CN113464145A - Excavation construction method for weak surrounding rock large-section tunnel - Google Patents

Excavation construction method for weak surrounding rock large-section tunnel Download PDF

Info

Publication number
CN113464145A
CN113464145A CN202110765032.0A CN202110765032A CN113464145A CN 113464145 A CN113464145 A CN 113464145A CN 202110765032 A CN202110765032 A CN 202110765032A CN 113464145 A CN113464145 A CN 113464145A
Authority
CN
China
Prior art keywords
construction method
surrounding rock
arch
weak surrounding
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110765032.0A
Other languages
Chinese (zh)
Inventor
谭忠盛
赵金鹏
高俊鹏
周振梁
李宗林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Original Assignee
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University filed Critical Beijing Jiaotong University
Priority to CN202110765032.0A priority Critical patent/CN113464145A/en
Publication of CN113464145A publication Critical patent/CN113464145A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The application discloses a weak surrounding rock large-section tunnel excavation construction method, which comprises the following steps: supporting arch part in advance; annularly excavating the upper step, and keeping the core soil of the upper step; primary support of an upper arch part; excavating upper step core soil; excavating the middle part of the lower step in an inverted trapezoid manner; excavating two sides of the lower step; the lower step primary support and the upper arch primary support are sealed to form a ring. According to the construction method, the construction efficiency is accelerated while the safety in the construction process is improved, the technical effect of reducing the project investment is achieved by shortening the construction period, and the problems that the excavation supporting technology steps are complicated, the construction efficiency is low, the safety is poor and the ring cannot be closed in time in the weak surrounding rock tunnel construction method in the related technology are solved.

Description

Excavation construction method for weak surrounding rock large-section tunnel
Technical Field
The application relates to the technical field of tunnel excavation construction, in particular to a weak surrounding rock large-section tunnel excavation construction method.
Background
China is a country with wide breadth, complex terrain and variable geology. With the further development of economy, the requirements of China on tunnel construction are greatly increased. Correspondingly, under the condition of weak surrounding rock, the problem that how to safely and efficiently realize the excavation process of the large-section tunnel is intuitively faced by the engineering interface is solved.
When the tunnel passes through the weak surrounding rock section, the tunnel has the characteristics of low overall strength and poor self-stability, so that great troubles are caused to the excavation support of engineering construction and the safety problems of workers. In the construction process of the tunnel at the weak surrounding rock section, the improper excavation and supporting measures can cause overlarge deformation of surrounding rocks around the tunnel face, invade lining clearance, even cause local block falling and even collapse of the tunnel face, thereby influencing the construction safety, prolonging the construction period and increasing the engineering investment. The existing weak surrounding rock tunnel construction method has the problems of complicated excavation supporting technical steps, low construction efficiency, poor safety and incapability of being sealed in time to form a ring.
Disclosure of Invention
The main purpose of the application is to provide a weak surrounding rock large-section tunnel excavation construction method, and the method is used for solving the problems that excavation supporting technology steps are complex, construction efficiency is low, safety is poor, and ring formation cannot be closed in time in a weak surrounding rock tunnel construction method in the related technology.
In order to achieve the purpose, the application provides a soft surrounding rock large-section tunnel excavation construction method, which comprises the following steps: supporting arch part in advance; annularly excavating the upper step, and keeping the core soil of the upper step; primary support of an upper arch part; excavating upper step core soil; excavating the middle part of the lower step in an inverted trapezoid manner; excavating two sides of the lower step; the lower step primary support and the upper arch primary support are sealed to form a ring.
Further, the arch part advance support specifically comprises: and an advanced large pipe shed is adopted for supporting at the opening of the hole, and an advanced small pipe or an advanced anchor rod is adopted for supporting in the hole.
Furthermore, during the construction process of the arch part advance support, arranging holes according to the technical requirements, mastering the advanced extrapolation angle, and adjusting the extrapolation angle according to the actual field condition;
the overlapping length of adjacent sections is required to meet the design and specification requirements, the support tail is required to be firmly welded with the steel support, grouting construction is required to be carried out strictly according to the design mixing proportion, and grouting pressure is well controlled.
Further, the section area of the core soil of the upper step occupies 50% of the section area of the upper step.
Furthermore, the distance between the upper end surface of the upper step core soil and the arch crown of the tunnel is 1.3-1.7 m.
Further, the preliminary bracing of the upper arch part is specifically as follows: primarily spraying concrete; setting a system anchor rod; hanging a net; erecting a steel arch frame; arranging a foot-locking anchor rod or anchor pipe; and spraying the concrete again to the designed thickness.
Furthermore, the steel arch frame in the erection steel arch frame is erected according to the designed size, the joints are connected and fixed by bolts and are welded when necessary;
the space and welding of the longitudinal connecting steel bars are strictly carried out according to the design and specification requirements so as to ensure the integrity of primary support, and in a particularly soft stratum, the arch wall foot can be provided with a profile steel joist so as to enhance the integrity and avoid cracking or overlarge deformation of the primary support caused by uneven settlement.
Furthermore, the section of the upper step core soil is in a regular trapezoid shape, and the bottom edge of the upper step core soil is the top edge of the inverted trapezoid section in the middle of the lower step.
Furthermore, the width of the lower part of the lower step is 2.5-3.0 m, the width of the upper part of the lower step is 4.0-5.0 m, and the distance between the lower part and the upper step is 5.0-6.0 m.
Furthermore, when two sides of the lower step are excavated, the lower step is staggered with the inverted trapezoidal excavated part in the middle of the lower step, and the staggered distance is 3.0-5.0 m.
In the embodiment of the application, the arch part is arranged for forepoling; annularly excavating the upper step, and keeping the core soil of the upper step; excavating core soil of an upper step of the primary support of the upper arch part; excavating the middle part of the lower step in an inverted trapezoid manner; excavating two sides of the lower step; the lower step primary support and the upper arch portion primary support are sealed to form a ring, so that the safety in the construction process is improved, the construction efficiency is accelerated, the construction period is shortened, the technical effect of engineering investment is reduced, and the problems that the excavation supporting technology steps are complex, the construction efficiency is low, the safety is poor, and the ring cannot be sealed in time in the weak surrounding rock tunnel construction method in the related technology are solved.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, serve to provide a further understanding of the application and to enable other features, objects, and advantages of the application to be more apparent. The drawings and their description illustrate the embodiments of the invention and do not limit it. In the drawings:
FIG. 1 is a schematic structural diagram according to an embodiment of the present application;
FIG. 2 is a schematic cross-sectional view A-A of FIG. 1;
the method comprises the following steps of 1 arch part advanced support, 2 upper step annular excavation, 3 upper step core soil excavation, 4 lower step two-side excavation, 5 lower step preliminary support, 6 lower step middle inverted trapezoid excavation and 7 upper arch part preliminary support.
Detailed Description
In order to make the technical solutions better understood by those skilled in the art, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only partial embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It should be noted that the terms "first," "second," and the like in the description and claims of this application and in the drawings described above are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It should be understood that the data so used may be interchanged under appropriate circumstances such that embodiments of the application described herein may be used.
In this application, the terms "upper", "lower", "inside", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings. These terms are used primarily to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to a particular orientation or to be constructed and operated in a particular orientation.
Moreover, some of the above terms may be used to indicate other meanings besides the orientation or positional relationship, for example, the term "on" may also be used to indicate some kind of attachment or connection relationship in some cases. The specific meaning of these terms in this application will be understood by those of ordinary skill in the art as appropriate.
Furthermore, the terms "disposed," "provided," "connected," "secured," and the like are to be construed broadly. For example, "connected" may be a fixed connection, a detachable connection, or a unitary construction; can be a mechanical connection, or an electrical connection; may be directly connected, or indirectly connected through intervening media, or may be in internal communication between two devices, elements or components. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as appropriate.
In addition, the term "plurality" shall mean two as well as more than two.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
As shown in fig. 1 to 2, an embodiment of the present application provides a soft surrounding rock large-section tunnel excavation construction method, including the following steps: supporting arch part in advance; annularly excavating the upper step, and keeping the core soil of the upper step; primary support of an upper arch part; excavating upper step core soil; excavating the middle part of the lower step in an inverted trapezoid manner; excavating two sides of the lower step; the lower step primary support and the upper arch primary support are sealed to form a ring.
In this embodiment, the tunnel face is divided into five parts for excavation, and the tunnel face is integrally divided into an upper part and a lower part, wherein the upper part includes an upper step annular part and an upper step core soil part, and the lower part includes a lower step middle inverted trapezoidal part located at a middle intersection and two lower step parts located at two sides. Because the construction method aims at weak surrounding rocks, advanced support is required between excavation, namely an arch support structure is arranged above the tunnel face of the tunnel. The arch part advance support specifically comprises the following steps: the method comprises the following steps that an advanced large pipe shed is adopted for supporting at a tunnel opening, an advanced small pipe or an advanced anchor rod is adopted for supporting in a tunnel, holes are distributed according to technical requirements in the construction process of the advanced support of the arch part, an advanced external insertion angle is mastered, and the external insertion angle is adjusted according to the actual situation on site; the overlapping length of adjacent sections is required to meet the design and specification requirements, the support tail is required to be firmly welded with the steel support, grouting construction is required to be carried out strictly according to the design mixing proportion, and grouting pressure is well controlled.
After the arch advance support construction is finished, firstly, annular excavation is carried out on the upper step to form an annular excavation area, and as the annular excavation is carried out on the upper step, the core soil of the upper step is kept, so that the stability of the tunnel face can be maintained. The section of the upper step core soil is in a regular trapezoid shape, and the section area of the upper step core soil occupies 50% of the section area of the upper step, so that the operation of a constructor is facilitated. The annular excavation height of the upper step is determined by combining the machining size of the steel arch according to the actual surrounding rock condition, the operation of personnel is convenient, and the annular excavation height is preferably controlled to be 3.5-4.0 m; the excavation circulating footage is preferably controlled according to the spacing of 2 steel arches, and is generally 0.5-1.0 m.
As shown in fig. 1 to 2, the distance between the upper end surface of the upper step core soil and the arch crown of the tunnel is 1.3-1.7m, preferably 1.5m, so that the operation is convenient for constructors to operate.
As shown in fig. 1 to 2, after each excavation, primary support should be performed in time to achieve "early shotcrete anchor", wherein the primary support of the upper arch part specifically includes: primarily spraying concrete; setting a system anchor rod; hanging a net; erecting a steel arch frame; arranging a foot-locking anchor rod or anchor pipe; and spraying the concrete again to the designed thickness. Erecting a steel arch frame in the erecting steel arch frame according to the designed size, connecting and fixing the joints by using bolts, and welding when necessary;
the space and welding of the longitudinal connecting steel bars are strictly carried out according to the design and specification requirements so as to ensure the integrity of primary support, and in a particularly soft stratum, the arch wall foot can be provided with a profile steel joist so as to enhance the integrity and avoid cracking or overlarge deformation of the primary support caused by uneven settlement.
As shown in fig. 1 to 2, the section of the core soil of the upper step is in a regular trapezoid shape, the bottom edge of the core soil of the upper step is the top edge of the inverted trapezoid section at the middle part of the lower step, the width of the lower part of the inverted trapezoid excavated at the middle part of the lower step is 2.5 to 3.0m, the width of the upper part of the inverted trapezoid excavated lower part of the lower step is 4.0 to 5.0m, and the distance from the core soil of the upper step is 5.0 to 6.0 m.
Specifically, the double-side-wall guide pit and CRD construction method adopts an excavation method of excavating two sides, then excavating a middle structure, and the middle soil body left after excavating the soil bodies on the two sides is in a regular trapezoid, square or other structure. In the construction method, the mode that the middle of the lower step is firstly excavated and the two sides of the lower step are excavated is adopted, due to the inverted trapezoidal structure in the middle, the downward excavation is facilitated, the width of the bottom is smaller, soil bodies on the two sides of the lower step can form soil pressure on the bottom, and the bottom uplift can be effectively prevented.
Furthermore, when two sides of the lower step are excavated, the lower step is staggered with the inverted trapezoidal excavated part in the middle of the lower step, the staggered distance is 3.0-5.0m, the length of the single-side excavation is not more than 1.2m, and the control is preferably carried out according to the space between 2 steel arches.
The construction method effectively reduces the construction difficulty, and the construction method has the advantages that the working procedure is simple, the excavation and the primary support of each part are easy to control, and the construction difficulty is reduced. The method has the advantages of simple process, easy control of excavation and initial support of each part and low construction difficulty.
Compared with the construction method of double-side-wall pilot tunnel and CRD, the construction method greatly saves temporary steel frames and temporary sprayed concrete, saves labor and materials; meanwhile, the excavation method is free of temporary support, and the time for dismantling the temporary support is saved, so that the working procedures are easy to convert when surrounding rocks change, and the construction progress is accelerated. In addition, the core soil supports the top working surface, so that the stability is good; excavating is carried out under the protection of a support; short footage and equipment utilization shorten the exposure time of surrounding rocks; the working procedures are less, the distance between the working procedures is short, the primary support can be sealed into a ring as soon as possible, and the support effect is exerted. The construction method can be flexibly applied, and when the construction method is used alone, the height of the staggered platform can be flexibly adjusted according to the actual surrounding rock condition.
The above description is only a preferred embodiment of the present application and is not intended to limit the present application, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims (10)

1. A construction method for excavating a weak surrounding rock large-section tunnel is characterized by comprising the following steps:
supporting arch part in advance;
annularly excavating the upper step, and keeping the core soil of the upper step;
primary support of an upper arch part;
excavating upper step core soil;
excavating the middle part of the lower step in an inverted trapezoid manner;
excavating two sides of the lower step;
the lower step primary support and the upper arch primary support are sealed to form a ring.
2. The weak surrounding rock large-section tunnel excavation construction method of claim 1, wherein the arch portion advance support specifically comprises: and an advanced large pipe shed is adopted for supporting at the opening of the hole, and an advanced small pipe or an advanced anchor rod is adopted for supporting in the hole.
3. The weak surrounding rock large-section tunnel excavation construction method of claim 2, wherein in the arch portion advance support construction process, holes are arranged according to technical requirements, an advance external insertion angle is mastered, and the external insertion angle is adjusted according to actual conditions on site;
the overlapping length of adjacent sections is required to meet the design and specification requirements, the support tail is required to be firmly welded with the steel support, grouting construction is required to be carried out strictly according to the design mixing proportion, and grouting pressure is well controlled.
4. The weak surrounding rock large-section tunnel excavation construction method of claim 3, wherein the upper step core soil section area occupies 50% of the upper step section area.
5. The weak surrounding rock large-section tunnel excavation construction method of claim 4, wherein the distance between the upper end face of the upper step core soil and the arch crown of the tunnel is 1.3-1.7 m.
6. The weak surrounding rock large-section tunnel excavation construction method according to any one of claims 1 to 5, characterized in that the preliminary bracing of the upper arch part is specifically as follows: primarily spraying concrete; setting a system anchor rod; hanging a net; erecting a steel arch frame; arranging a foot-locking anchor rod or anchor pipe; and spraying the concrete again to the designed thickness.
7. The weak surrounding rock large-section tunnel excavation construction method of claim 6, wherein the steel arch frame of the erection steel arch frame is erected according to a designed size, joints are fixedly connected through bolts, and welding connection is performed when necessary;
the space and welding of the longitudinal connecting steel bars are strictly carried out according to the design and specification requirements so as to ensure the integrity of primary support, and in a particularly soft stratum, the arch wall foot can be provided with a profile steel joist so as to enhance the integrity and avoid cracking or overlarge deformation of the primary support caused by uneven settlement.
8. The excavation construction method for the weak surrounding rock large-section tunnel according to claim 7, wherein the section of the core soil of the upper step is in a regular trapezoid shape, and the bottom edge of the core soil of the upper step is the top edge of the inverted trapezoid section in the middle of the lower step.
9. The excavation construction method of the weak surrounding rock large-section tunnel according to claim 8, wherein the width of the lower portion of the lower step is 2.5-3.0 m, the width of the upper portion of the lower step is 4.0-5.0 m, and the distance between the upper step and the core soil is 5.0-6.0 m.
10. The excavation construction method of the weak surrounding rock large-section tunnel according to claim 9, wherein the excavation on both sides of the lower step is staggered from the inverted trapezoidal excavation part in the middle of the lower step by a distance of 3.0-5.0 m.
CN202110765032.0A 2021-07-06 2021-07-06 Excavation construction method for weak surrounding rock large-section tunnel Pending CN113464145A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110765032.0A CN113464145A (en) 2021-07-06 2021-07-06 Excavation construction method for weak surrounding rock large-section tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110765032.0A CN113464145A (en) 2021-07-06 2021-07-06 Excavation construction method for weak surrounding rock large-section tunnel

Publications (1)

Publication Number Publication Date
CN113464145A true CN113464145A (en) 2021-10-01

Family

ID=77878767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110765032.0A Pending CN113464145A (en) 2021-07-06 2021-07-06 Excavation construction method for weak surrounding rock large-section tunnel

Country Status (1)

Country Link
CN (1) CN113464145A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114282287A (en) * 2021-11-19 2022-04-05 中交一公局桥隧工程有限公司 Method for determining primary support deformation grading control standard in step method construction of V-level surrounding rock tunnel
CN114458355A (en) * 2022-01-17 2022-05-10 西南交通大学 Method for directionally reinforcing advanced small conduits with different large deformation grades under longitudinal bedding

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101906974A (en) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 Supporting structure of extra-large cross-section loess tunnel and construction method thereof
CN102444407A (en) * 2011-12-12 2012-05-09 中铁二局股份有限公司 Construction deformation control method for lower step of high crustal stress weak surrounding rock tunnel
CN102926757A (en) * 2012-09-07 2013-02-13 中铁五局(集团)有限公司 Construction method of two-sidestep and four-step excavation support of weak large-span tunnel of mountain ridge
CN103174430A (en) * 2013-04-10 2013-06-26 中国水利水电第十四工程局有限公司 Shallow-buried large-span water conveying tunnel three-stage five-step digging method
CN103775092A (en) * 2014-01-09 2014-05-07 长业建设集团有限公司 Tunnel shallow-buried excavation reserved core soil improved CRD construction method
CN207144946U (en) * 2017-09-21 2018-03-27 中铁四局集团有限公司 The step of large-section loess tunnel three draws bracket groove to excavate the scope of operation
CN108756894A (en) * 2018-04-23 2018-11-06 中铁二十五局集团第工程有限公司 Tunnel micro- three step top Core Soil construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101906974A (en) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 Supporting structure of extra-large cross-section loess tunnel and construction method thereof
CN102444407A (en) * 2011-12-12 2012-05-09 中铁二局股份有限公司 Construction deformation control method for lower step of high crustal stress weak surrounding rock tunnel
CN102926757A (en) * 2012-09-07 2013-02-13 中铁五局(集团)有限公司 Construction method of two-sidestep and four-step excavation support of weak large-span tunnel of mountain ridge
CN103174430A (en) * 2013-04-10 2013-06-26 中国水利水电第十四工程局有限公司 Shallow-buried large-span water conveying tunnel three-stage five-step digging method
CN103775092A (en) * 2014-01-09 2014-05-07 长业建设集团有限公司 Tunnel shallow-buried excavation reserved core soil improved CRD construction method
CN207144946U (en) * 2017-09-21 2018-03-27 中铁四局集团有限公司 The step of large-section loess tunnel three draws bracket groove to excavate the scope of operation
CN108756894A (en) * 2018-04-23 2018-11-06 中铁二十五局集团第工程有限公司 Tunnel micro- three step top Core Soil construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114282287A (en) * 2021-11-19 2022-04-05 中交一公局桥隧工程有限公司 Method for determining primary support deformation grading control standard in step method construction of V-level surrounding rock tunnel
CN114458355A (en) * 2022-01-17 2022-05-10 西南交通大学 Method for directionally reinforcing advanced small conduits with different large deformation grades under longitudinal bedding
CN114458355B (en) * 2022-01-17 2023-02-28 西南交通大学 Method for directionally reinforcing advanced small conduits with different large deformation grades under longitudinal bedding

Similar Documents

Publication Publication Date Title
CN101864963B (en) Large-section loess tunnel construction method
CN109505609B (en) Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack
CN113464145A (en) Excavation construction method for weak surrounding rock large-section tunnel
CN103277118A (en) Joint steel frame supporting system for excavating auxiliary tunnel on main-tunnel arch wall and construction method of joint steel frame supporting system
CN109854280B (en) Core soil bearing type supporting system for underground excavation of subway station and construction method thereof
CN112302686B (en) Vertical jacking construction method for entering tunnel inclined shaft into main tunnel
CN108756932B (en) Tunnel construction method comprising supporting structure
CN109594995B (en) Weak surrounding rock tunnel perturbation motive machinery subsection tunneling construction method
CN112302687B (en) Support-changing and jacking construction method for entering main tunnel of tunnel inclined shaft
CN203285454U (en) Connector steel frame supporting system for drilling auxiliary tunnel in main cave arch wall
CN112682048B (en) Replacement reinforcement construction method for small clear distance up-span existing tunnel of newly-built tunnel
CN115467690A (en) Shallow-buried large-span underground excavation subway station new structure system and construction method thereof
CN215057408U (en) Reinforcing device for intersection of inclined shaft and main tunnel of highway tunnel
CN211737157U (en) Tunnel primary support structure of steel arch frame
CN114320317A (en) Construction method for weak surrounding rock section of short-step super-large section tunnel
CN112664205B (en) Tunnel excavation supporting method for cross intersection
CN114607389A (en) Improved double-side-wall pilot tunnel construction method for urban super-large-section shallow-buried station
CN112647978A (en) Construction method for leading small pilot tunnel of soft rock large-deformation tunnel
CN112664248A (en) Soft rock water spraying roadway supporting method
CN114086992B (en) Large-span tunnel expanding and excavating construction method under complex geological conditions
CN112431607B (en) Vertical cross tunnel construction method suitable for mountain construction
CN214062981U (en) Laminated tunnel cave group excavation reinforcing system
CN113107520B (en) Construction method for excavation and conversion process of inclined shaft and main tunnel of tunnel
CN110985011B (en) Three-step seven-step combined excavation method for upper step of soft soil layer by adopting middle partition wall
CN217897872U (en) Ingate entering construction structure suitable for circular vertical shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20211001