01 | 国网宁夏电力有限公司建设分公司 | A foundation for correcting uneven settlement of transmission towers |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006052530A (en) * | 2004-08-09 | 2006-02-23 | Yurtec Corp | Steel tower raising device |
| KR101019734B1 (en) * | 2009-12-29 | 2011-03-08 | (주)한국에스코 | Position and direction angle control device of power transmission substation distribution tower |
| CN204001928U (en) * | 2014-03-14 | 2014-12-10 | 国家电网公司 | Transmission line angle-steel tower leg structure after a kind of reinforcing |
| CN111779045A (en) * | 2020-06-15 | 2020-10-16 | 广州市城市规划勘测设计研究院 | A kind of foundation reinforcement rectification method |
| CN211973556U (en) * | 2020-03-16 | 2020-11-20 | 青岛华玺能源科技有限公司 | A kind of heightening iron tower shoe foot plate with correction function for transmission line tower |
Family Cites Families (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3817579B2 (en) * | 2003-10-30 | 2006-09-06 | 有限会社住環境設計室 | Building foundation lifting device, building foundation lifting method using the same, and subsidence building foundation correction method |
| JP2009068321A (en) * | 2007-09-12 | 2009-04-02 | Sano Shujiro | Level adjustment method and its device for unequally settled building |
| GB0902289D0 (en) * | 2009-02-12 | 2009-03-25 | Marine Current Turbines Ltd | Methods for installing pin-piled jacket type structures at sea |
| JP5378860B2 (en) * | 2009-03-31 | 2013-12-25 | 住友林業株式会社 | Foundation structure of buildings in soft ground |
| DE102012212700B4 (en) * | 2012-07-19 | 2015-08-06 | Peter Kellner | System for anchoring structures in the ground |
| AU2013204839B2 (en) * | 2013-03-08 | 2015-07-09 | Up First Construction Systems Pty Ltd | Building System |
| CN103669432B (en) * | 2013-11-18 | 2016-11-02 | 国家电网公司 | A kind of jacking device for deviation rectification of steel pylon in mining area of coal mine |
| US10710856B2 (en) * | 2017-11-26 | 2020-07-14 | Ampjack Industries Ltd. | Utility tower leveling apparatus and method |
| CN208830341U (en) * | 2018-09-11 | 2019-05-07 | 中原豫安建设工程有限公司 | A kind of electric power pylon foundation reinforcing structure |
-
2021
- 2021-06-23 CN CN202110699524.4A patent/CN113482034B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006052530A (en) * | 2004-08-09 | 2006-02-23 | Yurtec Corp | Steel tower raising device |
| KR101019734B1 (en) * | 2009-12-29 | 2011-03-08 | (주)한국에스코 | Position and direction angle control device of power transmission substation distribution tower |
| CN204001928U (en) * | 2014-03-14 | 2014-12-10 | 国家电网公司 | Transmission line angle-steel tower leg structure after a kind of reinforcing |
| CN211973556U (en) * | 2020-03-16 | 2020-11-20 | 青岛华玺能源科技有限公司 | A kind of heightening iron tower shoe foot plate with correction function for transmission line tower |
| CN111779045A (en) * | 2020-06-15 | 2020-10-16 | 广州市城市规划勘测设计研究院 | A kind of foundation reinforcement rectification method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN113482034A (en) | 2021-10-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113482034B (en) | A correction method for uneven settlement of transmission towers | |
| CN202492865U (en) | Correction device of transmission tower | |
| CN108999208A (en) | A kind of blower foundation anchor component construction method of installation | |
| CN103669431B (en) | A kind of colliery minery electric power pylon inclination adjusting device | |
| CN110397335A (en) | A kind of self-supporting tower tower seat method for correcting error | |
| CN103669432A (en) | Jacking device for deviation rectification of steel pylon in mining area of coal mine | |
| CN104929380A (en) | Heightening steel tower boot foot used for tilt centralizing adjustment of transmission line steel towers and method for tilt centralizing adjustment of transmission line steel towers | |
| CN212801921U (en) | Steel platform leveling mechanism | |
| CN212359211U (en) | Subsidence area steel pylons slope deviation correcting device | |
| CN211368731U (en) | A foundation ditch construction high strength supporting beam for construction | |
| CN103437385B (en) | A kind of transmission iron tower tilt rectification | |
| CN203960920U (en) | Colliery minery electric power pylon inclination adjusting device | |
| CN217457099U (en) | Tower section of thick bamboo transportation bearing structure | |
| CN217947492U (en) | Pre-buried landing leg device of fishtail plate-type tower machine basis | |
| CN117627035A (en) | A foundation for correcting uneven settlement of transmission towers | |
| CN112359888B (en) | Static pile reaction frame jacking system for carbon filter tank body deviation rectifying and reinforcing construction and construction method | |
| CN210714048U (en) | Self-supporting iron tower base deviation correcting device | |
| CN211395784U (en) | Building reinforcing apparatus that rectifies | |
| CN218990286U (en) | Integral lifting deviation rectifying structure for building | |
| CN209724376U (en) | Mining I-steel canopy | |
| CN223119915U (en) | Secret existing structure underground excavation primary support device of wearing under subsides | |
| CN206329604U (en) | The steel tower that a kind of electric power pylon tilts correction bolt and its application continues deviation correcting device | |
| CN216973474U (en) | Convenient adjusting device that subsides of transmission line iron tower basis | |
| CN204825950U (en) | Rear column single pile basis of connecting bridge | |
| CN118531833B (en) | Adjustable photovoltaic bracket foundation and deviation rectifying construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
