CN111779045A - A kind of foundation reinforcement rectification method - Google Patents

A kind of foundation reinforcement rectification method Download PDF

Info

Publication number
CN111779045A
CN111779045A CN202010545267.4A CN202010545267A CN111779045A CN 111779045 A CN111779045 A CN 111779045A CN 202010545267 A CN202010545267 A CN 202010545267A CN 111779045 A CN111779045 A CN 111779045A
Authority
CN
China
Prior art keywords
grouting
steel pipe
pile
foundation
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010545267.4A
Other languages
Chinese (zh)
Other versions
CN111779045B (en
Inventor
刘志方
彭卫平
刘伟
张庆华
张鹏
温忠义
张耀华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Urban Planning Survey and Design Institute
Original Assignee
Guangzhou Urban Planning Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Urban Planning Survey and Design Institute filed Critical Guangzhou Urban Planning Survey and Design Institute
Priority to CN202010545267.4A priority Critical patent/CN111779045B/en
Publication of CN111779045A publication Critical patent/CN111779045A/en
Application granted granted Critical
Publication of CN111779045B publication Critical patent/CN111779045B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of foundation construction, and discloses a foundation reinforcement deviation rectifying method, which comprises the following steps: implanting anchor rod reinforcing steel bars around the first pile hole, constructing an anchor rod static pressure steel pipe pile, repeatedly extruding and grouting deep soil through the steel pipe pile, installing a pressurizing assembly and temporarily locking the steel pipe pile after grouting is finished; and (2) arranging a second pile hole on the foundation ground to be constructed, inserting a grouting steel pipe, locally and directionally reinforcing the shallow soil body by using the grouting steel pipe in a repeated grouting mode, monitoring the pressure value of the steel pipe pile in the grouting process, and gradually repressing the steel pipe pile through a pressurizing assembly so as to realize slow reinforcement lifting of a subsided soil layer and foundation rectification. The method slowly reinforces and lifts the settled soil layer by repeatedly and multi-point grouting of deep and shallow soil bodies and gradual repression of the steel pipe piles, performs directional deviation rectification on the foundation, can effectively reduce or eliminate the generated uneven settlement and the inclination of the whole building, and realizes the combination of reinforcement and deviation rectification.

Description

一种地基加固纠偏方法A kind of foundation reinforcement rectification method

技术领域technical field

本发明涉及地基施工技术领域,特别是涉及一种地基加固纠偏方法。The invention relates to the technical field of foundation construction, in particular to a method for rectifying deviation of foundation reinforcement.

背景技术Background technique

目前已有建筑地基基础加固方法有很多种,包括桩基托换法、树根桩法、基底注浆法等,已形成成熟的设计施工方法,但上述方法仅能加强基础的强度和刚度,控制地基施工后的沉降,不能有效减少桩柱间沉降的差异程度,不能对已发生的建筑整体倾斜或局部倾斜进行定向合理纠偏,使其复位到原始位置,满足国家标准的要求。特别是当受施工场地条件和原地基基础强度弱的限制时,或天然地基基础底部土层承载力偏低时,其加固效果往往难以达到预期目标,如采用大直径成孔灌注桩或人工挖孔桩施工,还存在一定的安全风险,在旧基础旁施工容易进一步扰动基底土体,加剧地基沉降。At present, there are many methods for strengthening the foundation of building foundations, including the pile foundation underpinning method, the root pile method, the base grouting method, etc., and mature design and construction methods have been formed, but the above methods can only strengthen the strength and stiffness of the foundation. Controlling the settlement after foundation construction cannot effectively reduce the difference in settlement between the piles, and cannot orient and rectify the overall or local inclination of the building that has occurred so that it can be reset to its original position to meet the requirements of national standards. Especially when limited by the construction site conditions and the weak strength of the original foundation, or when the bearing capacity of the soil layer at the bottom of the natural foundation is low, the reinforcement effect is often difficult to achieve the expected goal, such as using large-diameter bored piles or artificial digging. There are also certain safety risks in the construction of hole piles. Construction next to the old foundation is easy to further disturb the base soil and aggravate the settlement of the foundation.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题是:如何实现对发生沉降的地基进行定向的加固纠偏。The technical problem to be solved by the present invention is: how to realize the directional reinforcement and rectification of the subsidence foundation.

为了解决上述技术问题,本发明提供了一种地基加固纠偏方法,包括以下步骤:在待施工地基的地面开设第一桩孔并延伸至深层土体,在所述第一桩孔的周围植入锚杆钢筋;In order to solve the above-mentioned technical problems, the present invention provides a foundation reinforcement and deviation correction method, which includes the following steps: opening a first pile hole on the ground of the foundation to be constructed and extending to the deep soil body, and implanting around the first pile hole Anchor bar;

将所述地基作为反力平台,通过锚杆静压施工方式将钢管桩压进所述第一桩孔;The foundation is used as a reaction force platform, and the steel pipe pile is pressed into the first pile hole by the anchor rod static pressure construction method;

将配置好的注浆液通过所述钢管桩的出浆口进行挤压注浆,以“注浆-清洗-注浆”的反复注浆方式向所述深层土体进行挤密加固;The configured grouting liquid is squeezed and grouted through the grouting outlet of the steel pipe pile, and the deep soil body is compacted and reinforced by the repeated grouting method of "grouting-cleaning-grouting";

注浆完成后,通过所述锚杆钢筋固定加压组件,利用所述加压组件将所述钢管桩临时锁定;After the grouting is completed, the pressurized component is fixed by the anchor bar, and the steel pipe pile is temporarily locked by the pressurized component;

在待施工地基的地面或者两个地基之间的地面开设多个第二桩孔并延伸至浅层土体,在各所述第二桩孔插入注浆钢管,所述注浆液通过所述注浆钢管进行挤压注浆,以同样的反复注浆方式向浅层土体进行局部定向加固,使得所述地基以下的沉降土层向上抬升和纠偏;A plurality of second pile holes are opened on the ground of the foundation to be constructed or on the ground between two foundations and extended to the shallow soil body, grouting steel pipes are inserted into each of the second pile holes, and the grouting liquid passes through the The grouting steel pipe is squeezed and grouted, and local directional reinforcement is carried out to the shallow soil body in the same repeated grouting method, so that the settled soil layer below the foundation is lifted upward and rectified;

在所述注浆钢管进行注浆过程中,获取所述钢管桩的压力变化值,判断所述钢管桩的压力变化值是否超过预设值,若是,则利用所述加压组件对所述钢管桩进行补偿加压,确保所述钢管桩的承载力;During the grouting process of the grouting steel pipe, the pressure change value of the steel pipe pile is obtained, and it is judged whether the pressure change value of the steel pipe pile exceeds a preset value. Compensate and pressurize the steel pipe pile to ensure the bearing capacity of the steel pipe pile;

加固纠偏完成后,将所述加压组件拆除,向所述钢管桩内浇注混凝土,并通过浇筑混凝土基础梁将所述钢管桩、所述注浆钢管与所述地基固定为一体。After the reinforcement and deviation correction are completed, the pressurizing assembly is removed, concrete is poured into the steel pipe pile, and the steel pipe pile, the grouting steel pipe and the foundation are fixed as a whole by pouring concrete foundation beams.

作为优选方案,在所述将配置好的注浆液通过所述钢管桩的出浆口进行挤压注浆的步骤,还包括:As a preferred solution, in the step of extruding and grouting the configured grouting liquid through the grouting outlet of the steel pipe pile, it also includes:

在所述钢管桩内焊接第一注浆管,将第二注浆管插入所述第一注浆管中并延伸至所述出浆口,所述注浆液通过所述第二注浆管进行挤压注浆。A first grouting pipe is welded in the steel pipe pile, a second grouting pipe is inserted into the first grouting pipe and extends to the grouting outlet, and the grouting liquid passes through the second grouting Tubes are squeeze grouted.

作为优选方案,在所述通过锚杆静压施工方式将钢管桩压进所述第一桩孔的步骤中,还包括:As a preferred solution, in the step of pressing the steel pipe pile into the first pile hole by the anchor rod static pressure construction method, it also includes:

对所述钢管桩的压桩压力以及垂直度进行检测,以保持所述钢管桩的垂直加压,且使得作用于所述钢管桩的压桩压力不超过最大的压桩压力。The piling pressure and verticality of the steel pipe piles are detected to maintain the vertical pressure of the steel pipe piles, and the piling pressure acting on the steel pipe piles does not exceed the maximum piling pressure.

作为优选方案,在所述通过所述锚杆钢筋固定加压组件,利用所述加压组件将所述钢管桩临时锁定的步骤中,具体为:As a preferred solution, in the step of fixing the pressurized component by the anchor rod reinforcement, and using the pressurized component to temporarily lock the steel pipe pile, the specific steps are:

将所述加压组件的第一压桩块通过所述锚杆钢筋固定于所述地基的地面上,所述加压组件的第二压桩块通过所述锚杆钢筋固定于所述第一压桩块的上方,将千斤顶设置于所述第一压桩块和所述第二压桩块之间,利用所述千斤顶为所述钢管桩施加预应力。The first pile pressing block of the compression assembly is fixed on the ground of the foundation through the anchor rod reinforcement, and the second pile driving block of the compression assembly is fixed to the first pile driving block through the anchor rod reinforcement bar. Above the pile pressing block, a jack is arranged between the first pile pressing block and the second pile pressing block, and the jack is used to apply prestress to the steel pipe pile.

作为优选方案,所述锚杆钢筋设有用于调节所述第一压桩块和所述第二压桩块位置的螺母。As a preferred solution, the anchor bar is provided with a nut for adjusting the positions of the first pile pressing block and the second pile pressing block.

作为优选方案,所述注浆液为水泥浆、水玻璃以及液态水配置而成,所述水泥浆、所述水玻璃和所述液态水的体积比依次为1.0~1.5:1:2~3。As a preferred solution, the grouting solution is configured by cement slurry, water glass and liquid water, and the volume ratio of the cement slurry, the water glass and the liquid water is 1.0-1.5:1:2-3 in sequence. .

作为优选方案,各所述第二桩孔的开孔方向为竖向或斜向,各所述第二桩孔的末端均朝向所述钢管桩。As a preferred solution, the opening direction of each of the second pile holes is vertical or oblique, and the ends of each of the second pile holes face the steel pipe pile.

作为优选方案,在所述注浆液通过所述注浆钢管进行挤压注浆,以同样的反复注浆方式向浅层土体进行局部定向加固,使得所述地基以下的沉降土层向上抬升和纠偏的步骤中,具体为:As a preferred solution, the grouting liquid is squeezed and grouted through the grouting steel pipe, and local directional reinforcement is performed on the shallow soil in the same repeated grouting method, so that the settled soil layer below the foundation is lifted upwards. And the steps of rectification are as follows:

将配置好的注浆液分成多组,将每组所述注浆液通过所述注浆钢管进行“注浆-清洗-注浆”的反复挤压注浆,对沉降土层的多个局部位置进行多次定向加固,以使沉降土层逐渐向上抬升并趋于稳定状态,其中,不同的所述注浆钢管采用不同注浆量的所述注浆液,以将各个局部位置差异化向上抬升,对沉降土层的不均匀沉降进行纠偏。Divide the configured grouting liquid into multiple groups, and carry out the repeated extrusion grouting of "grouting-cleaning-grouting" through the grouting steel pipe of each group, and grouting multiple parts of the settled soil layer. Several times of directional reinforcement are carried out at the location, so that the settled soil layer gradually rises upward and tends to a stable state, wherein, different grouting steel pipes use the grouting liquid with different grouting amounts to differentiate each local position upward. Uplift to correct the uneven settlement of the subsidence soil layer.

作为优选方案,在通过浇筑混凝土基础梁将所述钢管桩、所述注浆钢管与所述地基固定为一体的步骤中,具体为:As a preferred solution, in the step of fixing the steel pipe pile, the grouting steel pipe and the foundation into one body by pouring concrete foundation beams, specifically:

在所述地基的地面植入若个条纵横交错的固定钢筋,并通过混凝土浇筑成基础梁,将所述钢管桩、所述注浆钢管与所述地基固定为一体。Several criss-crossing fixed steel bars are implanted on the ground of the foundation, and the foundation beams are formed by pouring concrete, and the steel pipe piles, the grouting steel pipes and the foundation are fixed as a whole.

作为优选方案,在将所述地基作为反力平台的步骤中,还包括:As a preferred solution, in the step of using the foundation as a reaction force platform, it also includes:

若待施工地基的地面不是水平面,则在所述地基的地面上施工水平方向的反力平台。If the ground of the foundation to be constructed is not a horizontal plane, a reaction force platform in a horizontal direction is constructed on the ground of the foundation.

本发明所提供的一种地基加固纠偏方法与现有技术相比,其有益效果在于:Compared with the prior art, the method for ground reinforcement and rectification provided by the present invention has the following beneficial effects:

本发明利用锚杆静压施工方式将所述钢管桩压进所述第一桩孔,将所述注浆液通过所述钢管桩对深层土体进行挤密加固,注浆完成后利用加压组件锁定所述钢管桩,再通过所述第二桩孔内所述注浆钢管对浅层土体进行定向加固,注浆时对所述钢管桩的压力值变化进行监测,若所述钢管桩的压力值出现损失,则利用加压组件对所述钢管桩进行补偿加压,确保单个所述钢管桩的承载力,通过孔底混合、速凝挤密定向加固工艺,分别从深部和浅部,挤密加固地基底下沉降土层,反复多次注浆和多点同时注浆,实现沉降土层缓慢定向抬升,对所述地基之间已出现的不均匀沉降进行加固纠偏,能有效减少或消除已发生的不均匀沉降及整体建筑物的倾斜,同时通过新浇筑的基础梁将钢管桩、注浆钢管与原基础连为一体,强化地基基础的刚度,实现加固纠偏合二为一。In the present invention, the steel pipe pile is pressed into the first pile hole by means of the anchor rod static pressure construction method, and the grouting liquid is passed through the steel pipe pile to compact and reinforce the deep soil body, and after the grouting is completed, use The pressurizing component locks the steel pipe pile, and then directional reinforcement is performed on the shallow soil body through the grouting steel pipe in the second pile hole, and the pressure value change of the steel pipe pile is monitored during grouting. If the pressure value of the steel pipe piles is lost, the pressure components are used to compensate and pressurize the steel pipe piles to ensure the bearing capacity of a single steel pipe pile. , respectively, from the deep and shallow parts, compacting and strengthening the subsidence soil layer under the foundation, repeated multiple grouting and simultaneous grouting at multiple points to realize the slow and directional uplift of the settled soil layer, and carry out the uneven settlement between the foundations. Reinforcement and rectification can effectively reduce or eliminate the uneven settlement that has occurred and the inclination of the overall building. At the same time, the steel pipe pile, grouting steel pipe and the original foundation are connected by the newly poured foundation beam to strengthen the rigidity of the foundation and realize the Reinforcement and rectification are combined into one.

附图说明Description of drawings

图1为应用本发明优先实施例的地基加固纠偏方法的压桩状态示意图。FIG. 1 is a schematic diagram of a pile-pressing state applying a method for ground reinforcement and deviation correction according to a preferred embodiment of the present invention.

图2为应用本发明优先实施例的地基加固纠偏方法中钢管桩、第一注浆管和第二注浆管装配示意图。FIG. 2 is a schematic diagram showing the assembly of a steel pipe pile, a first grouting pipe and a second grouting pipe in the method for correcting deviation of foundation reinforcement according to the preferred embodiment of the present invention.

图3为应用本发明优先实施例的地基加固纠偏方法中反力平台示意图。FIG. 3 is a schematic diagram of a reaction force platform in a method for ground reinforcement and deviation correction applying a preferred embodiment of the present invention.

图4为应用本发明优先实施例的地基加固纠偏方法的注浆钢管平面布置示意图。FIG. 4 is a schematic diagram of the plane layout of the grouting steel pipe applying the method for rectifying deviation of the foundation reinforcement according to the preferred embodiment of the present invention.

图5为应用本发明优先实施例的地基加固纠偏方法的注浆钢管剖视示意图。FIG. 5 is a schematic cross-sectional view of a grouting steel pipe applying the method for correcting deviation of foundation reinforcement according to a preferred embodiment of the present invention.

图6为应用本发明优先实施例的地基加固纠偏方法的施工完成状态示意图。FIG. 6 is a schematic diagram of a construction completion state of applying the method for ground reinforcement and deviation correction according to the preferred embodiment of the present invention.

图中:1.第一桩孔;2.锚杆钢筋;3.钢管桩;4.出浆口;5.注浆钢管;6.菱形桩尖;7.第一注浆管;8.第二注浆管;9.止浆塞;10.反力平台;11.第一压桩块;12.第二压桩块;13.千斤顶;14.固定钢筋;15.基础梁。In the figure: 1. The first pile hole; 2. The anchor bar; 3. The steel pipe pile; 4. The grouting outlet; 5. The grouting steel pipe; 6. The diamond-shaped pile tip; The second grouting pipe; 9. The grouting plug; 10. The reaction platform; 11. The first pile pressing block; 12. The second pile pressing block; 13. The jack;

具体实施方式Detailed ways

下面结合附图和实施例,对本发明的具体实施方式作进一步详细描述。以下实施例用于说明本发明,但不用来限制本发明的范围。The specific embodiments of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments. The following examples are intended to illustrate the present invention, but not to limit the scope of the present invention.

在本发明的描述中,需要说明的是,术语“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be noted that the terms "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", The orientation or positional relationship indicated by "bottom", "inner", "outer", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the indicated device or Elements must have a particular orientation, be constructed and operate in a particular orientation and are therefore not to be construed as limitations of the invention.

在本发明的描述中,应当理解的是,本发明中采用术语“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是焊接连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系,除非另有明确的限定。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be understood that the terms "connected", "connected", "fixed" and other terms used in the present invention should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection, or It can be a mechanical connection or a welded connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication of two elements or the interaction relationship between the two elements, unless otherwise expressly defined . For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.

如图1至图6所示,本发明优选实施例提供了一种地基加固纠偏方法,包括以下步骤:在待施工地基的地面开设第一桩孔1并延伸至深层土体,在所述第一桩孔1的周围植入锚杆钢筋2;将所述地基作为反力平台10,通过锚杆静压施工方式将钢管桩3压进所述第一桩孔1;将配置好的注浆液通过所述钢管桩3的出浆口4进行挤压注浆,以“注浆-清洗-注浆”的反复注浆方式向所述深层土体进行挤密加固;注浆完成后,通过所述锚杆钢筋2固定加压组件,利用所述加压组件将所述钢管桩3临时锁定;在待施工地基的地面或者两个地基之间的地面开设多个第二桩孔并延伸至浅层土体,在各所述第二桩孔插入注浆钢管5,所述注浆液通过所述注浆钢管5进行挤压注浆,以同样的反复注浆方式向浅层土体进行局部定向加固,使得所述地基以下的沉降土层向上抬升和纠偏;在所述注浆钢管5进行注浆过程中,获取所述钢管桩3的压力变化值,判断所述钢管桩3的压力变化值是否超过预设值,若是,则利用所述加压组件对所述钢管桩3进行补偿加压,确保所述钢管桩3的承载力;加固纠偏完成后,将所述加压组件拆除,向所述钢管桩3内浇注混凝土,并通过浇筑混凝土基础梁15将所述钢管桩3、所述注浆钢管5与所述地基固定为一体。As shown in FIG. 1 to FIG. 6 , a preferred embodiment of the present invention provides a foundation reinforcement and deviation correction method, which includes the following steps: opening a first pile hole 1 on the ground of the foundation to be constructed and extending to the deep soil body, and in the first pile hole 1 An anchor rod reinforcement bar 2 is implanted around a pile hole 1; the foundation is used as a reaction force platform 10, and the steel pipe pile 3 is pressed into the first pile hole 1 by means of anchor rod static pressure construction; The grout is squeezed and grouted through the grouting outlet 4 of the steel pipe pile 3, and the deep soil body is compacted and reinforced by the repeated grouting method of "grouting-cleaning-grouting"; after the grouting is completed , fix the pressurized component by the anchor bar 2, and use the pressurized component to temporarily lock the steel pipe pile 3; open a plurality of second pile holes on the ground of the foundation to be constructed or the ground between two foundations And extend to the shallow soil body, insert grouting steel pipe 5 in each of the second pile holes, the grouting liquid is squeezed and grouted through the grouting steel pipe 5, and the grouting method is repeated to the shallow layer in the same way. Local directional reinforcement is performed on the soil body, so that the subsidence soil layer below the foundation is lifted upward and rectified; during the grouting process of the grouting steel pipe 5, the pressure change value of the steel pipe pile 3 is obtained, and the steel pipe pile 3 is judged. Whether the pressure change value of the pipe pile 3 exceeds the preset value, if so, use the pressurizing component to compensate and pressurize the steel pipe pile 3 to ensure the bearing capacity of the steel pipe pile 3; The pressurizing assembly is removed, concrete is poured into the steel pipe pile 3 , and the steel pipe pile 3 , the grouting steel pipe 5 and the foundation are fixed as a whole by pouring concrete foundation beams 15 .

基于上述技术特征的地基加固纠偏方法,利用锚杆静压施工方式将所述钢管桩3压进所述第一桩孔1,将所述注浆液通过所述钢管桩3对深层土体进行挤密加固,注浆完成后利用加压组件锁定所述钢管桩3,再通过所述第二桩孔内所述注浆钢管5对浅层土体进行定向加固,注浆时对所述钢管桩3的压力值变化进行监测,若所述钢管桩3的压力值出现损失,则利用加压组件对所述钢管桩3进行补偿加压,确保单个所述钢管桩3的承载力,通过孔底混合、速凝挤密定向加固工艺,分别从深部和浅部,挤密加固地基底下沉降土层,反复多次注浆和多点同时注浆,实现沉降土层缓慢定向抬升,对所述地基之间已出现的不均匀沉降进行加固纠偏,能有效减少或消除已发生的不均匀沉降及整体建筑物的倾斜,同时通过新浇筑的基础梁15将钢管桩3、注浆钢管5与原基础连为一体,强化地基基础的刚度,实现加固纠偏合二为一。Based on the above-mentioned technical feature of the foundation reinforcement and deviation correction method, the steel pipe pile 3 is pressed into the first pile hole 1 by means of the anchor rod static pressure construction method, and the grouting liquid is passed through the steel pipe pile 3 to compress the deep soil. After the grouting is completed, the steel pipe pile 3 is locked with a pressurizing component, and the shallow soil body is directionally reinforced through the grouting steel pipe 5 in the second pile hole. The change of the pressure value of the steel pipe pile 3 is monitored. If the pressure value of the steel pipe pile 3 is lost, the pressure value of the steel pipe pile 3 is compensated and pressurized by the pressurizing component to ensure a single steel pipe pile. The bearing capacity of 3, through the directional reinforcement process of hole bottom mixing and quick-setting compaction, respectively, from the deep and shallow parts, compaction and reinforcement of the subsidence soil layer under the foundation, repeated grouting and multi-point simultaneous grouting to achieve the settlement of soil layer Slowly directional lifting, strengthening and rectifying the uneven settlement that has occurred between the foundations, can effectively reduce or eliminate the uneven settlement that has occurred and the inclination of the overall building. 3. The grouting steel pipe 5 is connected with the original foundation to strengthen the rigidity of the foundation and realize the integration of reinforcement and correction.

在进行施工之前,需要对所述钢管桩3进行计算以及预制,如图2所示,首先根据建筑物的上部荷载和桩柱间距,计算确定单桩的承载力特征值,再根据场地地质条件预估所述钢管桩3长度,采用的锚杆静压钢管桩3通常可穿越黏土层和全风化层,强风化层可进入1-2m,中微风化岩层则无法进入。根据预估的桩长和单桩承载力特征值,选用采用直径为127、159或250mm,为壁厚8-14mm的钢管桩3。如计算所得桩径偏大,可适当压缩钢管桩3间距,降低单桩承载力特征值,从而减小桩径,避免压桩困难。Before construction, the steel pipe pile 3 needs to be calculated and prefabricated. As shown in Figure 2, firstly, according to the upper load of the building and the distance between the piles, the characteristic value of the bearing capacity of the single pile is calculated and determined, and then according to the site geology The length of the steel pipe pile 3 is estimated according to the conditions. The static pressure steel pipe pile 3 used can usually pass through the clay layer and the fully weathered layer. The strong weathered layer can enter 1-2m, and the moderately weathered rock layer cannot enter. According to the estimated pile length and the characteristic value of the single pile bearing capacity, the steel pipe pile 3 with a diameter of 127, 159 or 250 mm and a wall thickness of 8-14 mm is selected. If the calculated pile diameter is too large, the distance between the steel pipe piles 3 can be appropriately compressed to reduce the characteristic value of the bearing capacity of the single pile, thereby reducing the pile diameter and avoiding the difficulty of pile pressing.

根据预估桩长和桩径,先制作好所述钢管桩3,每节钢管长度不小于2.0m,可按现场实际情况确定,每节钢管的接头采用45度坡口焊,再用4条直径14-16mm,长度200mm钢筋或3块200×40×10mm(长×宽×厚度)钢片绑焊连接,在桩底以上1-2m范围内布置所述出浆口4,以实现注浆液在沉降土层的深部位置进行速凝,对沉降土层起到抬升定向作用。所述钢管桩3的桩底设有菱形桩尖6,便于进行压桩施工。According to the estimated pile length and pile diameter, first make the steel pipe pile 3. The length of each steel pipe is not less than 2.0m, which can be determined according to the actual situation on site. The diameter of the bar is 14-16mm, the length of 200mm of steel bars or three pieces of 200×40×10mm (length×width×thickness) steel sheets are tied and welded, and the slurry outlet 4 is arranged within the range of 1-2m above the pile bottom to realize the injection The slurry rapidly solidifies in the deep position of the subsidence soil layer, and plays an uplifting and directional effect on the subsidence soil layer. The bottom of the steel pipe pile 3 is provided with a diamond-shaped pile tip 6, which is convenient for pile pressing construction.

在本实施例中,在所述将配置好的注浆液通过所述钢管桩3的出浆口4进行挤压注浆的步骤,还包括:在压桩前完成,在所述钢管桩3内焊接第一注浆管7(直径45-50mm,壁厚3-4mm),将第二注浆管8插入所述第一注浆管7中并延伸至所述出浆口4,所述注浆液通过所述第二注浆管8直接往所述钢管桩3的桩底进行挤密加固。In this embodiment, the step of extruding and grouting the configured grouting liquid through the grouting outlet 4 of the steel pipe pile 3 further includes: completing the pile before pressing the A first grouting pipe 7 (diameter 45-50mm, wall thickness 3-4mm) is welded in the pile 3, and a second grouting pipe 8 is inserted into the first grouting pipe 7 and extends to the grouting outlet 4, The grouting liquid is directly squeezed and reinforced to the bottom of the steel pipe pile 3 through the second grouting pipe 8 .

其中,所述第一注浆管7的外壁与所述钢管桩3的内壁之间设有止浆塞9,在离桩底2m处管内焊接钢板作为止浆塞9进行隔离,在进行挤密注浆中,所述止浆塞9起到防止所述注浆液向上流动,所述止浆塞9由钢板进行焊接而成。Among them, a slurry stopper 9 is provided between the outer wall of the first grouting pipe 7 and the inner wall of the steel pipe pile 3, and a steel plate is welded in the pipe at a distance of 2m from the pile bottom as the slurry stopper 9 for isolation. In dense grouting, the grouting plug 9 prevents the grouting liquid from flowing upward, and the grouting plug 9 is welded by steel plates.

在本实施例中,在待施工地基的地面开设第一桩孔1并延伸至深层土体,在所述第一桩孔1的周围植入锚杆钢筋2的步骤中,具体为:对待施工的基础地面测量放线,在所述基础地面开钻所述第一桩孔1,所述第一桩孔1的直径略大于所述钢管桩3的直径,第一桩孔1的周围植入桩帽梁钢筋及带螺纹的锚杆钢筋2,如所述基础地面不是水平面,例如为斜面或者凹凸面,应先施工水平设置的施工平台作为反力平台10。In this embodiment, a first pile hole 1 is opened on the ground of the foundation to be constructed and extended to the deep soil body, and the steps of implanting the anchor reinforcement bar 2 around the first pile hole 1 are as follows: to be constructed The first pile hole 1 is drilled on the foundation ground, the diameter of the first pile hole 1 is slightly larger than the diameter of the steel pipe pile 3, and the surrounding of the first pile hole 1 is planted. For the pile cap beam steel bar and the threaded anchor bar steel bar 2, if the foundation ground is not a horizontal plane, such as an inclined plane or a concave-convex surface, a horizontally set construction platform should be constructed first as the reaction force platform 10.

在本实施例中,在所述通过锚杆静压施工方式将钢管桩3压进所述第一桩孔1的步骤中,还包括:对所述钢管桩3的压桩压力以及垂直度进行检测,以保持所述钢管桩3的垂直加压,且使得作用于所述钢管桩3的压桩压力不超过最大的压桩压力。压桩过程必须连续,并保持桩段垂直,压桩力不能超过设计最大压桩力,并应及时检查压力、桩的垂直度、接桩间歇时间、桩的连接质量及压入深度,终桩按照压桩荷载和稳压下沉量相结合的原则控制。In this embodiment, in the step of pressing the steel pipe pile 3 into the first pile hole 1 by means of anchor bolt static pressure construction, it also includes: the pile pressing pressure on the steel pipe pile 3 and the vertical In order to maintain the vertical pressure of the steel pipe pile 3, and make the pile pressure acting on the steel pipe pile 3 not exceed the maximum pile pressure. The pile pressing process must be continuous and keep the pile section vertical. The pile pressing force cannot exceed the design maximum pile pressing force, and the pressure, the verticality of the pile, the intermittent time of connecting the pile, the connection quality of the pile and the pressing depth, and the final pile should be checked in time. It is controlled according to the principle of combining the pile pressing load and the steady-state sinking amount.

在本实施例中,结合图1所示,在所述通过所述锚杆钢筋2固定加压组件,利用所述加压组件将所述钢管桩3临时锁定的步骤中,具体为:将所述加压组件的第一压桩块11通过所述锚杆钢筋2固定于所述地基的地面上,所述加压组件的第二压桩块12通过所述锚杆钢筋2固定于所述第一压桩块11的上方,将千斤顶13设置于所述第一压桩块11和所述第二压桩块12之间,利用所述千斤顶13为所述钢管桩3施加预应力。当压力损失过大时,可通过所述千斤顶13为所述钢管桩3复压,保证所述钢管桩3的单桩承载力。In this embodiment, as shown in FIG. 1 , in the step of fixing the pressurized component through the anchor rod 2 and using the pressurized component to temporarily lock the steel pipe pile 3 , the specific steps are: The first pile pressing block 11 of the compression assembly is fixed on the ground of the foundation through the anchor rod reinforcement 2 , and the second pile driving block 12 of the compression assembly is fixed to the ground through the anchor rod reinforcement rod 2 . Above the first pile driving block 11, a jack 13 is arranged between the first pile driving block 11 and the second pile driving block 12, and the jack 13 is used to apply prestress to the steel pipe pile 3 . When the pressure loss is too large, the jack 13 can be used to re-press the steel pipe pile 3 to ensure the single pile bearing capacity of the steel pipe pile 3 .

其中,所述锚杆钢筋2为带螺纹的钢筋锚杆,所述锚杆钢筋2上设有用于调节所述第一压桩块11和所述第二压桩块12位置的螺母,通过螺母将所述第一压桩块11固定住,再通过所述锚杆钢筋2和所述螺母将所述第二压桩块12进行固定,实现渐进式螺栓封桩结构,操作方便简单,临时锁定所述钢管桩3,且能调节钢管桩3的压力值,保证钢管桩3在封桩过程中有合适的预加力,实现桩土基础协同工作,有效消除后期沉降。Wherein, the anchor bar 2 is a threaded steel bar anchor, and the anchor bar 2 is provided with a nut for adjusting the position of the first pile pressing block 11 and the second pile pressing block 12, through the nut The first pile pressing block 11 is fixed, and then the second pile pressing block 12 is fixed by the anchor rod steel bar 2 and the nut, so as to realize the progressive bolt sealing pile structure, which is convenient and simple to operate and temporarily locked. The steel pipe pile 3 can adjust the pressure value of the steel pipe pile 3 to ensure that the steel pipe pile 3 has proper pre-stressing during the pile sealing process, realize the cooperative work of the pile-soil foundation, and effectively eliminate the later settlement.

进一步的,所述锚杆钢筋2的数量有多条,各所述锚杆钢筋2呈矩形阵列设于所述钢管桩3的周围,使得作用于所述钢管桩3的压力更加均匀。Further, the number of the anchor bars 2 is multiple, and the anchor bars 2 are arranged around the steel pipe piles 3 in a rectangular array, so that the pressure acting on the steel pipe piles 3 is more uniform.

其中,通过对所述钢管桩3进行多次重复注浆,每次注浆后,用清水冲洗管内残留浆液,再进行注浆,以此形成“注浆-清洗-注浆”的反复注浆方式,达到缓慢抬升的效果。Among them, by repeatedly grouting the steel pipe pile 3 for many times, after each grouting, rinse the residual grout in the pipe with clean water, and then perform grouting, so as to form the repeated grouting of "grouting-cleaning-grouting" The slurry method can achieve the effect of slow lifting.

在本实施例中,所述注浆液为水泥浆、水玻璃以及液态水配置而成,所述水泥浆的水灰比1:0.5~1.0,所述水泥浆、所述水玻璃和所述液态水的体积比依次为(1.0~1.5):1:(2~3),实现速凝挤密定向加固的工艺,进行缓慢抬升纠偏。In this embodiment, the grouting liquid is configured by cement slurry, water glass and liquid water, the water-cement ratio of the cement slurry is 1:0.5-1.0, and the The volume ratio of liquid water is (1.0-1.5): 1: (2-3) in order, which realizes the process of quick-setting, compacting, directional reinforcement, and slowly lifts and corrects deviation.

在本实施例中,结合图4和图5所示,所述第二桩孔的开孔方向为竖向或斜向,各所述第二桩孔均朝向所述钢管桩3。在沉降土层内布置长度5m~8m的网格状毛细注浆钢管5,管径

Figure BDA0002539673510000081
长短结合,局部挤密加固基础底下土体,实现多局部位置同时注浆,实现对桩底以上地层进行挤密注浆,多重管注浆加固钢管桩3周边范围内,主要受力土层定向抬升,进一步减少差异沉降。In this embodiment, as shown in FIG. 4 and FIG. 5 , the opening direction of the second pile holes is vertical or oblique, and each of the second pile holes faces the steel pipe pile 3 . Grid-like capillary grouting steel pipes 5 with a length of 5m to 8m are arranged in the subsidence soil layer.
Figure BDA0002539673510000081
Combination of length and length, local compaction and reinforcement of the soil under the foundation, to achieve simultaneous grouting in multiple local locations, to achieve compaction and grouting of the stratum above the pile bottom, and multi-pipe grouting to reinforce the surrounding area of the steel pipe pile 3, the main stress soil layer Directional uplift to further reduce differential settlement.

在本实施例中,在所述注浆液通过所述注浆钢管5进行挤压注浆,以同样的反复注浆方式向浅层土体进行局部定向加固,使得所述地基以下的沉降土层向上抬升和纠偏的步骤中,具体为:将配置好的注浆液分成多组,将每组所述注浆液通过所述注浆钢管5进行“注浆-清洗-注浆”的反复挤压注浆,对沉降土层的多个局部位置进行多次定向加固,以使沉降土层逐渐向上抬升并趋于稳定状态,其中,不同的所述注浆钢管5采用不同注浆量的所述注浆液,以对各个局部位置进行差异化加固,再通过所述钢管桩3的渐进式复压来同步实现加固抬升和纠偏,达到对沉降土层的不均匀沉降进行纠偏的目的。In this embodiment, the grouting liquid is squeezed and grouted through the grouting steel pipe 5, and local directional reinforcement is performed on the shallow soil body in the same repeated grouting method, so that the settled soil below the foundation In the steps of layer uplifting and deviation correction, the specific steps are: dividing the configured grouting liquid into multiple groups, and passing the grouting liquid of each group through the grouting steel pipe 5 to repeat “grouting-cleaning-grouting” Squeeze grouting to carry out multiple directional reinforcement for multiple local positions of the settled soil layer, so that the settled soil layer gradually rises upward and tends to a stable state, wherein, different grouting steel pipes 5 adopt different grouting amount The grouting liquid is used to strengthen each local position in a differentiated way, and then through the progressive recompression of the steel pipe piles 3, the reinforcement, lifting and deviation correction are synchronously achieved, so as to achieve the purpose of correcting the uneven settlement of the settled soil layer. .

其中,所述注浆钢管5为单栓式钢管,注浆总体顺序可采用自外向内,按照现场实际情况和基础层分布形式对所述注浆钢管5和所述注浆液进行分组,每组所述注浆钢管5可进行多组所述注浆液的注浆,通过“反复少量多次”的方式,直至基础土层的不均匀沉降趋于稳定,或抬升至设计要求并稳定后,可停止注浆。利用不同的所述注浆钢管5采用不同注浆量的所述注浆液,以将各个局部位置差异化向上抬升,也就不同的位置的抬升幅度不同,以克服沉降土层的不均匀沉降,达到纠偏的目的,注浆时应加强对建筑物及基坑进行实时监测,避免扰动建筑物及配套设备,适时调整注浆压力及注浆量,实现信息化施工。The grouting steel pipe 5 is a single-bolt type steel pipe, and the overall order of grouting can be from the outside to the inside. The grouting steel pipe 5 can be grouted for multiple groups of the grouting liquid, through the method of "repeating a small amount of times many times", until the uneven settlement of the foundation soil layer tends to be stable, or after it is raised to the design requirements and stabilized , the grouting can be stopped. Different grouting steel pipes 5 are used to use the grouting liquid with different grouting amounts to lift up each local position in a differentiated manner, that is, the lifting amplitude of different positions is different, so as to overcome the uneven settlement of the settled soil layer. In order to achieve the purpose of rectification, real-time monitoring of buildings and foundation pits should be strengthened during grouting to avoid disturbing buildings and supporting equipment, and to adjust grouting pressure and grouting volume in a timely manner to realize information-based construction.

其中,所述注浆钢管5可多次重复注浆,每次注浆后,用清水冲洗管内残留浆液,保持注浆钢管5干净,并用盖子封口,下次注浆时,在管内插入小口径内注浆管,可重复开始双液注浆,避免多次成孔,也就是“注浆-清洗-注浆”的反复注浆方式。所述注浆钢管55的注浆压力0.8~2.0MPa,所述注浆钢管55的注浆口的位置深度为5-8m,可根据基底土层情况适当加深,注浆材料同样采用双液浆,所述注浆液的凝固时间不大于10s,注浆速度不大于70升/分钟,其配比通过现场试验最终确定。The grouting steel pipe 5 can be repeatedly grouted for many times. After each grouting, rinse the residual grout in the pipe with clean water, keep the grouting steel pipe 5 clean, and seal it with a cover. When grouting next time, insert a small diameter into the pipe. The inner grouting pipe can start the double-liquid grouting repeatedly to avoid multiple hole formation, that is, the repeated grouting method of "grouting-cleaning-grouting". The grouting pressure of the grouting steel pipe 55 is 0.8-2.0 MPa, and the depth of the grouting port of the grouting steel pipe 55 is 5-8m, which can be appropriately deepened according to the conditions of the base soil layer. The grouting material also adopts double-liquid slurry. , the solidification time of the grouting liquid is not more than 10s, and the grouting speed is not more than 70 liters/min, and the proportion is finally determined by the field test.

在本实施例中,在通过浇筑混凝土基础梁15将所述钢管桩3、所述注浆钢管5与所述地基固定为一体的步骤中,具体为:在所述地基的地面植入若个条纵横交错的固定钢筋14,并通过混凝土浇筑成基础梁15,将所述钢管桩3、所述注浆钢管5与所述地基固定为一体。所述固定钢筋14的型号与数量需满足截面抗剪验算,而且所述钢管桩3的外壁与原地基土层之间应充填满超细水泥浆,确保所述钢管桩3与原有地基土层的有效连接固定。In this embodiment, in the step of fixing the steel pipe pile 3, the grouting steel pipe 5 and the foundation as a whole by pouring concrete foundation beams 15, the concrete step is: implanting the steel pipe on the ground of the foundation. The fixed steel bars 14 are crisscrossed and cast into a foundation beam 15 through concrete, and the steel pipe pile 3, the grouting steel pipe 5 and the foundation are fixed as a whole. The type and quantity of the fixed steel bars 14 need to meet the shear resistance check calculation of the section, and the outer wall of the steel pipe pile 3 and the original foundation soil layer should be filled with ultra-fine cement slurry to ensure that the steel pipe pile 3 and the original The effective connection of the foundation soil layer is fixed.

以下采用实际情况的应用例子作为补充说明,南方医院医疗综合楼基坑支护工程(一期)位于广州市广州大道北南方医科大学南方医院内,下设三层地下室,建筑相当于广州城建高度35.00m,基坑周长约400m,基坑开挖深度约12.30~15.40m。基坑挖深范围内依次揭露填土、冲洪积黏土层、砂层、可塑坚硬的残积黏性土层等,基坑底主要位于黏土层中,局部位于全强风化岩层。基坑周边环境复杂,北侧紧邻外科楼(13层,独立基础,一层地下室,基础埋深约5.2m),距离医疗综合楼地下室边线约6.0m;东侧为2~19层宿舍楼,距离地下室边约18.3m。基坑南侧地下室边距离道路5.0m。基坑西北侧5层医技楼独立基础,离地下室边线约8.3m。东侧和南侧道路下有给排水管线和供电线。北侧外科楼地下室分别安装有DSG及r刀等精密仪器,西北侧医技楼安装有核磁共振(MRI)成像仪等精密仪器,对变形、振动及噪音等干扰敏感,需重点保护。The application example of the actual situation is used as a supplementary explanation. The foundation pit support project of the medical complex building of Nanfang Hospital (Phase I) is located in the Nanfang Hospital of Nanfang Medical University, Guangzhou Avenue, Guangzhou City. 35.00m, the perimeter of the foundation pit is about 400m, and the excavation depth of the foundation pit is about 12.30-15.40m. Within the excavation depth of the foundation pit, the backfill, alluvial clay layer, sand layer, plastic and hard residual cohesive soil layer, etc. are sequentially exposed. The bottom of the foundation pit is mainly located in the clay layer, and partially in the fully weathered rock layer. The surrounding environment of the foundation pit is complex. The north side is adjacent to the surgical building (13 floors, independent foundation, a basement floor, the foundation depth is about 5.2m), and it is about 6.0m away from the sideline of the basement of the medical complex building; the east side is the dormitory building with floors 2-19. It is about 18.3m from the basement side. The basement side on the south side of the foundation pit is 5.0m away from the road. The independent foundation of the 5-storey medical technology building on the northwest side of the foundation pit is about 8.3m away from the sideline of the basement. There are water supply and drainage pipelines and power supply lines under the east and south roads. Precision instruments such as DSG and r-knife are installed in the basement of the surgical building on the north side, and precision instruments such as a nuclear magnetic resonance (MRI) imager are installed in the medical technology building on the northwest side, which are sensitive to disturbances such as deformation, vibration and noise and need to be protected.

在基坑支护结构和主体结构素砼桩施工期间,基坑北侧及西侧出现不均匀沉降,外科楼东南角最大沉降达到38.5mm,东南角倾斜率达到4.25‰,且不稳定,已超过设计控制值。为避免沉降持续发展出现险情,工地暂停支护结构施工,采用本实施例中的地基加固纠偏结构及加固纠偏方法对基坑北侧和西侧单独(条形)基础及基础下的土体进行抢险加固,实现对沉降量较大的区域进行定向抬升和加固纠偏,减小基础土层的不均匀沉降。在加固纠偏后,外科楼不均匀沉降得到有效控制,东南角(最大沉降点)经适量抬升后,沉降量稳定在约15mm,角点倾斜率恢复至约1.5‰,确保了外科楼主体结构继续安全使用,具有良好的社会和经济效益。During the construction of the foundation pit supporting structure and the plain concrete piles of the main structure, uneven settlement occurred on the north and west sides of the foundation pit. The maximum settlement of the southeast corner of the surgical building reached 38.5mm, and the inclination rate of the southeast corner reached 4.25‰. Exceeded design control value. In order to avoid the danger of continuous development of settlement, the construction of the support structure was suspended at the construction site, and the foundation reinforcement rectification structure and reinforcement rectification method in this embodiment were used to carry out the construction of the single (strip) foundation on the north and west sides of the foundation pit and the soil under the foundation. Rescue reinforcement, realize directional uplifting and reinforcement correction for areas with large settlement, and reduce the uneven settlement of the foundation soil layer. After the reinforcement and rectification, the uneven settlement of the surgical building was effectively controlled. After the southeast corner (the maximum settlement point) was properly lifted, the settlement was stabilized at about 15mm, and the inclination rate of the corner point was restored to about 1.5‰, which ensured that the main structure of the surgical building continued to be maintained. Safe use, with good social and economic benefits.

综上,本发明实施例提供一种地基加固纠偏方法具有以下优点:(1)利用锚杆静压方式在所述钢管桩3的顶部施加预应力,有效牵引基础土层,减少施工期间反复不均匀的沉降与抬升,实现基础土层、钢管桩3和地基协同作用,形成牵引式钢管桩3,以充分发挥基础底土体的承载力,尽量不改变原结构受力状态;(2)在所述钢管桩3设置第一注浆管77,通过第二注浆管8进行挤压注浆,三重管注浆加固钢管桩3周边土体,从深部定向局部抬升桩土共同体,减少已出现的不均匀沉降(差异沉降);(3)布置网格状的所述注浆钢管5,局部定向挤压注浆,长短结合,挤密加固基础底下土体,实现定向实现浅层主要受力土层定向抬升,进一步减少差异沉降;(4)定向注浆抬升纠偏,采用孔底混合、速凝挤密定向加固工艺,分别从深部和浅部,挤密加固基础底下土体,反复多次注浆和多点同时注浆,实现加固和纠偏于一体;(5)施工方便,可调预应力封锚。采用反复渐进式螺纹式封桩结构,通过压力计观测锚杆静压桩的荷载损失情况,如有损失可复压,可确保单桩承载力,有效减少停止注浆后的沉降;(6)施工周期短,比常规的方法可节约施工造价约20~50%,节约施工周期约30~60%。To sum up, the embodiment of the present invention provides a foundation reinforcement and deviation correction method with the following advantages: (1) Prestress is applied to the top of the steel pipe pile 3 by means of anchor bolt static pressure, so as to effectively pull the foundation soil layer, and reduce repetition during construction. Uneven settlement and uplift realize the synergy between the foundation soil layer, the steel pipe pile 3 and the foundation, and form the traction type steel pipe pile 3, so as to give full play to the bearing capacity of the foundation subsoil, and try not to change the stress state of the original structure; ( 2) A first grouting pipe 77 is set on the steel pipe pile 3, and extrusion grouting is performed through the second grouting pipe 8. The triple pipe grouting reinforces the surrounding soil of the steel pipe pile 3, and locally lifts the pile soil from the deep part. Community, reducing the uneven settlement (differential settlement) that has occurred; (3) arranging the grouting steel pipe 5 in a grid shape, local directional extrusion grouting, long and short combination, compaction and reinforcement of the soil under the foundation, to achieve directional realization The main stressed soil layer in the shallow layer is directional uplifted to further reduce differential settlement; (4) Directional grouting lifts and corrects deviation, adopts the directional reinforcement technology of hole bottom mixing and quick-setting compaction, and compacts and reinforces the soil under the foundation from the deep and shallow parts respectively. (5) The construction is convenient, and the prestressed anchorage can be adjusted. The repeated progressive threaded pile sealing structure is adopted, and the load loss of the anchor static pressure pile is observed by the pressure gauge. If there is any loss, it can be recompressed, which can ensure the bearing capacity of the single pile and effectively reduce the settlement after the grouting is stopped; (6) The construction period is short, and the construction cost can be saved by about 20-50% compared with the conventional method, and the construction period can be saved by about 30-60%.

上方所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和替换,这些改进和替换也应视为本发明的保护范围。The above description is only the preferred embodiment of the present invention. It should be pointed out that for those skilled in the art, without departing from the technical principle of the present invention, several improvements and replacements can be made. These improvements and replacements It should also be regarded as the protection scope of the present invention.

Claims (10)

1. A foundation reinforcement deviation rectifying method is characterized by comprising the following steps:
the method comprises the following steps of (1) forming a first pile hole in the ground of a foundation to be constructed and extending to a deep soil body, and implanting anchor rod reinforcing steel bars around the first pile hole;
pressing the steel pipe pile into the first pile hole by using the foundation as a counter-force platform in an anchor rod static pressure construction mode;
extruding and grouting the prepared grouting liquid through a grout outlet of the steel pipe pile, and compacting and reinforcing the deep soil body in a repeated grouting mode of grouting, cleaning and grouting;
after grouting is finished, fixing a pressurizing assembly through the anchor rod reinforcing steel bars, and temporarily locking the steel pipe pile by using the pressurizing assembly;
a plurality of second pile holes are formed in the ground of a foundation to be constructed or the ground between two foundations and extend to a shallow soil body, grouting steel pipes are inserted into the second pile holes, grouting liquid is extruded and grouted through the grouting steel pipes, local directional reinforcement is carried out on the shallow soil body in the same repeated grouting mode, and a settled soil layer below the foundation is lifted upwards and corrected;
in the process of grouting the steel pipe, acquiring a pressure change value of the steel pipe pile, judging whether the pressure change value of the steel pipe pile exceeds a preset value, if so, performing compensation pressurization on the steel pipe pile by using the pressurization assembly to ensure the bearing capacity of the steel pipe pile;
and after the reinforcement and the correction are finished, the pressurizing assembly is disassembled, concrete is poured into the steel pipe pile, and the steel pipe pile, the grouting steel pipe and the foundation are fixed into a whole through pouring a concrete foundation beam.
2. The method for correcting the foundation stabilization according to claim 1, wherein the step of performing extrusion grouting on the prepared grouting liquid through a grout outlet of the steel pipe pile further comprises:
and welding a first grouting pipe in the steel pipe pile, inserting a second grouting pipe into the first grouting pipe and extending to the grout outlet, and extruding and grouting the grouting liquid through the second grouting pipe.
3. The method for correcting the foundation stabilization according to claim 1, wherein in the step of pressing the steel pipe pile into the first pile hole by the anchor rod static pressure construction, the method further comprises:
and detecting the pile pressing pressure and the verticality of the steel pipe pile so as to keep the vertical pressurization of the steel pipe pile and ensure that the pile pressing pressure acting on the steel pipe pile does not exceed the maximum pile pressing pressure.
4. The method for correcting the foundation stabilization according to claim 1, wherein in the step of fixing a pressurizing assembly through the anchor rod reinforcing steel bars and temporarily locking the steel pipe pile by using the pressurizing assembly, the method specifically comprises the following steps:
fixing a first pile pressing block of the pressurizing assembly on the ground of the foundation through the anchor rod steel bars, fixing a second pile pressing block of the pressurizing assembly above the first pile pressing block through the anchor rod steel bars, arranging a jack between the first pile pressing block and the second pile pressing block, and applying prestress to the steel pipe pile by using the jack.
5. The deviation rectifying method for foundation stabilization according to claim 4, wherein the anchor bar is provided with nuts for adjusting the positions of the first pile block and the second pile block.
6. The foundation stabilization deviation rectifying method according to claim 1, wherein the grouting liquid is prepared from cement paste, water glass and liquid water, and the volume ratio of the cement paste to the water glass to the liquid water is 1.0-1.5: 1: 2 to 3.
7. The method for correcting the foundation stabilization according to claim 1, wherein the opening direction of each second pile hole is vertical or oblique, and the tail end of each second pile hole faces the steel pipe pile.
8. The method for correcting the foundation stabilization according to claim 1, wherein in the step of performing extrusion grouting on the grouting liquid through the grouting steel pipe and performing local directional reinforcement on the shallow soil body in the same repeated grouting manner to lift and correct the deviation of the settlement soil layer below the foundation, the method specifically comprises the following steps:
dividing the prepared grouting liquid into a plurality of groups, repeatedly extruding and grouting each group of grouting liquid through the grouting steel pipe, and directionally reinforcing a plurality of local positions of a subsided soil layer for a plurality of times so as to gradually lift the subsided soil layer upwards and tend to a stable state, wherein different grouting steel pipes adopt the grouting liquid with different grouting amounts so as to upwards lift each local position in a differentiation manner and correct uneven settlement of the subsided soil layer.
9. The method for correcting the foundation stabilization according to claim 1, wherein in the step of fixing the steel pipe piles, the grouting steel pipes and the foundation into a whole by pouring concrete foundation beams, the method comprises the following specific steps:
and implanting a plurality of criss-cross fixed steel bars into the ground of the foundation, pouring concrete into a foundation beam, and fixing the steel pipe pile, the grouting steel pipe and the foundation into a whole.
10. The method for correcting deviation of foundation stabilization according to any one of claims 1 to 9, wherein the step of using the foundation as a counterforce platform further comprises:
and if the ground of the foundation to be constructed is not the horizontal plane, constructing a horizontal reaction platform on the ground of the foundation.
CN202010545267.4A 2020-06-15 2020-06-15 Foundation reinforcement deviation rectifying method Active CN111779045B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010545267.4A CN111779045B (en) 2020-06-15 2020-06-15 Foundation reinforcement deviation rectifying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010545267.4A CN111779045B (en) 2020-06-15 2020-06-15 Foundation reinforcement deviation rectifying method

Publications (2)

Publication Number Publication Date
CN111779045A true CN111779045A (en) 2020-10-16
CN111779045B CN111779045B (en) 2022-04-01

Family

ID=72756794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010545267.4A Active CN111779045B (en) 2020-06-15 2020-06-15 Foundation reinforcement deviation rectifying method

Country Status (1)

Country Link
CN (1) CN111779045B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482034A (en) * 2021-06-23 2021-10-08 国网山西省电力公司阳泉供电公司 Deviation rectifying method for uneven settlement of power transmission iron tower
CN113863285A (en) * 2021-10-14 2021-12-31 山东建大工程鉴定加固设计有限公司 A method of preventing inclination of large-diameter piles on foundation side and external box-type high-rise buildings
CN114277863A (en) * 2021-12-31 2022-04-05 北京中岩大地科技股份有限公司 Construction method for reinforcing foundation soil body of existing building
CN114319471A (en) * 2021-12-31 2022-04-12 北京中岩大地科技股份有限公司 Construction method of pressure-controllable prestressed pile
CN114855769A (en) * 2022-06-09 2022-08-05 山西八建集团有限公司 A kind of rotary assembled foundation treatment steel pipe pile and construction method
CN115198722A (en) * 2022-08-24 2022-10-18 青岛理工大学 Anchor rod for reinforcing soft soil foundation of flood plain terrain
CN115928822A (en) * 2023-02-02 2023-04-07 山东省建筑科学研究院有限公司 CFG Pile Strengthening Construction Method
CN116122358A (en) * 2022-12-31 2023-05-16 河南文博建设工程有限公司 A method for rectifying the inclination of an ancient pagoda
CN116290096A (en) * 2023-03-22 2023-06-23 中建一局集团第二建筑有限公司 A structure and method for preventing uneven settlement of deformation joints of underground pipe gallery

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009057816A (en) * 2007-08-03 2009-03-19 Taisei Ulec Kk Method for correcting horizontal height of structure, equipment used in the method, and method for reinforcing bearing capacity of structure
CN101397796A (en) * 2008-09-12 2009-04-01 葛培中 Construction method of prestressed anchor rod static pressure pile
EP2918731A1 (en) * 2014-03-12 2015-09-16 Silvia Canteri Pile for strengthening and/or lifting buildings and other constructions
CN105951749A (en) * 2016-05-11 2016-09-21 中国水利水电第十四工程局有限公司 Construction method for reinforcement treatment of soft foundation steel pipe pile in confined space
CN106522292A (en) * 2016-09-20 2017-03-22 中科院广州化灌工程有限公司 Grouting combined prestressed anchor rod static pressure pile rectification and reinforcement method
CN206090653U (en) * 2016-09-30 2017-04-12 上海岩土工程勘察设计研究院有限公司 Anchor rod static pressure pile slip casting structure
CN206873517U (en) * 2017-05-09 2018-01-12 广东省建筑科学研究院集团股份有限公司 A kind of shallow foundation rectifying of leaned building ruggedized construction
CN109183867A (en) * 2018-11-12 2019-01-11 中铁西北科学研究院有限公司 A kind of non-disturbance is adjusted fast short stopping and inclines method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009057816A (en) * 2007-08-03 2009-03-19 Taisei Ulec Kk Method for correcting horizontal height of structure, equipment used in the method, and method for reinforcing bearing capacity of structure
CN101397796A (en) * 2008-09-12 2009-04-01 葛培中 Construction method of prestressed anchor rod static pressure pile
EP2918731A1 (en) * 2014-03-12 2015-09-16 Silvia Canteri Pile for strengthening and/or lifting buildings and other constructions
CN105951749A (en) * 2016-05-11 2016-09-21 中国水利水电第十四工程局有限公司 Construction method for reinforcement treatment of soft foundation steel pipe pile in confined space
CN106522292A (en) * 2016-09-20 2017-03-22 中科院广州化灌工程有限公司 Grouting combined prestressed anchor rod static pressure pile rectification and reinforcement method
CN206090653U (en) * 2016-09-30 2017-04-12 上海岩土工程勘察设计研究院有限公司 Anchor rod static pressure pile slip casting structure
CN206873517U (en) * 2017-05-09 2018-01-12 广东省建筑科学研究院集团股份有限公司 A kind of shallow foundation rectifying of leaned building ruggedized construction
CN109183867A (en) * 2018-11-12 2019-01-11 中铁西北科学研究院有限公司 A kind of non-disturbance is adjusted fast short stopping and inclines method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482034A (en) * 2021-06-23 2021-10-08 国网山西省电力公司阳泉供电公司 Deviation rectifying method for uneven settlement of power transmission iron tower
CN113482034B (en) * 2021-06-23 2023-07-14 国网山西省电力公司阳泉供电公司 A correction method for uneven settlement of transmission towers
CN113863285A (en) * 2021-10-14 2021-12-31 山东建大工程鉴定加固设计有限公司 A method of preventing inclination of large-diameter piles on foundation side and external box-type high-rise buildings
CN113863285B (en) * 2021-10-14 2022-10-18 山东建大工程鉴定加固设计有限公司 Inclination stopping method for high-rise building with foundation side large-diameter pile and external box type structure
CN114277863A (en) * 2021-12-31 2022-04-05 北京中岩大地科技股份有限公司 Construction method for reinforcing foundation soil body of existing building
CN114319471A (en) * 2021-12-31 2022-04-12 北京中岩大地科技股份有限公司 Construction method of pressure-controllable prestressed pile
CN114855769A (en) * 2022-06-09 2022-08-05 山西八建集团有限公司 A kind of rotary assembled foundation treatment steel pipe pile and construction method
CN115198722A (en) * 2022-08-24 2022-10-18 青岛理工大学 Anchor rod for reinforcing soft soil foundation of flood plain terrain
CN116122358A (en) * 2022-12-31 2023-05-16 河南文博建设工程有限公司 A method for rectifying the inclination of an ancient pagoda
CN115928822A (en) * 2023-02-02 2023-04-07 山东省建筑科学研究院有限公司 CFG Pile Strengthening Construction Method
CN116290096A (en) * 2023-03-22 2023-06-23 中建一局集团第二建筑有限公司 A structure and method for preventing uneven settlement of deformation joints of underground pipe gallery

Also Published As

Publication number Publication date
CN111779045B (en) 2022-04-01

Similar Documents

Publication Publication Date Title
CN111779045A (en) A kind of foundation reinforcement rectification method
CN107090860B (en) Deviation rectifying and reinforcing structure of shallow foundation building and construction method thereof
CN105586984B (en) A kind of quick-assembling cast-type reinforced earth bulkhead and its construction method
CN114000524A (en) Steel sheet pile cofferdam structure of deep silt geological adjacent structure and construction method
CN107447613B (en) A deep ultra-soft soil embankment and its construction method
CN103774674B (en) A kind of steel pipe underpinned pile and anchor pole deep foundation pit supporting structure and construction method thereof
CN215977211U (en) A composite foundation treatment structure of pipe pile combined with cement-soil mixing pile
CN107246015A (en) A kind of super-sized foundation pit subregion adds inner supporting structure and construction method after excavating
CN112376589A (en) Landslide belt pile plate type comprehensive protection construction system and construction method
CN105926963A (en) Vertical supporting method of underground top-down storey addition of existing high-rise building
CN108005104A (en) A kind of combined type retaining wall structure and its construction method
CN206873517U (en) A kind of shallow foundation rectifying of leaned building ruggedized construction
CN108035379A (en) A kind of pipe gallery and its construction method
CN115652719A (en) A load-bearing embankment structure of wall-pile-net composite foundation
CN108914947A (en) Foundation pit anchor wall draws the construction method of anchor supporting and its supporting construction of drilling tool and formation
CN108589769A (en) A kind of embedding rock T shapes combined type column plate high gear wall construction method of overlength
CN219568906U (en) A foundation pit support structure for settlement control of connected box culverts in deep fill areas
CN113832997B (en) Construction method of combined steel sheet pile cofferdam
CN216515676U (en) Steel sheet pile cofferdam structure of deep silt geology closes on structure
CN113266019B (en) A construction method of steel pipe support system for foundation pit
CN113863705B (en) Method for underpinning and reinforcing existing building based on static pressure jet grouting steel pipe pile and application device
CN117536282A (en) Excavation-free correction construction method for sedimentation of small-sized structures
CN116971413A (en) An emergency joint reinforcement construction method and reinforcement system for retaining walls
CN211228521U (en) Frame bridge supporting construction
CN113700004A (en) Deep foundation pit combined support construction device and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant